Home India Joint Electricity Regulatory Commission for UT of Jammu & Kashmir and UT of Ladakh In exercise of the powers conferred by Section 181 read with...
Date: 12-Dec-2023 Category: Extra Ordinary State: Union Government Country: India

In exercise of the powers conferred by Section 181 read with section 86 1 h of the Electricity Act,

Issued by Joint Electricity Regulatory Commission for UT of Jammu & Kashmir and UT of Ladakh · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task

Executive Summary & Key Takeaways

Overview

  • This gazette notification pertains to the Joint Electricity Regulatory Commission (JERC) for the Union Territories of Jammu & Kashmir (J&K) and Ladakh, issuing the State Grid Code Regulations for 2023.
  • The regulations aim to establish a framework for operating and maintaining an efficient and coordinated power system in the specified Union Territories, aligning with the Indian Electricity Grid Code (IEGC) and the National Electricity Policy.

Key Changes

  • The regulations are applicable to the Union Territories of Jammu & Kashmir and Ladakh and come into effect from the date of publication in the official gazette (December 12, 2023).
  • The notification defines various terms and expressions relevant to electricity regulation and grid management, including definitions related to grid operations, power generation, transmission, distribution, and consumer responsibilities.
  • It establishes a State Grid Code Review Committee to oversee the implementation, review, and amendment of the State Grid Code.
  • The regulations outline procedures for system planning, including demand forecasting, network studies, and coordination with the Central Transmission Utility (CTU).
  • It specifies conditions for connecting to the State Transmission System, including application procedures, technical requirements, and connection agreements.
  • The notification addresses system security aspects, including measures to maintain grid reliability and safety, and protocols for responding to system disturbances.
  • It defines responsibilities for frequency and voltage management, including maintaining system parameters within specified limits and implementing control measures.
  • The regulations establish protection standards for electrical equipment connected to the State Transmission System, including relay settings and fault clearance times.
  • It outlines procedures for operational planning, including demand estimation and demand control measures.
  • The notification addresses monitoring of generation and drawal, including requirements for reporting generating unit trippings and maintaining data on generation and drawal.
  • It establishes procedures for outage planning, including coordination of planned outages and managing system security during outages.
  • The regulations define contingency planning procedures for responding to system blackouts and restoring power supply.
  • It specifies safety procedures for working across inter-user boundaries, including the use of line clear permits and designated officers.
  • The notification outlines reporting requirements for operational events, including incidents affecting the State Transmission System.
  • It establishes procedures for scheduling and load dispatch, including the responsibilities of SLDC and Users.
  • The regulations define metering standards, including requirements for meter types, accuracy classes, and data recording.
  • It addresses dispute resolution mechanisms and provides powers to the Commission to remove difficulties and grant exemptions.

Impact Analysis

State Transmission Utility (STU)

  • Action Item: STU needs to establish the State Grid Code Review Committee, develop standard application forms, and ensure compliance with the new regulations.

Generating Companies (SGS, IPP, CPP)

  • Action Item: Review and update protection schemes, ensure compliance with grid code requirements, and provide necessary data to STU and SLDC.

Distribution Licensees

  • Action Item: Update load forecasting methodologies, implement demand control measures, and coordinate with the STU on outage planning.

Consumers and Open Access Customers

  • Action Item: Review connection agreements, ensure compliance with grid code requirements, and participate in demand response programs.

Joint Electricity Regulatory Commission (JERC)

  • Action Item: Oversee implementation of the State Grid Code and address any disputes or difficulties that arise.

Key Entities Referenced

Joint Electricity Regulatory Commission (JERC): The regulatory body for the electricity sector in the Union Territories of Jammu & Kashmir and Ladakh. State Transmission Utility (STU): The entity responsible for the transmission of electricity within the Union Territories of Jammu & Kashmir and Ladakh. State Load Despatch Centre (SLDC): The entity responsible for the real-time operation and control of the power system in the Union Territories of Jammu & Kashmir and Ladakh. Central Transmission Utility (CTU): The central transmission utility responsible for inter-state transmission of electricity. Indian Electricity Grid Code (IEGC): The set of rules and regulations governing the operation of the Indian electricity grid. Electricity Act, 2003: The primary legislation governing the electricity sector in India.
Official Source Record View Original Source →
See Full Document Text
रजिस्ट्री स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99 सी.जी.-जे.के.-अ.-18122023-250736 xxxGIDHxxx CG-JK-E-18122023-250736 xxxGIDExxx असाधारण EXTRAORDINARY भाग III—खण् ड 4 PART III—Section 4 प्राजधकार स ेप्रकाजित PUBLISHED BY AUTHORITY स.ं 830] िई कदल्ली, मगं लिार, कदसम्बर 12, 2023/अिहायण 21, 1945 No. 830] NEW DELHI, TUESDAY, DECEMBER 12, 2023/AGRAHAYANA 21, 1945 सयं क्तु जिद्यतु जिजियामक आयोग (केन्‍दर िाजसत प्रदिे िम्म ूऔर कश्म ीर ि केन्‍दर िाजसत प्रदेि लद्दाख) अजधसचू िा िम्मू, 29 ििम् बर, 2023 क्रमाकं : िईे आरसी-िेकेएल/रेग/2023/19.—जिद्युत अजधजियम, 2003 (2003 का 36) की धारा 86 (1) (एच) के साथ पठित धारा 181 द्वारा प्रदत्त िजक्तयों और इस संबंध में इसे सक्षम करिे िाली अन्‍दय सभी िजक्तयों का प्रयोग करत े हुए, संयुक्त जिद्युत जिजियामक आयोग केंर िाजसत प्रदेि िम्मू और कश्मीर ि केंर िाजसत प्रदिे लद्दाख एतद द्वारा जिम्नजलजखत जिजियम बिाता ह।ै अध्याय-1: सामान्‍दय 1.1 संजक्षप्त िीर्कष , जिस्ट्तार और प्रारंभ 1 इि जिजियमों को “संयुक्त जिद्युत जिजियामक आयोग केंर िाजसत प्रदिे िम्मू और कश्मीर ि केंर िाजसत प्रदेि लद्दाख (राज्य जिड कोड) जिजियम, 2023” कहा जाएगा। 2 ये जिजियम आजधकाठरक रािपत्र में प्रकािि की जतजथ से लाग ूहोंगे। 3 ये जिजियम केंर िाजसत प्रदेि िम्मू और कश्मीर और केंर िाजसत प्रदेि लद्दाख में लागू होंगे। 1.2 पठरभार्ाए ँ 1 इि जिजियमों म ें जिम्नजलजखत िब्दों और अजभव्यजक्तयों के अथष, िब तक कक जिर्य िस्ट्त ु या संदभ ष के अिुसार अन्‍दयथा आिश्यक ि हो या असंगत ि हो, जिम्नजलजखत होंगे: 7713 GI/2023 (1)2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] अजधजियम समय-समय पर संिोजधत जिद्युत अजधजियम, 2003 (2003 का अजधजियम संख्या 36); मान्‍दयता प्राप्त परीक्षण परीक्षण और अंिांकि प्रयोगिालाओं के जलए राष्ट्रीय प्रत्यायि बोडष (एिएबीएल) द्वारा मान्‍दयता प्राप्त प्रयोगिाला एक परीक्षण प्रयोगिाला; सकक्रय ऊिा ष एक समय अंतराल के दौराि जिद्युत सर्कषट द्वारा उत्पाकदत, प्रिाजहत या आपूर्त षकी गई जिद्युत ऊिाष, तात्काजलक िजक्त के समय के संबंध में अजभन्न अंग होती है, जिसे िाट-घंटे या उसके मािक गुणकों की इकाइयों में मापा िाता ह,ै सकक्रय जबिली िोल्टेि का उत्पाद और प्रत्यािती धारा के इि-फेि घटक को िाट और उसके मािक गुणकों की इकाइयों में मापा िाता ह,ै चते ाििी की जस्ट्थजत इसका अथष ह ै िह जस्ट्थजत जिसमें जबिली प्रणाली के पठरचालि पैरामीटर अपिी संबजं धत पठरचालि सीमाओं के अंदर हैं, लेककि एक भी एि-1 आकजस्ट्मकता से जसस्ट्टम सरु क्षा का उल्लंघि होता है; उपकरण सभी जिद्युत उपकरण िैसे मिीिें, कफटटंग, सहायक उपकरण और उपकरण जििमें जिद्युत कंडक्टर का उपयोग ककया िाता ह।ै प्रत्यक्ष जबिली िोल्ट-एम्पीयर और उसके मािक गुणकों की इकाई में मापा गया िोल्टेि और प्रत्यािती धारा का उत्पाद, उपयुक्त पारेर्ण उपयोजगता "सेंरल पारेर्ण यूठटजलटी" (सीटीयू) या "स्ट्टेट पारेर्ण यूठटजलटी" (एसटीयू), िैसा भी मामला हो; आपर्ू त षका क्षत्रे िह क्षेत्र जिसके अंदर एक जितरण लाइसेंसधारी अपिे लाइसेंस द्वारा जबिली की आपूर्तष करिे के जलए अजधकृत है। प्राजधकार केंरीय जिद्युत प्राजधकरण (सीईए) अजधजियम की धारा 70 की उपधारा (1) में संदर्भषत ह।ै स्ट्िचाजलत िोल्टेि जियामक ििरेटर टर्मषिलों पर मापी गई उत्पादि इकाई के िोल्टेि को जियंजत्रत करिे के जलए एक जिरंतर (एिीआर) कायष करिे िाली स्ट्िचाजलत उत्तेििा जियंत्रण प्रणाली। उत्पादि इकाइयों की उपलब्धता और घटकों, िैसे क्षमता िुल्क (सीसी), ऊिाष िुल्क (ईसी) या पठरितषिीय िुल्क (िीसी) और अजिधाषठरत इंटरचेंि (यूआई) के जलए िुल्क पर आधाठरत एक टैठरफ संरचिा। उपलब्धता आधाठरत टैठरफ एक उपभोक्ता िो 33 केिी या उससे ऊपर के िोल्टेि पर आपूर्तष का लाभ उिाता है। (एबीटी) थोक उपभोक्ता कोई भी उत्पादि कंपिी या लाइसेंसधारी या उपभोक्ता जिसका जसस्ट्टम उत्पादि कंपिी या लाइसेंसधारी की प्रणाली से जबिली प्राप्त करता ह।ै क्रेता ककसी भी व्यजक्त द्वारा अपिे स्ट्ियं के उपयोग के जलए जबिली उत्पन्न करिे के जलए स्ट्थाजपत ककया गया पािर पलांट और इसमें मुख्य रूप से ऐसी सहकारी सजमजत या एसोजसएिि के सदस्ट्यों के उपयोग के जलए जबिली पैदा करिे के जलए ककसी सहकारी सजमजत या व्यजक्तयों के संघ द्वारा स्ट्थाजपत पािर पलांट िाजमल ह।ै कैजपटि पॉिरपलाटं (सीपीपी) केंरीय जिद्युत जियामक आयोग (सीईआरसी) अजधजियम की धारा 76 की उप-धारा (1) में संदर्भषत ह।ै सरें ल पारेर्ण यठू टजलटी कोई भी सरकारी कंपिी जिसे केंर सरकार अजधजियम की धारा 38 की उपधारा (1) के अंतगषत (सीटीय)ू अजधसूजचत कर सकती है। िाचं मीटर एक मीटर, िो करंट रांसफामषर (सीटी) और िोल्टेि रांसफामषर (िीटी) के उसी कोर से िुडा होगा जिससे मुख्य मीटर िुडा हुआ ह ैऔर मुख्य मीटर की जिफलता के मामले में जबिली के लेखांकि और जबललंग के जलए उपयोग ककया िाएगा। आयोग संयुक्त जिद्युत जिजियामक आयोग केंर िाजसत प्रदिे िम्मू और कश्मीर ि केंर िाजसत प्रदिे लद्दाख किैक्िि उपयोगकताष के जसस्ट्टम के पारेर्ण प्रणाली से किेक्िि को प्रभाजित करिे के जलए उपयोग की िािे िाली जिद्युत लाइिें और जिद्युत उपकरण। किेक्िि की ित ें अध्याय 4 ("किेक्िि की ितें") में उजल्लजखत िे ितें जिन्‍दह ेंउपयोगकताष के जसस्ट्टम को जिड से किेक्ट करिे से पहले पूरा करिा होगा। किेक्िि लबंद ु पारेर्ण प्रणाली और उपयोगकताष के जसस्ट्टम के बीच जिद्युत किेक्िि का एक लबंद।ु उपभोक्ता कोई भी व्यजक्त जिसे ककसी लाइसेंसधारी या सरकार द्वारा या ककसी अन्‍दय व्यजक्त द्वारा अपिे उपयोग के जलए जबिली की आपूर्तष अजधजियम या ककसी अन्‍दय कािूि के अंतगषत ििता को जबिली की आपूर्तष के व्यिसाय में लगी हुई है और इसमें कोई भी ऐसा व्यजक्त िाजमल ह ै जिसका पठरसर एक समय के जलए ककसी लाइसेंसधारी, सरकार या ऐसे अन्‍दय व्यजक्त, िैसा भी मामला हो, के कायों से[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 3 जबिली प्राप्त करिे के उद्देश्य से िुडा हुआ होता ह।ै जियत्रं ण क्षत्रे एक जियंत्रण क्षेत्र एक जिद्युत प्रणाली ह ैिो इंटरकिेक्िि (टाई लाइि) मीटटरंग और टेलीमेरी से बंधी होती ह ै िो अपिे उत्पादि और/या लोड को जियंजत्रत करती ह ै ताकक िब भी आिश्यक हो तो अन्‍दय जियंत्रण क्षेत्रों के साथ अपिे इंटरचेंि िेड्यूल को बिाए रखा िा सके और लसंक्रोिस ऑपरेटटंग जसस्ट्टम के आिृजत्त जिजियमि में योगदाि कदया िा सके। मागँ िब तक अन्‍दयथा उल्लेख ि हो, मेगािाट में सकक्रय पािर की मांग और ठरएजक्टि पािर की मांग एमिीएआर में होती ह।ै मागं पर जियत्रं ण लोड में कमी लािे के जलए जिम्नजलजखत में से कोई भी तरीका: क) उपयोगकताषओं द्वारा िुरू ककया गया उपभोक्ता लोड जियंत्रण। ख) उपयोगकताषओं द्वारा िुरू ककए गए जडस्ट्किेक्िि द्वारा उपभोक्ता लोड में कमी (लोड जडस्ट्पैच सेंटर से जिदिे का पालि करिे के अलािा)। ग) लोड जडस्ट्पैच सेंटर द्वारा जिदजे ित उपभोक्ता लोड में कमी। घ) फ्रीक्वेंसी लोड जडसकिेक्िि के अंतगषत स्ट्िचाजलत। ङ) आपातकालीि मैिुअल लोड जडसकिेक्िि। जितरण प्रणाली पारेर्ण लाइिों या ििरेटटंग स्ट्टेिि किेक्िि पर जितरण लबंदओंु और उपभोक्ताओं की स्ट्थापिा के किेक्िि लबंद ुके बीच तारों और संबंजधत सुजिधाओं की प्रणाली। गुिरिा जिड से/तक जिद्युत ऊिाष का आयात/जियाषत; ऊिा ष लखे ाकं ि एिं एक जिर्दष्टष समय अिजध में ऊिाष की खपत और हाजि को जिधाषठरत करिे के जलए आगे का जिश्लेर्ण के लेखापरीक्षा मीटर जलए जिद्युत प्रणाली के जिजभन्न खंडों में जबिली के लेखांकि के जलए उपयोग ककए िािे िाले मीटर; अजतठरक्त उच्च िोल्टेि (ईएचिी) प्राजधकरण द्वारा अिुमत प्रजतित जभन्नता के अधीि सामान्‍दय के अंतगषत 33000 िोल्ट से अजधक िोल्टेि। या अजतठरक्त उच्च तिाि (ईएचटी) अजििाय षआउटेि ककसी खराबी या अन्‍दय कारण से ककसी उत्पादि इकाई या पारेर्ण सुजिधा का अजििायष रूप से बंद होिा जिसकी योििा िहीं बिाई गई है। उत्पादक कंपिी कोई भी कंपिी या जिकाय कॉपोरेट या एसोजसएिि या व्यजक्तयों का जिकाय, चाह े जिगजमत हो या िहीं, या कृजत्रम न्‍दयाजयक व्यजक्त, िो उत्पादि स्ट्टेिि का माजलक है या उसे संचाजलत करता ह ै या रखरखाि करता है। उत्पादि स्ट्टेिि जबिली पैदा करिे के जलए कोई भी स्ट्टेिि, जिसमें स्ट्टेप-अप रांसफामषर, जस्ट्िचयाडष, जस्ट्िच जगयर, केबल या अन्‍दय सहायक उपकरण के साथ कोई इमारत और संयंत्र िाजमल है, यकद कोई हो, िो उस उद्देश्य के जलए उपयोग ककया िाता ह ै और उसकी साइट, एक उत्पादि स्ट्टेिि के जलए उपयोग की िािे िाली साइट और कोई भी इमारत जिसका उपयोग उत्पादि स्ट्टेिि के ऑपरेटटंग कमषचाठरयों के आिास के जलए ककया िाता है और िहां पि-जबिली उत्पन्न की िाती है, इसमें पेिस्ट्टॉक, हडे और टेल कायष, मुख्य और जियामक िलािय, बांध और अन्‍दय हाइड्रोजलक कायष िाजमल हैं, लेककि ककसी भी सबस्ट्टेिि िाजमल िहीं होता ह।ै जिड आपस में िुडी पारेर्ण लाइिों, सब स्ट्टेििों और उत्पादि संयंत्रों की उच्च िोल्टेि बैक बोि प्रणाली। राज्य जिड कोड ये जिजियम केंर िाजसत प्रदिे िम्मू और कश्मीर ि केंर िाजसत प्रदिे लद्दाख के जलए जबिली व्यिस्ट्था की योििा और संचालि के दिषि और जिम्मेदाठरयों को जिर्दष्टष करते ह।ैं लोडतीय जिद्यतु जिड कोड लोडतीय जिद्युत जिड कोड (आईईिीसी), अजधजियम की धारा 79 की उपधारा (1) के खंड (एच) के (आईईिीसी) अंतगषत केंरीय आयोग द्वारा जिर्दष्टष । जिड मािक अजधजियम की धारा 73 के खंड (डी) के अंतगषत केंरीय जिद्युत प्राजधकरण द्वारा जिर्दष्टष जिड मािक। उच्च िोल्टेि (एचिी) या उच्च प्राजधकरण द्वारा अिुमत प्रजतित जभन्नता के अधीि सामान्‍दय पठरजस्ट्थजतयों में िोल्टेि 400 िोल्ट स े तिाि (एचटी) अजधक और 33000 िोल्ट से कम होती ह।ै स्ट्ितत्रं जिद्यतु उत्पादक पािर स्ट्टेिि का स्ट्िाजमत्ि एक उत्पादक के पास ह ै िो जबिली और जबिली जिभाग का जहस्ट्सा िहीं ह।ै लोडतीय मािक िे मािक और जिदिे िो लोडतीय मािक ब्यूरो द्वारा अिुमोकदत ह।ैं रासं फामरष उपकरण करंट रांसफामषर (सीटी), िोल्टेि रांसफामषर (िीटी) और कैपेजसटर िोल्टेि रांसफामषर (सीिीटी); इंटरकिले क्टंग रासं फामरष जिजभन्न िोल्टेि प्रणाजलयों की ईएचिी लाइिों को िोडिे िाला रांसफामषर।4 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] इंटरफेस मीटर जिजभन्न िोल्टेि प्रणाजलयों की ईएचिी लाइिों को िोडिे िाला रांसफामषर। जबिली के लेखांकि और जबललंग के जलए उपयोग ककया िािे िाला एक मीटर, िो उत्पादक कंपिी, लाइसेंसधारी और उपभोक्ताओं की जिद्युत प्रणाजलयों के बीच अंतरसंबंध के लबंद ु पर िुडा होता है, िो सीधे अंतर-राज्य पारेर्ण प्रणाली या इंरा-स्ट्टेट पारेर्ण प्रणाली से िुडा होता है, जिसे एबीटी के अंतगषत किर ककया िािा ह ैऔर जिसे उपयुक्त आयोग द्वारा खुली पहुंच की अिुमजत दी िाती ह।ै अतं रराज्यीय पारेर्ण प्रणाली अंतर-राज्यीय पारेर्ण प्रणाली में जिम्न िाजमल ह:ैं i) एक राज्य के क्षेत्र से दसू रे राज्य तक मुख्य पारेर्ण लाइि के माध्यम से जबिली पहुचं ािे की कोई प्रणाली; ii) एक हस्ट्तक्षेप करिे िाले राज्य के क्षेत्र में जबिली का पठरिहि और साथ ही एक राज्य के अंदर पठरिहि, िो जबिली के ऐसे अंतर-राज्य संचरण के जलए प्रासंजगक है। iii) केंरीय पारेर्ण यूठटजलटी द्वारा जिर्मतष , स्ट्िाजमत्ि, संचालि, रखरखाि या जियंत्रण िाले राज्य के क्षेत्र के अंदर जबिली का पारेर्ण। अतं रराज्यीय पारेर्ण प्रणाली अंतर-राज्य पारेर्ण प्रणाली के अलािा जबिली के पारेर्ण के जलए कोई भी प्रणाली। आइसोलिे ि जसस्ट्टम के िेर् भाग से ईएचिी/एचिी उपकरण का आइसोलेिि जिसमें िह ईएचिी/एचिी उपकरण जस्ट्थत ह।ै कम मागं की अिजध कदि की िह अिजध िब जिद्युत ऊिाष की मांग सबसे कम होती ह।ै लाइससें अजधजियम की धारा 14 के अंतगषत कदया गया लाइसेंस। लाइससें धारी इसका अथष ह ैिह व्यजक्त जिसे अजधजियम की धारा 14 के अंतगषत लाइसेंस कदया गया ह।ै लोड संदभष के अिुसार सकक्रय, प्रजतकक्रयािील या स्ट्पष्ट जबिली जिसे उत्पन्न, प्रसाठरत या जितठरत ककया िाता ह।ै कम िोल्टेि या एल.िी 440 िोल्ट तक की िोल्टेि मख्ु य मीटर एक मीटर जिसका उपयोग मुख्य रूप से जबिली के लेखांकि और जबललंग के जलए ककया िाएगा। मख्ु य सुरक्षा एक सुरक्षा उपकरण या प्रणाली से खराबी जििारण िुरू करिे या ककसी असामान्‍दय जस्ट्थजत को समाप्त करिे की कायषिाही में प्राथजमकता अपेक्षा की िाती ह।ै ओपि एक्ससे उपयुक्त आयोग द्वारा जिर्दष्टष जियमों के अिुसार ककसी भी लाइसेंसधारी या उपभोक्ता या उत्पादि म ें लगे व्यजक्त द्वारा पारेर्ण लाइिों या जितरण प्रणाजलयों या ऐसी लाइिों या जसस्ट्टम से िुडी सुजिधाओं के उपयोग के जलए गैर-भेदभािपूणष प्रािधाि। सचं ालि ककसी जसस्ट्टम के संचालि से संबंजधत एक जिधाषठरत या योििाबद्ध कायषिाही। पठरचालि प्रकक्रया ककसी किेलक्टंग साइट पर या उससे पलांट और/या उपकरण के िास्ट्तजिक संचालि के संबंध में सुरक्षा जियमों और संयंत्र और उपकरण के स्ट्थािीय और दरू स्ट्थ संचालि दोिों के जलए िारी प्रबंधि जिदिे और प्रकक्रयाएं आउटेि पारेर्ण या जितरण या उत्पादि सुजिधा की मरम्मत और रखरखाि या सहायक प्रणाली में खराबी के कारण उपलब्धता में पूणष या आंजिक जिजियमि। आजं िक लोड एक उत्पादि स्ट्टेिि की जस्ट्थजत, िो लोड तो ह ैलेककि अपिी घोजर्त उपलब्धता पर िहीं चल रहा ह।ै आजं िक िटडाउि जसस्ट्टम के एक जहस्ट्से के बंद होिे से या तो बाहरी किेक्िि से या जसस्ट्टम के स्ट्िस्ट्थ जहस्ट्से से जबिली की आपूर्तष जिफल हो िाती है। चरम अिजध कदि की िह अिजध िब जिद्युत ऊिाष की मांग सबसे अजधक होती ह।ै व्यजक्त कोई भी कंपिी या जिकाय कॉपोरेट या संघ या व्यजक्तयों का जिकाय, चाह े जिगजमत हो या िहीं, या कृजत्रम न्‍दयाजयक व्यजक्त। योििाबद्ध कटौती उत्पादि संयंत्र या पारेर्ण प्रणाली का जहस्ट्सा, या एसएलडीसी द्वारा समजन्‍दित उपयोगकताष जसस्ट्टम का जहस्ट्सा का आउटेि। ऊिा षघटक सकक्रय जबिली से (ककलो िाट) से प्रत्यक्ष जबिली (केिीए) का अिुपात। जिद्यतु प्रणाली जिद्युत प्रणाली का अथष है जबिली के उत्पादि, पारेर्ण, जितरण और आपूर्तष के सभी पहलू और इसमें जिम्नजलजखत में से एक या अजधक िाजमल हैं: क) उत्पादि स्ट्टेिि ख) पारेर्ण या मुख्य पारेर्ण लाइिें ग) सब-स्ट्टेिि[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 5 घ) टाई-लाइिें ङ) लोड प्रेर्ण गजतजिजधयाँ च) मेि या जितरण मेि छ) जिद्युत आपूर्तष लाइिें ज) ओिरहेड लाइिें झ) सर्िषस लाइिें ञ) कायष सरु क्षा ककसी जसस्ट्टम पर असामान्‍दय जस्ट्थजतयों का पता लगािे और खराबी जििारण िुरू करिे या संकेतों या संकेतों को सकक्रय करिे के जलए योििा और उपकरण। रेटेड मगे ािाट एक ििरेटटंग मिीि का "िेम पलेट" मेगािाट आउटपुट, िह आउटपुट ह ै जिस तक ििरेटटंग मिीि को संचाजलत करिे के जलए जडजाइि ककया गया ह।ै प्रजतकक्रयािील ऊिा ष िोल्टेि और करंट का गुणिफल और उिके बीच फेि कोण के साइि को िोल्ट-एम्पीयर प्रजतकक्रयािील और उसके मािक गुणकों की इकाइयों में मापा िाता है; अिरु ोधकता ष कैजपटि ििरेटटंग पलांट या पारेर्ण लाइसेंसधारी (राज्य पारेर्ण यूठटजलटी को छोडकर) या जितरण लाइसेंसधारी या थोक उपभोक्ता सजहत िेिरेटटंग कंपिी िैसा कोई व्यजक्त, िो 33 केिी से अजधक िोल्टेि स्ट्तर पर जिड में अपिे िए या जिस्ट्ताठरत जिद्युत संयंत्र का किेक्िि की मांग कर रहा है। सरु क्षा जियम संयंत्र/उपकरण पर काम करिे िाले व्यजक्तयों की सुरक्षा सुजिजित करिे के जलए उपयोगकताषओं और पारेर्ण लाइसेंसधारी द्वारा बिाए गए जियम। चाल ूकरिा ककसी उत्पादि इकाई को िटडाउि से लसंक्रोिस गजत में लािे की कक्रया। राज्य उत्पादि स्ट्टेिि उत्पादि संयंत्र को समय-समय पर सीईआरसी द्वारा िारी आईईिीसी के अिुसार एसएलडीसी द्वारा जिधाषठरत ककया िािा आिश्यक ह।ै राज्य पारेर्ण उपयोजगता इसका अथष ह ै धारा 39 की उपधारा (1) के अंतगषत उपयुक्त सरकार द्वारा जिर्दष्टष बोडष या सरकारी कंपिी। सब स्ट्टेिि पारेर्ण या जितरण के जलए जबिली को बदलिे या पठरिर्तषत करिे के जलए स्ट्टेिि और इसमें रांसफामषर, कििटषर, जस्ट्िचजगयर, कैपेजसटर, लसंक्रोिस कंडेिसर, संरचिाएं, केबल और अन्‍दय सहायक उपकरण और उस उद्देश्य के जलए उपयोग की िािे िाली कोई भी इमारत और उसकी साइट िाजमल ह।ै पयषिक्षे ी जियत्रं ण और डेटा संचार ललंक और डेटा प्रोसेलसंग जसस्ट्टम, िो अपेजक्षत पयषिेक्षी और जियंत्रण कायों के कायाषन्‍दियि को अजधिहण या (एससीएडीए) सक्षम करिे के जलए िािकारी प्रदाि करते हैं। आपर्ू तकष ता ष कोई भी उत्पादि कंपिी या लाइसेंसधारी जिसके जसस्ट्टम स े जबिली ककसी अन्‍दय उत्पादि कंपिी या लाइसेंसधारी या उपभोक्ता के जसस्ट्टम में प्रिाजहत होती ह ै लसक्रं ोिाइज िे जस्ट्थजतया ँिहां एक आिे िाली उत्पादि इकाई या जसस्ट्टम ककसी अन्‍दय जसस्ट्टम के बस बार स ेिुडा होता ह ै ताकक उस उत्पन्न करिे िाली इकाई या जसस्ट्टम की आिृजत्तयों और फेि संबंध, िैसा भी मामला हो, और जिस जसस्ट्टम से िह िुडा हुआ ह ैिह समाि हो। पारेर्ण लाइससें धारी पारेर्ण लाइिें स्ट्थाजपत करिे और संचाजलत करिे के जलए अजधकृत एक लाइसेंसधारी पारेर्ण लाइि सभी उच्च दबाि िाली केबल और ओिरहडै लाइिें (िो एक लाइसेंसधारी के जितरण जसस्ट्टम का आिश्यक भाग िहीं होती) िो एक उत्पादि स्ट्टेिि से दसू रे उत्पादि स्ट्टेिि तक या एक सबस्ट्टेिि तक जिद्युत का प्रसारण करती ह,ैं जिसमें कोई भी स्ट्टेप-अप और स्ट्टेप डाउि रांसफामषर, जस्ट्िच जगयर और अन्‍दय काय षिाजमल होते ह ैंजििका प्रयोग इस प्रकार की केबलों या ओिरहडै लाइिों को जियजं त्रत करिे के जलए ककया िाता ह,ै और ऐसे भििों या उिके जहस्ट्सों के जलए प्रयोग की िाती ह ैंजििकी आिश्यकता इस प्रकार के रांसफामषरों, जस्ट्िच जगयर और अन्‍दय कायों के जलए हो सकती ह।ै प्रसारण प्रणाली उत्पादि स्ट्टेिि से जितरण प्रणाली के साथ किेक्िि लबंद/ुइंटरफेस लबंद ुतक जिद्युत ऊिाष के संचरण के जलए जिद्युत उप-स्ट्टेििों सजहत पारेर्ण लाइसेंसधारी की उच्च दबाि केबल और ओिरहेड लाइिों से युक्त प्रणाली। इसमें जितरण प्रणाली का कोई भी भाग िाजमल िहीं होगा। अडं र फ़्रीक्वेंसी ठरल े एक जिद्युत मापिे िाला ठरले िो तब संचाजलत होता ह ैिब इसकी जििेर्ता मात्रा आिृजत्त में कमी स े ठरले सेटटंग्स तक पहुचं िाती है।6 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] उपयोगकता ष कैजपटि उत्पादि पलांट या पारेर्ण लाइसेंसधारी (एसटीयू के अलािा) या जितरण लाइसेंसधारी या राज्य के अंदर थोक उपभोक्ता सजहत एक उत्पादि कंपिी िैसे एक व्यजक्त, जिसका जिद्युत संयंत्र 33 केिी से अजधक िोल्टेि स्ट्तर पर इंरा-स्ट्टेट पारेर्ण प्रणाली से िुडा हुआ ह।ै 2 इि जिजियमों में प्रयक्तु और पठरभाजर्त िहीं ककए गए लेककि अजधजियम में पठरभाजर्त िब्दों और अजभव्यजक्तयों के िही अथष होंगे िो उन्‍दह ेंअजधजियम में कदए गए ह।ैं यहां प्रयुक्त अजभव्यजक्तयां, लेककि िो इि जिजियमों या अजधजियम में जििेर् रूप स े पठरभाजर्त िहीं हैं, लेककि सक्षम जिधाजयका द्वारा पाठरत ककसी भी कािूि के अंतगतष पठरभाजर्त ह ैंऔर राज्य में जबिली उद्योग पर लागू होती ह,ैं उिका िही अथ ष होगा िो उन्‍दह ें ऐस े कािूि म ें कदया गया ह।ै उपरोक्त के अधीि, यहां प्रयुक्त अजभव्यजक्तयां, लेककि इि जिजियमों या अजधजियम या ककसी सक्षम जिधाजयका द्वारा पाठरत ककसी कािूि म ें जििेर् रूप स े पठरभाजर्त िहीं की गई ह,ैं उिका िही अथ ष होगा िो आम तौर पर जबिली उद्योग में प्रयोग ककया िाता ह।ै 3 संजक्षप्त िब्द एबीटी उपलब्धता आधाठरत टैठरफ बीआईएस लोडतीय मािक ब्यूरो बीएस जिठटि मािक सीईए केंरीय जिद्युत प्राजधकरण सीईआरसी केंरीय जिद्युत जियामक आयोग सीपीपी कैजपटि पािर पलांट सीटी करंट रांसफामषर सीटीय ू सेंरल पारेर्ण यूठटजलटी ईएचटी अजतठरक्त उच्च तिाि एचटी उच्च तिाि आईसीटी इंटर किेलक्टंग रांसफामषर आईईसी अंतरराष्ट्रीय इलेक्रो-तकिीकी आयोग मािक आईईिीसी लोडतीय जिद्युत राज्य जिड कोड आईपीपी स्ट्ितंत्र जिद्युत उत्पादक आईएसटीएस अंतरराज्यीय पारेर्ण प्रणाली केिी ककलो िोल्ट एलएसपी लाइि जक्लयर परजमट एिएबीएल राष्ट्रीय परीक्षण एिं अंिांकि प्रत्यायि बोडष प्रयोगिालाएँ पीिीसीआईएल इंजडया जलजमटेड का पािर जिड कॉपोरेिि। पीटीडब्लू कायष करिे की अिुमजत आरएलडीसी क्षेत्रीय लोड प्रेर्ण केंर एससीएडीए पयषिेक्षी केंरी और डेटा अजधिहण एसिीसी राज्य जिड कोड एसिीएस राज्य उत्पादि स्ट्टेिि[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 7 एसएलडीसी राज्य लोड प्रेर्ण केंर एसटीएस राज्य पारेर्ण प्रणाली एसटीय ू राज्य पारेर्ण उपयोजगता िीटी िोल्टेि रांसफॉमषर 1.3 पठरचय 1 राज्य जिड कोड केंर िाजसत प्रदेि िम्मू और कश्मीर ि केंर िाजसत प्रदेि लद्दाख में समय-समय पर संिोजधत केंरीय जिद्युत जियामक आयोग (सीईआरसी) द्वारा िारी लोडतीय जिद्युत जिड कोड (आईईिीसी) के प्रािधािों के अिुसार और राष्ट्रीय जिद्युत िीजत के अिरूु प संबंजधत क्षेत्रीय जिड के साथ समन्‍दिय में एक कुिल और समजन्‍दित जबिली प्रणाली को संचाजलत करि े और बिाए रखिे के जलए राज्य पारेर्ण प्रणाली के सभी उपयोगकताओंष द्वारा पालि ककए िाि े िाले जियमों, कदिाजिदेिों और मािकों को जिधाषठरत करता ह।ै 2 राज्य पारेर्ण यठू टजलटी: केंर िाजसत प्रदेि िम्म ू और कश्मीर और केंर िाजसत प्रदेि लद्दाख का प्रिासि अपि े संबंजधत जबिली जिभागों को, जिन्‍दह ें जिद्युत अजधजियम 2003 की धारा 14 के अिुसार लाइसेंसधारी मािा िाता ह,ै राज्य पारेर्ण यूठटजलटीि (एसटीयू) के रूप में काय ष करि े के जलए सूजचत करेगा, बित े िे जबिली के व्यापार के व्यिसाय में संलग्न िहीं होंगे। राज्य पारेर्ण यूठटजलटीि जिद्युत अजधजियम, 2003 की धारा 39 (2) के अतं गतष जिधाषठरत कायों का जििषहि करेगी। 3 (क)एसएलडीसी की स्ट्थापिा: केंर िाजसत प्रदेि िम्मू और कश्मीर और केंर िाजसत प्रदेि लद्दाख का प्रिासि एक केंर स्ट्थाजपत करेगा जिसे िम्मू और कश्मीर केंर िाजसत प्रदेि और केंर िाजसत प्रदेि लद्दाख में स्ट्टेट लोड जडस्ट्पैच सेंटर (एसएलडीसी) के रूप में िािा िाएगा। राज्य लोड जडस्ट्पैच सटें र का संचालि ककसी सरकारी कंपिी या ककसी राज्य अजधजियम द्वारा या उसके अतं गषत स्ट्थाजपत या गठित ककसी प्राजधकरण या जिगम द्वारा ककया िाएगा, िैसा कक उपयुक्त सरकार द्वारा अजधसूजचत ककया िा सकता ह।ै िब तक ककसी सरकारी कंपिी या ककसी प्राजधकरण या जिगम को उपयुक्त सरकार द्वारा अजधसूजचत िहीं ककया िाता ह,ै तब तक राज्य पारेर्ण यूठटजलटी राज्य लोड जडस्ट्पैच सेंटर का संचालि करेगी। (ख) एसएलडीसी के काय:ष राज्य लोड जडस्ट्पैच सेंटर अजधजियम की धारा 32 (2) और 33 के अतं गतष जिधाषठरत कायों का जििषहि करेगा। (ग) एसएलडीसी की कार्मकष आिश्यकताओं को परू ा करिा: i. एसएलडीसी का संचालि योग्य और अिुभिी इंिीजियरों द्वारा ककया िाएगा िो राज्य पारेर्ण प्रणाली और जिड संचालि स ेअच्छी तरह पठरजचत ह।ैं ii. राज्य लोड जडस्ट्पैच सेंटर के कर्मषयों को उिके कौिल को अपडेट करिे के जलए समय-समय पर प्रजिक्षण कदया िाएगा ताकक िे अजधजियम की धारा 32 (2) और 33 के अंतगषत जिधाषठरत अपिे कायों का जििषहि करिे में सक्षम हो सकें। 1.4 राज्य जिड कोड के उद्देश्य राज्य जिड कोड राज्य पारेर्ण यूठटजलटी (एसटीयू) और उपयोगकताषओं के बीच की सीमा को जियंजत्रत करता ह ै और साथ ही उि लोगों के जलए सुजिधाओं के संचालि के जलए कदिाजिदेि स्ट्थाजपत करता ह ै िो िुडे हुए ह ैं और राज्य पारेर्ण प्रणाली का उपयोग करेंगे। यह एसटीयू और उपयोगकताषओं के बीच संबंधों को जियंजत्रत करिे िाली सूचिा आिश्यकताओं और प्रकक्रयाओं दोिों को जिधाषठरत करता ह।ै राज्य जिड कोड के प्रमुख उद्देश्य ह:ैं क. केंर िाजसत प्रदिे िम्म ू और कश्मीर ि केंर िाजसत प्रदेि लद्दाख के अंदर एसटीय,ू राज्य उत्पादि कंपजियों, जितरण लाइसेंसधाठरयों, आईपीपी / सीपीपी और राज्य जिड से िडु े खुली पहुचं िाल े िाहकों की राज्य जिड से संबजन्‍दधत भूजमकाओं, दाजयत्िों और जिम्मेदाठरयों को जिर्दष्टष करके उिके कायों में स्ट्पष्टता प्रदाि करिा। ख. जिड जस्ट्थरता म ेंसुधार करिा और जसस्ट्टम प्रदिषि के न्‍दयूितम मािकों को प्राप्त करिा। ग. दिषि के न्‍दयूितम मािकों को प्राप्त करिा।8 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] घ. िए प्रिेिकों अथाषत भजिष्य की िई उत्पादक कंपजियों, जितरण/व्यापार लाइसेंसधाठरयों, खुली पहुचं िाले िाहकों और उपभोक्ताओं के जलए पारेर्ण किेजक्टजिटी आिश्यकता को जिर्दष्टष करिा। ङ. आसाि संदभष और अिुपालि के जलए जिड संचालि में सामान्‍दय प्रथाओं का दस्ट्तािेिीकरण करिा। च. किेजक्टजिटी आिश्यकताओं को पूरा करिे के जलए ििरेटर स े उिके संयंत्र की प्रदिषि जििेर्ताओं पर डेटा प्राप्त करिा। छ. संबंजधत उपयोजगताओं के बीच सभी सूचिाओं के स्ट्पष्ट और लगातार प्रकटीकरण के जलए एक तंत्र प्रदाि करिा। ि. यह जिर्दष्टष करिा कक उत्पादि को कैसे जिधाषठरत और प्रेजर्त ककया िािा ह।ै झ. मौजखक रूप से सहमजत व्यक्त की गई बातों को िास्ट्ति म ेंलागू करिा। 1.5 प्रयोज्यता राज्य जिड कोड उि सभी उपयोगकताषओं, अिरु ोधकताषओं, राज्य पारेर्ण उपयोजगता और एसएलडीसी पर लाग ू होगा िो पारेर्ण िेटिकष स ेिुडे ह।ैं 1.6 राज्य जिड कोड का कायान्‍दष ियि: 1. राज्य पारेर्ण यूठटजलटी राज्य जिड कोड के कायाषन्‍दियि के जलए जिम्मेदार होगी। सभी उपयोगकताष इस राज्य जिड कोड के प्रािधािों का पालि करेंग े और सभी पहलओंु म ें राज्य पारेर्ण उपयोजगता की सहायता करेंगे। उपयोगकताओंष को राज्य जिड कोड के कायाषन्‍दियि के जलए आिश्यक सभी आिश्यक िािकारी प्रदाि करिी होगी। 2. यकद ककसी उपयोगकता षको राज्य जिड कोड के ककसी भी प्रािधाि का अिुपालि करि े म ेंकोई कठििाई होती ह,ै तो िह जबिा ककसी देरी के, प्रािधाि के अिपु ालि म ेंमागदष िषि के जलए राज्य पारेर्ण यूठटजलटी को सूजचत करेगा। 3. राज्य जिड कोड की प्रासंजगक धारा के प्रािधािों के अिुसार राज्य जिड कोड समीक्षा सजमजत द्वारा राज्य जिड के संचालि की जियजमत रूप से समीक्षा की िाएगी। 4. उपयोगकताष एसटीयू/एसएलडीसी को ऐसा उजचत सहयोग और सहायता प्रदाि करेंग े िैसा कक उिके द्वारा मांगा गया हो और अपेजक्षत हो। हालाँकक, एसटीयू/एसएलडीसी ऐसे सभी मामलों को समीक्षा पैिल की अगली बैिक म ें अिुसमथषि के जलए संदर्भषत करेगा। 1.7 उपयोगकता षद्वारा गरै -अिपु ालि 1. यकद कोई उपयोगकताष राज्य जिड कोड के ककसी भी प्रािधाि का अिुपालि करिे में जिफल रहता है, तो एसटीयू राज्य जिड कोड समीक्षा सजमजत को इसके गरै -अिुपालि के कारणों को जबिा दरे ी ककए सूजचत करेगा और इसका अिुपालि तुरंत सुजिजित करेगा। 2. एसएलडीसी राज्य जिड कोड समीक्षा सजमजत को एसिीसी के ककसी भी प्रािधाि के गंभीर उल्लघं ि के मामलों को और जिड संचालि की जस्ट्थरता सुजिजित करिे के जलए आिश्यक पयषिेक्षण और जियत्रं ण करिे के जलए िारी एसएलडीसी के जिदिे ों के लगातार गैर-अिुपालि की घटिाओं की ठरपोटष करेगा।. 3. राज्य जिड कोड प्रािधािों का अिुपालि करि ेम ेंलगातार जिफलता के कारण उपयोगकता षके संयंत्र और/या सुजिधाओं को जिड से अलग ककया िा सकता ह।ै उपभोक्ताओं को क्षजत के भगु ताि और मआु ििे सजहत आइसोलेिि के पठरणामों की जिम्मेदारी उस उपयोगकता षकी ह ैिो लगातार राज्य जिड कोड का उल्लघं ि करता ह।ै 1.8 कोड जिम्मदे ाठरया ँ 1. राज्य जिड कोड के अंतगषत अपिे कतषव्यों का जििषहि करिे में एसटीयू को िािकारी पर जिभषर रहिा पडता है, जिसे उपयोगकताष अपिी आिश्यकताओं और उद्देश्यों के संबंध म ेंप्रदाि करेंगे। 2. जिड संचालि के कुिल जििषहि के जलए एसएलडीसी द्वारा िारी जिदेिों का अिुपालि सुजिजित करि े के जलए एसटीय ू उपयोगकताषओं पर कडी जिगरािी रखगे ा। 1.9 गोपिीयता 1. राज्य जिड कोड की ितों के अतं गषत, एसटीयू उपयोगकताषओं से उिके उत्पादि या आपूर्तष व्यिसायों के संबंध में उिके प्रयोििों से संबंजधत िािकारी प्राप्त करेगा।[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 9 2. एसटीयू, राज्य जिड कोड द्वारा अपेजक्षत के अलािा, सूचिा प्रदाता की पूि ष जलजखत सहमजत के जबिा केंर या राज्य सरकार के अलािा ककसी अन्‍दय व्यजक्त को ऐसी िािकारी प्रदाि िहीं करेगा। 1.10 जिदेि उपयुक्त सरकार जबिली अजधजियम 2003 की धारा 37 के अिुसार राज्य के ककसी भी क्षेत्र में जबिली के सुचारू और जस्ट्थर संचरण और आपूर्त ष को बिाए रखिे के जलए आिश्यक उपाय करिे के जलए ककसी भी मामले में एसटीयू या एसएलडीसी को िीजत जिदेि िारी कर सकती ह,ै िैसा भी मामला हो। एसटीयू ऐसे जिदेिों की आिश्यकता के बारे म ें आयोग और सभी उपयोगकताओंष को तरु ंत सूजचत करेगा। उपयोगकताष, अजधजियम की प्रासंजगक धाराओं के अधीि, ऐसे सभी जिदेिों का पालि करेंगे। 1.11 लोडतीय जिद्यतु राज्य जिड कोड के साथ प्रासजं गकता यह राज्य जिड कोड आईईिीसी के अिुरूप/प्रासंजगक होगा। हालाँकक, अंतर-राज्यीय पारेर्ण से संबंजधत मामलों म,ें यकद राज्य जिड कोड का कोई भी प्रािधाि आईईिीसी के प्रािधािों के साथ असंगत है, तो सीईआरसी द्वारा अिुमोकदत आईईिीसी के प्रािधाि लाग ूहोंगे। 1.12 जिद्यतु जिभाग एक एकीकृत उपयोजगता के रूप म ें एसटीयू, एसएलडीसी, उत्पादि स्ट्टेिि और जितरण लाइसेंसधाठरयों के कायष जबिली जिभाग द्वारा अजधकृत संबंजधत अजधकाठरयों द्वारा ककए िाएगं ,े िब तक यह एक एकीकृत उपयोजगता के रूप म ेंकायष करिा िारी रखता ह।ै 1.13 केंर िाजसत प्रदेि िम्म ूऔर कश्मीर ि केंर िाजसत प्रदिे लद्दाख जिड कोड की सरं चिा केंर िाजसत प्रदिे िम्मू और कश्मीर ि केंर िाजसत प्रदिे लद्दाख के जलए राज्य जिड कोड म ें जिम्नजलजखत अध्याय िाजमल ह:ैं अध्याय-1: सामान्‍दय; अध्याय-2: राज्य जिड कोड का प्रबंधि अध्याय-3: जसस्ट्टम योििा; अध्याय-4: किेक्िि की ित;ें अध्याय-5: जसस्ट्टम सुरक्षा पहल;ू अध्याय-6: कफ्रक्वेन्‍दसी और िोल्टेि जियंत्रण; अध्याय-7: संरक्षण; अध्याय-8: संचालि योििा; अध्याय-9: उत्पादि और जिकासी की जिगरािी; अध्याय-10: आउटेि योििा; अध्याय-11: आकजस्ट्मकता योििा; अध्याय-12: उपयोगकताषओं के मध्य सीमा सुरक्षा; अध्याय-13: पठरचालिात्मक घटिा की सूचिा ठरपोर्टिंग; अध्याय-14: िेड्यूललगं और लोड प्रर्े ण; अध्याय-15: जमटटरंग ; अध्याय-16: सुरक्षा और लाइि जक्लयर परजमट; अध्याय-17: डेटा पंिीकरण; अध्याय-18: जिजिध.10 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] अध्याय-2 राज्य जिड कोड का प्रबधं ि 2.1 उद्देश्य राज्य पारेर्ण यूठटजलटी (एसटीयू) को राज्य जिड कोड को लागू करिे और उसका अिुपालि करिे और आयोग की मंिूरी के साथ समय-समय पर समीक्षा और संिोधि करिे की आिश्यकता होती ह।ै िैसा कक इस अध्याय में आिश्यक ह,ै एसटीयू द्वारा एक राज्य जिड कोड समीक्षा सजमजत का गिि ककया िाएगा, जिसमें पारेर्ण प्रणाली के उपयोगकताषओं के प्रजतजिजध िाजमल होंगे। 2.2 राज्य जिड कोड समीक्षा सजमजत 1. राज्य जिड कोड समीक्षा सजमजत प्रत्येक एसटीयू द्वारा अलग से स्ट्थाजपत की िाएगी। 2. राज्य जिड कोड समीक्षा सजमजत का अध्यक्ष एसटीयू का एक इंिीजियर होगा िो कायषकारी इंिीजियर के पद से िीच े का िहीं होगा। समीक्षा सजमजत के सदस्ट्य सजचि को भी एसटीयू द्वारा िाजमत ककया िाएगा। समीक्षा सजमजत म ें संबंजधत संगििों के प्रमुखों द्वारा अिुिंजसत जिम्नजलजखत सदस्ट्य िाजमल होंगे: क. पारेर्ण लाइसेंसधारी की तरफ से कायषकारी स्ट्तर पर एक इंिीजियटरंग प्रजतजिजध। ख. संबंजधत क्षेत्रीय लोड प्रर्े ण केंर से कायषकारी स्ट्तर पर एक प्रजतजिजध ग. राज्य लोड प्रर्े ण केंर से कायषकारी स्ट्तर पर एक प्रजतजिजध। घ. राज्य के जितरण लाइसेंसधाठरयों से कायषकारी स्ट्तर पर एक प्रजतजिजध। ङ. राज्य उत्पादि कंपिी और आईपीपी से कायषकारी स्ट्तर पर एक प्रजतजिजध। च. राज्य के जबिली मामलों से िडु ा हुआ राज्य सरकार का एक सदस्ट्य। छ. आयोग द्वारा सहयोजित/िामांककत कोई अन्‍दय सदस्ट्य। 3. एसटीयू द्वारा िाजमत सदस्ट्य सजचि संयोिक होगा और िह सजमजत के कामकाि का समन्‍दिय करेगा। 4. एसटीयू सभी उपयोगकताषओं को समीक्षा सजमजत के अध्यक्ष और सदस्ट्य सजचि के िाम और पत े की िािकारी दगे ा। ककसी भी आगामी पठरितषि के बारे में एसटीयू द्वारा सभी उपयोगकताषओं को सूजचत ककया िाएगा। इसी प्रकार, प्रत्येक उपयोगकताष को समीक्षा सजमजत के सदस्ट्य सजचि को अपिे प्रजतजिजधयों के िाम और पदिाम की िािकारी देिी होगी। 2.3 राज्य जिड कोड समीक्षा सजमजत के कायष समीक्षा सजमजत के कायष इस प्रकार ह:ैं क. राज्य जिड कोड का कायाषन्‍दियि, और जिरंतर िांच और समीक्षा। ख. ककसी भी उपयोगकता ष द्वारा प्रस्ट्ताजित समीक्षा के सभी अिुरोधों पर जिचार करिा और ऐस े पठरितषिों के कारणों के साथ राज्य जिड कोड में बदलाि के जलए जसफाठरिों का प्रकािि। ग. ककसी भी उपयोगकताष द्वारा उिाई गई समस्ट्याओं पर जिचार करिा एिं समस्ट्याओं का समाधाि। घ. ककसी भी जिड में गडबडी के मामले में सुरक्षा प्रणाली की जिफलता के कारणों की समीक्षा और जिश्लेर्ण करिा और सुधार के तरीकों की जसफाठरि करिा। ङ. यह सुजिजित करिा कक राज्य जिड कोड में प्रस्ट्ताजित पठरितषि/संिोधि लोडतीय जिद्युत जिड कोड (आईईिीसी) के अिरूु प और संगत ह।ैं च. ऐसे अन्‍दय मामले िो आयोग द्वारा समय-समय पर जिदेजित ककये िायें। राज्य जिड कोड समीक्षा सजमजत आिश्यकतािुसार इस ित ष के अधीि ककतिी भी बैिकें आयोजित कर सकती है कक हर बारह (12) महीिे म ें कम से कम एक बैिक आयोजित की िाएगी। समीक्षा सजमजतयों के जिचार के जलए प्रस्ट्ताि तैयार करिे हते ु व्यजक्तगत आिश्यकताओं पर चचाष करिे के जलए एसटीयू द्वारा उपयोगकताषओं के साथ उप-बैिकें आयोजित की िा सकती ह।ैं[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 11 2.4 समीक्षा और सिं ोधि 1. राज्य जिड कोड की समीक्षा राज्य जिड कोड समीक्षा सजमजत द्वारा प्रत्येक बारह महीि े म ें कम स े कम एक बार की िाएगी 2. राज्य जिड कोड में कोई भी बदलाि राज्य जिड कोड समीक्षा सजमजत द्वारा जिचार-जिमिष और सहमजत के जबिा और आयोग द्वारा अिुमोकदत ककए जबिा िहीं ककया िाएगा। 3. राज्य जिड कोड में ककसी भी संिोधि की मांग करिे िाले उपयोगकताषओं को राज्य जिड कोड समीक्षा सजमजत के सदस्ट्य सजचि को जलजखत अिरु ोध भेििा होगा। 4. सदस्ट्य सजचि राज्य जिड कोड के जलए सभी प्रस्ट्ताजित संिोधिों को समीक्षा सजमजत के समक्ष जिचार हते ु रखेंगे। 5. समीक्षा बैिक में चचाष के बाद, राज्य जिड कोड समीक्षा सजमजत एसटीयू और आयोग को एक ठरपोटष भेिेगी, जिसमें जिम्नजलजखत के बारे म ेंिािकारी प्रदाि की िाएगी: (i) समीक्षा का पठरणाम; (ii) राज्य जिड कोड में कोई प्रस्ट्ताजित संिोधि; और (iii) उपयोगकताषओं द्वारा प्रस्ट्तुत सभी जलजखत अभ्यािेदि; 6. एसटीयू प्रस्ट्ताजित संिोधि/संिोधिों के संबंध म ें अपिी जसफाठरिों के साथ सभी संबंजधत पत्राचार के साथ अिुमोदि के जलए आयोग को ठरपोट षभेिेगा। 7. राज्य जिड कोड म ें संिोधि को आयोग द्वारा िारी जियमों के जलए अपिाई गई जिधाषठरत प्रकक्रया के माध्यम स ेआयोग द्वारा अंजतम रूप कदया िाएगा और अजधसूजचत ककया िाएगा। 8. आयोग द्वारा अिुमोदि के बाद, एसटीयू राज्य जिड कोड में सिं ोधि को प्रकाजित करेगा और सभी उपयोगकताषओं को अिुमोकदत संिोधिों की प्रजतया ंअिेजर्त करेगा। 9. एसटीयू ििीितम संिोधिों के साथ राज्य जिड कोड की प्रजतयां रखेगा और उन्‍दह ें इसकी आिश्यकता िाले ककसी भी व्यजक्त को उजचत कीमत पर उपलब्ध कराएगा। इसे यथािीघ्र िेबसाइट पर भी उपलब्ध कराया िा सकता ह।ै यह सुजिजित करिे के जलए कक राज्य जिड कोड का ििीितम संस्ट्करण सभी संबंजधतों तक पहुचं े, एसटीयू राज्य जिड कोड की सभी प्रजतयों के प्राप्तकताषओं की एक अपडेट की गई सूची रखेगा। 10. आयोग, उपयोगकताष के आिदे ि पर या अन्‍दयथा आिश्यकता पडिे पर राज्य जिड कोड समीक्षा सजमजत की आपातकालीि बैिक बलु ा सकता ह ै और राज्य जिड कोड म ें ऐसे पठरितषि या संिोधि कर सकता ह ै िैसा िह उजचत समझे। अध्याय-3 जसस्ट्टम योििा 3.1 उद्देश्य यह अध्याय भजिष्य की मांग की आिश्यकताओं को परू ा करि े के जलए एक कुिल, समजन्‍दित, सुरजक्षत और ककफायती राज्य पारेर्ण प्रणाली सुजिजित करिे के जलए उपयोगकताषओं के परामिष से एसटीयू को सक्षम करिे के जलए 'जसस्ट्टम पलालिंग' के जलए प्रकक्रयाएं तैयार करता ह।ै 3.2 राज्य पारेर्ण प्रणाली का जिकास 1. राज्य पारेर्ण प्रणाली का सुदढृ ीकरण या जिस्ट्तार कई कारणों से होता ह ैजििमें स ेकुछ का उल्लेख िीच ेककया गया ह:ै i. राज्य पारेर्ण प्रणाली से पहले से िुडे उपयोगकताष के जसस्ट्टम पर होि े िाले जिकास/पठरितिष । ii. उपयोगकताष के जसस्ट्टम और राज्य पारेर्ण प्रणाली के बीच एक िए किेक्िि लबंद ुकी िरुु आत। iii. राज्य के अंदर या बाहर उत्पादि स्ट्टेििों से जबिली की जिकासी की प्रणाली iv. ठरएजक्टि पािर का मआु ििा। v. मांग में सामान्‍दय िृजद्ध को समायोजित करिे के जलए जसस्ट्टम क्षमता बढािे, पठरचालि संबंधी बाधाओं को दरू करि े और सुरक्षा के मािकों को बिाए रखिे की आिश्यकता।12 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] vi. क्षजणक और जस्ट्थर अिस्ट्था जस्ट्थरता संबंधी मामले। vii. उपरोक्त के ककसी भी संयोिि का संचयी प्रभाि। viii. राज्य पारेर्ण प्रणाली में पठरितषि लािे की कोई अन्‍दय आिश्यकता। राज्य पारेर्ण प्रणाली के सुदढृ ीकरण या जिस्ट्तार म ें उपयोगकताष के राज्य पारेर्ण प्रणाली में प्रिेि या जिकास लबंद ु(किेक्िि लबंद)ु पर काम िाजमल हो सकता ह।ै 2. राज्य पारेर्ण प्रणाली के जिकास की योििा पहल े स े बिाई िािी चाजहए ताकक सहमजत और रास्ट्ता सुजिजित ककया िा सके और जिस्ट्तृत इंिीजियटरंग जडिाइि/जिमाणष कायष पूरा ककया िा सके। जियोिि कोड इस आिय से एसटीयू और उपयोगकताषओं के बीच आिश्यक िािकारी के आदाि-प्रदाि के जलए समय सीमा जिधाषठरत करता ह।ै 3.3 जियोिि िीजत 1. एसटीयू राज्य पारेर्ण प्रणाली के जलए अगल े 10 िर्ों के जलए एक पठरप्रेक्ष्य पारेर्ण योििा जिकजसत करेगा। लोड अिुमािों, उत्पादि क्षमता िृजद्ध आकद में ककसी भी संिोधि/संिोधि का ध्याि रखिे के जलए इि पठरप्रेक्ष्य पारेर्ण योििाओं को हर साल अपडेट ककया िाएगा। पठरप्रेक्ष्य योििाओं को अिुमोदि के जलए आयोग को प्रस्ट्तुत ककया िाएगा। 2. एसटीयू राज्य पारेर्ण प्रणाली को मिबूत करिे और जिस्ट्तार की योििा बिािे के जलए िेटिकष अध्ययि करेगा और खराबी स्ट्तरों की समीक्षा करेगा। 3. एसटीयू योििा में जिम्नजलजखत चरणों का पालि करेगा: i. जितरण लाइसेंसधाठरयों द्वारा प्रदाि ककए गए लोड पूिाषिुमािों के आधार पर आपूर्त ष के क्षत्रे म ें जबिली की मांग का पूिाषिुमाि लगािा। इिमें मांग पूिाषिुमाि, डेटा पद्धजत और उि मान्‍दयताओं का जििरण िाजमल होगा जिि पर पूिाषिुमाि आधाठरत ह।ैं इि पिू ाषिुमािों की िार्र्षक समीक्षा की िाएगी और िब भी मौिदू ा प्रणाली में बडे बदलाि की आिश्यकता होगी अपडेट ककया िाएगा। ii. उपरोक्त लोड पूिाषिुमाि और उत्पादि योििा, आिश्यक ठरएजक्टि पािर (िीएआर) मआु ििे आकद के अिरूु प राज्य पारेर्ण प्रणाली के जलए एक पारेर्ण योििा तैयार करिा। iii. ऊिाष और चरम मांग दोिों को पूरी तरह स े पूरा करि े के जलए राज्य पारेर्ण प्रणाली जिस्ट्तार के जलए एक दीघषकाजलक (10 िर्ष) योििा तैयार करिा और आयोग को प्रस्ट्तुत करिा। iv. अंतर-क्षेत्रीय योििाओं सजहत प्रमुख अतं रराज्यीय पारेर्ण प्रणाली की पहचाि के जलए 5 साल की अजिम अिजध के अिुरूप िार्र्षक योििा को अंजतम रूप दिे े के जलए सीटीयू को पूण ष सहायता देिा िो सीईए द्वारा जिकजसत दीघषकाजलक योििा के साथ कफट होगी। v. राज्य पारेर्ण यूठटजलटी, पारेर्ण प्रणाली योििा में अिुमाजित अंतर-राज्य पारेर्ण योििाओं और जसस्ट्टम सुदढृ ीकरण योििाओं के आधार पर अपिी जििेि योििा भी प्रस्ट्तुत करेगी। vi. इस जिजियमि के अिुसार ककए गए पारेर्ण प्रणाली योििा अध्ययि की लागत को राज्य पारेर्ण उपयोजगता के िुल्क के जिधाषरण म ेंअिुमजत दी िाएगी 4. सभी उपयोगकताषओं को राज्य जिड कोड की अजधसूचिा की जतजथ स े 6 महीिे के अंदर डेटा पंिीकरण अध्याय के पठरजिष्ट क और पठरजिष्ट ख के अिुसार जिधाषठरत योििा डेटा एसटीयू को आपूर्तष करिी होगी और उसके बाद ऐसा डेटा सक्षम करि े के जलए हर साल 31 माचष तक प्रस्ट्तुत ककया िाएगा। एसटीयू को अगले 5 िर्ों के जलए प्रत्येक िर् ष 30 जसतंबर तक अपडेिि योििा तैयार करिी होगी और अंजतम रूप देिा होगा। 3.4 योििा मािदंड 1. जियोिि उस मािक सुरक्षा जसधान्‍दत पर आधाठरत होगा जिस पर इंटर स्ट्टेट पारेर्ण प्रणाली (आईएसटीएस) और स्ट्टेट पारेर्ण प्रणाली (एसटीएस) दोिों की योििा बिाई गई ह।ै सुरक्षा दिषि समय-समय पर संिोजधत सीईए (जिड मािक) जिजियम 2010 में सीईए द्वारा जिधाषठरत पारेर्ण योििा मािदंड और अन्‍दय कदिाजिदेिों के अिुसार होगा। पारेर्ण प्रणाली योििा जिकजसत करते समय एसटीयू जसस्ट्टम का उजचत अध्ययि करेगा।[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 13 2. राज्य पारेर्ण प्रणाली, एक सामान्‍दय जियम के रूप म,ें जस्ट्थर राज्य संचालि के दौराि लोड िेलडंग या उत्पादि के पिु र्िषधारष ण की आिश्यकता के जबिा जिम्नजलजखत आकजस्ट्मक आउटेि का सामिा करि ेऔर सुरजक्षत रखि ेम ेंसक्षम होगा: क. 66 केिी से ऊपर और 400 केिी से कम िोल्टेि की डीसी लाइि का आउटेि, ख. 400 केिी और उससे अजधक िोल्टेि की एस/सी लाइि का आउटेि, ग. एक भी इंटर किेलक्टंग रांसफामषर का खराब होिा, घ. एचिीडीसी बाइपोल लाइि के एक पोल का खराब होिा या ङ. 765 केिी एस/सी लाइि का आउटेि। उपरोक्त आकजस्ट्मकताओं पर ककसी अन्‍दय 220 केिी डी/सी लाइि या ककसी अन्‍दय कॉठरडोर में 400 केिी एस/सी लाइि की पूिष- आकजस्ट्मकता प्रणाली म ेंकमी (योििाबद्ध आउटेि) और उसी सब-स्ट्टेिि से िहीं मािते हुए जिचार ककया िाएगा ह।ै 3. सभी उत्पादक इकाइयां अपिी प्रजतकक्रयािील क्षमता िक्रों के अंदर काम कर सकती ह ैं और िेटिकष िोल्टेि प्रोफाइल को भी जिर्दष्टष िोल्टेि सीमाओं के अंदर बिाए रखा िाएगा। 4. राज्य पारेर्ण प्रणाली (एसटीएस) जस्ट्थरता के िुकसाि के जबिा फीड में गंभीरतम एकल प्रणाली के िुकसाि का सामिा करिे म ेंसक्षम होगा। 5. उपरोक्त उप परै ा 3.4 (2) म ेंपठरभाजर्त घटिाओं म ेंसे कोई भी घटिा जिम्न का कारण िहीं बिगे ी: (i) आपूर्तष की हाजि; (ii) जिर्दष्टष सीमा से िीच ेऔर ऊपर जसस्ट्टम आिृजत्त का लंबे समय तक संचालि; (iii) अस्ट्िीकायष उच्च या जिम्न िोल्टेि; (iv) जसस्ट्टम अजस्ट्थरता; (v) आईएसटीएस/एसटीएस घटकों की अस्ट्िीकायष ओिरलोलडंग 6. सभी अजतठरक्त उच्च िोल्टेि सब-स्ट्टेििों में जिश्वसिीयता के जलए उपयुक्त संख्या (कम से कम दो) और उजचत क्षमता के रांसफामषर उपलब्ध कराए िाएंगे। एचिीडीसी सबस्ट्टेििों में, कम से कम एक अजतठरक्त कििटषर/इन्‍दिटषर रांसफामषर ककसी भी समय उपयोग के जलए तैयार रखा िाएगा। 7. एसटीयू राज्य उत्पादि स्ट्टेििों के जस्ट्िचयाडष पर प्रजतकक्रयािील जबिली खपत की आिश्यकता सजहत राज्य पारेर्ण प्रणाली की प्रजतकक्रयािील जबिली क्षजतपूर्त षके जलए योििा का अध्ययि करेगा। 3.5 योििा दाजयत्ि 1. जितरण लाइसेंसधारी के आपूर्तष क्षेत्र के अंदर लोड पिू ाषिुमाि की प्राथजमक जिम्मेदारी संबंजधत जितरण लाइसेंसधाठरयों की ह।ै जितरण लाइसेंसधारी प्रत्येक आगामी 5 िर्ों के जलए लोड की प्रत्येक श्रेणी के जलए अपि े क्षेत्रों के चरम लोड और ऊिाष पूिाषिमु ाि का जिधाषरण करेगा और पारेर्ण प्रणाली संिधषि के जलए उिके प्रस्ट्तािों ि े साथ साथ मांग पूिाषिुमाि, डेटा, कायषप्रणाली और उि धारणाओं के जििरण 31 माचष तक एसटीयू को िार्र्षक रूप से प्रस्ट्तुत करेगा जिि पर य े अिमु ाि आधाठरत ह।ैं लोड का पिू ाषिुमाि एसटीयू और जितरण लाइसेंसधाठरयों के बीच प्रचजलत और प्रस्ट्ताजित अंतर-संयोिि लबंदओंु म ें से प्रत्येक के जलए ककया िाएगा और इसम ें िार्र्षक पीक लोड और ऊिाष अिुमाि िाजमल होंगे। मांग पूिाषिुमािों को िार्र्षक रूप से या िब भी मौिूदा पूिाषिमु ािों या योििा में बड े बदलाि ककए िाएंगे,अपडेट ककया िाएगा । बडी मांग (1 मेगािाट या अजधक) िाले एकल उपभोक्ताओं की आिश्यकताओं को इंजगत करत े समय जितरण उपयोजगता/लाइसेंसधारी मांग की पूर्तष की जिजितता की जडिी के अिुसार खुद को संतष्टु करेगा। 2. उत्पादि स्ट्टेिि अगल े 5 िर्ों म ें से प्रत्येक के जलए अपि े जबिली स्ट्टेििों से जबिली जिकालिे के जलए एसटीय ू को पारेर्ण प्रस्ट्तािों म ेंिृजद्ध के जलए अपिे प्रस्ट्तािों के साथ अपिी उत्पादि क्षमता प्रदाि करेंग ेऔर इसे िार्र्षक 31 माच षतक एसटीय ूको िमा करेंगे। 3. बाहरी राज्य स्ट्टेििों से जबिली की जिकासी के जलए राज्य पारेर्ण प्रणाली को मिबूत करिे की योििा एसटीयू द्वारा िरूु14 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] की िाएगी। 3.6 योििा डेटा 1. राज्य उत्पादि कंपजियां/आईपीपी/लाइसेंसधारक पारेर्ण योििा जिकजसत करिे के उद्देश्य से एसटीयू को जिम्नजलजखत प्रकार के डेटा प्रदाि करेंगे: (i) मािक योििा डेटा (ii) जिस्ट्तृत योििा डेटा मािक योििा डेटा:- i) मािक योििा डेटा में ि े जििरण िाजमल होंगे िो उपयोगकताष/पारेर्ण लाइसेंसधारी जिकास के कारण राज्य पारेर्ण प्रणाली (एसटीएस) पर प्रभाि की िांच करि े के जलए एसटीयू के जलए सामान्‍दय रूप से पयाषप्त होिे की उम्मीद ह।ै ii) उपयोगकताष और पारेर्ण लाइसेंसधारी समय-समय पर एसटीयू को जिम्नजलजखत डेटा प्रदाि करेंग े (क) प्रारंजभक पठरयोििा योििा डेटा, (ख) प्रजतबद्ध पठरयोििा योििा डेटा और (ग) किेक्टेड पलालिगं डेटा। जिस्ट्ततृ योििा डेटा:- जिस्ट्तृत योििा डेटा में राज्य पारेर्ण प्रणाली पर उपयोगकताष/पारेर्ण लाइसेंसधारी जिकास के प्रभाि का आकलि करिे के जलए एसटीयू द्वारा आिश्यक जिस्ट्तृत डेटा िाजमल होगा। एसटीयू द्वारा अिुरोध ककए िािे पर जिस्ट्तृत योििा डेटा उपयोगकताषओं और पारेर्ण लाइसेंसधाठरयों द्वारा प्रस्ट्तुत ककया िाएगा। प्रारूप: उपरोक्त डेटा िमा करिे के प्रारूप डेटा पंिीकरण अध्याय -17 के पठरजिष्ट म ेंकदए गए ह ैं 2. इस राज्य जिड कोड की अजधसूचिा की जतजथ से छह (6) महीिे के अंदर सभी उपयोगकताषओं और पारेर्ण लाइसेंसधाठरयों द्वारा एसटीयू को एकमुश्त डेटा प्रस्ट्तुत ककया िाएगा। 3. एसटीयू सभी उपयोगकताषओं को िार्र्षक पारेर्ण योििा ठरपोटष, जिड मािजचत्र और आयोग द्वारा जिर्दष्टष कोई अन्‍दय िािकारी भी प्रदाि करेगा। 3.7 पारेर्ण योििा का कायान्‍दष ियि राज्य पारेर्ण लाइिों, इंटर-किेलक्टंग रांसफामषर, ठरएक्टर/कैपेजसटर और अन्‍दय पारेर्ण तत्िों के कायाषन्‍दियि का िास्ट्तजिक कायषक्रम संबंजधत एिेंजसयों के परामि ष स े एसटीयू द्वारा जिधाषठरत ककया िाएगा। इि कायों को संबंजधत एिेंजसयों के माध्यम से समय सीमा के अंदर परू ा करिा एसटीयू द्वारा सुजिजित ककया िाएगा। अध्याय-4: किक्ै िि की ित ें 4.1 उद्देश्य इस अध्याय का उद्देश्य जिम्नजलजखत सुजिजित करिा ह:ै 1. सभी उपयोगकताषओं और संभाजित उपयोगकताषओं के साथ समाि व्यिहार ककया िािा चाजहए। 2. स्ट्थाजपत होिे पर कोई भी िया या संिोजधत किेक्िि मौिूदा उपयोगकताषओं पर कोई प्रजतकूल प्रभाि िहीं डालेगा और िए किेक्ििों को मौिूदा उपयोगकताष किेक्िि के कारण प्रजतकूल प्रभाि िहीं पडेगा। 3. उपयोगकताषओं को लाइसेंस दाजयत्िों के अिुपालि में सहायता करिे के जलए न्‍दयूितम जडिाइि और पठरचालि मािदंड जिर्दष्टष करके स्ट्िीकायष गुणित्ता की एक प्रणाली सुजिजित की िाती ह।ै 4. सभी उपकरणों का स्ट्िाजमत्ि और जिम्मेदारी प्रत्येक साइट के जलए एक अिुसूची "(साइट जिम्मेदारी अिुसूची)" में स्ट्पष्ट रूप से जिर्दष्टष है, िहां किेक्िि बिाया गया ह।ै 4.2 राज्य पारेर्ण प्रणाली स ेकिक्े िि की प्रकक्रया 1. संबंजधत उपयोगकताष द्वारा एसटीएस से किेक्िि की िई या मौिूदा व्यिस्ट्था में संिोधि के जलए आिेदि राज्य पारेर्ण यूठटजलटी को प्रस्ट्तुत ककया िाएगा।[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 15 आिेदि का प्रारूप राज्य पारेर्ण यूठटजलटी द्वारा जिकजसत ककया िाएगा और इस राज्य जिड कोड की अजधसूचिा के दो (2) महीिे के अंदर उसके कायाषलय और उसकी िेबसाइट पर उपलब्ध कराया िाएगा। 2. उपरोक्त आिेदि जिम्नजलजखत जििरण के साथ प्रस्ट्तुत ककया िाएगा: (i) प्रस्ट्ताजित किेक्िि या संिोधि का उद्देश्य, पारेर्ण लाइसेंसधारी जिसके जसस्ट्टम से किेक्िि प्रस्ट्ताजित है, किेक्िि लबंद,ु किेक्ट ककए िािे िाले उपकरण का जििरण या पहले से िुडे उपकरण का संिोधि और प्रस्ट्ताजित किेक्िि के लाभाथी; (ii) पूणषता जतजथ सजहत जिमाषण कायषक्रम, और (iii) यहा पुजष्ट कक उपयोगकताष राज्य जिड कोड के प्रािधािों का पालि करेगा। 3. एसटीयू आिेदि की एक प्रजत पारेर्ण लाइसेंसधारी को भेिेगा जिसके जसस्ट्टम में किेक्िि मांगा िा रहा ह ै और राज्य लोड जडस्ट्पैच सेंटर को उिकी ठटपपजणयों के जलए भेिा िाएगा। 4. पारेर्ण लाइसेंसधारी, जिसके जसस्ट्टम में किेक्िि मांगा िा रहा है, ककसी भी िए किेक्िि की अिुमजत देिे से पहल े उजचत समझे िािे िाले जबिली जसस्ट्टम का अध्ययि कर सकता ह।ै 5. एसटीयू, आिेदि प्राप्त होिे के तीस (30) कदिों के अंदर और ऊपर पैरा (3) के अंतगषत जचजन्‍दहत पक्षों से प्राप्त सभी सुझािों और ठटपपजणयों पर जिचार करिे के बाद, ऐसे संिोधि या ऐसी ितों के साथ आिेदि स्ट्िीकार करेगा िैसा कक एसटीयू द्वारा जिर्दष्टष ककया िा सकता है। 6. ककसी आिेदि की स्ट्िीकृजत पर, एसटीयू सहमजत के जलए आिेदक को एक औपचाठरक प्रस्ट्ताि देगा, जिसमें आिेदक के प्रस्ट्ताि द्वारा आिश्यक राज्य पारेर्ण प्रणाली के जिस्ट्तार या सुदढृ ीकरण के जलए आिश्यक ककसी भी कायष को जिर्दष्टष ककया िाएगा। प्रस्ट्ताि की एक प्रजत संबंजधत पारेर्ण लाइसेंसधारी को भेि दी िाएगी। 7. एसटीयू, उपयोगकताष द्वारा आिश्यक ितों के अिुपालि पर, संबंजधत उपयोगकताष को सूजचत करेगा कक उसे एसटीएस से िोडा िा सकता ह।ै 8. आिेदक और संबंजधत पारेर्ण लाइसेंसधारी या एसटीयू, जिसके जसस्ट्टम में किेक्िि मांगा िा रहा है, आिेदक द्वारा प्रस्ट्ताि स्ट्िीकार करिे पर एक किेक्िि समझौते को अंजतम रूप देंगे। किेक्िि समझौते की एक प्रजत एसटीयू और एसएलडीसी को प्रदाि की िाएगी। 4.3 आिेदि की अस्ट्िीकृजत 1. एसटीयू राज्य पारेर्ण प्रणाली से किेक्िि के जलए ककसी भी आिेदि को जलजखत रूप में दिष ककए िािे िाले कारणों स े अस्ट्िीकार करिे का हकदार होगा, यकद ऐसा आिेदि राज्य जिड कोड के प्रािधािों के अिुसार िहीं है। 2. एसटीय ू द्वारा आिेदि की अस्ट्िीकृजत के संबंध में ककसी भी जििाद की जस्ट्थजत में, उपयोगकताष आयोग से संपकष कर सकता ह।ै 4.4 किक्े िि समझौता 1. एसटीयू से िुडे या किेक्िि चाहिे िाल े सभी उपयोगकताषओं को एसटीयू के साथ एक किेक्िि समझौता करिा होगा; 2. एक किेक्िि समझौते में इसके जियमों और ितों में जिम्नजलजखत िाजमल होंग:े (i) एक ितष जिसमें दोिों पक्षों को राज्य जिड कोड के प्रािधािों का अिुपालि करिे की आिश्यकता होती है। (ii) किेक्िि, तकिीकी आिश्यकताएं और िाजणजज्यक व्यिस्ट्था का जििरण। (iii) जसस्ट्टम के सुदढृ ीकरण या जिस्ट्तार, डेटा संचार आकद से उत्पन्न होिे िाले ककसी भी पूंिी संबंधी व्यय का जििरण और संबंजधत पक्षों के बीच उसका सीमांकि। (iv) िोडे िािे िाले संयंत्रों और उपकरणों का जििरण। (v) एक साइट जिम्मेदारी अिुसूची।16 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] (vi) सुरक्षा पर सामान्‍दय दिषि, कदिाजिदेि आकद। (vii) एसटीयू द्वारा उजचत समझी गई कोई अन्‍दय िािकारी। 4.5 साइट उत्तरदाजयत्ि अिसु चू ी 1. राज्य पारेर्ण प्रणाली के प्रत्येक किेक्िि के जलए जिसके जलए एक किेक्िि समझौते की आिश्यकता है, उपयोगकता ष 'साइट जिम्मेदारी अिुसूची' िामक एक िेड्यूल तैयार करेगा, जिसमें किेक्िि साइट पर स्ट्थाजपत उपकरणों के प्रत्येक आइटम के जलए जिम्नजलजखत को दिाषया िाएगा। i) उपकरण का स्ट्िाजमत्ि ii) उपकरणों के जियंत्रण की जिम्मेदारी iii) उपकरणों के रखरखाि की जिम्मेदारी iv) उपकरण के संचालि की जिम्मेदारी v) किेक्िि/इंटरफेस साइट पर ककसी भी व्यजक्त की सुरक्षा से संबंजधत सभी मामलों की जिम्मेदारी। vi) किेक्िि/इंटरफेस साइट का प्रबंधि। 2. साइट उत्तरदाजयत्ि अिुसूची की तैयारी में उपयोग ककया िािे िाला प्रारूप डेटा पंिीकरण अध्याय में पठरजिष्ट –ग म ें कदया गया है। 4.6 जसस्ट्टम प्रदििष 1. राज्य पारेर्ण प्रणाली से िुडे सभी उपकरणों का जडिाइि और जिमाषण प्रासंजगक लोडतीय मािक जिजिदेिों को पूरा करेगा। ऐसे उपकरणों के मामले में जििके जलए लोडतीय मािक जिजिदेि मौिूद िहीं हैं, उपयुक्त आईईसी, या आईईईई या अन्‍दय अंतराषष्ट्रीय मािक लागू होंगे। 2. सभी जिद्युत उपकरणों की स्ट्थापिा आईई जियम, 1956 के अिुरूप होगी िो ितषमाि में लागू ह ैं या जिद्युत अजधजियम, 2003 के अंतगषत बिाए गए िए जियमों द्वारा प्रजतस्ट्थाजपत ककए गए ह।ैं 3. मांगे गए प्रत्येक िए / संिोजधत किेक्िि के जलए एसटीयू किेक्िि लबंद,ु तकिीकी आिश्यकताओं और उपयोग ककए िाि े िाले िोल्टेि को जिर्दष्टष करेगा, और साथ ही सुरक्षा कोड (अध्याय -7) और मीटटरंग कोड (अध्याय -15) में जिर्दष्टष सुरक्षा और मीटटरंग आिश्यकताओं को जिर्दष्टष करेगा। 4. उपयोगकताष के उपकरण का इन्‍दसुलेिि समन्‍दिय लोडतीय मािकों के अिुसार लागू होगा। जस्ट्िचजगयर की टूटिे की क्षमता लोडतीय मािकों के अिुसार जिर्दष्टष से कम िहीं होगी। 5. सुरक्षा योििाएं और मीटटरंग योििाएं सुरक्षा कोड और मीटटरंग कोड अध्याय में िर्णषत अिुसार होंगी। 6. राज्य पारेर्ण प्रणाली की रेटेड आिृजत्त 50.00 हर्टिष होगी और आमतौर पर प्राजधकरण द्वारा िारी जिजियमों के अिुसार सीमा के अंदर जियंजत्रत की िाएगी। 7. उपयोगकताष एसएलडीसी और आरएलडीसी द्वारा जिधाषठरत जिड अिुिासि के अधीि होगा। 8. क्षेत्रीय जिड में जिड गडबडी की जस्ट्थजत में, एसएलडीसी िोल्टेि और आिृजत्त की सामान्‍दय सीमा के अंदर जसस्ट्टम मापदंडों को बिाए रखिे के जलए उत्तरदायी िहीं होगा। 4.7 किक्े िि लबदं /ुइंटरफेस लबदं ु 1. राज्य उत्पादि स्ट्टेिि (एसिीएस)/आईपीपी/सीपीपी:  राज्य पारेर्ण प्रणाली के साथ किेक्िि लबंद/ुइंटरफेस लबंद ु पर िोल्टेि 220/132/110/66 केिी या एसटीयू के साथ सहमजत के अिुसार हो सकता है।  िब तक एसटीयू के साथ जििेर् रूप से सहमजत ि हो, ििरेटटंग स्ट्टेिि के साथ किेक्िि लबंद ुफीडर के आउटगोइंग ढांचे से िीक पहले प्रदाि ककया गया टर्मषिल आइसोलेटर होगा।  एसिीएस उत्पादि स्ट्टेिि के अंदर प्रदाि ककए गए सभी टर्मषिलों, संचार और सुरक्षा उपकरणों का संचालि और रखरखाि करेगा।[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 17  उत्पादि स्ट्टेिि और एसटीयू प्रणाली के बीच मीटटरंग के प्रािधाि मीटटरंग कोड के अिुसार होंगे।  संबंजधत उपयोगकता षििरेटटंग स्ट्टेिि से जिकलि ेिाल ेआउटगोइंग फीडरों के ढांचे म ेंअपि ेउपकरणों का रखरखाि करेंगे। 2. जितरण लाइसेंसधारी:  स्ट्टेट पारेर्ण प्रणाली के किेक्िि पिाइंट/इंटरफेस पिाइंट पर िोल्टेि जितरण लाइसेंसधारी द्वारा जिर्दष्टष या एसटीयू के साथ सहमजत के अिुसार हो सकता है। पारेर्ण प्रणाली से सीधे िुडे ईएचिी उपभोक्ता के जलए, िोल्टेि 220 केिी या 132 केिी हो सकता है।  िब तक जितरण लाइसेंसधारी के साथ जििेर् रूप से सहमजत ि हो, एसटीयू सबस्ट्टेिि से आउटगोइंग फीडर ढांचा एसटीयू के साथ किेक्िि लबंद ुहोगा।  एसटीयू अपिे सब-स्ट्टेिि के अंदर प्रदाि ककए गए सभी टर्मषिलों, संचार और सुरक्षा उपकरणों का संचालि और रखरखाि करेगा।  जितरण लाइसेंसधारी और एसटीयू जसस्ट्टम के बीच मीटटरंग के प्रािधाि मीटटरंग कोड के अिुसार होंगे।  संबंजधत उपयोगकताष एसटीयू सब-स्ट्टेिि से जिकलिे िाले फीडरों की आउटगोइंग ढांचे के बाद अपिे उपकरणों का रखरखाि करेंगे। 3. क्षत्रे ीय पारेर्ण प्रणाली:  किेक्िि, सुरक्षा योििा, मीटटरंग योििा और िोल्टेि आईईिीसी के प्रािधािों के अिुसार होंगे। 4. ईएचिी उपभोक्ता और ओपि एक्सेस िाहक:  िोल्टेि 220/132/110/66 केिी या एसटीयू के साथ सहमजत के अिुसार हो सकता है।  किेक्िि लबंद ु उिके पठरसर में फीडर ढांचे के िीक पहले होगा। जमटटरंग पॉइंट उिके जसस्ट्टम के साथ किेक्िि लबंद/ुइंटरफेस लबंद ुहोगा। 4.8 ििीकरणीय ऊिा षउत्पादि स्ट्टेिि की जिड स ेकिेजक्टजिटी ििीकरणीय ऊिा षकी किजे क्टजिटी के जलए सामान्‍दय ितें ििीकरणीय स्रोतों की किेजक्टजिटी के जलए सामान्‍दय ितें राज्य के जितरण स्ट्तर (33 केिी से अजधक िहीं) या पारेर्ण स्ट्तर (33 केिी से ऊपर) पर िोडी िा सकती हैं, जिन्‍दह ेंआिश्यकता पडिे पर संिोजधत ककया िा सकता ह।ै 4.9 डेटा आिश्यकताएँ:  उपयोगकताष डेटा पंिीकरण अध्याय में जिर्दष्टष अिुसार एसटीयू को डेटा प्रदाि करेंगे।  िब तक किेक्िि समझौते में अन्‍दयथा सहमजत ि हो, डेटा पारेर्ण और संचार के जलए उपकरण का संचालि और रखरखाि उस उपयोगकता षद्वारा ककया िाएगा जिसके पठरसर में यह उसके स्ट्िाजमत्ि के जबिा स्ट्थाजपत ककया गया ह।ै अध्याय - 5: जसस्ट्टम सरु क्षा पहल ू 5.1 उद्देश्य सभी उपयोगकताष अपि-े अपि े जबिली जसस्ट्टम और उत्पादि स्ट्टेििों को हर समय एक-दसू रे के साथ तालमले म ें संचाजलत करि े का प्रयास करेंग,े ताकक राज्य जिड लसंक्रिाइज जसस्ट्टम और संबंजधत क्षेत्रीय जिड के एकीकृत जहस्ट्से के रूप म ें काम करे। एसटीयू अतं रराज्यीय ललंक को इस तरह से संचाजलत करि े का प्रयास करेगा कक आिश्यकता पडि े पर जबिली का हस्ट्तांतरण सुचारू रूप स े ककया िा सके। जबिली प्रणाली की सुरक्षा और जबिली उपकरणों की सुरक्षा को आर्थषक रूप से इष्टतम संचालि की तलु िा म ें प्राथजमकता दी िाएगी। 5.2 क्षत्रे जसस्ट्टम सुरक्षा उपयोगकताओंष सजहत संपूणष इंटर-किेक्टेड पािर जसस्ट्टम से संबंजधत ह।ै राज्य पारेर्ण प्रणाली के संचालि का पयषिेक्षण और जिजियमि आरएलडीसी के जिदेिािुसार एसएलडीसी द्वारा ककया िाएगा।18 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 5.3 जसस्ट्टम सरु क्षा 1. सभी जस्ट्िलचंग ऑपरेिि, चाह े िे मैन्‍दयुअल रूप स े प्रभाजित हों या स्ट्िचाजलत, जिम्न के िीजत कदिाजिदेिों पर आधाठरत होंगे: i) आईईिीसी ii) आईई जियमों के अंतगषत आरएलडीसी के जिदेि/कदिाजिदेि iii) राज्य जिड कोड 2. राज्य पारेर्ण प्रणाली का कोई भी जहस्ट्सा जिम्नजलजखत ितों को छोडकर िािबूझकर एकीकृत जिड से अलग िहीं ककया िाएगा; i) आपातकालीि पठरजस्ट्थजतयों म,ें जिसमें इस तरह के आइसोलिे ि से जिड को पूरी तरह ध्िस्ट्त होिे से रोका िा सकेगा और/या जबिली आपूर्तष की िीघ्र बहाली संभि हो सकेगी ii) िब ककसी महगं े उपकरण को गभं ीर क्षजत होिा संभि हो और इस तरह के आइसोलिे ि से इस े रोका िा सकता हो और iii) िब इस तरह के आइसोलिे ि का जििेर् रूप से एसएलडीसी द्वारा जिदेि कदया गया हो। 3. आपातकालीि जस्ट्थजत म ें एसटीएस के ककसी भी महत्िपूण ष तत्ि को अलग करिे की जस्ट्थजत में, घटिा के बाद यथािीघ्र एसएलडीसी को सूजचत ककया िाएगा। 4. िैसे ही पठरजस्ट्थजतयाँ अिुकूल होंगी, जिड का पणू ष समन्‍दियि बहाल कर कदया िाएगा। बहाली प्रकक्रया की जिगरािी एसएलडीसी द्वारा की िाएगी। 5. ककसी भी ठरलपंग, चाह ेिह 66 केिी और उससे अजधक की पारेर्ण लाइिों या 66 केिी के पािर रांसफामषर की मैिुअल या स्ट्िचाजलत हो, ऐसी ठरलपंग के कारणों और बहाली के जलए आिश्यक संभाजित समय के साथ एसएलडीसी को िल्द से िल्द ठरपोटष की िाएगी। खराब उपकरण/लाइि को बहाल करते समय एसएलडीसी को सूजचत ककया िाएगा और मंिूरी प्राप्त की िाएगी। 6. प्रत्येक उपयोगकताष और पारेर्ण लाइसेंसधारी जिड की जिश्वसिीयता और सुरक्षा बिाए रखिे के जलए आिश्यक डेटा/सूचिा के आदाि-प्रदाि को सुजिजित करि े के जलए आंतठरक रूप स े और राज्य लोड जडस्ट्पैच सेंटर, अन्‍दय उपयोगकताषओं और अन्‍दय पारेर्ण लाइसेंसधाठरयों के साथ पयाषप्त और जिश्वसिीय संचार सुजिधा प्रदाि करेगा। 7. सभी उत्पादि इकाइया,ं िो िीआरआईडी के साथ लसंक्रिाइज हैं, उिके स्ट्िाजमत्ि, प्रकार और आकार के बाििूद, उिके गििषर हर समय सामान्‍दय संचालि में रहगें े। यकद पचास (50) मेगािाट से अजधक आकार की ककसी उत्पादि इकाई को सामान्‍दय संचालि म ें उसके गििषर के जबिा संचाजलत करि े की आिश्यकता होती है, तो एसएलडीसी के माध्यम स े एिआरएलडीसी को तुरंत ऐसे संचालि के कारण और अिजध के बारे में सूजचत ककया िाएगा। थमषल और गैस- आधाठरत जबिली स्ट्टेििों के जबिा ककसी तालाब के स्ट्टीम टरबाइि के िदी िलजिद्युत स्ट्टेििों के संचालि के संबंध म ें मुफ्त गििषर मोड की सुजिधा िहीं होिे पर मफ्ु त गििरष मोड संचालि से छूट सीईआरसी से आईईिीसी के खंड 1.6 के अंतगतष मागं ी िाएगी। छूट के जलए ऐसी याजचकाओं स ेपहल ेअजधमाितः सीईए द्वारा एक अध्ययि ककया िाएगा। 8. जसस्ट्टम ऑपरेटर उपलब्ध सौर और पिि ऊिाष को खाली करि े के जलए सभी प्रयास करेगा और इस े अिश्य चलि े िाल े स्ट्टेिि के रूप में मािगे ा। हालाँकक, जसस्ट्टम ऑपरेटर ककसी भी उपकरण या कर्मषयों की सुरक्षा को खतरे पर जिचार करते हुए सौर/पिि ििरेटर को उत्पादि बंद करि े का जिदिे दे सकता ह ै और सौर/पिि ििरेटर उसी का अिुपालि करता ह।ै 9. उपयोगकताष और राज्य पारेर्ण उपयोजगता ककसी भी जिड गडबडी/घटिा के जिश्लेर्ण के उद्देश्य से जडस्ट्टबेंस ठरकॉडषर/पठरणामी घटिा ठरकॉडषर आउटपुट आकद सजहत अिरु ोजधत िािकारी/डेटा को राज्य लोड जडस्ट्पैच सेंटर को भेिेगी।[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 19 अध्याय -6: कफ्रक्वेन्‍दसी और िोल्टेि प्रबधं ि 6.1 उद्देश्य इस अध्याय के उद्देश्य इस प्रकार ह:ैं 1. आिृजत्त और िोल्टेि प्रबंधि में योगदाि दिे े के जलए सभी उपयोगकताषओं की जिम्मेदाठरयों को पठरभाजर्त करिा। 2. आईईिीसी कदिाजिदेिों के साथ-साथ केंरीय आयोग द्वारा जिर्दष्टष अंतर-राज्य पारेर्ण प्रणाली के जलए योििा और सुरक्षा मािकों, यकद कोई हो, के अिुसार राज्य पारेर्ण प्रणाली िोल्टेि और आिृजत्त को स्ट्िीकायष स्ट्तरों के अंदर बिाए रखिे के जलए एसएलडीसी और एसटीयू को सक्षम करिे के जलए आिश्यक कायों को पठरभाजर्त करिा। . 6.2 आिजृ त्त प्रबधं ि 1. जसस्ट्टम की रेटेड आिृजत्त 50 हर्टिष होगी और आम तौर पर समय-समय पर संिोजधत केंरीय जिद्युत प्राजधकरण या लोडतीय जिद्युत जिड कोड द्वारा जिर्दष्टष सीमा के अंदर जियंजत्रत की िाएगी। 2. एसटीयू और एसएलडीसी यह सुजिजित करि े के जलए हर संभि प्रयास करेंग े कक जिड आिृजत्त 49.9 - 50.05 हर्टिष बैंड के अंदर बिी रह।े हालाँकक, घटती और बढती आिृजत्त की जस्ट्थजतयों में जिम्नजलजखत उपायों को अपिािे की आिश्यकता ह;ै क) आिजृ त्त का कम होिा आिृजत्त के कम होि े की जस्ट्थजतयों के अतं गतष , एसएलडीसी आिृजत्त को कम होिे से रोकिे और अिुमेय सीमा के अंदर आिृजत्त को बहाल करिे के जलए आरएलडीसी के साथ समन्‍दिय में जिदेि िारी करिे के जलए उजचत कायषिाही करेगा। ऐसे जिदेिों म ें उत्पादि बढािे के जलए एसिीएस को प्रेर्ण जिदेि और/या जितरण लाइसेंसधाठरयों और ओपि एक्सेस िाहकों को उजचत मैिअु ल और/या स्ट्िचाजलत लोड िेलडंग द्वारा लोड मांग को कम करि े के जिदेि िाजमल हो सकत े ह।ैं ख) बढती हुई आिजृ त्त बढती आिृजत्त जस्ट्थजतयों के अतं गषत, एसएलडीसी बढती आिृजत्त को रोकिे और अिुमेय सीमा के अंदर आिृजत्त को बहाल करिे के जलए आरएलडीसी के साथ समन्‍दिय में एसिीएस को जिदेि िारी करिे के जलए उजचत कायषिाही करेगा। एसएलडीसी अजतठरक्त लोड लिे े के जलए लोड िेलडंग (यकद मौिूद ह)ै उिाि े के जलए आरएलडीसी के साथ समन्‍दिय में जितरण लाइसेंसधाठरयों और ओपि एक्सेस िाहकों को जिदेि भी िारी करेगा। लोड क्रैि की जस्ट्थजत में, एसएलडीसी इस संजहता के पैरा 8.4 के अिुसार कदम उिाएगा। 6.3 िोल्टेि प्रबधं ि 1. राज्य पारेर्ण प्रणाली और एसटीयू का उपयोग करिे िाल े उपयोगकताष यह सुजिजित करिे के जलए हर संभि प्रयास करेंग ेकक जिड िोल्टेि हमेिा आईईिीसी में खडं 5.2 (आर) में जिर्दष्टष सीमा के अंदर रह।े िोल्टेि (केिी आरएमएस) मामलू ी अजधकतम न्‍दयिू तम 400 420 380 220 245 198 132 145 122 ििीितम आईईिीसी में न्‍दयूितम िोल्टेि को 400 केिी के जलए 360 से 380 केिी, 220 केिी के जलए 200 से 198 केिी और 132 केिी के जलए 120 से 122 केिी तक संिोजधत ककया गया ह।ै इसी प्रकार, उपरोक्त समाि प्रजतित िोल्टेि जभन्नताओं को ध्याि म ें रखत े हुए, 110 केिी और 66 केिी िोल्टेि की अजधकतम और न्‍दयूितम सीमाएं िीचे दी गई होंगी। मामलू ी अजधकतम न्‍दयिू तम 110 121 102 66 72 6120 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 2. एसटीयू और/या एसएलडीसी समय-समय पर पठरचालि डेटा के आधार पर लोड प्रिाह का अध्ययि करेंगे ताकक यह अिुमाि लगाया िा सके कक िोल्टेि की समस्ट्याएं कहां आ सकती ह ैं और यह सुजिजित करिे के जलए उजचत उपायों की पहचाि की िाएगी कक िोल्टेि जिधाषठरत सीमा के अंदर रहे। इि अध्ययिों के आधार पर, एसएलडीसी एसिीएस को इंटरकिेलक्टंग लबंदओंु पर जिर्दष्टष िोल्टेि स्ट्तर बिाए रखिे का जिदेि देगा। एसएलडीसी रणिीजतक सब-स्ट्टेििों पर 220 केिी, 132 केिी, 110 केिी और 66 केिी िोल्टेि स्ट्तर की लगातार जिगरािी करेगा। 3. एसएलडीसी राज्य पारेर्ण प्रणाली िोल्टेि को जियंजत्रत करिे के जलए उजचत उपाय करेगा, जिसमें 110 केिी, 66 केिी या 33 केिी सबस्ट्टेििों पर जितरण लाइसेंसधाठरयों द्वारा रांसफामषर टैप बदलिा, कैपेजसटर / ठरएक्टर जस्ट्िलचंग और कैपेजसटर जस्ट्िलचंग और एसटीयू और िेिरेटर के बीच तकिीकी सीमाओं पर सहमजत पर एमिीआर ठरििष का प्रयोग िाजमल है। ििे रेटर अिुरोध पर तुरंत एसएलडीसी को अपिी प्रजतकक्रयािील आरजक्षत क्षमता के बारे में सूजचत करेंगे। 4. एसएलडीसी यह सुजिजित करेगा कक पारेर्ण िेटिकष पर न्‍दयूितम प्रजतकक्रयािील जिद्युत प्रिाह हो। लोड प्रिाह अध्ययि के अिुसार उपयुक्त सब स्ट्टेििों पर कैपेजसटर बैंकों की स्ट्थापिा से प्रजतकक्रयािील ऊिाष की मांग पूरी की िाएगी। 5. जितरण लाइसेंसधारी और ओपि एक्सेस िाहक स्ट्थािीय िीएआर हिाषिा (िहां तक संभि हो लोड लबंदओंु के करीब कम िोल्टेि प्रणाली में) प्रदाि करके िोल्टेि प्रबंधि में भाग लेंगे, ताकक िे प्रजतकक्रयािील सहायता के जलए ईएचिी जिड पर जिभषर ि रहें। अध्याय-7: सरं क्षण 7.1. उद्देश्य 1. इस अध्याय का उद्देश्य दोर्ों से सुरक्षा के जलए राज्य पारेर्ण प्रणाली से िुडे ककसी भी उपकरण के जलए न्‍दयूितम सुरक्षा आिश्यकताओं को पठरभाजर्त करिा ह ैऔर इस प्रकार दोर्ों के कारण ककसी भी व्यिधाि को कम करिा है। 2. न्‍दयूितम सरु क्षा आिश्यकताएं जिधाषठरत की गई ह ैं क्योंकक अपयाषप्त सुरक्षा या ककसी इकाई की सुरक्षा प्रणाली के खराब संचालि के पठरणामस्ट्िरूप दरू गामी पठरणाम, गडबडी और यहां तक कक अन्‍दय संस्ट्थाओं की प्रणाली को िुकसाि हो सकता ह।ै 7.2. सामान्‍दय जसद्धातं 1. जिद्युत उपकरण की ककसी भी िस्ट्तु को राज्य पारेर्ण प्रणाली से िुडे रहि ेकी अिुमजत िहीं दी िाएगी िब तक कक यह जिश्वसिीयता, चयिात्मकता, गजत, जस्ट्थरता और संिेदििीलता के उद्देश्य स े न्‍दयूितम जिर्दष्टष सुरक्षा ठरल े सेटटंग्स द्वारा किर ि हो। 2. सभी उपयोगकताष इस अिुभाग म ें जिर्दष्टष समय के अंदर खराबीपूणष उपकरणों को प्रभािी और भेदभािपूणष रूप स े हटािे के जलए सुरक्षा की सही और उजचत सेटटंग्स सुजिजित करिे के जलए एसटीयू के साथ सहयोग करेंगे। 3. सभी प्रभाजित उपयोगकताओंष के बीच परामि ष और सहमजत के जबिा सुरक्षात्मक ठरले सेटटंग्स में बदलाि िहीं ककया िाएगा, या सुरक्षा ठरले को अिदेखा िहीं ककया िाएगा और/या जडस्ट्किेक्ट िहीं ककया िाएगा। ऐसे मामल े में िहा ं ककसी समझौते द्वारा सुरक्षा को दरककिार कर कदया िाता ह ै और/या काट कदया िाता है, तो कारण को िीक ककया िािा चाजहए और जितिी िल्दी हो सके सुरक्षा को सामान्‍दय जस्ट्थजत म ें बहाल ककया िािा चाजहए। यकद कोई समझौता िहीं हुआ ह,ै तो सुरक्षा ि रखि ेिाले जिद्युत उपकरण को तुरंत सेिा से हटा कदया िाएगा। 7.3. सरं क्षण समन्‍दिय 1. राज्य जिड कोड समीक्षा सजमजत राज्य जिड कोड के अध्याय-2 के अिुसार गठित की िाएगी और सभी सुरक्षा समन्‍दिय कायों के जलए भी जिम्मेदार होगी। 2. ििरेटटंग यूजिट स े िुरू होकर 110 केिी /66केिी /33 केिी लाइि के ठरमोट जसरे तक सुरक्षात्मक ठरल े की सेटटंग्स ऐसी होंगी कक सभी पठरजस्ट्थजतयों में केिल खराबीपूणष अिुभाग को अलग ककया िाए। 3. एसटीयू समय-समय पर उपयोगकताषओं को प्रारंजभक सेटटंग्स और सजमजत द्वारा अिुमोकदत ककसी भी बाद के बदलाि के बारे में सूजचत करेगा। सभी सुरक्षात्मक ठरले का आिजधक परीक्षण छह महीिे में एक बार ककया िाएगा। 4. ककसी भी सुरक्षात्मक ठरले की खराबी के बारे में तुरंत जिश्लेर्ण करिे और आिश्यक सधु ारात्मक कायषिाही की जसफाठरि करिे के जलए राज्य जिड कोड समीक्षा सजमजत को सजू चत ककया िाएगा।[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 21 5. सुरक्षा ठरल,े मीटर और अन्‍दय िुडे उपकरणों के परीक्षण और रखरखाि के जलए, एसटीयू द्वारा जसस्ट्टम की सुरक्षा म ें अिुभि रखि े िाले और आिश्यक सहायक तकिीकी और गरै -तकिीकी कमषचाठरयों से यक्तु कायषकारी स्ट्तर के एक इंिीजियर की अध्यक्षता में एक अलग सले स्ट्थाजपत ककया िाएगा। . 6. सभी स्ट्थािों पर िहां सरु क्षा योििाएं स्ट्थाजपत ह,ैं उन्‍दह ेंलसंगल लाइि डायिाम में प्रदर्िषत करिा होगा। 7. स्ट्थाजपत सभी सुरक्षा ठरल े के जिजिदेिों की प्रजतया ं उि सभी स्ट्थािों पर प्रदाि की िाएंगी िहां ऐसे ठरले स्ट्थाजपत ककए गए ह।ैं 7.4. खराबी जििारण समय 1. सभी उपकरण सही ढंग से संचाजलत होिे पर, राज्य पारेर्ण प्रणाली से सीधे िुडे उपयोगकताष उपकरण पर तीि-फेि की खराबी (बस बार के करीब) के जलए और राज्य पारेर्ण पर तीि- फेि की खराबी (बस बार के करीब) के जलए तो खराबी जििारण समय जिम्न से अजधक अजधक िहीं होगा; क) 400 केिी िगष के िोल्टेि के जलए 100 जमलीसेकंड ख) 220 केिी, 132 केिी और 110 केिी िगष के िोल्टेि के जलए 160 जमलीसेकंड ग) 66 केिी िगष के िोल्टेि के जलए 300 जमलीसेकंड 2. उपरोक्त स ेकम खराबी जििारण समय बेहतर ह।ै 3. उपयोगकताष के जसस्ट्टम पर दोर्ों के जलए कम खराबी जििारण समय पर सहमजत दी िा सकती है, लेककि केिल तभी, िब एसटीयू की राय में, जसस्ट्टम जस्ट्थजतयां इसकी अिुमजत दते ी ह।ैं एसटीयू पारेर्ण प्रणाली से सीधे िुडे एसटीयू और जितरण लाइसेंसधाठरयों/ओपि एक्सेस िाहकों के जलए जिजभन्न स्ट्थािों पर सर्कषट िेकरों के खुलि े का आिश्यक समय और टूटि े की क्षमता जिर्दष्टष करेगा। उत्पादि स्ट्टेििों पर, महत्िपूणष जक्लयटरंग समय के अंदर उत्पादि स्ट्टेिि के अतं म ें लाइि दोर्ों को दरू ककया िािा चाजहए ताकक ििरेटर समकाजलकता म ेंबिे रह।ें 7.5. ििे रेटर की आिश्यकताए ँ 1. राज्य पारेर्ण प्रणाली से िुडी सभी उत्पादि इकाइयों और उत्पादि इकाइयों के सभी संबद्ध जिद्युत उपकरणों म ें संरक्षण समन्‍दिय सजमजत द्वारा अिुमोकदत पयाषप्त सुरक्षा और बैकअप सुरक्षा प्रणाली होिी चाजहए ताकक राज्य पारेर्ण प्रणाली को उत्पन्न होि े िाली ककसी भी गडबडी के कारण िुकसाि ि हो। 2. सीबीआईपी के प्रकािि संख्या 274 के अतं गतष ििरेटर, ििरेटर रांसफामषर आकद की सुरक्षा पर मिै ुअल म ें उजल्लजखत कदिाजिदेिों को भी ध्याि में रखा िाएगा। 7.6. पारेर्ण लाइि आिश्यकताए ँ 1. सामान्‍दय ििरेटटंग स्ट्टेिि या सब-स्ट्टेिि या जस्ट्िलचंग स्ट्टेिि स े जिकलिे िाली प्रत्येक ईएचटी लाइि में सुरक्षा समन्‍दिय सजमजत द्वारा अिुमोकदत पयाषप्त सुरक्षा और बैकअप सरु क्षा होिी चाजहए। ििरेटटंग स्ट्टेिि से जिकलि े िाली एसटीयू की लाइिों की सुरक्षा के जलए जस्ट्िचजगयर उपकरण और ठरल े पैिल का स्ट्िाजमत्ि और रखरखाि िेिरेटर के पास होगा। ककसी भी पारेर्ण लाइि से संबंजधत ठरले सेटटंग्स या ठरल े सेटटंग्स में कोई भी बदलाि िेिरेटर द्वारा एसटीयू के साथ जिकट समन्‍दिय और परामि ष म ें ककया िाएगा। कैठरयर कैजबिेट/उपकरण, िेि रैप और संचार केबल सजहत लाइि जमलाि इकाइयां एसटीयू के स्ट्िाजमत्ि में होंगी और उसी के द्वारा रखरखाि कदया िाएगा। सभी िेिरेटर ऐसे उद्देश्य के जलए स्ट्थाि, किेक्िि सुजिधा और एसटीयू तक पहुचं प्रदाि करेंगे। सीबीआईपी के प्रकािि संख्या 274 के अंतगषत 220 केिी और 400 केिी िेटिकष आकद की सुरक्षा पर मैिअु ल म ें उजल्लजखत कदिाजिदेिों को भी ध्याि म ेंरखा िाएगा। 2. 400केिी पारेर्ण लाइि ें एसटीयू के स्ट्िाजमत्ि िाली सभी 400 केिी पारेर्ण लाइिों म ें दो तेिी से काम करि े िाली सुरक्षा योििाएं होंगी, दो ठरल े के िोल्टेि को लाइि सीिीटी के दो अलग-अलग कोर से फीड ककया िाएगा और दो ठरल े की धाराओं को लाइि सी.टी के दो अलग-अलग कोर से फीड ककया िाएगा। .22 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] मेि 1 सुरक्षा योििा संख्यात्मक, तीि िोि, िॉि-जस्ट्िच्ड तेिी से काम करिे िाली ठरमोट सुरक्षा योििा होगी जिसम ें ठरमोट एंड पर अिुमत इंटर-ठरप (िोि -2 त्रुठट के मामले म)ें होगी। मुख्य 2 सुरक्षा योििा या तो समाि प्रकार की संख्यात्मक, तीि जोि, गैर-जस्ट्िच्ड तेिी स े कायष करिे िाली ठरमोट सुरक्षा योििा होगी जिसमें ठरमोट एंड पर अिुमत इंटर-ठरप (जोि -2 त्रुठट के मामले म)ें योििा या रांजिएन्‍दट िेि पहचाि, कदिात्मक तलु िा या चरण तलु िा िाहक ठरलइे ंग को जियोजित करि े िाली एक इकाई सुरक्षा योििा होगी। समायोज्य डेड-टाइम के साथ एक पोल ठरलपंग और लसंगल िॉट ऑटो-ठरक्लोलिंग प्रदाि की िाएगी। सभी 400 केिी सब-स्ट्टेिि म ें एलबीबी और पारेर्ण लाइिों के जलए ऑटो-ठरक्लोिर के साथ बस-बार अंतर सुरक्षा योििा होगी। 3. 220 केिी पारेर्ण लाइि ें एसटीयू के स्ट्िाजमत्ि िाली सभी 220 केिी पारेर्ण लाइिों म ेंदो तेिी से काम करि े िाली सुरक्षा योििाएं होंगी। मेि 1 सुरक्षा योििा संख्यात्मक, तीि िोि, िॉि-जस्ट्िच्ड तेिी से काम करिे िाली ठरमोट सुरक्षा योििा होगी जिसम ें दरू स्ट्थ छोर पर अिुमत इंटर ठरप (िोि -2 त्रुठट के मामल े में) होगी। योििा में पािर लस्ट्िंग ब्लॉककंग, फॉल्ट ठरकॉर्डिंग का स्ट्थाि, जडस्ट्टबेंस ठरकॉर्डगिं , इिेंट लॉगर, संचार पोट,ष लसंगल और थ्री िॉट ऑटो रीक्लोलिंग के साथ-साथ लोकल िेकर बैकअप (एलबीबी) भी होगा। मेि 2 सुरक्षा योििा जस्ट्थर/संख्यात्मक, तीि जोि, जस्ट्िच्ड/िॉि-जस्ट्िच्ड तेिी से कम करि े िाली सुरक्षा योििा होगी जिसमें ऑटो रीक्लोलिंग और स्ट्थािीय िेकर बैकअप (एलबीबी) को छोडकर मेि-1 की तरह सभी सुजिधाएं होंगी। बैक-अप सरु क्षा के जलए, ितषमाि ठरले और यूजिडायरेक्ििल अथ ष फॉल्ट ठरल े पर तीि कदिात्मक आईडीएमटीएल प्रदाि ककया िाएगा। 4. 132 केिी/110 केिी/66 केिी लाइि ें लसंगल स्ट्कीम थ्री िोि, लसंगल और थ्री फेि ठरलपंग, कैठरयर इंटर-ठरलपंग, आईडीएमटी ओिर करंट और अथष फॉल्ट, पािर लस्ट्िंग ब्लॉककंग और एलबीबी सुरक्षा िैसी मािक जिर्मषत सुजिधाओं के साथ गैर-जस्ट्िच्ड संख्यात्मक ठरमोट सुरक्षा मेि सुरक्षा के रूप म ेंप्रदाि की िाएगी। बैकअप सुरक्षा ितषमाि ठरल ेपर कम से कम दो कदिात्मक आईडीएमटीएल और एक कदिात्मक अथ षखराबी ठरले होगी। छोटी पारेर्ण रेजडयल लाइिों के जलए, उजचत िैकजल्पक सुरक्षा योििाएं अपिाई िा सकती ह।ैं 7.7. रांसफामरष आिश्यकताए ँ 1. पािर रांसफामषर की सुरक्षा सुरक्षा समन्‍दिय सजमजत द्वारा अिमु ोकदत की िाएगी। सेंरल बोड ष ऑफ इठरगिे ि एंड पािर (सीबीआईपी) प्रकािि संख्या 275 द्वारा प्रकाजित रांसफामषर पर मिै ुअल में उजल्लजखत कदिाजिदेिों को भी ध्याि म ें रखा िाएगा। रांसफामषर के जलए जिम्नजलजखत न्‍दयूितम सुरक्षा सुजिजित की िाएगी: (i) सभी 220 केिी िगष के पािर रांसफामषर को संख्यात्मक फास्ट्ट एलक्टंग जडफरेंजियल, आरईएफ, ओपि डेल्टा (न्‍दयूरल जडस्ट्पलेसमेंट ठरल)े और ओिर-फ्ललक्संग ठरले प्रदाि ककए िाएंगे। इसके अलािा, करंट और अथष फॉल्ट प्रोटेक्िि पर बैकअप आईडीएमटीएल होगा। समािांतर संचालि के जलए, ऐसी बैक अप सरु क्षा म ें एचिी और एलिी दोिों िेकरों की इंटर-ठरलपंग होगी। भारी िॉटष सर्कषट से सुरक्षा के जलए, ओिर करंट ठरले म ें एक उच्च सेट तात्काजलक तत्ि िाजमल होिा चाजहए। जिद्युत सुरक्षा के अलािा, रांसफामषर की स्ट्ियं की सुरक्षा अथाषत अलाम ष और ठरप कायों के जलए बुखोल्ि ओएलटीसी ऑयल सिष, गसै संचाजलत ठरल,े िाइंलडंग तापमाि संरक्षण, तेल तापमाि संरक्षण, पीआरिी ठरले प्रदाि ककया िाएगा। (ii) 10 एमिीए और उससे अजधक क्षमता के 132 केिी, 110 केिी और 66 केिी श्रणे ी के जबिली रांसफामषर के जलए ओिर-फ्ललक्संग, आरईएफ और पीआरिी ठरले को छोडकर सुरक्षा ऊपर 7.7 (1) (i) में उजल्लजखत के समाि होगी। (iii) 10 एमिीए से कम क्षमता िाल े 132 केिी, 110 केिी और 66 केिी श्रेणी के पािर रांसफामषर के जलए, रांसफामषर आिश्यकताओं के अिुसार रांसफामषर ठरप और अलाम ष कायों के जलए सहायक ठरले के साथ उच्च सेट तात्काजलक तत्ि के साथ ओिर-करंट प्रदाि ककया िाएगा।[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 23 2. जिद्युत सुरक्षा के अलािा, गैस संचाजलत ठरल,े िाइंलडंग तापमाि सुरक्षा और तले तापमाि सरु क्षा प्रदाि की िाएगी। 7.8. सब-स्ट्टेिि म ेंअजग्न सरु क्षा पयाषप्त सािधाजियां बरती िाएंगी और आईई जियमों में प्रासंजगक लोडतीय मािक जिजिष्टता और प्रािधािों की अिुपालिा करिे िाले सभी उपकरणों और अन्‍दय संपजत्तयों को आग के खतरों से सुरक्षा प्रदाि की िाएगी। स्ट्थाजपत अजग्निमि उपकरणों को अच्छी कायषिील जस्ट्थजत में बिाए रखा िाएगा और संबंजधत प्रभारी व्यजक्त द्वारा प्रजतकदि जिरीक्षण ककया िाएगा और रखरखाि लॉग बुक में दि ष ककया िाएगा। पांच-संरक्षण व्यिस्ट्था का एकल लाइि योििाबद्ध आरेख सब-स्ट्टेिि जियंत्रण कक्ष में प्रदर्िषत ककया िाएगा। 7.9. अिं ाकं ि और परीक्षण सुरक्षा योििा का परीक्षण प्रत्येक 220 केिी, 132 केिी, 110 केिी, 66 केिी सब-स्ट्टेिि पर एसटीयू और उपयोगकताषओं द्वारा छह महीिे में एक बार या ककसी बडी खराबी के तुरंत बाद, िो भी पहले हो, ककया िाएगा। उत्पादि इकाइयों/स्ट्टेििों स े संबंजधत सभी सुरक्षा योििाओं का परीक्षण और अंिांकि संबंजधत एसिीएस की जिम्मेदारी होगी। 7.10. डेटा आिश्यकताएँ: उपयोगकताष एसटीयू और एसएलडीसी को डेटा पंिीकरण अध्याय में पठरजिष्ट-घ म ेंजिर्दष्टष डेटा प्रदाि करेंगे। अध्याय -8: सचं ालि योििा 8.1. उद्देश्य यह अध्याय उस प्रकक्रया का िणषि करता ह ै जिसके द्वारा एसएलडीसी पठरचालि योििा और मांग जियंत्रण प्रकक्रयाओं को पूरा करता ह।ै राज्य पारेर्ण प्रणाली के सभी जहस्ट्सों में पठरचालि समस्ट्याओं से बचि े के जलए एसएलडीसी को ओिरलोलडंग को कम करि े म ें सक्षम बिािे के जलए जिस्ट्तृत प्रकक्रया की आिश्यकता ह।ै एसएलडीसी मांग जियंत्रण का उपयोग इस तरीके स े करेगा, जिससे ककसी एक या उपभोक्ताओं के समूह के प्रजत अिजु चत भेदभाि ि हो। 8.2. मागं अिमु ाि 1. दीघषकाजलक मांग अिुमाि और लोड पूिाषिुमाि (1 िर्ष से अजधक के जलए) एसटीयू द्वारा ककया िाएगा। इसे अंजतम रूप कदए िािे पर एसएलडीसी को इसकी एक प्रजत उपलब्ध कराई िाएगी। 2. सभी जितरण लाइसेंसधाठरयों की यह जिम्मेदारी होगी कक ि े परू े राज्य के जलए मागं अिुमाि और लोड पूिाषिुमाि तैयार करिे म ेंएसटीयू के साथ पूरा सहयोग करें। 3. जितरण लाइसेंसधारी प्रत्येक िर्ष 31 िििरी तक अगल े जित्तीय िर्ष के जलए प्रत्येक इंटर किेक्िि लबंद ु पर महीिे के आधार पर आगामी िर् ष के जलए मांग का अपिा अिुमाि एसटीयू को प्रदाि करेंगे। जितरण लाइसेंसधाठरयों को अगल े महीिे के जलए प्रत्येक इंटर किक्े िि लबंद ुपर 25 जतजथ तक दैजिक मांग भी प्रदाि करिी होगी। 4. जितरण लाइसेंसधाठरयों द्वारा प्रस्ट्तुत आंकडों के आधार पर, एसटीयू अगले िर् ष के जलए माजसक पीक और लीि अिजध की मांग का अिुमाि लगाएगा और आिे िाले महीि े के जलए दैजिक पीक और लीि अिजध की मांग का अिुमाि लगाएगा और उसे एसएलडीसी को प्रस्ट्तुत करेगा। 5. जितरण लाइसेंसधारी एसएलडीसी को ऐसे लोड िेलडंग की व्यिस्ट्था के जििरण के साथ जििेकिील ब्लॉकों म ें आिश्यकता पडि े पर िडे ककए िािे िाले लोड का अिुमाि प्रदाि करेगा। 6. जितरण लाइसेंसधाठरयों को एसटीयू और एसएलडीसी को आिश्यक लोड, िामीण क्षेत्रों में बिाए रखी िाि े िाली आपूर्तष लाइिों, लगाए गए या लगाए िािे िाल े जबिली कटों आकद के जििरण के साथ श्रणे ी-िार िास्ट्तजिक मांग भी प्रस्ट्तुत करिी होगी। 7. एसएलडीसी जतमाही, माजसक, साप्ताजहक और अंततः दैजिक आधार पर मागं पूिाषिुमाि (मेगािाट के साथ-साथ ककलोिाट में) को अपडेट करेगा जिसका उपयोग अगल ेकदि िड्ये ूललगं म ेंककया िाएगा।24 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 8.3. मागं जियत्रं ण 1. जबिली प्रणाली की समि अखडं ता को बिाए रखिे के जलए एसएलडीसी के जिदेिों के अिुसार एसटीयू के उप स्ट्टेििों पर अंडर फ्रीक्वेंसी ठरल े की स्ट्थापिा के माध्यम स े स्ट्िचाजलत लोड िेलडंग का सहारा जलया िाएगा। लोड िेलडंग के जलए स्ट्िचाजलत अंडर फ़्रीक्वेंसी ठरले का उपयोग करि े िाल े असतत ब्लॉकों की संख्या और आकार प्रत्येक जितरण लाइसेंसधारी के परामिष से रोटेिि के आधार पर जिधाषठरत ककया िाएगा। इि ठरल े की आिृजत्त सेटटंग्स को आरएलडीसी के परामि षसे समजन्‍दित ककया िाएगा। 2. िब भी स्ट्िचाजलत लोड िेलडंग द्वारा प्रभाजित कुल मागं जडस्ट्किेक्िि के बडे जहस्ट्स े की बहाली उजचत समय के अंदर संभि िहीं होती है, तो एसएलडीसी जडस्ट्किेक्ट की गई मांग की समतुल्य राजि को बहाल करिे के जलए मैन्‍दयअु ल रूप से अजतठरक्त जडस्ट्किेक्िि लाग ूकरेगा। प्रत्येक जितरण लाइसेंसधारी ऐस े लोड ब्लॉकों की पहचाि करि े म ें एसएलडीसी की मदद करेगा। स्ट्िचाजलत लोड िेलडंग उपकरणों के संचालि द्वारा लोड िडे को एसएलडीसी के जिजिष्ट जिदेिों के जबिा बहाल िहीं ककया िाएगा। 3. िब उत्पादि में कमी हो, या पारेर्ण प्रणाली में बाधा हो, या बाहरी किेक्िि आकद के माध्यम से आयात में कमी हो, तो आईएसिीएस से जबिली की अजधक जिकासी को जियंजत्रत करिे के जलए मांग जियंत्रण की आिश्यकता होि े पर एसएलडीसी द्वारा जियोजित मैिुअल लोड िेलडंग लाग ू की िाएगी। ऐस े मामलों म ें िहां तक संभि हो सभी उपभोक्ताओं के जलए समाि व्यिहार सुजिजित करिे के जलए एक रोटेििल लोड िेलडंग योििा अपिाई िाएगी। 4. अस्ट्िीकायष िोल्टेि और आिृजत्त स्ट्तर आकद से जिपटि े के जलए आपातकालीि मैिअु ल लोड िेलडंग को एसएलडीसी द्वारा लागू ककया िाएगा िब उत्पादि की हाजि, मांग के साथ उत्पादि का बेमेल होिा, पारेर्ण प्रणाली म ें बाधाए,ं जिड से संबंजधत से अजधक जिकासी हो। 49 हर्टिष से िीचे क्षेत्रीय जिड की आिृजत्त को प्रभाजित करिे िाला िेड्यलू , एक जिजियमि मार्िषि बिाए रखि े के जलए, अल्प सूचिा पर या जबिा ककसी सूचिा के लोड िेलडंग की आिश्यकता होती ह।ै 5. इि जियंत्रण उपायों को तब तक िापस िहीं जलया िाएगा िब तक कक जसस्ट्टम आिृजत्त में सुधार िहीं हो िाता और िब एसएलडीसी जस्ट्थजत की समीक्षा के बाद ऐसे जिदिे िारी करता ह।ै 8.4. लोड क्रैि 1. मौसम की गडबडी या ककसी अन्‍दय कारण स े जसस्ट्टम म ें लोड क्रैि होि े की जस्ट्थजत में, जस्ट्थजत को एसएलडीसी द्वारा अिरोही प्राथजमकताओं में जिम्नजलजखत तरीकों से जियंजत्रत ककया िाएगा: (i) लोड प्रजतबंध हटािा, यकद कोई हो (ii) पडोसी क्षेत्रों/राज्यों को जबिली जियाषत करिा (iii) योग्यता क्रम में कम अिजध के जलए 5-10 जमिट के समय अंतराल के साथ थमलष स्ट्टेििों का बकै अप लेिा। (iv) िहरों म ें पािी के प्रिाह और िहरों/िल चिै लों की सुरक्षा को ध्याि म ें रखते हुए िल जिद्युत इकाइयों को बंद करिा (पािी के ि जगरि े और लसंचाई पर प्रभाि के अधीि)। उपरोक्त कायषप्रणाली की समय-समय पर समीक्षा की िाएगी। 2. उपरोक्त को लाग ू करत े समय, राज्य जिड कोड के अध्याय 5 म ें परै ा 5.3 के प्रािधािों के अिुसार जसस्ट्टम सरु क्षा पहलओंु का उल्लघं ि िहीं ककया िािा चाजहए। अध्याय-9: उत्पादि एि ंजिकासी की जिगरािी 9.1. उद्देश्य इस अध्याय का उद्देश्य उत्पादि इकाई की जिश्वसिीयता और प्रदििष की जिगरािी में सभी राज्य उत्पादि स्ट्टेििों (एसिीएस) की जिम्मेदाठरयों को पठरभाजर्त करिा, और एसटीयू/उपयोगकताष की सूचीबद्ध जिकास की अिपु ालिा सुजिजित करिा ह ै ताकक िोल्टेि और कफ्रक्वेन्‍दसी के जियंत्रण जसस्ट्टम प्रदिषि और जिड अििु ासि म ें सुधार करि े म ें एसएलडीसी की सहायता की िा सके।[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 25 9.2. उत्पादि की जिगरािी 1. राज्य पारेर्ण प्रणाली के प्रभािी संचालि के जलए, यह महत्िपूणष ह ै कक एसिीएस की घोजर्त उपलब्धता यथाथषिादी हो और उपलब्धता से कोई भी जिचलि अजििायष रूप से एसएलडीसी को सूजचत ककया िाए। 2. एसएलडीसी िेिरेटटंग यूजिट आउटपुट और बस िोल्टेि की लगातार जिगरािी करेगा। ककसी भी समय अजधक किोर जिगरािी की िा सकती ह ै िब यह माििे का कारण हो कक एसिीएस की घोजर्त उपलब्धता िास्ट्तजिक उपलब्धता से मेल िहीं खाती ह ैया घोजर्त आउटपुट िास्ट्तजिक आउटपुट स ेमेल िहीं खाता ह।ै 3. एसएलडीसी यह सुजिजित करेगा कक राज्य के अंदर 200 मेगािाट और उससे अजधक क्षमता िाली सभी थमलष इकाइयां जिःिुल्क गििरष ऑपरेिि के साथ संचाजलत हों। 4. एसएलडीसी िेिरेटर द्वारा जिर्दष्टष समय के अंदर घोजर्त उपलब्धता तक पहुचं िे के जलए ििे रेटटंग स्ट्टेिि को जिदेि देकर घोजर्त उपलब्धता प्रदर्ितष करिे के जलए एक िेिरेटटंग स्ट्टेिि लगाि े के जलए कह सकता ह।ै 5. यकद जिरंतर जिगरािी प्रर्े ण जिदेिों और ििरेटटंग यूजिट आउटपुट या किेक्िि ितों के उल्लघं ि के बीच एक स्ट्पष्ट लगातार या महत्िपूण ष बेमेल को प्रदर्िषत करती ह,ै तो एसएलडीसी एसिीएस को जलजखत रूप म ें सूजचत करेगा। भजिष्य में प्रदिषि में सुधार करि,े अजधक यथाथषिादी घोर्णाएं प्रदाि करिे या किेजक्टजिटी ितों के ककसी भी उल्लघं ि के जलए उजचत कायषिाही िुरू करिे की दजृ ष्ट से जिरंतर जिसंगजतयों को राज्य जिड कोड समीक्षा सजमजत द्वारा हल ककया िाएगा। उत्पादि स्ट्टेििों द्वारा लगातार चूक करिे पर आयोग द्वारा जिधाषठरत दंड लगाया िा सकता ह।ै 6. िहां भी एससीएडीए/आरटीयू उपकरण के माध्यम से टेलीमेरी डेटा उपलब्ध िहीं है, एसिीएस एसएलडीसी को 15 जमिट के ब्लॉक-िार िेिरेिि सारांि आउटपुट प्रदाि करेगा। सीपीपी एसएलडीसी को 15 जमिट का ब्लॉक-िार जियाषत/आयात (मगे ािाट और एमिीएआर) प्रदाि करेगा। 7. एसिीएस कोई अन्‍दय लॉग रीलडंग प्रदाि करेगा जिसकी एसएलडीसी को जिगरािी उद्देश्यों के जलए उजचत रूप स े आिश्यकता हो सकती ह,ै िहां एससीएडीए डेटा उपलब्ध िहीं ह।ै 9.3. जिकासी की जिगरािी 1. एसएलडीसी िहां भी उपलब्ध हो, एससीएडीए उपकरण के उपयोग के माध्यम से, या अन्‍दयथा उपलब्ध मीटटरंग का उपयोग करके जितरण लाइसेंसधाठरयों और अन्‍दय उपयोगकताओंष द्वारा उिके िेड्यलू के अिसु ार िास्ट्तजिक जिकासी (मेगािाट में) की लगातार जिगरािी करेगा। एसएलडीसी इस जिगरािी को सक्षम करिे के जलए आिश्यक अजतठरक्त डेटा प्रदाि करि े के जलए आरएलडीसी और जिकटिती राज्यों से उजचत अिुरोध करेगा। 2. एसएलडीसी राज्य पारेर्ण प्रणाली के िोल्टेि प्रबंधि म ें सहायता के जलए िास्ट्तजिक एमिीएआर जिकासी की लगातार जिगरािी करेगा। 9.4. ििरेटटंग यजू िट ठरलपगं 1. एसिीएस ककसी उत्पादि इकाई की ठरलपंग के बारे में तरु ंत एसएलडीसी को कारण सजहत सजू चत करेगा, एसएलडीसी ठरलपंग और उिके पिु ः िरूु के बारे में आरएलडीसी को सूजचत करेगा। एसएलडीसी जसस्ट्टम प्रदिषि पर प्रभाि को प्रदर्िषत करिे और उपचारात्मक उपायों की आिश्यकता की पहचाि करि े के उद्देश्य से कारणों सजहत ऐसी सभी ठरलपंग का एक जलजखत लॉग रखेगा। 2. एसिीएस अपिी उत्पादि इकाइयों की ठरलपंग की अजधक जिस्ट्तृत माजसक ठरपोटष एसएलडीसी को प्रस्ट्ततु करेगा। 9.5. डेटा सबं धं ी आिश्यकता एसिीएस, आईपीपी और आरईिी डेटा पंिीकरण अध्याय-17 के पठरजिष्ट-ई (ई-5) में सूचीबद्ध अिुसार एसएलडीसी को डेटा प्रस्ट्तुत करेंगे।26 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] अध्याय-10: आउटेज योजना 10.1 उद्देश्य इस अध्याय का उद्देश्य उस प्रक्रिया को परिभाषित किना ह,ै जो एसटीयू को िाज्य उत्पादन स्टेशनों औि षितिण लाइसेंसधारियों के षनयोषजत पारेर्ण आउटेज को अनुकूषलत किन े की अनुमषत देगा, जबक्रक षसस्टम सुिक्षा को यथासंभि बनाए िखेगा। 10.2 आउटेज योजना प्रक्रिया 1. प्रत्येक उपयोगकता ा पूिे िाज्य पारेर्ण प्रणाली के षलए एक समग्र आउटेज योजना तैयाि किन े के षलए एसएलडीसी को आगामी षित्तीय ििा के षलए अपना आउटेज कायािम प्रदान किेगा। एसएलडीसी पारेर्ण नेटिका के आउटेज के षलए एसजीएस, षितिण लाइसेंसधारियों औि एसटीयू शेड्यलू सषहत सभी उपयोगकतााओं के आउटेज शेड्यूल का षिश्लेिण किने औि आिएलडीसी द्वािा क्षत्रे के षलए तैयाि क्रकए गए आउटेज प्लान के समन्िय म ें िाज्य पारेर्ण प्रणाली के षलए िार्िाक आउटेज योजना का मसौदा तैयाि किन े के षलए षजम्मेदाि होगा। उपयोगकता ा डेटा पंजीकिण अध्याय-17 के परिषशष्ट-ई म ेंसूचीबद्ध जानकािी एसएलडीसी को प्रस्तुत किेंगे। 2. हालााँक्रक, एसएलडीसी षनम्नषलषखत म ें से क्रकसी भी घटना के मामले म ें षनयोषजत आउटेज को स्थषगत किन े के षलए अषधकृत ह:ै क. प्रमुख षग्रड गड़बड़ी ख. षसस्टम आइसोलेिि ग. िाज्य म ें ब्लैक आउट घ. षसस्टम म ेंकोई अन्य घटना जो प्रस्ताषित आउटेज द्वािा षसस्टम सुिक्षा पि प्रषतकूल प्रभाि डाल सकती ह।ै 3. प्रत्येक उपयोगकताष को आउटेि का लाभ उिािे से पहल े एसएलडीसी का अिुमोदि प्राप्त करिा होगा। ककसी भी सर्कषट को आउटेि के जलए िारी करत े समय एसएलडीसी जिजिष्ट कोड िारी करेगा। इसी प्रकार, एसएलडीसी द्वारा जिजिष्ट कोड/अिुमोदि के जबिा ककसी भी अतं र उपयोगकताष सीमा सर्कषट को राज्य पारेर्ण प्रणाली स े िापस िहीं िोडा िाएगा। हालाँकक, यह प्रजतबंध सीपीपी की व्यजक्तगत उत्पादि इकाइयों पर लाग ूिहीं होगा। 4. षसस्टम म ें आपात षस्थषत के मामल े म,ें अथाात। उत्पादन की हाषन, षसस्टम को प्रभाषित किन े िाली पारेर्ण लाइन का टूटना, षग्रड म ें गड़बड़ी, षसस्टम आइसोलेिि, एसएलडीसी षनयोषजत आउटेज की मंजूिी स े पहल े क्रिि स े अध्ययन कि सकता ह।ै 10.3 िार्िका आउटेज योजना 1. समय-समय पि एसएलडीसी द्वािा अषधसूषचत षबजली स्टेशनों औि ईएचिी लाइनों की अनुसूषचत कटौती, िार्िाक योजना के अधीन होगी। 2. िाज्य षग्रड स े जुड़ े एसजीएस औि सीपीपी अगल े षित्तीय ििा के षलए अपन े प्रस्ताषित आउटेज कायािम को प्रत्येक िि ा 15 निंबि तक षलषखत रूप म ेंप्रस्तुत किेंगे। 3. एसजीएस आउटेज कायािम म ें यूषनट की पहचान, आउटेज का कािण, ऐसे आउटेज के कािण प्रभाषित उत्पादन उपलब्धता, आउटेज प्रािंभ षतषथ औि आउटेज की अिषध जैसे षिििण शाषमल होंगे। एसएलडीसी िाज्य पारेर्ण प्रणाली के आउटेज की रूपिेखा तैयाि किन े के षलए माषसक आधाि पि एसजीएस स े प्राप्त आउटेज कायािम की समीक्षा किेगा। 4. एसएलडीसी प्रत्येक ििा 15 निंबि तक अगल े षित्तीय ििा के षलए पारेर्ण लाइनों, उपकिणों औि सब-स्टेशनों आक्रद के षलए प्रस्ताषित आउटेज कायािम भी एसटीय ू स े प्राप्त किेगा। एसटीयू आउटेज कायािम म ें लाइनों/सबस्टेशनों की पहचान, आउटेज के कािण, आउटेज प्रािंभ षतषथ औि आउटेज की अिषध शाषमल होगी। 5. जलषिद्युत उत्पादन स्टेशनों के मामले म ें ऐसी योजना म ें षबजली उत्पादन के प्रयोजन के षलए पानी के िैकषपपक उपयोग स े संबंषधत लाग ू बाधाओं के अधीन पानी के उपयोग को अषधकतम किन ेका भी प्रयास क्रकया जाएगा।[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 27 बशते क्रक कम हिा के मौसम के दौिान पिन जनिेटरों के आउटेज की योजना बनाई जा सकती ह,ै बारिश के मौसम के दौिान यक्रद आिश्यक हो तो सौि ऊजा ा के आउटेज औि कम पानी के मौसम म ें िन-ऑि-द-रििि जलषिद्युत संयंत्र के आउटेज की योजना बनाई जा सकती ह।ै 6. सभी उपयोगकता ा औि एसटीयू एसएलडीसी द्वािा प्रकाषशत िार्िाक आउटेज योजनाओं का पालन किेंगे। यक्रद क्रकसी षिचलन की आिश्यकता ह,ै तो उसे एसएलडीसी की पूिा अनुमषत स े प्राप्त क्रकया जाएगा। ऊजाा के इन निीकिणीय स्रोतों स े अषधकतम षबजली षनकालन े के षलए िन-ऑि-द-रििि हाइड्रो प्लांट, पिन औि सौि ऊजा ा संयंत्र औि इसके सबं ंषधत षनकासी नेटिका की आउटेज योजना की योजना बनाई जाएगी। 7. पारेर्ण आउटेज प्लाननंग को जेनिेशन आउटेज प्लाननंग औि षितिण प्रणाली आउटेज प्लाननंग के साथ सामंजस्य स्थाषपत क्रकया जाएगा औि आउटेज प्लाननंग को जेनिेशन औि पारेर्ण आउटेज प्लाननंग के साथ सामंजस्यपूणा बनाया जाएगा। 8. इस अनुभाग म ें षनर्दष्टा अनुसूषचत आउटेज के संबंध में आगामी षित्तीय ििा के षलए िार्िाक आउटेज योजना के संबंध म ें एक कैलेंडि तैयाि क्रकया जाएगा। 9. एसएलडीसी के पास षनम्नषलषखत घटनाओं के घरटत होने की षस्थषत म ें क्रकसी भी षनयोषजत आउटेज को स्थषगत किन े का अषधकाि होगा: (क) प्रमुख षग्रड गड़बड़ी (जैसे, आंषशक/पूण ाब्लैकआउट); (ख) षसस्टम आइसोलेिि; औि (ग) षसस्टम म ेंकोई अन्य घटना जो प्रस्ताषित आउटेज द्वािा षसस्टम सुिक्षा पि प्रषतकूल प्रभाि डाल सकती ह।ै 10. षसस्टम म ें आपात षस्थषत के मामले म,ें षजसम ें उत्पादन की हाषन, पारेर्ण लाइन का टूटना, षग्रड म ें गड़बड़ी औि षसस्टम आइसोलेिि जैसी घटनाएं शाषमल हो सकती ह,ैं एसएलडीसी षनयोषजत आउटेज की मंजूिी स े पहल े षस्थषत की उषचत समीक्षा कि सकता ह:ै बशते क्रक समय-समय पि एसएलडीसी द्वािा अषधसूषचत 10 मेगािाट औि उससे अषधक क्षमता के षबजली स्टेशनों की अनुसूषचत कटौती िार्िाक योजना के अधीन होगी। 11. एसएलडीसी प्रत्येक ििा के षलए 31 क्रदसंबि तक अगल े षित्तीय ििा के षलए अपनी आउटेज योजना षलषखत रूप म ें आिपीसी को तैयाि औि प्रस्ततु किेगा। इनम ें प्रत्येक जनिेटटंग यूषनट/पारेर्ण लाइन/इंटिकनेन्टंग ट्ांसिामाि की पहचान शाषमल होगी षजसके षलए आउटेज के जलए बिाई िा रही योजना, आउटेज के कािण, प्रत्येक आउटेज के षलए पसंदीदा जतजथ औि उसकी अिषध औि जहां लचीलापन ह,ै जपद स े जपद प्रािंभ षतषथ औि निीनतम समाषप्त षतषथ शाषमल होगी। एसएलडीसी अगल े षित्तीय ििा के षलए पीक औि ऑि-पीक परिदश्ृ य के षलए लोड जेनिेशन बैलेंस रिपोट ा आिपीसी को 31 अ्टूबि तक प्रस्तुत किेगा। घाटे/अषधशेि के प्रबंधन के षलए िार्िाक योजनाओं को लोड जेनिेशन बैलेंस रिपोट ा (एलजीबीआि) म ें स्पष्ट रूप स े दशााया जाएगा। 12. क्षेत्रीय षबजली प्रणाली को प्रभाषित किने िाले षबजली स्टेशनों औि ईएचिी पारेर्ण लाइनों की अनुसूषचत कटौती केिल एसएलडीसी के समन्िय म ेंआिएलडीसी की मंजूिी स ेप्रभाषित होगी। 13. एसएलडीसी यह सुषनषित किेगा क्रक ििा की कम षबजली मांग की अिषध के दौिान िाज्य की उत्पादन इकाइयों को िार्िाक िखिखाि के षलए बाहि ल ेजाया जाए। 14. एसएलडीसी अपनी िेबसाइट पि त्रैमाषसक, अध-ा िार्िाक, िार्िाक आउटेज रिपोट ाअपलोड किेगा। 10.4 शटडाउन शड्ये लू का लाभ उठाना 1. एसएलडीसी दैषनक आधाि पि अगल े दो क्रदनों के षलए प्रस्ताषित आउटेज शेड्यूल की समीक्षा किेगा औि क्रकसी भी आकषस्मकता या षस्थषत जैसे क्रक षग्रड की गड़बड़ी, षसस्टम आइसोलेिि, आंषशक ब्लैक आउट या षसस्टम म ें क्रकसी अन्य घटना के मामले में प्रषतकूल प्रभाि पड़ सकता ह।ै प्रस्ताषित आउटेज द्वािा षसस्टम सुिक्षा, यह उसके कािणों को बतात े हुए क्रकसी भी षनयोषजत आउटेज को स्थषगत कि सकता ह।ै ऐसे मामलों म ें उपयोगकताा के पिामश ा से संशोषधत षतषथयों को अंषतम रूप क्रदया जाएगा। 2. एसटीयू औि उपयोगकताा को आउटेज का लाभ उठाने स ेपहल े एसएलडीसी का अनुमोदन प्राप्त किना होगा।28 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 3. जहां षनयोषजत आउटेज का लाभ उठाने के कािण उपभोक्ताओं को षबजली आपूर्त ा म ें बाधा उत्पन्न होती ह,ै षितिण लाइसेंसधािी को आयोग की पिू ा स्िीकृषत प्राप्त किनी होगी औि आपूर्ता समय में बाधा के संबंध म ें दैषनक समाचाि पत्र म ें प्रकाषशत किके उपभोक्ताओं को पूिा सूचना भी देनी होगी। अध्याय - 11: आकषस्मकता योजना 11.1 उद्देश्य इस अध्याय का उद्देश्य आिश्यक लोड, उत्पादन स्टेशनों की क्षमताओं औि िाज्य पारेर्ण प्रणाली की परिचालन बाधाओं को ध्यान म ें िखते हुए, िाज्य पारेर्ण प्रणाली या क्षेत्रीय षसस्टम ब्लैकआउट की षस्थषत म ें सबसे तेज़ संभि पुनप्रााषप्त के षलए सभी उपयोगकतााओं की षजम्मेदारियों को परिभाषित किना ह।ै 11.2 आकषस्मकता योजना प्रक्रिया 1. एसएलडीसी षनम्नषलषखत प्रकाि की आकषस्मकताओं को कुशलतापूिाक संभालेगा औि षसस्टम को सामान्य षस्थषत म ें बहाल किेगा: (क) षबजली स्टेशनों/उप-स्टेशनों स े षनकलन े िाली पारेर्ण लाइनों की बाि-बाि रट्नपंग के कािण केंद्र शाषसत प्रदेश जम्म ू औि कश्मीि औि केंद्र शाषसत प्रदेश लद्दाख म ें आंषशक षसस्टम ब्लैकआउट (ख) केंद्रशाषसत प्रदेश जम्मू-कश्मीि औि केंद्रशाषसत प्रदेश लद्दाख म ेंपूणा ब्लैक आउट (ग) षसस्टम आइलैंड/ षसस्टम षिभाजन 2. स्टाट-ा अप पािि को पूिा किने के षलए प्रत्येक पािि स्टेशन पि पयााप्त क्षमता के डीजल जेनिेटटंग (डीजी) सेट उपलब्ध किाए जाएंगे। 3. इंटि स्टेट पारेर्ण प्रणाली के साथ इंटि-कने्शन िाले सभी षबजली स्टेशनों औि 220 केिी, 132 केिी, 110 के औि 66 केिी उप-स्टेशनों पि नसंिोनाइनज़ंग सुषिधा उपलब्ध होगी। 4. षसस्टम/िाज्य म ें आंषशक ब्लैकआउट के मामल े म,ें पािि स्टेशन इकाइयों की शीघ्र बहाली को प्राथषमकता दी जानी ह,ै जो रट्प हो गई ह।ैं 5. संपूणा क्षेत्रीय ब्लैकआउट की षस्थषत म,ें एसएलडीसी पूिे षग्रड की शीघ्र बहाली के षलए क्षेत्रीय लोड षडस्पैच सेंटि (आिएलडीसी) के षनदेशों का समन्िय औि पालन किेगा। 6. आपूर्त ा की सुिषक्षत औि तेज बहाली के षलए, एसएलडीसी िाज्य के अंदर प्रमुख उत्पादन इकाइयों, लाइनों, ट्ांसिामाि औि लोड के षलए संचालन का उषचत िम तैयाि किेगा। संचालन के िम म ें सर्काट ब्रेकि, आइसोलेटसा, ऑन-लोड टैप-चेंजसा आक्रद को खोलना, बंद किना/रट्प किना शाषमल होगा। 11.3 पनु स्थापा ना प्रक्रिया 1. आंषशक/पूण ा ब्लैकआउट के अतं गषत िाज्य षग्रड की बहाली के षलए षिस्तृत औि प्रक्रिया आिएलडीसी औि सभी उपयोगकतााओं के पिामश ा स े एसएलडीसी द्वािा षिकषसत की जाएगी औि आईईजीसी के अंतगतष षनधाारित षसस्टम पुनस्थाापना प्रक्रिया के अनरूु प होगी। प्रक्रिया की िार्र्षक समीक्षा की िाएगी/अपडेट की जाएगी। 2. िाज्य के अंदर प्रत्येक उपयोगकताा के षसस्टम के आंषशक/पूणा ब्लैकआउट के अंतगतष बहाली के षलए षिस्तृत प्रक्रियाओं को संबंषधत उपयोगकता ा द्वािा एसएलडीसी के समन्िय स ेअंषतम रूप क्रदया जाएगा। 3. ब्लैक स्टाट ा सुषिधा, अंतििाज्यीय/अंतिक्षेत्रीय संबंध, नसंिोनाइनज़ंग पॉइंट औि प्राथषमकता पि बहाल क्रकए जाने िाल े आिश्यक लोड िाले उत्पादन स्टेशनों की सूची एसएलडीसी के पास उपलब्ध होगी। 4. बहाली प्रक्रिया के षलए केिल षग्रड सामान्य षस्थषत बहाल होने तक परिचालन संचाि के षलए आिश्यक सभी संचाि चैनलों का उपयोग क्रकया जाएगा। 5. आकषस्मक योजना पूिोक्त षसद्धांतों के अनुसाि औि समय-समय पि अपडेट क्रकए गए पारेर्ण प्लाननंग मापदंड 2023 पि सीईए मैनुअल के अनुसाि की जाएगी। आकषस्मकता के षलए मानदंड की संषक्षप्त प्रक्रिया औि अिधािणाए ं अनुबंध- ि में दी गई ह।ैं[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 29 11.4 आकषस्मक योजना पि लाग ूषिशिे षिचाि 1. िाज्य पारेर्ण प्रणाली या क्षेत्रीय षसस्टम ब्लैकआउट षस्थषतयों की बहाली की प्रक्रिया के दौिान, िोपटेज औि आिृषत्त के सामान्य मानकों पि जोि देन ेकी आिश्यकता नहीं ह ैऔि इसे एसएलडीसी के षििेक पि छोड़ा जा सकता ह।ै 2. षितिण लाइसेंसधािी गिै -आिश्यक भािों की अलग स े पहचान किेंग,े षजन्ह ें षसस्टम आकषस्मक परिषस्थषतयों के दौिान बंद िखा जा सकता ह।ै िे प्रत्येक मामल े म ें संबंषधत लोड ब्लॉक के साथ एक उषचत शेड्यूल भी तैयाि किेंगे। गैि-आिश्यक लोड केिल तभी डाला जा सकता ह ै जब षसस्टम सामान्य षस्थषत बहाल हो या एसएलडीसी द्वािा सलाह दी जाए। 3. सभी उपयोगकतााओं को अनुषचत जपदबाजी या अनुषचत लोनडंग संचालन षस्थषतयों के कािण षसस्टम के षद्वतीयक पतन को िोकने के षलए प्रक्रियाओं को पूिा किन े म ेंषिशेि ध्यान देना होगा। 4. षस्थषत की तात्काषलकता के बािजूद, घटना की बाद की जांच औि बहाली प्रक्रिया की दक्षता की समीक्षा की सुषिधा के षलए सभी उपयोगकतााओं द्वािा सभी परिचालनों औि परिचालन संदेशों की त्िरित औि पूण ा लॉनगगं सुषनषित की जाएगी। ऐसी जांच घटना के बाद की जाएगी, औि इसकी अगली बैठक म ें िाज्य षग्रड कोड समीक्षा सषमषत के समक्ष िखी जाएगी। 11.5 गडबडी के बाद षिश्लिे ण आिएलडीसी के क्रदशाषनदेशों औि षनदेशों के अनुसाि एसएलडीसी सभी प्रमुख षग्रड गड़बड़ी की गड़बड़ी की घटना के बाद का षिश्लेिण किेगा, षजसके परिणामस्िरूप पूणा या आंषशक षसस्टम ब्लैकआउट हो जाएगा औि िाज्य षग्रड के क्रकसी भी षहस्स े का नसंिनाइज़ेशन बंद हो जाएगा। सभी उपयोगकता ा एसएलडीसी को सक्षम किेंग,े षसस्टम गड़बड़ी का षिश्लेिण किेंग े औि आिएलडीसी को रिपोट ाप्रस्तुत किेंगे। अध्याय - 12: उपयोगकताओंष के मध्य सीमा सरु क्षा 12.1 उद्देश्य इस अध्याय का उद्देश्य लोडतीय जिद्युत जियम 1956 में जिधाषठरत सुरक्षा के जसद्धांतों पर एक सहमजत और जस्ट्थरता प्राप्त करिा ह ै िो ितषमाि में लागू हैं और एक उपयोगकताष और दसू रे उपयोगकताष के बीच अंतर उपयोगकताष सीमा (क्रॉस बाउंड्री) में काम करते समय जिद्युत अजधजियम, 2003 के अंतगषत बिाए गए जियमों द्वारा प्रजतस्ट्थाजपत ककए िाएंगे। । 12.2 नाषमत व्यषक्त एसटीयू औि सभी उपयोगकताा अपनी सीमा के पाि सुिक्षा के समन्िय के षलए षजम्मेदाि अषधकृत व्यषक्तयों को नामांक्रकत औि सूषचत किेंगे। इन व्यषक्तयों को नाषमत अषधकािी के रूप म ेंजाना जाएगा। 12.3 उपयोगकताओंष के मध्य सीमा सर्काट पि काम किन ेकी प्रक्रिया 1. एसटीयू उन सभी उपयोगकतााओं को नाषमत व्यषक्तयों के नाम, पदनाम औि टेलीिोन नंबिों की एक सूची जािी किेगा षजनकी उसके साथ सीधी अंति-उपयोगकता ा सीमा ह।ै जब भी सूची म ें नाषमत क्रकसी भी नाषमत व्यषक्त के नाम, पदनाम या टेलीिोन नंबि म ेंपरिितान होता ह,ै तो यह सूची तिु ंत अपडेट की जाएगी। 2. एसटीयू के साथ सीधी अंति-उपयोगकता ा सीमा िाले सभी उपयोगकता ा अपन े नाषमत व्यषक्तयों की एक समान सूची एसटीयू को जािी किेंगे। जब भी सूची म ेंनाम आक्रद में कोई परिितान होगा तो यह सूची तुिंत अपडेट की जाएगी। 3. जब भी उपयोगकता ा या एसटीय ू द्वािा अंति-उपयोगकताा सीमा के पाि कोई काया क्रकया जाना ह,ै तो उपयोगकताा या एसटीयू का नाषमत अषधकािी, जैसा भी मामला हो, अन्य संबंषधत नाषमत अषधकािी स े व्यषक्तगत रूप स े संपका करके लाइन ष्लयि पिषमट / पिषमट टू िका (पीटीडब्पय)ू की मांग करेगा । यक्रद काम किने का पिषमट व्यषक्तगत रूप स े प्राप्त नहीं क्रकया जा सकता ह,ै तो नाषमत अषधकािी टेलीिोन के माध्यम स े संपका किेगा औि दोनों एजेंषसयों की सही पहचान सुषनषित किन ेके षलए कोड िडा का आदान-प्रदान किेगा। 4. यक्रद काय ा एक षशफ्ट से अषधक चलता ह,ै तो नाषमत अषधकािी यह सुषनषित किेगा क्रक कायामुक्त किन े िाले नाषमत अषधकािी को काया की प्रकृषत औि संचालन म ें कोड शब्दों के बािे म ेंपूिी जानकािी दी गई ह।ै30 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 5. नाषमत अषधकािी आिश्यक काय ा को सुिषक्षत तिीके से किन े के षलए आिश्यक सािधाषनयां बरतिे औि बनाए िखन े म ें सहयोग किेंगे। स्थाषपत आइसोलेिि औि स्थाषपत अथ ष दोनों को "आदमी काम कर रह ें ह ैं " टैग के साथ बंद षस्थषत म ेंिखा जाएगा, जहां ऐसी सुषिधाएं मौजूद ह,ैं औि स्पष्ट रूप स ेपहचान की िाएगी। 6. काम तब तक शुरू नहीं होगा जब तक क्रक उपयोगकताा के काम के प्रभािी नाषमत अषधकािी, जो काम किना चाहते ह,ैं संतुष्ट नहीं हो जाते क्रक सभी सुिक्षा सािधाषनयां स्थाषपत कि ली गई ह।ैं यह नाषमत अषधकािी काम शुरू किन े की अनुमषत देन े के षलए काया दल को अनुमोक्रदत सुिक्षा दस्तािजे औि िका पिषमट (पीटीडब्पय)ू जािी किेगा। षनर्दष्टा ईएचिी लाइनों औि अन्य इंटिकने्शन के संबंध म ें काम किने का पिषमट एसएलडीसी की सहमषत स े जािी क्रकया जाएगा। 7. जब काया पूिा हो जाता ह ै औि सुिक्षा सािधाषनयों की आिश्यकता नहीं िह जाती ह,ै तो नाषमत अषधकािी, जो क्रकए जा िह े काय ा के षलए षजम्मेदाि ह,ै काय ा पिषमट िापस किने औि उन सुिक्षा सािधाषनयों को हटाने के षलए अन्य नाषमत व्यषक्त स े सीधे संपका किेगा। षनर्दष्टा ईएचिी लाइनों औि इंटिकने्शन के संबंध म ें काि्य पिषमट की िापसी की सूचना एसएलडीसी को दी जाएगी। 8. उपकिण को सेिा म ें िापस जोड़न े के षलए केिल तभी उपयुक्त माना जाएगा जब दो नाषमत अषधकारियों के बीच कोड िडा संपका का उपयोग किके सीधे संचाि द्वािा सभी सुिक्षा उपायों को हटाए जाने की पुषष्ट की जाती ह,ै औि यह सुषनषित ककया िाता ह ैकक काम किने िाली पाटी से कायष पिषमट की िापसी हो चुकी ह।ै 9. एसटीयू अंति-उपयोगकता ा सीमा सुिक्षा के षलए एक सहमत षलषखत प्रक्रिया षिकषसत किेगा औि इस े लगाताि अपडेट किेगा। 10. अंति-उपयोगकता ा सीमा सुिक्षा स े संबंषधत क्रकसी भी षििाद का समाधान एसटीयू के स्ति पि क्रकया जाएगा, यक्रद एसटीयू एक पक्ष नहीं ह।ै यक्रद एसटीयू एक पक्ष ह,ै तो षििाद को सुलझाने के षलए षििाद को िाज्य षग्रड कोड समीक्षा सषमषत को भेजा जाएगा। 12.4 षिशिे षिचाि 1. एसटीयू औि अन्य उपयोगकतााओं के सर्काट के बीच अंति-उपयोगकता ा सीमा के षलए, सभी उपयोगकताओंा को अनुमोक्रदत सुिक्षा षनयमों का पालन किना होगा, जो आईई षनयमों के अनुसाि होना चाषहए। 2. प्रत्येक नाषमत अषधकािी उसके द्वािा भेज े गए औि प्राप्त क्रकए गए सुिक्षा समन्िय स े संबंषधत सभी संचालन औि संदेशों का कालानुिषमक िम म ें एक स्पष्ट रूप स े षलषखत सुिक्षा लॉग बनाए िखेगा। सभी सुिक्षा लॉग कम स े कम 10 ििा की अिषध के षलए बनाए िखे जाएंगे। अध्याय-13: परिचालनात्मक घटना की रिपोर्टिंग 13.1 उद्देश्य यह अध्याय रिपोट ा की जाने िाली घटनाओं, अपनाए जाने िाल े रिपोर्टिंग माध्यम औि घटनाओं की रिपोर्टिंग के षलए एक सुसंगत दषृ ष्टकोण सुषनषित किने के षलए प्रदान की जाने िाली जानकािी को परिभाषित किता ह।ै 13.2 रिपोट ा किन ेयोग्य घटनाए ाँ 1. िाज्य पारेर्ण प्रणाली में उपयोगकता ा के षसस्टम पि परिचालन प्रभाि डालन े िाली सभी घटनाओं की सूचना एसटीय ू द्वािा एसएलडीसी औि उन उपयोगकतााओं को दी जाएगी षजनके षसस्टम प्रभाषित ह।ैं 2. उपयोगकता ा द्वािा उपयोगकताा के षसस्टम म ें िाज्य पारेर्ण प्रणाली पि परिचालन प्रभाि डालने िाली सभी घटनाओं की सूचना एसटीय ू औि एसएलडीसी को दी जाएगी औि जो बदल े म ें अन्य उपयोगकतााओं को सूषचत किेगा षजनके षसस्टम पि घटना का परिचालन प्रभाि हो सकता ह।ै 3. षनम्नषलषखत म ें से कोई भी घटना जो िाज्य पारेर्ण प्रणाली को प्रभाषित कि सकती ह,ै उसके षलए रिपोर्टिंग की आिश्यकता ह:ै क) ब्लैकआउट/आंषशक षसस्टम ब्लकै आउट[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 31 ख) षसस्टम आइलैंनडंग/षसस्टम षिभाजन ग) असाधािण रूप से उच्च/षनम्न षसस्टम िोपटेज या आिृषत्त। घ) प्रमुख सर्काट ब्रेकि, ट्ांसिामाि या बस बाि से संबंषधत गंभीि उपकिण समस्या। ङ) प्रमुख उत्पादन इकाई की षििलता। च) षसस्टम षस्प्लट, स्टेट पारेर्ण प्रणाली ब्रेकअि ेया ब्लैक स्टाटा। छ) पारेर्ण लाइन, आईसीटी (इंटि कनेन्टंग ट्ांसिामाि) औि कैपेषसटि बैंकों की रट्नपंग। ि) बडी आग लगािा झ) सुिक्षा उपकिणों की बड़ी षििलता. ञ) उपकिण औि पारेर्ण लाइन ओििलोड। ट) दघु ाटनाए-ाँ घातक औि सामान्‍दय ि) लोड िैश / लोड की हाषन ड) अत्यषधक षनकासी षिचलन. ढ) छोटे उपकिण अलाम ा ण) सुिक्षा मानकों का उपलघं न त) समय-समय पि आयोग द्वािा षनधाारित कोई अन्य कायािम षपछली दो रिपोट ा योग्य घटनाए ाँ जो कम परिणाम िाली ह,ैं लेक्रकन षजनका अभी भी िाज्य पारेर्ण प्रणाली पि प्रभाि ह ै औि उन्ह ें उषचत रूप स े मामूली के रूप म ें िगीकृत क्रकया जा सकता ह,ै उन्ह ें शीघ्र सुधािात्मक कायषिाही की आिश्यकता होती ह।ै 13.3 रिपोर्टिंग प्रक्रिया 1. 33 केिी से ऊपि की लाइनों औि उपकिणों पि होने िाली सभी घटनाएं औि िे सभी लाइनें षजन पि िाज्य पारेर्ण प्रणाली को प्रभाषित किन े िाला अंति-उपयोगकता ा प्रिाह ह,ै तुिंत उपयोगकता ा या एसटीय ू द्वािा टेलीिोन पि या पािि लाइन िाहक संचाि आक्रद के माध्यम से मौषखक रूप से सूषचत क्रकया जाएगा षजनके उपकिण ह ैं एसएलडीसी को घटना का अनुभि हुआ ह।ै रिपोर्टिंग उपयोगकता ा या एसटीय ू ऐसी मौषखक रिपोटा के एक घंटे के अंदर एसएलडीसी को टेलीिोन संदेश/िै्स/ई-मेल द्वािा एक पुषष्टकिण रिपोटा प्रस्तुत किेगा। 2. एसएलडीसी अन्य उपयोगकतााओं या एसटीय ू को प्रभाषित किन े िाली क्रकसी भी घटना पि क्रकसी भी उपयोगकताा स े स्ित: रिपोट ा मांगेगा। हालााँक्रक, यह क्रकसी भी उपयोगकता ा को िाज्य षग्रड कोड के प्रािधानों के अनुसाि एसएलडीसी / एसटीयू को घटनाओं की रिपोट ाकिने के दाषयत्ि से मुक्त िहीं करेगा। 3. मौषखक रिपोट ा की पुषष्ट किन े िाले षनम्नषलषखत षिििणों िाली एक षलषखत रिपोटा उपयोगकता ा या एसटीयू द्वािा एसएलडीसी को भेजी जाएगी। (i) घटना का स्थान (ii) घटना का समय औि जतजथ। (iii) सीधे तौि पि शाषमल संयंत्र औि उपकिण। (iv) खराबी षनषहताथा की प्रकृषत के साथ रिले संकेतों का षिििण। (v) मांग/पािेिण या उत्पादन (एमिी म)ें बाषधत औि रुकािट की अिषध। (vi) घटना का संषक्षप्त षिििण एि ंकािण। (vii) सेिा पि लौटन े का अनुमाषनत समय (viii) आपूर्त ा बहाल किन े के षलए िैकषपपक व्यिस्था की संभािना32 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] (ix) समय के साथ रट्नपंग का िम (x) उपचािात्मक उपायों के साथ लाल झंडों का षिििण (xi) सभी रिकॉर्डिंग उपकिणों, इिेंट लॉगि, डीएएस, आक्रद के रिकॉड ा की प्रषतयों सषहत कोई अनय् प्रासंषगक जानकािी। 13.4 रिपोर्टिंग के जलए प्रपत्र दघु ाटनाओं के अलािा िाज्य षग्रड कोड समीक्षा सषमषत द्वािा समय-समय पि मानक रिपोर्टिंग िॉमा अनुमोक्रदत क्रकया जाएगा। मानक रिपोर्टिंग िॉमा एसटीय ू औि एसएलडीसी की िेबसाइट पि उपलब्ध किाया जाएगा। डेटा पंजीकिण अध्याय-17 म ें एक षिषशष्ट प्रपत्र संलग्न ह ै(परिषशष्ट-च)। 13.5 बड़ी षििलता जब भी कोई बड़ी षििलता जैसे क्रक उत्पादन इकाई या ईएचिी पारेर्ण लाइन का रट्नपंग, िैधाषनक सीमा के बाहि षसस्टम फ्रीक्वेंसी या िोपटेज, षसस्टम ओििलोड, दघु ाटनाए ं होती ह,ैं तो उपयोगकताा एसटीयू / एसएलडीसी / आयोग स े ऐसी षििलता के कािण के बािे म ें पूछताछ किेगा औि स्थाषपत किेगा। एसटीयू आग े के षिश्लेिण के षलए एक महीने के अंदर िाज्य षग्रड कोड समीक्षा सषमषत को रिपोट ा प्रस्ततु किेगा। आयोग द्वािा मांग े जाने पि प्रमुख षििलताओं पि एक षिस्तृत रिपोट ा आयोग को सौंपी जाएगी। 13.6 दघु टा ना की रिपोर्टिंग यक्रद षबजली के उत्पादन, पािेिण, आपूर्त ा के षितिण या उपयोग के संबंध म ें या क्रकसी व्यषक्त की षिद्युत लाइनों या षिद्युत संयंत्र के क्रकसी भी षहस्स े के संबंध म ें कोई दघु ाटना होती ह ै औि दघु ाटना के परिणामस्िरूप मानि हाषन होने की संभािना ह ै या पश ु जीिन या क्रकसी इंसान या जानिि को कोई चोट लगन े पि षबजली अषधषनयम, 2003 की धािा 161 के अनुसाि कायषिाही की िाएगी। अध्याय - 14: शड्ये नू लगं औि लोड प्रिे ण 14.1 उद्देश्य यह अध्याय उत्पादन की दैषनक अनुसूची तैयाि किन े औि जािी किने म ें एसएलडीसी की कािािाइयों औि षजम्मेदारियों औि आिश्यक डेटा की आपूर्त ा किन े औि शेड्यूल का अनुपालन किन े के षलए उपयोगकतााओं की षजम्मेदारियों का षिििण देता ह।ै 14.2 सामान्य 1. एसएलडीसी की जिम्न जिम्मेदाठरयाँ होंगी: (i) िाज्य उत्पादन स्टेशनों के उत्पादन का षनधाािण/प्रेिण (उनके एम्बेडेड लाइसेंसधारियों के उत्पादन सषहत), (ii) अपन ेषनयंत्रण क्षत्रे में मांग को षिषनयषमत किना, (iii) आईएसजीएस स ेउनकी षनकासी का षनधाािण (संबंषधत संयंत्र की अपेषक्षत क्षमता म ेंउनके षहस्स ेके अंदर) (iv) अनुबंधों के अनुसाि एम्बेडेड जेनिेटि/उपभोक्ताओं के षलए दीघाकाषलक, मध्यम अिषध औि अपपकाषलक खुली पहुचं की अनुमषत देना, औि (v) सीईआिसी के संबंषधत षिषनयमों के अनुसाि क्षेत्रीय षग्रड स े उनके षनयंत्रण क्षत्रे म ें शुद्ध षनकासी को षिषनयषमत किना। 2. कायािम तैयाि कित े औि अंषतम रूप देते समय षनम्नषलषखत षिषशष्ट नबंदओंु को ध्यान म ें िखा जाएगा: (i) एसएलडीसी 15 षमनट आग े के उत्पादन कायािम के अनुसाि सभी उत्पादन औि आयात को षिषनयषमत किन े के षलए आिश्यक प्रेिण षनदेश जािी किेगा। एसएलडीसी द्वािा क्रकसी भी प्रेिण षनदेश के अभाि म,ें एसजीएस अगल े क्रदन के उत्पादन कायािम के अनुसाि उत्पादन/षनयाात कि सकता ह ै औि जरूितमंद उपयोगकतााओं के षलए आपूर्त ा को षिषनयषमत किने के षलए एसएलडीसी को इसकी सूचना दे सकता ह।ै[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 33 (ii) एसएलडीसी समग्र िाज्य उत्पादन को इस तिह से षिषनयषमत किेगा क्रक ऊजाा क्षमता िाले षनम्नषलषखत प्रकाि के षबजली स्टेशनों से उत्पादन, यक्रद उपयोग नहीं क्रकया जाता ह,ै तो व्यथष नहीं होगा। क) नदी प्रिाह (भंडािण के षबना) या नहि आधारित हाइड्रो स्टेशन। ख) तालाब औि भंडािण प्रकाि के हाइड्रो-स्टेशनों के साथ नदी का प्रिाह जब जल स्ति चिम जलाशय स्ति पि होता ह ैया प्रिाह के अनुसाि चिम जलाशय स्ति को छून े की उम्मीद होती ह।ै ग) पिन औि सौि ऊजाा आधारित उत्पादन स्रोत। घ) उपलब्ध सौि ऊजाा का उपयोग किन े के षलए आिश्यक पािंपरिक ईंधन स े न्यूनतम उत्पादन िाले हाइषब्रड सौि ऊजा ा स्टेशन। (iii) एसजीएस को प्रेिण षनदेश एसएलडीसी द्वािा मानक प्रारूप म ेंसूषचत क्रकए जाएंगे। 14.3 शड्ये नू लगं औि प्रिे ण प्रक्रिया 1. आईएसजीएस औि एसजीएस/आईपीपी/सीपीपी के शेड्यूनलंग की प्रक्रिया नीच ेिर्णात अनुसाि होगी i) 00.00 बज े स ेशुरू होने िाल े प्रत्येक क्रदन को 15 षमनट के अंतिाल के 96 समय खंडों म ेंषिभाषजत क्रकया जाएगा। ii) प्रत्येक क्रदन सुबह 9:00 बजे तक, एसजीएस एसएलडीसी को अगल े क्रदन के षलए अनुमाषनत स्टेशन-िाि ए्स- पािि प्लांट मेगािाट औि एमडब्पयूएच क्षमताओं के बािे म ें सूषचत किेगा, अथाषत अगल े क्रदन 00.00 स े 24.00 बज े के बीच। iii) प्रजतक्रदन सुबह 9:00 बज े तक प्रत्येक षितिण लाइसेंसधािी एसएलडीसी को अगल े क्रदन अथातष अगल े क्रदन 00.00 स े 24.00 बज ेके बीच मेगािाट औि मेगािाट म ें समग्र आिश्यकता के बािे म ेंसूषचत किेगा। iv) प्रजतक्रदन सुबह 10:00 बज े तक, आिएलडीसी द्वािा क्रदए गए षिषभन्न अंतििाज्यीय उत्पादन स्टेशनों म ें िाज्य की हकदारियों के साथ उपिोक्त जानकािी, एसएलडीसी एसजीएस की कुल उत्पादन क्षमता, आईएसजीएस षद्वपक्षीय इंटिचेंज स े पात्रता, यक्रद कोई हो, को सकं षलत किेगा। v) दोपहर बाद 3:00 बिे तक, एसएलडीसी एसजीएस के उत्पादन कायािम औि प्रत्येक षितिण लाइसेंसधारियों के षनकासी कायािम को अंषतम रूप देगा, आरएलडीसी को प्रत्येक आईएसिीएस स े िुद्ध जिकास की िािकारी के साथ अन्‍दय राज्य/राज्यों के साथ सहमत और अपेजक्षत जद्वपक्षीय जिजिमयों के बारे में िािकारी देगा और राज्य म ें अिुमाजित मागं /उपलबद्धता और प्राप्त की िािे िाली अजतठरक्त जबिली के बारे में िािकारी दगे ा। vi) शाम 6:00 बज े तक, आिएलडीसी प्रत्येक आईएसजीएस स े िाज्य के षलए षनकासी कायािम की जानकािी एसएलडीसी को देगा। vii) शाम 7:00 बजे तक, एसएलडीसी जिम्न को सूषचत किेगा, क) अगल े क्रदन के षलए अलग-अलग घंटों के षलए मेगािाट म ें प्रत्येक एसजीएस के षलए ए्स-पािि प्लांट प्रेिण कायािम ख) अगल े क्रदन के षलए अलग-अलग घंटों के षलए मेगािाट म ें षितिण लाइसेंसधािी को "शुद्ध षनकासी अनुसूची"। viii) एसजीएस औि षितिण लाइसेंसधािी उपिोक्त स्टेशनिाि षनकासी अनुसूची में क्रकए जाने िाले क्रकसी भी संशोधन/परिितान को एसएलडीसी को िात 9:00 बज े तक या अषधमानतः पहल ेसूषचत किेंगे। ix) एसएलडीसी इस पि षिचाि किन े के बाद िात 10:00 बज े तक आिएलडीसी को संशोषधत कायािम बताएगा। 2. एसएलडीसी आिएलडीसी को आिश्यक डेटा भी दे सकता ह ैताक्रक आिएलडीसी स्ियं िाज्य के षलए सिोत्तम षनकासी कायािम तय कि सके। 3. एसएलडीसी षनम्नषलषखत को ध्यान म ें िखत े हुए अगल े क्रदन का उत्पादन कायािम तैयाि किेगा i) पारेर्ण प्रणाली म ें समय-समय पि बाधाएं आती ह।ैं ii) एसएलडीसी द्वािा अनुमाषनत 15 षमनट की लोड आिश्यकताएं।34 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] iii) बनाए िखन ेके षलए आिश्यक परिचालन मार्जान/भंडाि प्रदान किने की आिश्यकता। iv) प्रत्येक मामल े म ेंक्रकसी भी बाधा के साथ एसजीएस, सेंट्ल से्टि जेनिेटि औि अन्य से उत्पादन की उपलब्धता। 4. संचालन के क्रदन के दौिान, उत्पादन अनुसूची को षनम्नषलषखत शतों के अंतगषत संशोषधत क्रकया जा सकता ह:ै i) क्रकसी भी एसजीएस की एक इकाई के जबिन बंद होने की षस्थषत म,ें एसएलडीसी प्रभाषित एसजीएस द्वािा संशोषधत घोषित क्षमता के आधाि पि उत्पादन अनुसूची को संशोषधत कि सकता ह।ै संशोषधत घोषित क्षमता औि संशोषधत कायािम चौथ े टाइम ब्लॉक स े प्रभािी हो जाएंग,े उस समय ब्लॉक को ध्यान म ें िखत े हुए षजसमें आईएसजीएस या एसएसजीएस द्वािा संशोधन की सलाह दी गई ह।ै ii) क्रकसी भी षग्रड गड़बड़ी के मामल े म,ें सभी एसजीएस का जिधाषठरत उत्पादि औि सभी लाभार्थायों की षनधाारित षनकासी को षग्रड गड़बड़ी स े प्रभाषित सभी समय ब्लॉकों के षलए उनके िास्तषिक उत्पादन/षनकासी के बिाबि संशोषधत माना जाएगा। षग्रड गड़बड़ी औि उसकी अिषध का प्रमाणीकिण एसएलडीसी द्वािा क्रकया जाएगा iii) एसजीएस द्वािा घोषित क्षमता म ें संशोधन औि क्रदन की शेि अिषध के षलए लाभाथी द्वािा मांग की भी अषग्रम सूचना के साथ अनुमषत दी जाएगी। ऐस े मामलों म ें संशोषधत कायािम/घोषित क्षमता छठे टाइम ब्लॉक स े प्रभािी हो जाएगी, उस टाइम ब्लॉक को षगनत ेहुए षजसम ें एसएलडीसी म ेंसंशोधन के षलए अनुिोध प्राप्त हुआ ह।ै iv) यक्रद, क्रकसी भी समय, एसएलडीसी को लगता ह ै क्रक बेहति षसस्टम संचालन के षहत म ें अनुसूषचयों म ें संशोधन की आिश्यकता ह,ै तो िह स्िय ं ऐसा कि सकता ह,ै औि ऐसे मामलों म,ें संशोषधत अनुसूषचयां चौथे टाइम ब्लॉक स े प्रभािी हो जाएंगी, उस टाइम ब्लॉक की षगनती किते हुए षजसम ें एसएलडीसी द्वािा संशोषधत शेड्यूल जािी क्रकया गया ह।ै v) षनिथाक संशोधनों को हतोत्साषहत किने के षलए, एसएलडीसी, अपन े षििेकाषधकाि पि, षपछली अनुसूची/क्षमता के दो (2) प्रषतशत से कम के शेड्यूनलगं /क्षमता परिितानों को स्िीकाि किन े स े इनकाि कि सकता ह।ै vi) 24:00 बज े परिचालन क्रदिस समाप्त होने के बाद, क्रदन के दौिान अंषतम रूप से लाग ू क्रकया गया शेड्यलू (उत्पादन स्टेशनों के प्रेिण शेड्यूल औि िाज्यों के षनकासी शेड्यूल म ें सभी परिितानों को ध्यान म ें िखते हुए) एसएलडीसी द्वािा जािी क्रकया जाएगा। ये अनुसूषचयााँ िाषणषज्यक लेखांकन के षलए आधाि होंगी। प्रत्येक एसजीएस के षलए औसत ए्स-बस क्षमता भी एसएलडीसी को तथ्यों के आधार पर पूि ा सुझाि के आधाि पि तैयाि की जाएगी। vii) एसएलडीसी उपिोक्त सभी सूचनाओं का उषचत रूप स े दस्तािेजीकिण किेगा, अथाात, उत्पादन स्टेशनों द्वािा सुझाि दी गई स्टेशन-िाि अनुमाषनत पूिा-पािि प्लांट क्षमताए,ं लाभार्थायों द्वािा सुझाि कदय े गए षनकासी कायाक्िम, एसएलडीसी द्वािा जािी क्रकए गए सभी कायािम आकद। viii) शेड्यूनलगं की प्रक्रिया औि एसएलडीसी द्वािा जािी अंषतम शेड्यूल 5 क्रदनों की अिषध के षलए क्रकसी भी जांच/सत्यापन के षलए सभी घटकों के षलए खुला िहगे ा। यक्रद कोई गलती/चूक पाई जाती ह,ै तो आिएलडीसी तुिंत जांच पूिी किेगा औि उसमें संिोधि करेगा। ix) सौि औि पिन उत्पादन का शेड्यूल नीच े दी गई रूपिेखा का पालन किना चाषहए: क) षिचलन की गणना के उद्देश्य स े सौि औि पिन ऊजाा उत्पादन संयंत्रों का शेड्यूल बिािा होगा, जहां ऐसे संयंत्रों की उत्पादन क्षमता का योग एक पूनलंग स्टेशन पि जोड़ा जाता ह ै औि िो कने्शन नबंद ु पि एक लाइन (लाइनों) के माध्यम स े पारेर्ण या षितिण प्रणाली से िुडा होता ह ै िो 10 मेगािाट औि उससे अषधक ह ै औि कने्शन नबंद ु 33 केिी औि उससे अषधक ह,ै औि जहां पीपीए पि अभी तक हस्ताक्षि नहीं क्रकए गए ह।ैं इससे नीच े की क्षमता औि िोपटेज स्ति के षलए, साथ ही पुिान े पिन िामों के षलए (एक पिन िामा पिन टिबाइन जनिेटि का संग्रह ह ै जो एक सामान्य कने्शन नबंद ु से जुड़ा होता ह ै षजसे आमतौि पि पूनलंग स्टेशन के रूप म ें जाना जाता ह)ै , इसे पिन जनिेटि के बीच पािस्परिक रूप स े तय क्रकया जा सकता ह।ै औि पारेर्ण या षितिण उपयोषगता, जैसा भी मामला हो, यक्रद इसके षिपिीत कोई मौजूदा संषिदात्मक समझौता नहीं ह।ै पिन ऊजाा उत्पादन स्टेशनों द्वािा कायािम (सामूषहक लेनदने को छोड़कि) को एसएलडीसी को अषग्रम सूचना देकि संशोषधत क्रकया जा सकता ह।ै पिन ऊजाा उत्पादन स्टेशनों औि सौि ऊजाा उत्पादन स्टेशनों द्वािा संशोधन चौथे टाइम ब्लॉक स े प्रभािी होंगे, िहां पहला समय-ब्लॉक िह होता ह ै षजसम ें नोरटस क्रदया गया था। क्रकसी षिशेि क्रदन के 00:00 बज े से शुरू होने िाले 1.5 घंटे के प्रत्येक समय स्लॉट के षलए एक संशोधन हो सकता ह,ै जो क्रदन के दौिान अषधकतम 16 संशोधनों के अधीन ह ैया जैसा क्रक[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 35 समय-समय पि जािी औि संशोषधत सीईआिसी (सौर और पिन उत्पादन स्रोतों के जलए पूिाानुमान, शेड्यूनलगं , षिचलन षनपटान औि संबंषधत मामले) षिषनयम म ें षनर्दष्टा ह।ै ख) सौि ऊजाा उत्पादन का कायािम जनिेटि की उपलब्धता, मौसम पूिाानुमान, मौसम औि सामान्य सौि उत्पादन िि के आधाि पि जनिेटि द्वािा क्रदया जाएगा औि एसएलडीसी द्वािा इसकी जांच की जाएगी। यक्रद एसएलडीसी की िाय ह ै क्रक शेड्यूल यथाथािादी नहीं ह,ै तो िह सौि जनिेटि को शेड्यलू को संशोषधत किन े के षलए कह सकता ह ै ग) एसएलडीसी षग्रड सुिक्षा के दषृ ष्टकोण से निीकिणीय ऊजाा स्रोतों के प्रकाि अथाषत पिन या सौि के आधाि पि निीकिणीय ऊजा ा उत्पादन स्टेशनों स े शेड्यूल का रिकॉड ा बनाए िखेगा। िाज्य म ें उत्पादन स्टेशनों का षनधाािण कित े समय, षसस्टम ऑपिेटि का लक्ष्य उपलब्ध सौि औि पिन ऊजाा का पूिी तिह स े उपयोग किना होगा। 14.4 षनकासी शड्ये नू लगं एसएलडीसी षनधाारित समय पि प्रत्येक षितिण लाइसेंसधारियों के षलए षनकासी अनुसूची के संग्रह, पिीक्षण औि संकलन के षलए षजम्मेदाि ह।ै प्रत्येक षितिण लाइसेंसधािी को अगल े क्रदन के षलए मेगािाट म ें 15 षमनट की औसत मांग का अनुमान एसएलडीसी को प्रदाि किना होगा। 14.5 जनिेशन षडस्पचै 1. एसजीएस एसएलडीसी द्वािा जािी प्रेिण षनदेश का तुिंत अनुपालन किेगा। क्रकसी षनदशे के पालन म ें क्रकसी भी अप्रत्याषशत करठनाई की षस्थषत म ें एसजीएस तुिंत एसएलडीसी को सूषचत किेगा। 2. प्रेिण षनदेश ई-मेल/िै्स/टेलीिोन द्वािा जािी क्रकए जाएंग,े षजसकी पुषष्ट भेजने औि प्राप्त किन े िाले ऑपिेटिों के नाम के आदान-प्रदान औि प्रत्येक छोि पि इस े लॉग किने स े होगी। सभी मौषखक षनदेशों का तुिंत अनुपालन क्रकया जाएगा औि िै्स, टेली-नप्रंटि, या अन्यथा षलषखत पुषष्ट तुिंत जािी की जाएगी। 14.6 षजम्मदे ारिया ाँ 1. एसएलडीसी षनधाारित षबजली औि आंतरिक उत्पादन की मांग के मुकाबले िास्तषिक षबजली षनकासी की षनगिानी किेगा। एसएलडीसी प्रषतक्रियाशील षबजली षनकासी औि कैपेषसटि बैंकों की उपलब्धता की भी षनगिानी किेगा। 2. िाज्य के अंदर उत्पादन स्टेशन एसएलडीसी द्वािा जािी प्रेिण षनदेशों का पालन किेंगे। 3. षितिण लाइसेंसधािी औि ओपन ए्सेस ग्राहक षसस्टम की आिश्यकता के अनुसाि लोड औि प्रषतक्रियाशील षबजली षनकासी के प्रबंधन के षलए एसएलडीसी के षनदेशों का पालन किेंगे। 14.7 डेटा आिश्यकता उपयोगकता ाएसएलडीसी को अध्याय-17 डेटा पािीकरि, के परिषशष्ट-ड 2 में जिर्दष्टष डेटा प्रदाि करेंगे। अध्याय -15: मीटटिंग 15.1 उद्देश्य यह अध्याय मीटटिंग उपकिण के न्यूनतम स्िीकाय ा मानकों को परिभाषित किता ह ै जो लेखांकन, िाषणषज्यक षबनलगं औि षिद्युत ऊजाा के षनपटान के उद्देश्य स े षिषभन्न ऑपिेटटंग षसस्टम मापदंडों की उषचत मीटटिंग प्रदान किेगा औि जानकािी प्रदान किेगा जो षसस्टम को आर्थाक तिीके से संचाषलत किने म ें सक्षम किेगा। 15.2 क्षत्रे 1. यह मीटटिंग उन प्रथाओं को िाजमल किती ह ै षजन्ह ें षनयोषजत क्रकया जाएगा औि िे सुषिधाएं िाजमल की िाएंगी जो सक्रिय/प्रषतक्रियाशील/जक्लयर जिद्युत/ऊजा,ा पािि िै्टि, िोपटेज, आिृषत्त इत्याक्रद जैसे षिषभन्न पैिामीटिों का मापि औि रिकॉर्डिंग के षलए प्रदान की जाएंगी। 2. यह मीटटिंग टैरिि औि परिचालन मीटटिंग के षलए उत्पादन स्टेशनों, सब-स्टेशनों औि इंटििेस पि मीटटिंग की आिश्यकताओं को षनधाारित या संदर्भात किती ह।ै36 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 3. यह मीटटिंग मीटटिंग उपकिणों के अंशांकन, पिीक्षण औि कमीशननंग, संबंषधत सहायक उपकिण, ितामान ट्ांसिामाि औि िोपटेज ट्ांसिामाि के साथ ऊजाा मीटि की आिश्यकता को भी षनर्दष्टा किती ह।ै मीटटिंग मोटे तौि पि मीटटिंग, डेटा संचाि औि पिीक्षण प्रणाली के षिषभन्न तत्िों की तकनीकी षिशेिताओं को इंषगत किती ह।ै 15.3 प्रयोग यह मीटटिंग स्थाषपत मीटिों पि लाग ूहोगी औि जिम्न द्वािा स्थाषपत की जाएगी: क) एसटीयू/पारेर्ण लाइसेंसधािी, ख) िाज्य पारेर्ण प्रणाली से जुड़े उत्पादन स्टेशन, ग) िाज्य पािेिण प्रणाली से जुड़े षितिण लाइसेंसधािी, घ) षितिण लाइसेंसधारियों के ईएचिी उपभोक्ता सीधे िाज्य पारेर्ण प्रणाली से जुड़े हुए ह,ैं ङ) िाज्य पारेर्ण प्रणाली पि ओपन ए्सेस का लाभ उठाने िाल े ग्राहक, औि च) िाज्य पारेर्ण प्रणाली से जुड़े कैषप्टि जेनिेटि 15.4 मीटि के प्रकाि 1. सभी इंटिफेस मीटि, उपयोगकता ा मीटि औि ऊजा ा लेखांकन औि ऑषडट मीटि षस्थि प्रकाि के होंग।े 2. षनर्दष्टा प्रकाि का अनुपालन नहीं किन े िाले मीटिों को एसटीयू द्वािा स्िय ं या उपयोगकता ा के अनिु ोध पि बदला जाएगा। 3. मीटिों को आयोग के षनयमों या षनदेशों के अनुसाि या सिकाि के सुधाि कायािम के अनुसाि भी बदला जा सकता ह।ै 15.5 मानक सभी इंटिफेस मीटि, औि ऊजा ालेखांकन औि लेखापिीक्षा मीटि: क) लोडतीय मानक ब्यूिो (बीआईएस) के प्रासंषगक मानकों का अनुपालन करेंग।े यक्रद क्रकसी षिशेि उपकिण या सामग्री के षलए बीआईएस मानक उपलब्ध नहीं ह,ैं तो संबंषधत षब्ररटश मानक (बीएस), अंतिाष्ट्रा ीय इले्ट्ो- तकनीकी आयोग (आईईसी) मानक, या क्रकसी अन्य समकक्ष मानक का पालन क्रकया जाएगा: बशते क्रक जब भी क्रकसी अंतििाष्ट्रीय मानक या आईईसी मानक का पालन क्रकया जाता ह,ै तो उक्त मानक को िास्तषिक रूप से अपनान े स े पहल े लोडत म ें प्रचषलत न्‍दयूितम षसस्टम आिृषत्त, न्‍दयूितम षसस्टम िोपटेज, परििेश तापमान, आद्रता ा औि अन्य षस्थषतयों के षलए आिश्यक सुधाि या संशोधन क्रकए जाएंग;े ख) केंद्रीय षिद्युत प्राषधकिण (मीटिों की स्थापना औि संचालन) षिषनयम, 2006 स े जुड़ी अनुसूची म ें षनर्दष्टा औि समय-समय पि संशोषधत 'मीटिों की स्थापना औि संचालन' पि मानकों के अनुरूप होंग।े 15.6 मीटिों का स्िाषमत्ि 1. इंटिफेस मीटि क) षबजली लेखांकन औि षबनलंग के उद्देश्य स े अंति-िाज्य पारेर्ण प्रणाली (आईएसटीएस) के साथ इंटिकने्शन के नबंदओंु पि स्थाषपत सभी इंटिफेस मीटि सीटीयू के स्िाषमत्ि म ेंहोंगे। ख) षबजली लेखांकन औि षबनलंग के प्रयोजन के षलए उपिोक्त उप-खंड (क) के अंतगषत किि क्रकए गए षसस्टम को छोड़कि िाज्य पारेर्ण प्रणाली के साथ इंटिकने्शन के नबंदओंु पि स्थाषपत सभी इंटिफेस मीटि एसटीयू के स्िाषमत्ि म ें होंगे। ग) षबजली लेखांकन औि षबनलंग के प्रयोजन के षलए उपिोक्त उप-खंड (क) औि (ख) के अंतगता आन े िाल े मीटिों को छोड़कि, दो लाइसेंसधारियों के बीच अंति-संबंध के नबंदओंु पि स्थाषपत सभी इंटिफेस मीटि प्रत्येक छोि के संबंषधत लाइसेंसधािी के स्िाषमत्ि म ेंहोंगे।[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 37 घ) षबजली लेखांकन औि षबनलंग के प्रयोजन के षलए इंटि कने्शन के नबंदओंु पि स्थाषपत सभी इंटिफेस मीटि जो उपिोक्त उप खंड (क), (ख) औि (ग) के अंतगात नहीं आत े ह,ैं षबजली के आपूर्ताकता ाके स्िाषमत्ि म ेंहोंगे। 2. ऊजा ालखे ाकं न औि लखे ापिीक्षा मीटि ऊजाा लेखांकन औि ऑषडट मीटि का स्िाषमत्ि उत्पादन कंपनी या एसटीय ू के पास होगा, जैसा भी मामला हो। 15.7 मीटिों का स्थान 1. इंटिफेस मीटि औि ऊजाा लखे ांकन औि ऑषडट मीटि का स्थान नीच ेदी गई ताषलका के अनुसाि होगा: क्रम चरण मख्ु य जमटर चके जमटर स्टैंडबाई मीटि सख्ं या क. जनिेटटंग स्टेशन सभी आउटगोइंग िीडिों पि। सभी (i) जेनिेटि ट्ांसिामाि की उच्च आउटगोइंग िोपटेज (एचिी) साइड िीडिों पि। ii) सभी स्टेशन सहायक ट्ांसिामािों की उच्च िोपटेज (एचिी) साइड (व्याख्या: मौजूदा उत्पादन स्टेशनों पि स्थाषपत मुख्य, चेक औि स्टैंडबाय मीटि का स्थान जब तक प्राषधकािी द्वािा अनुमषत न दी जाए तब तक परिितान नहीं क्रकया जाएगा) ख. पारेर्ण एि ं एक ही लाइसेंसधारी के सब-स्ट्टेििों के बीच कोई अलग स्ट्टैंडबाय मीटर िहीं जितरण प्रणाली लाइि के एक छोर पर, और दो अलग-अलग होगा। दो अलग-अलग लाइसेंसधाठरयों के सब-स्ट्टेििों के बीच लाइसेंसधाठरयों के मामल े में लाइि के दोिों जसरों पर लग े मीटरों को लाइि के दसू रे छोर पर स्ट्थाजपत संबंजधत लाइसेंसधाठरयों के जलए मुख्य मीटर स्ट्टैंडबाय मीटर के रूप में मीटर मािा िाएगा। काम करेगा। ग. इंटर-किेलक्टंग आईसीटी की उच्च िोल्टेि (एचिी) साइड आईसीटी की जिम्न िोल्टेि रांसफामषर (एलिी) साइड। (आईसीटी) 2. उत्पादन कंपषनयां या लाइसेंसधािी आिश्यकता के आधाि पि अपन े षसस्टम म ें अषतरिक्त स्थानों पि मीटि स्थाषपत कि सकते ह।ैं 3. इंटिफेस मीटि i) षजन उपयोगकतााओं का अंति-िाज्य पारेर्ण प्रणाली या िाज्य पारेर्ण प्रणाली से इंटिकन्े शन ह ै औि उन्ह ें आयोग द्वािा खुली पहुचं की अनुमषत दी गई ह,ै उन्ह ें इंटिफेस मीटि प्रदान क्रकया जाएगा। ii) षितिण प्रणाली स े जुड़े औि खुली पहुचं की अनुमषत िाल े उपयोगकतााओं के षलए, इंटिफेस मीटि का प्रािधान षनयमों के अनुसाि क्रकया जा सकता ह ैया आयोग को इंटिफेस मीटि प्रदान क्रकया जाएगा। 4. ऊजा ालखे ाकं न औि लखे ापिीक्षा मीटि ऊजाा लेखांकन औि ऑषडट मीटि ऐस े स्थानों पि स्थाषपत क्रकए जाएगं े ताक्रक षबजली प्रणाली के षिषभन्न खंडों म ें उत्पन्न, प्रसारित, षितरित ऊजाा औि ऊजाा हाषन के लेखांकन की सुषिधा षमल सके। इन मीटिों का स्थान षनम्नानुसाि होगा: (i) जनिेटटंग स्टेशन 1) जनिेटि के स्टेटि टर्मानल पि; 2) स्टेशन औि यूषनट सहायक ट्ांसिामाि के एचिी औि एलिी क्रकनािों पि;38 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 3) षिषभन्न सहायकों के िीडिों पि। (ii) पारेर्ण प्रणाली सभी इनकनमंग औि आउटगोइंग िीडि (यक्रद इंटिफेस मीटि मौजूद नहीं ह)ैं । (iii) षितिण प्रणाली 1) सभी इिकमींग िाले िीडि (11 केिी औि ऊपि); 2) सभी आउटगोइंग िीडि (11 केिी औि ऊपि); 15.8 मीटिों की सटीकता श्रणे ी प्रत्येक मीटि सटीकता िगा की आिश्यकता को पूिा किेगा जैसा क्रक केंद्रीय षिद्युत प्राषधकिण "मीटिों की स्थापना औि संचालन" षिषनयम, 2006 (अनुलग्नक) स ेजुड़ी अनुसूची म ेंक्रदए गए मानकों म ें षनर्दष्टा ह।ै 15.9 मीटि की स्थापना 1. उत्पादन कंपनी या एसटीयू, जैसा भी मामला हो, स्थापना स े पहल े सभी मीटिों की जांच, पिीक्षण औि षिषनयमन किेगी औि केिल सही मीटि ही लगाए जाएंगे। 2. मीटि ऐसे स्थानों पि स्थाषपत क्रकया जाएगा, जो स्थापना, पिीक्षण, कमीशननंग, िीनडंग, रिकॉर्डिंग औि िखिखाि के षलए आसानी से पहुचं योग्य हो। 3. यक्रद सीटी औि िीटी मीटि का षहस्सा बनत े ह,ैं तो सेकेंडिी लीड म ें संभाषित षगिािट को कम किन े के षलए मीटि को यथासंभि उपकिण ट्ांसिामाि के पास स्थाषपत क्रकया जाएगा। 15.10 मीटिों का सचं ालन, पिीक्षण औि िखिखाि सभी प्रकाि के मीटिों का संचालन, पिीक्षण औि िखिखाि, जैसा भी मामला हो, उत्पादन कंपनी या एसटीयू द्वािा क्रकया जाएगा। 15.11 मीटि तक पहुचं उस परिसि का माषलक जहां मीटि स्थाषपत ह,ै मीटि की स्थापना, पिीक्षण, कमीशननंग, िीनडंग औि रिकॉर्डिंग औि िखिखाि के षलए एसटीयू के अषधकृत प्रषतषनषधयों तक पहुचं प्रदान किेगा। 15.12 मीटिों की सीनलगं 1. सीनलगं व्यिस्था क. सभी मीटिों को षनमााता द्वािा अपन े कायास्थल पि सील कि क्रदया जाएगा। षनमााता द्वािा अपन े कायों पि प्रदान की गई सील के अलािा, सभी मीटिों की सीनलंग केंद्रीय षिद्युत प्राषधकिण (मीटिों की स्थापना औि संचालन) षिषनयम, 2006 से जुड़ी अनसु ूची म ें क्रदए गए मानकों के अनुसाि षिषभन्न सीनलंग नबंदओंु पि षनम्नानुसाि की जाएगी। ख. इंटिफेस मीटि की सीनलंग भी आपूर्ताकता ा औि खिीदाि दोनों द्वािा की जाएगी। i. उपयोगकता ामीटिों की सीनलंग एसटीयू द्वािा की जाएगी। ii. ऊजाा लेखांकन औि लेखापिीक्षा मीटिों की सीनलंग एसटीय ू या उत्पादन कंपनी द्वािा की जाएगी, जैसा भी मामला हो। ग. प्रत्येक उपयोषगता के षलए सील अषद्वतीय होगी औि उपयोषगता का नाम या लोगो मुहिों पि स्पष्ट रूप स े क्रदखाई देगा। घ. केिल पेटेंट सील (षनमााता की सील षजसके पास सील के षनमााण का आषधकारिक अषधकाि ह)ै का उपयोग क्रकया जाएगा। ङ. पॉलीकाबोनेट या ऐिेषलक सील या प्लाषस्टक सील या होलोग्राक्रिक सील या क्रकसी अन्य बेहति सील का उपयोग क्रकया जाएगा।[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 39 च. नए मीटिों म ें लडे सील का प्रयोग नहीं क्रकया जाएगा। पुिानी लीड सील को चिणबद्ध तिीके स े नई सील से बदला जाएगा औि इसकी समय सीमा अनुमोदन के षलए एसटीय ू द्वािा आयोग को प्रस्तुत की जाएगी। 2. मीटिों स ेसील हटाना (क) इंटिफेस मीटि जब भी क्रकसी भी कािण स े इंटिफेस मीटि की सील को हटाना पड़ता ह,ै तो सील को हटाने औि इंटिफेस मीटि को क्रिि से सील किने के षलए दसू िे पक्ष को अषग्रम सूचना दी जाएगी। मीटिों के टूटने औि दोबािा सील होने को काम किन े िाली पाटी द्वािा मीटि िषजस्टि म ें दजा क्रकया जाएगा, षजसम ें हटाने औि दोबािा सील किने की जतजथ, टूटी औि नई सीलों की िम संख्या औि सील हटाने का कािण बताया जाएगा। . (ख)ऊजा ा लखे ाकं न औि लखे ापिीक्षा मीटि ऊजाा लेखांकन औि ऑषडट मीटि की सील केिल उत्पादन कंपनी या एसटीयू द्वािा हटाई जाएगी षजसके पास मीटि ह।ै 15.13 मीटिों की सिु क्षा 1. आपूर्ताकता ा या खिीदाि षजसके परिसि म ें इंटिफेस मीटि स्थाषपत ह,ैं उनकी सुिक्षा के षलए षजम्मेदाि होगा। 2. उपयोगकता,ा जहां तक परिषस्थषत अनुमषत दे, एसटीयू या षितिण लाइसेंसधािी के अपन े परिसि म ें स्थाषपत मीटि की सुिक्षा के षलए सािधानी बितेगा। 3. उत्पादन कंपनी या एसटीयू, षजसके पास ऊजाा लेखांकन औि लेखापिीक्षा मीटि ह,ैं इसकी सुिक्षा के षलए षजम्मेदाि होंगे। 15.14 मीटि िीनडंग एि ंरिकार्डिंग 1. इंटिफेस मीटि मीटि िीनडंग लेन े औि मीटि क्रकए गए डेटा को रिकॉडा किने, इंटिफेस मीटि स े जुड़ी सभी सूचनाओं का डेटाबेस बनाए िखन े औि मीटि क्रकए गए डेटा की शुद्धता को सत्याषपत किने औि षिषभन्न एजेंषसयों को प्रस्तुत किन े की षजम्मेदािी उपयुक्त पारेर्ण यूरटषलटी या षितिण लाइसेंसधािी की होगी। . 2. ऊजा ालखे ाकं न औि लखे ापिीक्षा मीटि मीटि क्रकए गए डेटा को रिकॉड ा किना, ऊजाा लेखांकन औि ऑषडट मीटि स े जुड़ी सभी सूचनाओं का डेटाबेस बनाए िखना औि मीटि क्रकए गए डेटा की शुद्धता को सत्याषपत किना उत्पादन कंपनी या एसटीय ू की षजम्मेदािी होगी। प्रत्येक उत्पादन कंपनी या एसटीय ू कुशल संचालन औि षसस्टम षिकास के षलए उषचत कायषिाही किने के षलए अपन े षसस्टम के षलए त्रैमाषसक, अध-ा िार्िाक औि िार्िाक ऊजा ा खाता तैयाि किेगी। 15.15 मीटि की षििलता या षिसगं षतया ाँ 1. इंटिफेस मीटि क. जब भी क्रकसी महीने के षलए मुख्य मीटि औि चेक मीटि की िीनडंग के बीच अंति 0.5% स े अषधक हो, तो षनम्नषलषखत कदम उठाए जाएंग:े i) सीटी औि िीटी कने्शन की जांच; ii) पिीक्षणाधीन मीटि से अषधक सटीकता िग ा के संदभा मानक मीटि के साथ साइट पि इंटिफेस मीटि की सटीकता का पिीक्षण; यक्रद ऐसी जांच या पिीक्षण के बाद भी अंति िहता ह,ै तो खराबीपूणा मीटि के स्ट्थाि पर सही मीटर लगा कदया जाएगा। ख. मीटि के जलन े औि मीटि के मापदंडों के अषनयषमत प्रदशान जैसी षिषशष्ट षििलताओं के मामल े म ें औि जब मीटि के पिीक्षण म ें पाई गई त्रुरट संबंषधत मानक म ें प्रदान की गई त्रुरट की अनुमेय सीमा स े अजधक ह,ै तो मीटि को तुिंत बदल क्रदया जाएगा।40 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] ग. ऐस े मामले म ें जहां मुख्य मीटि औि चेक मीटि दोनों खिाब हो जाते ह,ैं कम स े कम एक मीटि को तुिंत सही मीटि स े बदल क्रदया जाएगा। घ. षििलता अिषध के षलए षबनलंग: i) एसएलडीसी/एसटीयू मीटि की षििलता अिषध के दौिान खराबीपूणा मीटि की खपत के आकलन के षलए एक प्रक्रिया षिकषसत किेगा औि उसे अनुमोदन के षलए आयोग को प्रस्ततु किेगा। मीटि की षििलता अिषध के षलए षबनलंग इस अनुमोक्रदत प्रक्रिया के अनुसाि की जाएगी। ii) प्रत्येक टाइम स्लॉट के षलए मुख्य, चेक औि स्टैंडबाय मीटि द्वािा दजा की गई िीनडंग का एसएलडीसी द्वािा षिश्लेिण, िॉस चेक औि सत्यापन क्रकया जाएगा। िीनडंग म ें देखी गई षिसंगषतयों, यक्रद कोई हो, को ऊजा ा के उषचत लेखांकन के षलए एसएलडीसी द्वािा ऊजा ा लेखा एजेंसी को षलषखत रूप म ें सूषचत क्रकया जाएगा। एसएलडीसी िाज्य पारेर्ण यूरटषलटी या उपयोगकता ा को षिसंगषतयों के बािे म ें भी सूषचत किेगा, जो षनधाारित प्रािधानों के अनुसाि खराबीपूणा मीटिों के पिीक्षण, अंशांकन या प्रषतस्थापन के संबंध में आग े आिश्यक कायषिाही किेगा। ड) ख़िाब मीटि का तुिंत पिीक्षण औि अंशांकन क्रकया जाएगा। 2. ऊजा ालखे ाकं न औि लखे ापिीक्षा मीटि ऊजाा लेखांकन औि लेखापिीक्षा मीटिों को षनम्नषलषखत म ें स े क्रकसी भी असामान्यता की सूचना के तुिंत बाद उत्पादन कंपनी या लाइसेंसधािी द्वािा ठीक क्रकया जाएगा या प्रषतस्थाषपत क्रकया जाएगा: क. मीटि िीनडंग म ेंत्रुरटयां षनर्दष्टा सटीकता िगा के षलए षनधाारित सीमा के अिुसार िहीं ह;ैं ख. मीटि िीनडंग लोड मांग के सामान्य पैटना के अनुसाि नहीं ह;ै ग. मीटि से छेड़छाड़, या अषनयषमत प्रदशान या क्षषत। 15.16 मीटिों की छेड़छाड़-िोधी षिशिे ताएं मीटिों को केंद्रीय षिद्युत प्राषधकिण (मीटिों की स्थापना औि संचालन) षिषनयम, 2006 स े जुड़ी अनुसूची म ें क्रदए गए मीटिों की स्थापना औि संचालन पि मानकों के अनुसाि ऐसी छेड़छाड़-िोधी षिशेिताएं प्रदान की जाएंगी। 15.17 मीटिों की गणु ित्ता आश्वासन 1. एसटीयू उषचत संख्या में मान्यता प्राप्त पिीक्षण इकाइयााँ स्थाषपत किेगा या अन्य मान्यता प्राप्त पिीक्षण प्रयोगशालाओं की सेिाओं का उपयोग किेगा। एसटीयू को अपनी मौजूदा मीटि पिीक्षण प्रयोगशालाओं की एनएबीएल से मान्यता प्राप्त किने के षलए तत्काल कायषिाही किनी चाषहए, यक्रद पहल ेसे नहीं हुई ह।ै 2. उत्पादन कंपनी या एसटीयू यह सुषनषित किेगी क्रक षनमााता द्वािा प्रासंषगक बीआईएस या बीएस या आईईसी, जैसा भी मामला हो, की आिश्यकता का अनुपालन कित े हुए सभी प्रकाि, षनयषमत औि स्िीकृषत पिीक्षण क्रकए जाएं। 15.8 मीटिों का अशं ाकं न एि ं आिषधक पिीक्षण 1. इंटिफेस मीटि क) कमीशननंग के समय, प्रत्येक इंटिफेस मीटि को पिीक्षण के अंतगतष मीटि की तुलना म ें बेहति सटीकता िग ा के मानक संदभा मीटि का उपयोग किके सटीकता के षलए साइट पि ही एसटीय ू द्वािा पिीक्षण क्रकया जाएगा। ख) सभी इंटिफेस मीटिों का पिीक्षण हि पांच साल म ें कम स े कम एक बाि क्रकया जाएगा। जब भी मीटि द्वािा दजा की गई ऊजा ा औि अन्य मात्राएं अन्‍दय मीटिों के साथ असामान्य या असंगत हों तो इन मीटिों का भी पिीक्षण क्रकया जाएगा। जब भी इंटिफेस मीटि द्वािा दजा की गई मात्रा औि संचाि नेटिका के माध्यम स े षबनलंग केंद्र पि षनगिानी क्रकए गए संबंषधत मूपय के बीच अनुषचत अंति होता ह,ै तो संचाि प्रणाली औि टर्मानल उपकिण का पिीक्षण औि सुधाि क्रकया जाएगा। मीटिों का पिीक्षण एनएबीएल मान्यता प्राप्त मोबाइल प्रयोगशाला या क्रकसी मान्यता प्राप्त प्रयोगशाला का उपयोग किके क्रकया जा सकता ह ै औि यक्रद आिश्यक हो तो षनमााता के कायों म ें पुन: कैषलब्रेट क्रकया जा सकता ह।ै[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 41 ग) इंटिफेस मीटि का पिीक्षण औि अंशांकन आपूर्ताकता ा औि खिीदाि के प्रषतषनषधयों की उपषस्थषत म ें पिीक्षण की उषचत सूचना देकि क्रकया जा सकता ह।ै 2. ऊजा ालखे ाकं न औि लखे ापिीक्षा मीटि ऊजाा लेखांकन औि लेखापिीक्षा मीटिों का पिीक्षण पांच साल म ें कम से कम एक बाि साइट पि क्रकया जाएगा या जब भी सटीकता संक्रदग्ध हो या जब भी िीनडंग अन्य मीटिों, जैसे चेक मीटि, स्टैंडबाय मीटि की िीनडंग के साथ असंगत हो। पिीक्षण सीटी औि िीटी कने्शन को हटाए षबना क्रकया जाना चाषहए। पिीक्षण एनएबीएल मान्यता प्राप्त मोबाइल प्रयोगशाला के माध्यम स े माध्यषमक इंजे्शन क्रकट, माप इकाई औि िैंटम लोनडंग का उपयोग किके या क्रकसी भी मान्यता प्राप्त पिीक्षण प्रयोगशाला म ें क्रकया जा सकता ह ैऔि यक्रद आिश्यक हो तो षनमााता के कायों में पुन: कैषलब्रेट क्रकया जा सकता ह।ै 15.9 डेटा आिश्यकताएाँ िाज्य उत्पादन स्टेशन (एसजीएस) औि िाज्य पारेर्ण यूरटषलटी (एसटीयू) डेटा पंजीकिण अध्याय -17 के परिषशष्ट - जी म ेंषनर्दष्टा अनुसाि एक दसू िे औि एसएलडीसी को डेटा प्रदान किेंगे। अध्याय - 16: सिु क्षा औि लाइन ष्लयि पिषमट 16.1 यह अध्याय एसटीयू/षितिण लाइसेंसधािी के कायाित कर्मायों औि उपयोगकतााओं की सुिक्षा औि कायाित कर्मायों को काम किन े की अनुमषत देन े के षलए लाइन ष्लयि पिषमट जािी किन े के षलए उषचत रिकॉड ा के िखिखाि से संबंषधत ह।ै 16.2 सिु क्षा मानक: 1. एसटीयू को पारेर्ण लाइनों औि सबस्टेशनों के िखिखाि के षलए अपना स्िय ं का "सुिक्षा मैनुअल" तैयाि किना होगा औि एक मान्यता प्राप्त एजेंसी द्वािा इसकी जांच किानी होगी। इस सुिक्षा मैनुअल की प्रषतयां सभी सबस्टेशनों, एसटीय ू के संबंषधत षिभागों औि उपयोगकतााओं को प्रदान की जाएंगी। षशफ्ट ऑपिेटिों के मागादशान के षलए, प्रत्येक सबस्टेशन के षलए “ऑपिेशन औि िखिखाि मैनुअल" एसटीयू औि उपयोगकतााओं द्वािा तैयाि क्रकया जाएगा षजसमें सबस्टेशन म ें स्थाषपत षिषभन्न उपकिणों के षनमााताओं की षसिारिशों के आधाि पि सभी िखिखाि औि संचालन कायािम शाषमल होंगे। प्राप्त अनुभि औि उपकिणों के प्रषतस्थापन के आधाि पि इन मैनुअल की समय-समय पि समीक्षा की जाएगी। स्टेशन बैटरियों सषहत सभी उपकिणों के षलए एक िखिखाि िषजस्टि संबंषधत सबस्टेशनों पि िखा जाएगा। जब भी िखिखाि काया क्रकया जाएगा, इन्ह ें अपडेट क्रकया जाएगा औि आयोग द्वािा समय-समय पि समीक्षा की जाएगी। पारेर्ण औि सब-पारेर्ण लाइनों के षलए समान िषजस्टि बनाए िखा जाएगा। 2. 'संचालन औि िखिखाि मैनुअल' म ें उपकिणों पि काम की अनुमषत देन े के षलए प्रदान क्रकए जाने िाले आइसोलेिि औि अर्थिंग का षिििण स्पष्ट रूप स े षनर्दष्टा क्रकया जाएगा। षिषभन्न पृथक उपकिणों की षस्थषत को दशाान े िाले सबस्टेशन का 'नसंगल लाइन आिेख' स्टेशन म ें प्रमुखता से प्रदर्शात क्रकया जाएगा। अलग-अलग उपकिणों पि काम किन े के षलए लाइि पार्टसा (से्शन ्लीयिेंस) से ्लीयिेंस क्रदखाने िाले चाटा, जहां श्रषमकों को काम किन े की अनुमषत ह,ै प्रत्येक सबस्टेशन पि प्रमुखता से प्रदर्शात क्रकए जाएंगे। 3. एसटीयू औि उपयोगकता ा आईई षनयमों के अनुसाि सभी स्थानों पि एक षिषशष्ट स्थान पि प्रमुखता स े प्रदर्शात "खतरा” बोडा (प्रासंषगक आईएसएस नंबि 2551 के अनुसाि एक षडजाइन) षचपकाएंगे। 4. रिसीनिंग स्टेशनों औि सबस्टेशनों म ें षसस्टम बैटिी सषहत सभी उपकिणों को षनमााताओं के मैनुअल औि प्रासंषगक लोडतीय औि/या अंतििाष्ट्रीय मानकों के अनुसाि अच्छी षस्थषत म ें बनाए िखा जाएगा। इन सभी स्टेशनों म ें प्रदान की गई डीसी प्रणाली को षबना क्रकसी महत्िपूणा लीकेज किंट के उषचत रूप से बनाए िखा जाएगा। रिसाि की षनगिानी औि जमीनी खिाबी का पता लगान ेके षलए ऑनलाइन षनगिानी प्रणाली अपनाई जाएगी। 16.3 लाइन ष्लयि पिषमट (एलसीपी): लाइन ष्लयि पिषमट जािी किन े औि लौटाने के दौिान संलग्न प्रारूप का उपयोग क्रकया जाएगा। प्रारूप - 1 षजसे "लाइन ष्लयि पिषमट के षलए अनिु ोध" के रूप में नाषमत क्रकया गया ह,ै का उपयोग अनुिोध किन े िाले सुिक्षा समन्ियक द्वािा क्रकया जाएगा जो एक अषधकृत व्यषक्त ह।ै लाइन ष्लयि पिषमट जािी किते समय "लाइन ष्लयि पिषमट" के रूप म ें नाषमत प्रारूप - 2 का उपयोग क्रकया जाएगा। षजस काय ा के षलए लाइन ष्लयि पिषमट षलया गया42 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] ह,ै उसके पूिा होने के बाद लाइन ष्लयि पिषमट की िापसी के षलए "लाइन ष्लयि रिटना" के रूप म ें षनर्दष्टा प्रारूप - 3 का उपयोग क्रकया जाएगा। प्रारूप-1 क्रमांक xxxxxxx लाइि जक्लयर परजमट की मागं कदिांक................ समय ………………… मैं श्री/श्रीमती जिम्नजलजखत ईएचटी/एचटी लाइि/उपकरण पर लाइि जक्लयर परजमट का अिरु ोध करता ह।ं ईएचटी/एचटी उपकरण/लाइि पहचाि:................. ककये िािे िाले कायों का जििरण: ........................ कायष पूरा होि े के जलए आिश्यक अिुमाजित समय: ...................... िाम और हस्ट्ताक्षर …………………………. ………………………. (लाइि जक्लयर परजमट का अिरु ोध करिे िाला व्यजक्त) (चालक दल का प्रभारी) पदिाम………………………… … जतजथ …………………… ………………………….. (सबस्ट्टेिि म ेंउपयोग के जलए िहां से लाइि जक्लयर परजमट िारी ककया िाएगा) क) लाइि जक्लयर परजमट िारी ककया गया: हां/िहीं ख) संख्या और िारी करिे की जतजथ (कोड संख्या): ग) िारी करिे का समय: घ) िापसी की जतजथ और समय: ई) ठटपपजणयाँ: िाँच सूची एलसीपी –च देख ें एलसीपी की रसीद मुझे ………………………….. (िारीकताष सुरक्षा समन्‍दियक का िाम) से पुजष्ट प्राप्त हुई ह ै की ………………………….(स्ट्थाि) कक सुरक्षा सािधाजियां स्ट्थाजपत कर दी गई ह ैं और उिके स्ट्थाि पर उन्‍दह ें हटाि े के जलए जिदेि तब तक िारी िहीं ककए िाएंगे िब तक कक उिका एलसीपी रद्द िहीं कर कदया िाता। िाम और हस्ट्ताक्षर……………………………… (लाइि जक्लयर परजमट का अिरु ोध करिे िाला व्यजक्त) ............................... पर क्रू के प्रभारी ........................... (जतजथ) को …………………….. (समय) प्रारूप-2 क्रमांक xxxxxx लाइि जक्लयर परजमट एलसीपी िंबर…………………………. कदिांक……………………………………समय…………. लाइि जक्लयर परजमट की िाचं सचू ी: (क) स्ट्थाि का िाम जिसके जलए लाइि जक्लयर परजमट िारी ककया गया ह।ै (ख) लाइि जक्लयर चाहिे िाले संदभष और प्राजधकारी: (एलसीपी मांग की क्रम संख्या इंजगत करें)।[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 43 (ग) एचिी उपकरण की पहचाि। (घ) स्रोत जििसे लाइि/उपकरण चािष ककया िाता ह।ै (ङ) उपरोक्त प्रत्येक स्रोत पर खुल ेसर्कषट िेकर/आइसोलेटटंग जस्ट्िच का िंबर/िाम। (च) क्या इसकी पुजष्ट हो गई ह ैकक लाइि दोिों छोर स ेकट गई ह।ै (छ) क्या लाइि दोिों जसरों पर अथयष ुक्त ह।ै (ि) क्या फीडर/उपकरण को जियंजत्रत करि े िाल े इिडोर जस्ट्िचजगयर के मामले म ें सर्कषट िेकर रक को हटा कदया गया ह ै जिसके जलए लाइि जक्लयर कदया गया ह।ै (झ) क्या फीडर/उपकरण को जियंजत्रत करि े िाले आइसोलेटटंग जस्ट्िच, जिसके जलए लाइि जक्लयर कदया गया ह,ै बंद ह ैंऔर सुरजक्षत ह।ैं (ञ) लाइि जक्लयर परजमट और एलसीपी िंबर िारी करि े का समय। (ट) अिुरोध करि े िाल ेसुरक्षा समन्‍दियक का िाम जिस पर एलसीपी िारी ककया गया ह।ै (ि) अिुरोधकता षसमन्‍दियक से एलसीपी िाजपस करिे का अिुमाजित समय। िाम और हस्ट्ताक्षर……………………………………………….. (सुरक्षा समन्‍दियक िारी करत ेहुए) पदिाम…………………………………………………………. लाइि जक्लयर परजमट एलसीपी िंबर……………………. मैं श्री/श्रीमती ----------------- (िारीकताष सुरक्षा समन्‍दियक) एतद्द्वारा श्री/श्रीमती (अिुरोधकताष) को अिुमजत िारी करता ह ँ सुरक्षा समन्‍दियक) मागं संख्या ……………….कदिांक………………..समय …….के अिुसार कायष करिे के जलए यहां िर्णषत ईएचटी/एचटी लाइि/उपकरण सुरजक्षत घोजर्त ककया गया ह।ै यह अिुमजत इस परजमट के पीछे दी गई ितों के अधीि ह।ै िाम और हस्ट्ताक्षर……………………………….. (लाइि जक्लयर परजमट िारी करिे िाला व्यजक्त) पदिाम…………………………………………. (एलसीपी के पीछे मुकरत होि ेके जलए: प्रारूप-2) ित:ें (क) यह परजमट केिल यहां उजल्लजखत फीडर/उपकरण पर काम करिे के जलए िैध है, ककसी अन्‍दय फीडर/उपकरण पर िहीं। (ख) केिल अजधकृत व्यजक्तयों को ही फीडर/उपकरण पर काम करिे की अिुमजत ह ैजिसके जलए परजमट िारी ककया गया ह।ै (ग) केिल मांग के अिुसार ही कायष ककया िािा चाजहए (घ) फीडर/उपकरण के ककसी भी जहस्ट्से को छूिे से पहल े यह सुजिजित ककया िािा चाजहए कक अच्छे अथष से िडु े मािक जडस्ट्चािष रॉड के माध्यम से दोिों तरफ दो लबंदओंु पर अर्थगिं ककए गए ह।ैं सभी कायों के पूरा होिे के बाद और सभी लोगों के फीडर/उपकरण स ेिीचे आि े के बाद अस्ट्थायी जमट्टी को हटाया िा सकता ह।ै (ङ) कायष इस प्रकार जियोजित होिा चाजहए कक लाइि जक्लयर बताए गए समय से पहले या समय पर िापस हो। यकद अपठरहायष जिलंब की आिंका हो तो उस स्ट्थाि को अजिम सूचिा दी िािी चाजहए िहां स े लाइि जक्लयर िारी ककया िाता ह।ै (च) लाइि जक्लयर की िापसी से पहले, यह सुजिजित ककया िािा चाजहए कक लाइि पर मौिूद सभी लोग, सामिी, उपकरण/टैकल आकद िापस आ गए ह ैं और ठरपोटष ककया ह ै कक सभी अस्ट्थायी अथष हटा कदए गए ह।ैं कायष के जलए िारी44 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] की गई सामिी, उपकरण और संयंत्र की भी िांच होिी चाजहए ताकक यह सुजिजित हो सके कक लाइि या उपकरण पर कुछ भी पीछे िहीं छूटा ह।ै (छ) केिल अजधकृत व्यजक्तयों को ही लाइि जक्लयर परजमट लौटािा चाजहए। (ि) यकद लाइि जक्लयर को व्यजक्तगत रूप से िापस िहीं ककया िा सकता है, तो इसे जिर्दष्टष कोड िब्दों और टेलीफोि िंबर का िाम देकर टेलीफोि पर लाइि जक्लयर िारीकताष प्राजधकारी को िापस ककया िा सकता है, जिसका उपयोग असाइि ककए गए कोड िब्दों के िामकरण के जलए ककया िाता ह।ै यकद दो या दो स े अजधक व्यजक्तयों को, जििके पक्ष में परजमट कदया गया ह,ै दो या दो से अजधक अलग-अलग कोड िडष िारी ककए िात े ह,ैं तो उि व्यजक्तयों को संयुक्त रूप से अपि ेस्ट्ियं के कोड िड षका िाम देकर लाइि जक्लयर िापस करिा होगा। लाइि जक्लयर ठरटिष तब तक स्ट्िीकार िहीं ककया िाएगा िब तक कक ये सभी व्यजक्त इसे िापस िहीं कर देते। (झ) लाइि जक्लयर िारी करि े िाले प्राजधकारी को इसे स्ट्िीकार करिे से पहले लाइि जक्लयर ठरटिष की चेकजलस्ट्ट को पढ लेिा चाजहए। (ञ) यकद लाइि जक्लयर टेलीफोि पर लौटाया िाता ह,ै तो लाइि जक्लयर ठरटिष फॉम ष जिजधित भरा हुआ और हस्ट्ताक्षठरत लाइि जक्लयर िारीकताष प्राजधकारी को ठरकॉडष के जलए तुरंत डाक द्वारा भेिा िािा चाजहए। (ट) जियंत्रण व्यजक्तयों को िारी ककए गए एलसीपी और प्राप्त एलसीआर के सभी आिश्यक डेटा का रखरखाि ककया िािा चाजहए। िब एक ही लाइि/उपकरण/बे पर एक से अजधक एलसीपी िारी ककए िाते ह ैंतो उसे कोड िब्दों के साथ लॉग िीट में जिजिष्ट िोट म ेंजलखिा चाजहए। प्रारूप-3 क्रम संख्या xxxxxxxxx एलसीपी िंबर…………………………. जतजथ ……………………………………………… समय.............. मैं श्री/श्रीमती .........................................एतद्द्वारा जिम्नजलजखत एचटी/ईएचटी लाइि/उपकरण के जलए िारी एलसीपी िंबर ................................. (समय पर) लौटाता ह।ं म ैं घोर्णा करता ह ं कक काम पर भेि े गए सभी कमषचारी िापस आ गए ह,ैं अस्ट्थायी जमट्टी हटा दी गई ह,ै सभी मरम्मत उपकरणों और सामजियों की िांच की गई ह ै और िीचे उजल्लजखत फीडर/उपकरण जबिली होिे के जलए सरु जक्षत ह।ैं (क) ईएचटी/एचटी उपकरण/लाइि की पहचाि: (ख) सुरक्षा सािधािीयां िो अब आिश्यकता िहीं: (ग) आइसोलेिि [स्ट्थािों और आइसोलेिि के प्रत्येक लबंद ुको इंजगत करें जिसके माध्यम से आइसोलेिि ककया गया था।] (घ) अर्थिंग [स्ट्थाि बताएं िहां अर्थगिं स्ट्थाजपत की गई थी और अर्थिंग के प्रत्येक लबंद ुकी पहचाि करें, जिससे अर्थिंग प्राप्त हुई।] (ङ) ककए गए कायष का जििरण िाचं सचू ी पर जििाि लगाएं: (क) क्या सभी लोग िापस आ गए ह:ैं हा ँ (ख) क्या सभी अस्ट्थायी अथ षहटा कदए गए ह:ैं हाँ (ग) क्या कायष में प्रयक्तु सामिी, उपकरण एि ंसंयंत्र की िाँच की गई ह:ै हाँ (घ) कोड िंबर (यकद फोि पर लाइि जक्लयर लौटािे पर उपयोग ककया िाता ह)ै ----------------- िाम और हस्ट्ताक्षर……………………………………. (लाइि जक्लयर परजमट का अिरु ोध करिे िाला व्यजक्त) पदिाम……………………………………………… दल के प्रभारी ---------------------- (पद का िाम)[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 45 अध्याय -17: डेटा पिं ीकरण 17.1 यह अध्याय राज्य जिड कोड के प्रािधािों के अिुसार उपयोगकताषओं द्वारा एसटीयू और/या एसएलडीसी और इसके जिरुद्ध प्रदाि ककए िािे िाल ेसभी आिश्यक डेटा को सूचीबद्ध करिे से संबंजधत ह।ै 17.2 जिम्मदे ारी 1. सभी उपयोगकताष राज्य जिड कोड के प्रािधािों के अिुसार एसटीयू/एसएलडीसी को आिश्यक अपडेट डेटा िमा करिे के जलए जिम्मेदार ह।ैं 2. सभी उपयोगकताष एसटीयू और एसएलडीसी, डेटा भेििे के जलए जिम्मेदार व्यजक्तयों के िाम, पते और टेलीफोि िंबर प्रदाि करेंगे। 3. डेटा की िुद्धता की जिम्मेदारी डेटा उपलब्ध करािे िाल ेसबं ंजधत उपयोगकता षकी ह।ै 4. एसटीयू सभी उपयोगकताओंष और एसएलडीसी को डेटा प्राप्त करि े के जलए जिम्मेदार व्यजक्तयों के िाम, पते और टेलीफोि िंबर सूजचत करेगा। 5. एसटीयू इस राज्य जिड कोड के प्रासंजगक अध्यायों में कदए गए अिुसार उपयोगकताओंष को अपडेट ककए गए डेटा प्रदाि करेगा। 17.3 पिं ीकृत ककया िाि ेिाला डेटा पंिीकृत/जिजिमय करिे के जलए आिश्यक डेटा को जिजभन्न श्रेजणयों के अंतगषत इस अध्याय के पठरजिष्ट म ें सूचीबद्ध ककया गया ह।ै अब तक जििेर् उपयोगकता ष पर लाग ू डेटा को केिल एसटीयू या एसएलडीसी के साथ पंिीकृत और आदाि-प्रदाि करिे की आिश्यकता ह।ै 17.4 उपयोगकता षके डेटा म ेंपठरितिष िब भी ककसी उपयोगकताष को एसटीयू के साथ पंिीकृत डेटा के ककसी भी आइटम म ें बदलाि के बारे म ें पता चलता ह,ै तो उपयोगकताष को पठरितिष ों के बारे म ें एसटीयू को तुरंत सूजचत करिा चाजहए। पठरितिष ों की सूचिा प्राप्त होि े पर एसटीयू तरु ंत डेटाबेस को तदिुसार सही करेगा। यह एसटीयू द्वारा अपि े जसस्ट्टम के संबधं म ें संकजलत ककसी भी डेटा पर भी लाग ूहोगा। 17.5 डेटा सबजमट करि ेकी जिजध 1. डेटा प्रस्ट्ततु करि े के जलए डेटा मािक प्रारूपों म ें प्रस्ट्ततु ककया िाएगा और ऐस े प्रारूपों का उपयोग एसएलडीसी और एसटीयू को डेटा प्रस्ट्तुत करि े के जलए जलजखत रूप म ें ककया िािा चाजहए। िहां मािक प्रारूप सलं ग्न िहीं हैं, उन्‍दह ें उपयोगकताषओं के परामिष से एसएलडीसी या एसटीयू द्वारा जिकजसत ककया िाएगा। 2. अिुसूची के अतं गतष प्रस्ट्तुत ककए िािे िाले सभी डेटा को एसएलडीसी / एसटीयू या ऐसे अन्‍दय जिभाग और/या इकाई को प्रस्ट्तुत ककया िािा चाजहए जिसे एसटीयू समय-समय पर उपयोगकताषओं को सूजचत कर सकता ह।ै डेटा की प्रत्येक अिुसूची प्रस्ट्तुत करि े िाले व्यजक्त का िाम दिाषया िाएगा। 3. िहां उपयोगकताष और एसएलडीसी/एसटीयू के बीच कंपयूटर डेटा ललंक मौिूद है, िहां डेटा इस ललंक के माध्यम स े सबजमट ककया िा सकता ह।ै डेटा उसी प्रारूप में होगा िो पेपर पारेर्ण के जलए जिर्दष्टष ह।ै उपयोगकताष एसएलडीसी/एसटीयू के परामिष से उपयोग की िाि े िाली जिजध को जिर्दष्टष करेगा और पारेर्ण के समय प्रोटोकॉल, पारेर्ण गजत आकद िैसे मुद्दों को हल करेगा। 17.6 डेटा उपलब्ध िहीं कराया गया सभी उपयोगकताष इस राज्य जिड कोड के अलग-अलग अध्यायों में उजल्लजखत और इस डेटा पंिीकरण अध्याय पठरजिष्ट म ें सूचीबद्ध डेटा की आपूर्तष करिे के जलए बाध्य ह।ैं यकद कोई डेटा ककसी उपयोगकताष द्वारा प्रदाि िहीं ककया िाता ह ै या उपलब्ध िहीं ह,ै तो एसटीयू या एसएलडीसी, यकद आिश्यक हो, तो उजचत कायषिाही करते हुए, जस्ट्थजत की तात्काजलकता के आधार पर ऐसे डेटा का अिुमाि लगा सकता ह।ै इसी प्रकार, यकद एसटीयू द्वारा कोई डेटा प्रदाि िहीं ककया िाता ह,ै तो संबंजधत उपयोगकता,ष यकद आिश्यक हो, तो उजचत कायषिाही करत े हुए, जस्ट्थजत की तात्काजलकता के आधार पर ऐसे डेटा का अिुमाि लगा सकता ह।ै इस तरह के अिुमाि प्रत्येक मामल े में, समाि संयंत्र46 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] या उपकरण के जलए संबंजधत डेटा या ऐसी अन्‍दय िािकारी पर आधाठरत होंगे, िैसा भी उपयोगकताष या एसटीयू या एसएलडीसी उजचत समझे। 17.7 जििर्े जिचार एसएलडीसी और कोई भी अन्‍दय उपयोगकताष ककसी भी समय आिश्यकतािुसार अजतठरक्त डेटा के जलए एसटीयू स े उजचत अिरु ोध कर सकता ह।ै एसटीयू आिश्यक/अिुरोजधत डेटा की आपूर्तष करेगा। अध्याय – 18: जिजिध 18.1 जििाद का समाधाि: राज्य जिड कोड के ककसी भी प्रािधाि की व्याख्या के संबंध म ें कोई भी जििाद, आयोग के सजचि को भेिा िाएगा। आयोग का जिणषय अंजतम और सभी संबंजधत पक्षों के जलए बाध्यकारी मािा िाएगा। 18.2 कठििाइयों को दरू करि ेकी िजक्त: यकद गडष कोड के ककसी भी प्रािधाि को प्रभािी करिे में कोई कठििाई उत्पन्न होती है, तो आयोग, सामान्‍दय या जिजिष्ट आदिे द्वारा, ऐसे प्रािधाि बिा सकता ह ै िो अजधजियम के प्रािधािों से असंगत ि हों, िो कठििाई को दरू करिे के जलए आिश्यक प्रतीत हों। 18.3 छूट देि ेकी िजक्त आयोग सामान्‍दय या जििेर् आदेि द्वारा, कारणों को जलजखत रूप म ें दि ष करके और छूट कदए िाि े से प्रभाजित होि े िाले पक्षों को सिु िाई का अिसर दिे े के बाद या ककसी इच्छुक व्यजक्त द्वारा उसके समक्ष ककए गए आिेदि पर अपि े स्ट्ियं के प्रस्ट्ताि पर राज्य जिड कोड के ककसी भी प्रािधाि म ेंढील द ेसकता ह।ै 18.4 सिं ोधि करि ेकी िजक्त आयोग, ककसी भी समय, राज्य जिड कोड के ककसी भी प्रािधाि में बदलाि, पठरितषि, संिोधि या सुधार कर सकता है। आयोग के आदेि द्वारा। िी.के. धर, सजचि [जिज्ञापि-III/4/असा./612/2023-24] पठरजिष्ट क: मािक योििा डेटा (सदं भ:ष अध्याय 3 परै ा 3.3 (4), परै ा 3.6 (1,2,3) और अध्याय 4 परै ा 4.2 (6)) क-1 मािक योििा डेटा (उत्पादि) एसिीएस के जलए - थमलष क-1.1 थमलष (कोयला/गसै /ईंधि स ेिडु ा हुआ) 1. साधारण i साइट सडकों, रेलिे लाइिों, पारेर्ण लाइिों, िहरों, तालाबों और िलाियों, यकद कोई हो, को दिाषिे िाले पैमािे पर स्ट्थाि मािजचत्र प्रस्ट्तुत करें। ii कोयला ललंकेि/ईंधि (िैसे तरलीकृत कोयला पठरिहि/ढुलाई के साधिों की िािकारी दें। अन्‍दय ईंधि के मामल े प्राकृजतक गैस, िेफ्था आकद) ललंकेि म,ें ईंधि के स्रोत और उिके पठरिहि का जििरण दें। iii िल स्रोतों पािर स्ट्टेिि के संचालि के जलए पािी की उपलब्धता की िािकारी दें। iv पयाषिरण बताएं कक क्या िि या अन्‍दय भूजम क्षेत्र प्रभाजित हैं। v साइट मािजचत्र (पैमािे के अिुसार) पािर स्ट्टेिि कोयला ललंकेि, कोयला याडष, िल पाइप लाइि, राख जिपटाि क्षेत्र, कॉलोिी आकद के जलए आिश्यक क्षेत्र कदखा रहा है।[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 47 vi जिमाषण की अिुमाजित अिजध 2. किक्ै िि i किेक्िि का लबंद ु जसस्ट्टम के साथ प्रस्ट्ताजित किेक्िि का लसंगल लाइि आरेख प्रस्ट्ततु करें ii किेक्िि के जलए स्ट्टेप अप िोल्टेि (केिी) 3. स्ट्टेिि की क्षमता i कुल उत्पादि स्ट्टेिि क्षमता (मगे ािाट) बताएं कक क्या जिकास चरणों में ककया िाएगा और यकद हां, तो जििरण प्रस्ट्ततु करें। ii इकाइयों की संख्या और इकाई आकार (मगे ािाट) 4. उत्पादि इकाई का डेटा i भाप उत्पन्न करिे िाली इकाई प्रकार, क्षमता, भाप का दबाि, भाप का तापमाि आकद बताएं। ii िाष्प टरबाइि प्रकार, क्षमता बताए ं iii ििरेटर प्रकार रेटटंग (मगे ािाट) गजत (आरपीएम) टर्मिष ल िोल्टेि (केिी) रेटेड पािर फैक्टर ठरएजक्टि पािर क्षमता (एमिीएआर) 0.95 लीलडंग और 0.85 लैलगगं िॉटष सर्कषट अिपु ात की सीमा म ें प्रत्यक्ष अक्ष (सतं ृप्त) क्षजणक प्रजतकक्रया (एमिीए रेटटंग पर%) प्रत्यक्ष अक्ष (सतं ृप्त) सब-रंजिएंट प्रजतकक्रया (एमिीए रेटटंग पर%) सहायक जिद्यतु आिश्यकता मगे ािाट और एमिीएआर क्षमता िक्र रैंप-अप और रैंप-डाउि दर िेिरेटर जििर्े ता िक्र iv िेिरेटर रांसफामषर मेक, फेि प्रकार रेटेड क्षमता (एमिीए) िोल्टेि अिुपात (एचिी/एलिी) टैप पठरितषि रेंि (+ % स े- %) प्रजतित प्रजतबाधा (पणू ष लोड पर सकारात्मक अिुक्रम) क-1.2 हाइड्रो इलजे क्रक (एसिीएस के जलए) 1. सामान्‍दय i साइट सडकों, रेलिे लाइिों और पारेर्ण लाइिों को दिाषिे िाल े पमै ािे पर स्ट्थाि मािजचत्र दें। ii साइट मािजचत्र (पैमािे पर) प्रस्ट्ताजित िहर, िलािय क्षेत्र, िल संिाहक प्रणाली, फोर-बे, पािर हाउस आकद दिाषएं। iii िलमग्न क्षेत्र िलमग्न क्षत्रे , िलमग्न गािं , िलमग्न िि भूजम, कृजर् भजू म आकद की िािकारी दें। iv भंडारण प्रकार ह ैया िदी प्रिाह प्रकार v क्या िलिहण क्षेत्र को अन्‍दय िलाियों या जबिली संयंत्र से जििषहि प्राप्त हो रहा ह।ै48 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] vi पूणष िलािय स्ट्तर vii न्‍दयूितम ड्रा डाउि स्ट्तर viii टाइल रेस स्ट्तर ix जडजाइि हडै x िलािय स्ट्तर और ऊिाष क्षमता िक्र xi िल जिस्ट्सरण पर रोक, यकद कोई हो xii जिमाषण की अिुमाजित अिजध 2. किैक्िि i किेक्िि का लबदं ु पारेर्ण प्रणाली के साथ प्रस्ट्ताजित किेक्िि का एक एकल रेखा आरेख दें। ii किेक्िि के जलए स्ट्टेप अप िोल्टेि (केिी) 3. स्ट्टेिि क्षमता i कुल पािर स्ट्टेिि क्षमता (मगे ािाट) बताएं कक क्या जिकास चरणों में ककया िाता ह ै और यकद हां, तो जििरण प्रस्ट्ततु करें। ii इकाइयों की सख्ं या और इकाई आकार (मगे ािाट) 4. उत्पादि इकाई का डेटा i ऑपरेटटंग हडे (मीटर म)ें क) अजधकतम: ख) न्‍दयूितम: ग) औसत ii हाइड्रो यजू िट लसंक्रोिस कंडेिसर के रूप में काम करि ेकी क्षमता। िाटर हडै बिाम जििषहि िक्र (पूणष और आंजिक लोड पर) लसंक्रोिस कंडेिसर के रूप म ें काम करते समय जबिली की आिश्यकता या पािी का जििषहि iii टबाषइि प्रकार और क्षमता बताए ं iv िेिरेटर प्रकार रेटटंग (एमिीए) स्ट्पीड (आरपीएम) टर्मिष ल िोल्टेि (केिी) रेटेड पािर फैक्टर ठरएजक्टि पॉिर कैपजे बजलटी (एमिीएआर) एडिासं की 0.95 और लैलगगं की 0.85 की सीमा म ें उत्पादि इकाई िॉटष सर्कषट अिपु ात का मगे ािाट और एमिीएआर क्षमता िक्र प्रत्यक्ष अक्ष रांजिएन्‍दट (सतं प्तृ ) प्रजतकक्रया (%पर रेटेड एमिीए) प्रत्यक्ष अक्ष आंजिक राजं िएन्‍दट (संतप्तृ ) प्रजतकक्रया (% पर रेटेड एमिीए) सहायक जिद्यतु आिश्यकता (मगे ािाट)[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 49 v िेिरेटर- रांसफामषर मके फेज टाइप रेटेड क्षमता (एमिीए) िोल्टेि अिपु ात एचिी/एलिी टैप चिें रेट (+% से -%) प्रजतित प्रजतबाधा (पूणष लोड पर सकारात्मक अिक्रु म)। क.2 मािक योििा डेटा (सचं रण) एसटीय ूऔर पारेर्ण लाइससें धाठरयों के जलए एसटीयू अपि े मािक योििा डेटा को िीच े कदए गए प्रारूप म ें अपडेट करिे के जलए एसटीयू के जिजभन्न जिभागों/अन्‍दय पारेर्ण लाइसेंसधाठरयों (यकद कोई हो) से आिश्यक डेटा प्राप्त करिे की व्यिस्ट्था करेगा: i) लाइि का िाम (पािर स्ट्टेििों और िुडे सबस्ट्टेििों का संकेत) ii) लाइि का िोल्टेि (केिी)। iii) सर्कषट की संख्या iv) मागष की लंबाई (ककमी) v) कंडक्टर आकार vi) लाइि पैरामीटर (पीयू माि) क) प्रजतरोध/ककमी ख) अजधष्ठापि/ककमी ग) संिेदििीलता/ककमी vii) अिुमाजित जबिली प्रिाह अपेजक्षत- मेगािाट और एमिीएआर viii) मागष का भूभाग- भूभाग की प्रकृजत अथाषत िि भूजम, परती भूजम, कृजर् और िदी बेजसि, पहाडी ढलाि आकद के बारे में िािकारी दें। ix) मागष मािजचत्र (पैमाि े पर) - मौिूदा जबिली लाइिों और दरू संचार लाइिों को दिाषिे िाल े मागष को दिाषि े िाला स्ट्थलाकृजतक मािजचत्र प्रस्ट्ततु करें। x) किेक्िि का उद्देश्य- योििा का संदभष, अन्‍दय राज्यों म ेंव्हीललगं आकद। xi) जिमाषण की अिुमाजित अिजध क-3 मािक योििा डेटा (जितरण) जितरण लाइससें धाठरयों के जलए 1. सामान्‍दय i क्षेत्र मािजचत्र (पैमाि ेपर) जितरण लाइसेंसधारी के जलए प्रासंजगक आपूर्तष क्षेत्र के साथ जिजधित जचजनित िम्म ूऔर कश्मीर केंर िाजसत प्रदिे और लद्दाख केंर िाजसत प्रदिे का िक्िा प्रस्ट्तुत करें। ii उपभोक्ता डेटा उपभोक्ताओं की श्रेजणया,ं उिकी संख्या और किेक्टेड लोड प्रस्ट्तुत करें। iii ितषमाि में जितरण के प्रभारी जिद्युत प्रभागों का संदभष।50 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 2. किेक्िि i किेक्िि के लबंद ु किेक्िि के लबंदओंु को दिाषि ेिाला लसगं ल लाइि आरेख प्रस्ट्ततु करें ii किेक्िि के लबंदओंु पर आपूर्त षका िोल्टेि iii किेक्िि के लबंदओंु को फीड करि े िाल े जिड सब-स्ट्टेिि के िाम 3. लाइि ें और सबस्ट्टेिि i लाइि डेटा क्षेत्र के अंदर लाइि की लंबाई और िोल्टेि प्रस्ट्ततु करें। ii सब-स्ट्टेिि डेटा 132/33 केिी उप-स्ट्टेिि, 33/11 केिी उप-स्ट्टेिि आकद का जििरण प्रस्ट्तुत करें। 4. लोड i किेक्िि के लबंदओंु पर जलया गया लोड ii ईएचिी पर डाल ेगए लोड का जििरण, यकद कोई हो। उपभोक्ता का िाम, आपूर्त षका िोल्टेि, अिुबधं मांग/लोड और जिड सब-स्ट्टेिि का िाम िहां स े लाइि खींची गई ह,ै जिड सब-स्ट्टेिि से उपभोक्ता के पठरसर तक ईएचिी लाइि की लंबाई बताएं। iii स्ट्थाजपत ठरएजक्टि पािर भरपाई 5. मागं डेटा (1 मगे ािाट और उसस ेअजधक के सभी लोड के जलए) i लोड का प्रकार भट्ठी लोड, रोललगं जमल, कर्षण लोड, अन्‍दय औद्योजगक लोड, पंलपगं लोड आकद की िािकारी दें ii रेटेड िोल्टेि और फेि iii उपकरणों की जिद्युत लोलडंग मोटरों की सख्ं या और आकार, ड्राइि के प्रकार और जियत्रं ण व्यिस्ट्था बताएं। iv िोल्टेि और आपूर्त ष की आिृजत्त के प्रजत लोड की संिेदििीलता। v लोड की अजधकतम हामोजिक सामिी. vi लोड का औसत और अजधकतम फेि असंतलु ि। vii जिकटतम सब-स्ट्टेिि िहां से लोड डाला िािा ह।ै viii पैमािे के अिुसार स्ट्थाि मािजचत्र आस-पास की लाइिों और उप-स्ट्टेििों के संदभ षमें लोड का स्ट्थाि दिाषएँ 6. लोड अिुमाि का डेटा i आगामी 5 िर्ों म ेंप्रत्येक श्रणे ी के लोड के जलए अजधकतम लोड और ऊिाष पूिाषिुमाि। ii कायषप्रणाली और मान्‍दयताओं का जििरण जिि पर पूिाषिुमाि आधाठरत ह।ैं iii 1 मेगािाट और उससे अजधक लोड का जििरण। क. भािी उपभोक्ता का िाम[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 51 ख. लोड का स्ट्थाि और प्रकृजत ग. सब-स्ट्टेिि िहा ंसे फीड ककया िािा ह।ै घ. आपूर्तष का िोल्टेि ङ. लोड का चरणबद्ध होिा। पठरजिष्ट ख: जिस्ट्ततृ योििा डेटा (संदभष: अध्याय 3 परै ा 3.3 (4), पैरा 3.6 (1,2,3) और अध्याय 4 पैरा 4.2 (6)) ख-1 जिस्ट्ततृ योििा डेटा (उत्पादि) ख-1.1 थमलष पािर स्ट्टेिि (एसिीएस के जलए) 1. साधारण I. पािर स्ट्टेिि का िाम. II. उत्पादि इकाइयों (मगे ािाट) की संख्या और क्षमता। III. सभी प्रमुख उपकरणों (बॉयलर और प्रमुख सहायक उपकरण, टबाषइि, अल्टरिेटर, िेिरेटर यूजिट रांसफामषर आकद) की रेटटंग। IV. पािर स्ट्टेिि और जस्ट्िचयाड षका लसंगल लाइि आरेख। V. ठरलेइंग और मीटटरंग आरेख। VI. उत्पादि इकाइयों की न्‍दयूरल िाउंलडंग। VII. उत्तेििा जियंत्रण- (ककस प्रकार का उपयोग ककया िाता ह?ै ) उदाहरण के जलए, थाइठरस्ट्टर, फास्ट्ट ििलेस एक्साइटसष) VIII. अथ षप्रजतरोध मल्ू यों के साथ अर्थगिं व्यिस्ट्था। 2. सरु क्षा और जमटटरंग I. ििरेटटंग यूजिट, िेिरेटर यूजिट रांसफामषर, सहायक रांसफामषर और प्रमुख उपकरणों की जिद्युत मोटर आकद पर स्ट्थाजपत सभी ठरल ेऔर सुरक्षा प्रणाजलयों के जलए सेटटंग्स सजहत पणू ष जििरण। II. पािर स्ट्टेिि जस्ट्िचयाड,ष टाई सर्कषट िेकर और इिकलमंग सर्कषट िेकर से सभी आउटगोइंग फीडर पर स्ट्थाजपत सभी ठरले के जलए सेटटंग्स सजहत पूण ष जििरण। III. पारेर्ण प्रणाली के साथ किेक्िि के लबंद ुया लबंदओंु पर सर्कषट िेकरों की इंटर-ठरलपंग का पूरा जििरण। IV. उपयोगकताष के जसस्ट्टम पर जिद्युत दोर्ों के जलए सबसे संभाजित खराबी जििारण समय। V. पठरचालि और िाजणजज्यक मीटटरंग योििाओं का पूरा जििरण। 3. जस्ट्िचयाड ष I. इंटरकिेलक्टंग रांसफामषर के संबधं में: 1. रेटेड एमिीए। 2. िोल्टेि अिपु ात। 3. िेक्टर समूह। 4. अजधकतम, न्‍दयूितम, सामान्‍दय टैप के जलए सकारात्मक अिुक्रम प्रजतकक्रया। (% पर एमिीए) 5. अजधकतम, न्‍दयूितम, सामान्‍दय टैप के जलए सकारात्मक अिुक्रम प्रजतरोध। (% पर एमिीए) 6. िून्‍दय अिुक्रम प्रजतकक्रया (% पर एमिीए)। 7. टैप चेंिर रेंि (+% से -%) और फेि52 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 8. टैप चेंिर का प्रकार (बंद/लोड पर)। II. किेक्िि के लबंदओंु से िुडे सभी सर्कषटों पर सर्कषट िेकर, आइसोलेटर सजहत जस्ट्िचजगयर के संबधं में: 1. रेटेड िोल्टेि (केिी) 2. सर्कषट िेकर का प्रकार (एमओसीबी / एबीसीबी /एस एफ6)। 3. रेटेड िॉटष सर्कषट िेककंग करंट (केए) 3 फेि। 4. रेटेड िॉटष सर्कषट िेककंग करंट (केए) 1 फेि। 5. रेटेड िॉटष सर्कषट मेककंग करंट (केए) 3 फेि। 6. रेटेड िॉटष सर्कषट मेककंग करंट (केए) 1-फेि। 7. जििरण के साथ स्ट्ित: पिु ः समापि का प्रािधाि। III. तजडत जिरोधकों के संबंध में – तकिीकी डाटा IV. संचार के संबंध म-ें कॉि किेक्िि के लबंदओंु पर स्ट्थाजपत संचार उपकरणों का जििरण। V. बेजसक इंसुलेिि लेिल (केिी) के संबंध में – 1. बस बार 2. जस्ट्िचजगयर. 3. रांसफामषर बुलिंग 4. रांसफामषर िाइंलडंग्स। 4. उत्पादि इकाइयों के परै ामीटर I. रेटेड टर्मषिल िोल्टेि (केिी)। II. रेटेड एमिीए III. रेटेड मगे ािाट IV. गजत (आरपीएम) या ध्रुिों की संख्या V. िडत्ि जस्ट्थरांक एच (मेगािाट सेक/एमिीए)। VI. िॉटष सर्कषट अिुपात VII. प्रत्यक्ष अक्ष तल्ु यकाजलक प्रजतकक्रया (% पर एमिीए) एक्सडी VIII. प्रत्यक्ष अक्ष (संतप्तृ ) रांजिएन्‍दट प्रजतकक्रया (% पर एमिीए) एक्सडी ' IX. प्रत्यक्ष अक्ष (संतप्तृ ) सब-रंजिएंट प्रजतकक्रया (% पर एमिीए) एक्सडी " X. चतुभुषि अक्ष तुल्यकाजलक प्रजतकक्रया (% पर एमिीए) एक्सक्यू । XI. चतुभुषि अक्ष (संतप्तृ ) रांजिएन्‍दट प्रजतकक्रया (% पर एमिीए) एक्सक्यू’। XII. चतुभुषि अक्ष (संतप्तृ ) आंजिक रूप से रांजिएन्‍दट प्रजतकक्रया (% पर एमिीए) एक्सक्य”ू । XIII. प्रत्यक्ष अक्ष रांजिएन्‍दट ओपि सर्कषट समय जस्ट्थरांक (सेकंड) टी'डी ओ. XIV. प्रत्यक्ष सब-रांजिएन्‍दट -क्षजणक खुला सर्कषट समय जस्ट्थरांक (दखे ें) टी'डी ओ. XV. चतुभुषि अक्ष क्षजणक खुला सर्कषट समय जस्ट्थरांक (सेकंड) टी'क्य ू ओ.[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 53 XVI. चतुभुषि अक्ष सब-रंजिएंट ओपि सर्कषट समय जस्ट्थरांक (सेकंड) टी'क्य ू ओ.. XVII. स्ट्टेटर प्रजतरोध (ओम) आरए XVIII. न्‍दयूरल िाउंलडंग जििरण। XIX. स्ट्टेटर ठरसाि प्रजतकक्रया (ओम) एक्स1. XX. स्ट्टेटर समय जस्ट्थरांक (सेकंड)। XXI. रेटेड फील्ड करंट (ए)। XXII. जिजभन्न टर्मषिल िोल्टेि के जलए ओपि सर्कषट संतृजप्त जििेर्ता िो इसे प्राप्त करि े के जलए कंपाउंलडंग करंट देती ह ै XXIII. मेगािाट और एमिीएआर क्षमता िक्र। 5. उत्तिे िा जियत्रं ण प्रणाली के परै ामीटर: I. उत्तेििा का प्रकार. II. अजधकतम फील्ड िोल्टेि III. न्‍दयूितम फील्ड िोल्टेि IV. रेटेड फील्ड िोल्टेि V. आई.ई.ई.ई. प्रतीक.का प्रयोग करते हुए व्यजक्तगत तत्िों के स्ट्थािांतरण कायों को दिाषिे िाले ब्लॉक आरेखों में उत्तेििा लूप का जििरण VI. अजत-उत्तेििा सीमक की गजतिील जििेर्ताएँ। VII. अंडर-उत्तेििा सीमक की गजतिील जििेर्ताएं। 6. गििरष के मािदंड: I. गििषर औसत लाभ (मगे ािाट/हर्टिष)। II. स्ट्पीडर मोटर सेटटंग रेंि। III. भाप या ईंधि गििषर िाल्ि का समय जस्ट्थरांक। IV. गििषर िाल्ि खोलिे की सीमा V. गििषर िाल्ि दर सीमा VI. टरबाइि का समय जस्ट्थरांक VII. आईईईई प्रजतकों का उपयोग करके व्यजक्तगत तत्िों के स्ट्थािांतरण कायों को दिाषिे िाला गििषर ब्लॉक आरेख। 7. पठरचालि परै ामीटर: A ककसी ििरेटटंग यूजिट को डी-लसंक्रिाइजेिि से लसंक्रोिाइज करिे के जलए न्‍दयूितम सूचिा आिश्यक ह।ै I. एक पािर स्ट्टेिि म ेंजिजभन्न उत्पादि इकाइयों को लसंक्रिाइज करिे के बीच न्‍दयूितम समय। II. लसंक्रोिाइज करिे पर न्‍दयिू तम ब्लॉक लोड आिश्यकताएँ। III. जिम्नजलजखत जस्ट्थजतयों के जलए एक उत्पादि इकाई को लसंक्रिाइज करि े के जलए आिश्यक समय: 1. गम ष 2. िामष 3. िंडा54 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] IV. जिम्नजलजखत जस्ट्थजतयों के जलए अजधकतम उत्पादि इकाई लोलडंग दरें: 1. गम ष 2. िामष 3. िंडा V. तेल के जबिा न्‍दयिू तम लोड (मगे ािाट)। 8. सामान्‍दय जस्ट्थजत I. जिस्ट्तृत पठरयोििा ठरपोट ष II. जस्ट्थजत ठरपोटष 1. भूजम 2. कोयला 3. पािी 4. पयाषिरण मंिरू ी 5. जिस्ट्थाजपत व्यजक्तयों का पुििाषस III. केंरीय जिद्युत प्राजधकरण (सीईए) द्वारा तकिीकी-आर्थषक अिमु ोदि। IV. राज्य सरकार/लोडत सरकार की स्ट्िीकृजत। V. जित्तीय सम्झौता 9. किक्े िि I. राज्य पारेर्ण प्रणाली के साथ समािांतर संचालि के जलए अध्ययि की ठरपोटष। II. िॉटष सर्कषट अध्ययि III. जस्ट्थरता अध्ययि IV. लोड प्रिाह अध्ययि V. राज्य पारेर्ण प्रणाली के साथ प्रस्ट्ताजित किेक्िि। क. िोल्टेि ख. सर्कषट की संख्या ग. किेक्िि का लबंद.ु ख-1.2 हाइड्रो - जिद्यतु स्ट्टेिि (एसिीएस के जलए) 1. सामान्‍दय I. पािर स्ट्टेिि का िाम II. इकाइयों की संख्या और क्षमता. (एमिीए) III. सभी प्रमुख उपकरणों की रेटटंग. क. टबाषइि (एचपी) ख. िेिरेटर (एमिीए) ग. िेिरेटर रांसफामषर (एमिीए) घ. सहायक रांसफामषर (एमिीए)[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 55 IV. पािर स्ट्टेिि और जस्ट्िचयाडष का लसंगल लाइि आरेख। V. ठरलेइंग और मीटटरंग आरेख। VI. ििे रेटर की न्‍दयूरल िाउंलडंग। VII. उत्तेििा जियंत्रण. VIII. अथ षप्रजतरोध मूल्यों के साथ अर्थिंग व्यिस्ट्था। IX. िलािय डेटा. क. मुख्य जििेर्ताए ं ख. िलािय का प्रकार ग. बहुउद्देिीय घ. िजक्त के जलए ङ. ऑपरेटटंग टेबल के साथ X. क्षेत्र क्षमता िक्र और XI. जिजभन्न िेट िीर्ों पर इकाई क्षमता 2. सरु क्षा I. ििरेटटंग यूजिट पर स्ट्थाजपत सभी ठरले और सुरक्षा प्रणाजलयों के जलए सेटटंग्स सजहत पणू ष जििरण, जिसमें ििरेटर रांसफामषर, सहायक रांसफामषर और प्रमुख उपकरणों की जिद्युत मोटर आकद िाजमल ह।ैं II. पािर स्ट्टेिि जस्ट्िचयाड,ष टाई िेकर और इिकलमगं िेकर स े सभी आउटगोइंग फीडर पर स्ट्थाजपत सभी ठरल े के जलए सेटटंग्स सजहत पणू ष जििरण। III. पारेर्ण प्रणाली के साथ किेक्िि के लबंद ुया लबंदओंु पर िेकरों की इंटर-ठरलपंग का परू ा जििरण। IV. उपयोगकताष के जसस्ट्टम पर जिद्युत दोर्ों के जलए सिाषजधक सभं ाजित खराबी जििारण समय। 3. जस्ट्िचयाड ष I. इंटरकिेलक्टंग रांसफामषर: 1. रेटेड एमिीए 2. िोल्टेि अिपु ात 3. िेक्टर समूह 4. अजधकतम, न्‍दयूितम और सामान्‍दय टैप के जलए सकारात्मक अिक्रु म प्रजतकक्रया (% पर एमिीए)। 5. अजधकतम, न्‍दयूितम और सामान्‍दय टैप के जलए सकारात्मक अिक्रु म प्रजतरोध (% पर एमिीए)। 6. िून्‍दय अिुक्रम प्रजतकक्रया (% पर एमिीए) 7. चेंिर रेंि (+% से -%) और फेि 8. टैप चेंिर का प्रकार (बंद/लोड पर)। 9. न्‍दयूरल िाउंलडंग जििरण। II. जस्ट्िचजगयर (किेक्िि के लबंदओंु से िडु े सभी सर्कषट पर सर्कषट िेकर, आइसोलेटर सजहत)। 1. रेटेड िोल्टेि (केिी)। 2. िेकर का प्रकार (एमओसीबी/एबीसीबी/एसएफ6)। 3. रेटेड िॉटष सर्कषट िेककंग करंट (केए) 3 फेि।56 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 4. रेटेड िॉटष सर्कषट िेककंग करंट (केए) 1 फेि। 5. रेटेड िॉटष सर्कषट मेककंग करंट (केए) 3 फेि 6. रेटेड िॉटष सर्कषट मेककंग करंट (केए) 1 फेि 7. जििरण के साथ स्ट्ित: पुिः समापि का प्रािधाि। III. लाइटलिंग अरेस्ट्टर तकिीकी डेटा IV. संचार किेक्िि लबंदओंु पर स्ट्थाजपत संचार उपकरणों का जििरण। V. बजियादी इन्‍दसुलेिि स्ट्तर (केिी) 1. बस बार 2. जस्ट्िचजगयर 3. रांसफामषर बुलिंग्स 4. रांसफामषर िाइंलडंग्स। 4. उत्पादि इकाइया ँ I. िेिरेटर के परै ामीटर 1. रेटेड टर्मषिल िोल्टेि (केिी)। 2. रेटेड एमिीए। 3. रेटेड मगे ािाट 4. गजत (आरपीएम) या ध्रुिों की संख्या। 5. िडत्ि जस्ट्थरांक एच (मेगािाट सेकंड/एमिीए)। 6. िॉटष सर्कषट अिुपात 7. प्रत्यक्ष अक्ष तल्ु यकाजलक प्रजतकक्रया (% पर एमिीए) एक्सडी 8. प्रत्यक्ष अक्ष (संतप्तृ ) क्षजणक प्रजतकक्रया ((% पर एमिीए पर%) एक्स’डी 9. प्रत्यक्ष अक्ष (संतप्तृ ) सब-रंजिएंट प्रजतकक्रया ((% पर एमिीए) एक्स’डी 10. चतुभुषि अक्ष तल्ु यकाजलक प्रजतकक्रया ((% पर एमिीए) एक्सक्यू 11. चतुभुषि अक्ष (संतप्तृ ) क्षजणक प्रजतकक्रया ((% पर एमिीए) एक्स’क्य ू 12. चतुभुषि अक्ष (संतप्तृ ) सब रांजिएन्‍दट प्रजतकक्रया (% पर एमिीए) एक्स”क्य ू 13. प्रत्यक्ष अक्ष क्षजणक ओपि सर्कषट समय जस्ट्थरांक (सेकंड) टी’क्य ूओ 14. प्रत्यक्ष अक्ष सब-रंजिएंट ओपि सर्कषट समय जस्ट्थरांक (सेकंड) टी"क्य ू ओ. 15. चतुभुषि अक्ष क्षजणक ओपि सर्कषट समय सामिी (सेकंड) टी’क्य ू ओ. 16. चतुभुषि अक्ष क्षजणक ओपि सर्कषट समय जस्ट्थरांक (सेकंड) टी"क्य ू ओ. 17. स्ट्टेटर प्रजतरोध (ओम) RA 18. स्ट्टेटर ठरसाि प्रजतकक्रया (ओम) एक्स1. 19. टर समय जस्ट्थरांक (सेकंड)[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 57 20. रेटेड फील्ड करंट (ए)। 21. न्‍दयूरल िाउंलडंग जििरण। 22. जिजभन्न टर्मषिल िोल्टेि के जलए ििरेटर की ओपि सर्कषट सतं ृजप्त जििेर्ताए,ँ िो इसे प्राप्त करिे के जलए कंपाउंलडंग करंट देता ह।ै 23. टरबाइि का प्रकार. 24. ऑपरेटटंग हडे (मीटर) 25. पूरा गेट खुलि े पर जडस्ट्चािष (क्यूमेक्स) 26. कुल लोड थ्रो ऑफ पर गजत िृजद्ध (%)। 27. मेगािाट और एमिीएआर क्षमता िक्र II. उत्तेििा जियंत्रण प्रणाली के पैरामीटर: III. गििषर के परै ामीटर: IV. पठरचालि पैरामीटर: 1. ककसी ििरेटटंग यूजिट को डी-लसंक्रिाइजेिि से लसंक्रोिाइज करिे के जलए न्‍दयूितम सूचिा आिश्यक ह।ै 2. एक पािर स्ट्टेिि म ेंजिजभन्न उत्पादि इकाइयों को लसंक्रोिाइज करिे के बीच न्‍दयूितम समय। 3. लसंक्रोिाइलजंग पर न्‍दयूितम ब्लॉक लोड आिश्यकताएँ। 5. सामान्‍दय जस्ट्थजत I. जिस्ट्तृत पठरयोििा ठरपोटष. II. जस्ट्थजत ठरपोटष। 1. स्ट्थलाकृजतक सिेक्षण 2. भूिैज्ञाजिक सिेक्षण 3. भूजम 4. पयाषिरण मंिरू ी 5. जिस्ट्थाजपत व्यजक्तयों का पुििाषस. III. केंरीय जिद्युत प्राजधकरण द्वारा तकिीकी-आर्थषक अिुमोदि। IV. राज्य सरकार/लोडत सरकार की स्ट्िीकृजत V. जित्तीय सम्झौता 6. किक्े िि I. राज्य पारेर्ण प्रणाली के साथ समािांतर संचालि के जलए अध्ययि की ठरपोटष। 1. िॉटष सर्कषट अध्ययि 2. जस्ट्थरता अध्ययि 3. लोड प्रिाह अध्ययि। II. राज्य पारेर्ण प्रणाली के साथ प्रस्ट्ताजित किेक्िि।58 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 1. िोल्टेि 2. सर्कषट की संख्या 3. किेक्िि का लबंद.ु 7. िलािय के डेटा I. मृत क्षमता II. लाइि क्षमता बी-1.3 गसै पािर स्ट्टेिि (एसिीएस के जलए) 1. सामान्‍दय I. पािर स्ट्टेिि का िाम II. उत्पादि इकाइयों (एमिीए) की संख्या और क्षमता। III. सभी प्रमुख उपकरणों (टबाषइि, अल्टरिेटर, हीट ठरकिरी बॉयलर िेिरेटर यूजिट रांसफामषर आकद) की रेटटंग। IV. पािर स्ट्टेिि और जस्ट्िचयाडष का लसंगल लाइि आरेख। V. ठरलेइंग और मीटटरंग आरेख। VI. उत्पादि इकाइयों की न्‍दयूरल िाउंलडंग। VII. उत्तेििा जियंत्रण- (ककस प्रकार का उपयोग ककया िाता ह?ै ) उदाहरण के जलए, थाइठरस्ट्टर, फास्ट्ट ििलेस एक्साइटस ष VIII. अथ षप्रजतरोध मूल्यों के साथ अर्थिंग व्यिस्ट्था। IX. स्ट्टाट-ष अप इंिि X. टरबाइि जििरण 2. सरु क्षा और जमटटरंग I. प्रमुख उपकरणों की ििरेटटंग इकाइयों, िेिरेटर यूजिट रांसफामषर, सहायक रांसफामषर और जिद्युत मोटर पर स्ट्थाजपत सभी ठरल ेऔर सुरक्षा प्रणाजलयों के जलए सेटटंग्स सजहत पणू ष जििरण। II. पािर स्ट्टेिि जस्ट्िचयाड,ष टाई सर्कषट िेकर और इिकलमंग सर्कषट िेकर से सभी आउटगोइंग फीडर पर स्ट्थाजपत सभी ठरले के जलए सेटटंग्स सजहत पणू ष जििरण। III. पारेर्ण प्रणाली के साथ किेक्िि के लबंद ुया लबंदओंु पर सर्कषट िेकरों की अंतर-ठरलपंग का परू ा जििरण। IV. उपयोगकताष के जसस्ट्टम पर जिद्युत दोर्ों के जलए सबसे संभाजित खराबी जििारण समय। V. पठरचालि और िाजणजज्यक मीटटरंग योििाओं का पूरा जििरण। 3. जस्ट्िचयाड ष क. इंटरकिेलक्टंग रांसफामषर के संबंध में: I. रेटेड एमिीए. II. िोल्टेि अिपु ात III. िेक्टर समूह IV. अजधकतम, न्‍दयूितम और सामान्‍दय टैप के जलए सकारात्मक अिक्रु म प्रजतकक्रया। (% पर एमिीए) V. अजधकतम, न्‍दयूितम और सामान्‍दय टैप के जलए सकारात्मक अिक्रु म प्रजतरोध। (% पर एमिीए ) VI. िून्‍दय अिुक्रम प्रजतकक्रया (पर%एमिीए)।[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 59 VII. टैप चेंिर रेंि (=% से -%) और फेि VIII. टैप पठरितषक का प्रकार. (बंद/लोड पर)। ख. किेक्िि के लबंदओंु स े िुडे सभी सर्कषटों पर सर्कषट िेकर और आइसोलेटर सजहत जस्ट्िचजगयर के संबंध म:ें I. रेटेड िोल्टेि (केिी) II. सर्कषट िेकर का प्रकार (एमओसीबी / एबीसीबी / एस एफ 6)। III. रेटेड िॉटष सर्कषट िेककंग करंट (केए) 3 फेि IV. रेटेड िॉटष सर्कषट िेककंग करंट (केए) 1 फेि V. रेटेड िॉटष सर्कषट मेककंग करंट (केए) 3 फेि VI. रेटेड िॉटष सर्कषट मेककंग करंट (केए) 1-फेि VII. जििरण के साथ स्ट्ित: पिु ः बंद करिे का प्रािधाि। ग. जबिली जिरोधक- तकिीकी डाटा घ. संचार - किेक्िि लबंदओंु पर स्ट्थाजपत संचार उपकरणों का जििरण। ड. बुजियादी इन्‍दसुलिे ि स्ट्तर (केिी) - I. बस बार II. जस्ट्िचजगयर III. रांसफामषर बुलिंग IV. रांसफामषर की िाइंलडंग्स 4.उत्पादि इकाइया ँ क) उत्पादि इकाइयों के परै ामीटर: I. रेटेड टर्मषिल िोल्टेि (केिी) II. रेटेड एमिीए III. रेटेड मगे ािाट IV. गजत (आरपीएम) या ध्रुिों की संख्या V. िडत्ि जस्ट्थरांक एच (मेगािाट सेक./एमिीए) VI. िॉटष सर्कषट अिुपात VII. प्रत्यक्ष अक्ष तल्ु यकाजलक प्रजतकक्रया (एमिीए पर%) एक्सडी VIII. प्रत्यक्ष अक्ष (संतप्तृ ) क्षजणक प्रजतकक्रया (एमिीए पर%) एक्सडी’ IX. प्रत्यक्ष अक्ष (संतप्तृ ) सब-रंजिएंट प्रजतकक्रया (एमिीए पर%) एक्सडी" X. चतुभुषि अक्ष तल्ु यकाजलक प्रजतकक्रया (एमिीए पर%) एक्स क्य ू XI. चतुभुषि अक्ष (संतप्तृ ) क्षजणक प्रजतकक्रया (एमिीए पर%) एक्स क्य'ू XII. चतुभुषि अक्ष (संतप्तृ ) सब-रंजिएंट प्रजतकक्रया (एमिीए पर%) एक्स क्य"ू XIII. प्रत्यक्ष अक्ष क्षजणक खुला सर्कषट समय जस्ट्थरांक (सेकंड) टीडीओ.60 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] XIV. प्रत्यक्ष अक्ष सब-रंजिएंट खुला सर्कषट समय जस्ट्थरांक (सेकंड) टी” डीओ XV. चतुभुषि अक्ष क्षजणक खुला सर्कषट समय जस्ट्थरांक (सेकंड) टी’ डीओ. XVI. चतुभुषि अक्ष सब-रंजिएंट खुला सर्कषट समय जस्ट्थरांक (सेकंड) टी” डीओ. XVII. स्ट्टेटर प्रजतरोध (ओम) रा. XVIII. तटस्ट्थ िाउंलडंग जििरण। XIX. स्ट्टेटर ठरसाि प्रजतकक्रया (ओम) एक्स1. XX. स्ट्टेटर समय जस्ट्थरांक (सेकंड)। XXI. रेटेड फील्ड करंट (ए)। XXII. जिजभन्न टर्मषिल िोल्टेि के जलए ओपि सर्कषट संतृजप्त जििेर्ता, इसे प्राप्त करि े के जलए कंपाउंलडंग करंट दते ी ह।ै XXIII. मेगािाट और एमिीएआर क्षमता िक्र। ख) उत्तिे िा जियत्रं ण प्रणाली के परै ामीटर: I. उत्तेििा का प्रकार. II. अजधकतम फील्ड िोल्टेि. III. न्‍दयूितम फील्ड िोल्टेि. IV. रेटेड फील्ड िोल्टेि V. आईईईई प्रतीक का प्रयोग करिे िाल े व्यजक्तगत तत्िों के स्ट्थािांतरण कायों को दिाषि े िाले ब्लॉक आरेखों म ें उत्तेििा लूप का जििरण VI. अजत-उत्तेििा सीमक की गजतिील जििेर्ताएँ। VII. अंडर-उत्तेििा सीमक की गजतिील जििेर्ताएं। ग) गििरष का परै ामीटर: I. गििषर औसत लाभ (मगे ािाट/हर्टिष) II. स्ट्पीडर मोटर सेटटंग रेंि। III. भाप या ईंधि गििषर िाल्ि का समय जस्ट्थरांक। IV. गििषर िाल्ि खोलिे की सीमा. V. गििषर िाल्ि दर सीमा. VI. टरबाइि का समय जस्ट्थरांक. VII. आईईईई प्रतीकों का उपयोग करके व्यजक्तगत तत्िों के स्ट्थािातं रण कायों को दिाषि ेिाला गििरष ब्लॉक आरेख। घ) पठरचालि परै ामीटर: I. ककसी ििरेटटंग यूजिट को डीलसंक्रिाइजेिि स ेलसंक्रोिाइज करि ेके जलए न्‍दयिू तम सूचिा की आिश्यकता होती ह।ै II. एक पािर स्ट्टेिि म ेंजिजभन्न उत्पादि इकाइयों को लसंक्रिाइज करिे के बीच न्‍दयूितम समय III. लसंक्रोिाइज करिे पर न्‍दयिू तम ब्लॉक लोड आिश्यकताएँ। IV. जिम्नजलजखत जस्ट्थजतयों के जलए एक उत्पादि इकाई को लसंक्रिाइज करि े के जलए आिश्यक समय: क. गम ष ख. िामष ग. िंडा[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 61 V. जिम्नजलजखत जस्ट्थजतयों के जलए अजधकतम उत्पादि इकाई लोलडंग दरें: क. गम ष ख. िामष ग. िंडा VI. तेल के जबिा न्‍दयूितम लोड (मेगािाट)। 5. सामान्‍दय जस्ट्थजत I. जिस्ट्तृत पठरयोििा ठरपोटष. II. जस्ट्थजत ठरपोटष। क. स्ट्थलाकृजतक सिेक्षण ख. भूिैज्ञाजिक सिेक्षण ग. भूजम घ. पयाषिरण मंिरू ी ङ. जिस्ट्थाजपत व्यजक्तयों का पुििाषस. III. केंरीय जिद्युत प्राजधकरण द्वारा तकिीकी-आर्थषक अिुमोदि। IV. राज्य सरकार/लोडत सरकार की स्ट्िीकृजत 6. किक्े िि I. राज्य पारेर्ण प्रणाली के साथ समािांतर संचालि के जलए अध्ययि की ठरपोटष। क. िॉटष सर्कषट अध्ययि ख. जस्ट्थरता अध्ययि ग. लोड प्रिाह अध्ययि। II. राज्य पारेर्ण प्रणाली के साथ प्रस्ट्ताजित किेक्िि। क. िोल्टेि ख. सर्कषट की संख्या ग. किेक्िि का लबंद.ु ख-2 जिस्ट्ततृ प्रणाली डेटा-पारेर्ण एसटीय ूऔर पारेर्ण लाइससें धाठरयों के जलए 1 सामान्‍दय I. जिड सब-स्ट्टेिि पर 66केिी, 33केिी बस तक पारेर्ण प्रणाली का लसंगल लाइि आरेख जििरण: 1. सब-स्ट्टेिि का िाम. 2. पािर स्ट्टेिि िडु ा। 3. सर्कषट की संख्या और लंबाई. 4. इंटरकिेलक्टंग रांसफामषर। 5. सब-स्ट्टेिि बस लआे उट। 6. जबिली रांसफामरष . 7. प्रजतकक्रयािील क्षजतपूर्त षउपकरण। II. जिम्न को प्रदर्िषत करत े हुए सब-स्ट्टेिि लेआउट:62 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 1. बस बार लआे उट 2. जिद्युत सर्कषटरी, लाइि,ें केबल, रांसफामषर, जस्ट्िचजगयर आकद। 3. चरणबद्ध व्यिस्ट्था. 4. अर्थिंग व्यिस्ट्था. 5. जस्ट्िलचंग सुजिधाएं और इंटरलॉककंग व्यिस्ट्था। 6. ऑपरेटटंग िोल्टेि. 7. क्रमांकि और िामकरण: 8. रांसफामषर. 9. सर्कषट. 10. सर्कषट िेकर। 11. अलग करि े िाले जस्ट्िच। 2. लाइि परै ामीटर (सभी सर्कषट के जलए) I. रेखा का पदिाम. 1. लाइि की लंबाई (ककमी). 2. प्रजत सर्कषट मािों पर सर्कषट की संख्या। 3. ऑपरेटटंग िोल्टेि (केिी)। 4. सकारात्मक चरण अिुक्रम प्रजतकक्रया (पीयू पर 100 एमिीए) एक्स1 5. सकारात्मक चरण अिुक्रम प्रजतरोध (पीयू पर 100 एमिीए) आर1 6. सकारात्मक चरण अिुक्रम सिं ेदििीलता (पीयू पर 100 एमिीए) बी 1 7. िन्‍दू य चरण अिुक्रम प्रजतकक्रया (पीयू पर 100 एमिीए) एक्स0 8. िन्‍दू य चरण अिुक्रम प्रजतरोध (पीयू पर 100 एमिीए) आर 0 9. िन्‍दू य चरण अिुक्रम संिेदििीलता (पीयू पर 100 एमिीए ) बी 0 3. रासं फामरष परै ामीटर (सभी रांसफामरष के जलए) I. रेटेड एमिीए II. िोल्टेि अिपु ात III. िेक्टर समूह IV. सकारात्मक अिुक्रम प्रजतकक्रया, अजधकतम, न्‍दयूितम और सामान्‍दय (पीयू पर 100 एमिीए) एक्स1 V. सकारात्मक अिुक्रम प्रजतरोध, अजधकतम, न्‍दयूितम और सामान्‍दय (100 एमिीए पर पीयू) आर1 VI. िून्‍दय अिुक्रम प्रजतकक्रया (पीयू पर 100 एमिीए) । VII टैप रेंि (+% से -%) और फेि VIII. टैप रेंि का जििरण. (ऑफ/ऑि-लोड)। 4. उपकरण जििरण (सभी सबस्ट्टेििों के जलए) I पठरपथ िेकर II आइसोलेिि जस्ट्िच[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 63 III. करंट रांसफामषर IV. संभाजित रांसफामषर/सीिीटी 5. ठरलइे ंग और मीटटरंग I. सभी रांसफामषर और फीडरों के जलए उिकी सेटटंग्स और अन्‍दय उपयोगकताषओं के साथ समन्‍दिय के स्ट्तर के साथ सुरक्षा ठरले स्ट्थाजपत ककए गए ह।ैं II मीटटरंग जििरण. 6. जसस्ट्टम अध्ययि I. लोड फ्लो अध्ययि (अजधकतम हाइड्रो और अजधकतम तापीय उत्पादि के जलए पीक और लीि लोड)। II. महत्िपूणष लाइिों में तीि-चरण खराबी के जलए क्षजणक जस्ट्थरता अध्ययि। III. गजतिील जस्ट्थरता अध्ययि IV. िॉटष सर्कषट अध्ययि (अथष पर तीि चरण और एकल चरण) V. पारेर्ण प्रणाली में पारेर्ण और जितरण हाजियाँ। 7. मागं डेटा (सभी सबस्ट्टेििों के जलए) अगले 5 िर्ों के जलए जडमांड प्रोफाइल (पीक और लीि लोड)। 8. प्रजतकक्रयािील भरपाई उपकरण I उपकरण का प्रकार (जस्ट्थर या पठरितषििील) । II क्षमताएं और/या आगमिात्मक रेटटंग या एमिीएआर म ेंइसकी ऑपरेटटंग रेंि। III. जियंत्रण का जििरण IV. जसस्ट्टम से किेक्िि का लबदं .ु ख-3 जिस्ट्ततृ योििा डेटा (जितरण) जितरण लाइससें धाठरयों के जलए 1. सामान्‍दय I. जितरण मािजचत्र (पैमािे पर) जिसमें आपूर्तषकता षसे संबंजधत 11केिी तक की सभी लाइि ेंऔर सब-स्ट्टेिि कदखाए गए हों II. जितरण प्रणाली का लसंगल लाइि आरेख (पारेर्ण प्रणाली के साथ किेक्िि के लबंदओंु से जितरण लाइिें, 132/33 केिी सब स्ट्टेिि, 33/11 केिी 110/22-11 केिी सबस्ट्टेिि, और पारेर्ण प्रणाली से सीधे उपभोक्ताओं के मामले म ें उपभोक्ता बस को दिाषता हुआ) III. लाइिों और सब-स्ट्टेििों की संख्या और िामकरण (लाइसेंसधारी के पारेर्ण के फीलडंग जिड उप-स्ट्टेििों और संबंजधत 220/132/33/11 केिी, 132/33/11 केिी, और 33/11 केिी 110/22-11 केिी सब-स्ट्टेििों के साथ जचजन्‍दहत) 2. किक्े िि I किेक्िि के लबंद ु(किेक्िि की मौिूदा व्यिस्ट्था का जििरण प्रस्ट्तुत करें)। II किेक्िि लबंदओंु पर मीटटरंग का जििरण। 3. लोड I. अगल े5 िर्ों के जलए अिुबंजधत ककए िाि े िाल े1 मगे ािाट और उससे अजधक के प्रमुख लोड का जििरण। II. जितरण प्रणाली की मांग प्रोफाइल (ितषमाि और पूिाषिुमाि) ।64 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] पठरजिष्ट ग: साइट जिम्मदे ारी अिसु चू ी (संदभष: अध्याय 4 परै ा 4.5 (2)) पािर स्ट्टेिि/सब-स्ट्टेिि का िाम: साइट का स्ट्िामी:................................. साइट प्रबंधक:......................................... दरू भार्. िंबर:................................. फैक्स िंबर:........................................ ईमेल आईडी: ......................................... सयं त्रं /उपकरण का आइटम पलाटं का सरु क्षा जजम्मदे ारी जियत्रं ण की सचं ालि की रखरखाि की ठटपपजणया ँ स्ट्िामी जजम्मदे ारी जजम्मदे ारी जजम्मदे ारी केिी जस्ट्िचयाडष बस बार सजहत सभी उपकरण फीडर उत्पादि इकाइयाँ स्ट्टेिि/यूजिट-1 स्ट्टेिि/यूजिट-2 स्ट्टेिि/यूजिट-3 पठरजिष्ट घ: सरु क्षा डेटा(सदं भ:ष अध्याय 7) सरु क्षा: आइटम जियत जतजथ/समय क) िेिरेटर/सीपीपी/आईपीपी ख-1 के उपखंड "संरक्षण और जमटटरंग" के अंतगषत जिर्दषष्ट िैसा कक जिस्ट्तृत योििा डेटा पर लागू जिस्ट्तृत योििा डेटा अिुसार सुरक्षा आिश्यकता और उिके द्वारा स्ट्थाजपत योििाओं का होता ह ै जििरण प्रस्ट्तुत करेंगे। ख) एसटीयू ख-2 में जिर्दष्टष अिुसार उिके द्वारा स्ट्थाजपत सुरक्षा उपकरणों और योििाओं का िैसा कक जिस्ट्तृत योििा डेटा पर लागू जििरण प्रस्ट्तुत करेगा। ककसी भी उपयोगकताष के साथ किेक्िि के संबंध में उप-धारा "ठरलेइंग होता ह ै और मीटटरंग" के अंतगषत जिस्ट्तृत जसस्ट्टम डेटा, पारेर्ण। पठरजिष्ट ड: पठरचालि योििा डटे ा (सदं भ:ष अध्याय 10 परै ा 10.3 (1)) ड.1 आउटेि पलालिगं डेटा 1. मागं अिमु ाि (जितरण लाइससें धाठरयों के जलए) आइटम जियत जतजथ/समय क) अगल े जित्तीय िर् ष के जलए प्रत्येक किेक्िि लबंद ु पर जमजलयि यूजिट म ें ऊिाष की चालू िर्ष का 15 ििम्बर अिुमाजित माजसक जबक्री और मगे ािाट और एमिीएआर म ेंपीक और लीि मांग। ख) अगले महीिे के जलए प्रत्येक किेक्िि लबंद ुपर जमजलयि यूजिट में ऊिाष की अिुमाजित चालू माह की 25 जतजथ कुल दैजिक माजसक जबक्री और मेगािाट और एमिीएआर में पीक और लीि मांग।[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 65 ग) आिे िाल ेकदि के जलए 15 जमिट का ब्लॉक-िार मांग अिुमाि। प्रजतकदि 09.00 बिे। 2.जितरण लाइससें धारी के जलए लोड िले डंग का अिमु ाि आइटम जियत जतजथ/समय क) प्रत्यके किेक्िि लबंद ु स े आिश्यकता पडि े पर एसएलडीसी द्वारा िारी जिदेिों का किेक्िि के तरु ंत बाद अिुपालि करि ेके जलए अलग-अलग लोड ब्लॉकों का जििरण छोडा िा सकता ह।ै 3.आगामी िर् षआउटेि कायक्रष म (जित्तीय िर् ष के जलए) (क) (एसिीएस) के जलए ििे रेटर आउटेि प्रोिाम आइटम जियत जतजथ/समय क) उत्पादि इकाई की पहचाि। प्रत्येक िर्ष 15 ििम्बर ख) मगे ािाट, िो आउटेि के पठरणामस्ट्िरूप उपलब्ध िहीं होगा। ग) पसंदीदा प्रारंभ जतजथ और प्रारंभ-समय या प्रारंभ जतजथयों की सीमा और प्रारंभ समय और आउटेि की अिजध। घ) यकद िैधाजिक आिश्यकता को पूरा करिे के जलए आउटेि की आिश्यकता ह,ै तो ििीितम - िह जतजथ िब तक आउटेि जलया िािा चाजहए। (ख) इंरा-स्ट्टेट पारेर्ण प्रणाली प्रभाि आइटम जियत जतजथ/समय क) मेगािाट, िो बाहरी किेक्िि के माध्यम से आयात से आउटेि के पठरणामस्ट्िरूप प्रत्येक िर्ष 15 ििम्बर उपलब्ध िहीं होगा। ख) प्रारंभ जतजथ और प्रारंभ समय और आउटेि की अिजध। (ग) आगामी िर् षसीपीपी का आउटेि कायक्रष म (इंरा-स्ट्टेट पारेर्ण प्रणाली को प्रभाजित करत ेहुए) आइटम जियत जतजथ/समय क) मेगािाट, िो बाहरी किेक्िि के माध्यम से आयात स े आउटेि के पठरणामस्ट्िरूप प्रत्येक िर्ष 15 ििम्बर उपलब्ध िहीं होगा। ख) प्रारंभ जतजथ और प्रारंभ समय और आउटेि की अिजध। (घ) आगामी िर् षजितरण लाइसेंसधारी आउटेि कायक्रष म आइटम जियत जतजथ/समय क) ककसी भी किेक्िि लबंद ु स े मगे ािाट म ें लोड उपलब्ध िहीं ह।ै किेक्िि लबंद ु की प्रत्येक िर्ष 15 ििम्बर पहचाि। ख) प्रारंभ जतजथ और प्रारंभ समय के साथ जिकासी के जिलंबि की अिजध। (ड) एसटीय ूका समि आउटेि कायक्रष म आइटम जियत जतजथ/समय क) प्रस्ट्ताजित आउटेि कायषक्रम पर ठरपोटष प्रत्येक िर्ष 15 ििम्बर ख) अंजतम रूप से सहमत आउटेि योििा िारी करिा66 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] ड-2 ििरेिि िड्ये लू लगं डेटा (संदभष: अध्याय 14) अिसु चू ी और प्रर्े ण (सीिीएस, आईपीपी और सीपीपी के जलए) आइटम जियत जतजथ/समय अगल ेकदि 15 जमिट ब्लॉक-िार मेगािाट/एमिीएआर उपलब्धता (00.00 - 24.00 घंटे)। 09.00 बि े क) सेिा में इकाई उत्तेििा एिीआर उत्पन्न करिे की जस्ट्थजत (हा/ंिहीं)। 09.00 बि े ख) ििरेटटंग यूजिट स्ट्पीड कंरोल जसस्ट्टम की जस्ट्थजत। राज्यपाल सेिा में (हाँ/िहीं)। 09.00 बि े ग) जस्ट्पलिगं आरजक्षत क्षमता (मगे ािाट)। 09.00 बि े घ) तेल (मगे ािाट) के साथ/जबिा तेल क्षमता 09.00 बि े िल भडं ार स्ट्तर और प्रजतबधं 09.00 बि े क) 15 जमिट की ब्लॉक-िार समि आउटपुट (मेगािाट) उत्पन्न करिे िाली इकाइयाँ। 09.00 बि े ख) केंरीय क्षेत्र के उत्पादि जिद्यतु स्ट्टेििों स े अगल े कदि 15 जमिट की ब्लॉक-िार मेगािाट 09.0 बि े पात्रता। िािकारी साझा करि ेके जलए प्रारूप िीच ेअिभु ाग ई-2.2 म ेंकदए गए हैं ड-2.1 एक कदि पहल ेकी जिकासी अिसु चू ी प्रारूप -क क्रेता द्वारा टी<>डी पठरजध पर अगल ेकदि की जिकासी अिसु चू ी एसएलडीसी को प्रस्ट्ततु करिा प्रारूप-क आग ेका कदि (डी-1 कदि) क्रेता का आहरण (टी<>डी पठरजध पर) सस्ट्ं था/खरीदार का िाम क्रेता कोड जडलीिरी की जतजथ सिं ोधि सख्ं या (अिुसूची में संिोधि के मामले में) समय खंड अिमु ाजित मागं अल्पािजध का ओए मध्यम अिजध का ओए जद्वपक्षीय अिबु धं मगे ािाट मगे ािाट मगे ािाट मगे ािाट मगे ािाट मगे ािाट मगे ािाट मगे ािाट घटं ा घटं ा घटं ा घटं ा 1 2 3 4 …. 96[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 67 कुल औसत न्‍दयिू तम अजधकतम ठटपपणी: 1. अगले कदि (डी-1)- डी- जडलीिरी की जतजथ ह।ै 2. अिुसूची में ककसी भी 'संिोधि' के मामले म,ें उपरोक्त प्रारूप लागू होगा। ड-2.2 यजू िट-िार एक्स-बस अगल ेकदि उपलब्धता प्रारूप-ख जिक्रेता द्वारा यजू िट िार अगल ेकदि एक्स-बस उपलब्धता का प्रस्ट्तजु तकरण प्रारूप-ख आगल ेकदि (डी-1 कदि) एक्स-बस पर घोजर्त क्षमता (डीसी) (यजू िट िार) जिक्रेता का िाम यजू िट िार जिक्रेता कोड जडलीिरी की जतजथ सिं ोधि सख्ं या(डीसी के सिं ोधि के मामल े म)ें समय खंड अगल े कदि एलटीओए एलटीओए एलटीओए सामजू हक डीसी (मगे ािाट) (मगे ािाट) (मगे ािाट) (मगे ािाट) (मगे ािाट) अतं र- अतं र- अतं र- राज्य राज्य राज्य खरीदार 1 खरीदार 2 खरीदार 1 खरीदार 2 खरीदार खरीदार 1 2 1 2 3 4 …. 96 कुल औसत न्‍दयिू तम अजधकतम ठटपपणी: 1. अगले कदि (डी-1)- डी- जडलीिरी की जतजथ ह।ै 2. अिुसूची में ककसी भी 'संिोधि' के मामले म,ें उपरोक्त प्रारूप लागू होगा।68 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] प्रारूप-ग जिक्रेता (हाइड्रो) द्वारा यजू िट-िार एक्स-बस कदिस की माजसक उपलब्धता प्रस्ट्ततु करिा प्रारूप-ग (हाइड्रो) (डी-1) हाइड्रो ििे रेटर द्वारा प्रस्ट्ततु की िाि ेिाली अगल ेकदि के जलए एक्स-बस यजू िट-िार घोजर्त क्षमता जिक्रेता का िाम जिक्रेता कोड (यजू िट िार) सिं ोधि सख्ं या जडलीिरी की जतजथ माहिार िल उपलब्धता (एमसीयएू म एि ंटीएमसी म)ें आि की जतजथ म ेंझील का स्ट्तर (मीटर म)ें । िल उपयोग के जलए ठरब्यिू ल/डब्ल्यआू रडी के िधै ाजिक प्रजतबधं , यकद कोई हों हाइड्रो पलाटं के साथ पीपीए रखि े िाल े लाभाथी की सहमजत महीि ेके कदिों के जलए डीसी (मगे ािाट) समय खंड 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 ठटपपणी 1 2 … 96 कुल औसत न्‍दयूितम. अजधकतम. िल उपय ोग (एमसीयूएम/टीएमसी) ठटपपणी: 1. पंपड हाइड्रो के मामल े म ें भी यही प्रारूप लाग ू होगा प्रारूप-घ एसएलडीसी द्वारा एमओडी पर आधाठरत अगल ेकदि जिकासी कायक्रष म की घोर्णा प्रारूप-घ क्रेता का अगल े कदि का जिकासी कायषक्रम- XXXXX (टी<>डी पठरजध पर जिकेंरीकृत मोड के आधार पर) क्रेता का िाम क्रेता कोड[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 69 जडलीिरी की जतजथ समय खडं ििे 1 ििे 2 ििे 3 ििे 4 ििे 5 ििे एि कुल जिकासी 1 2 3 4 …. 96 प्रारूप-च क्रेता द्वारा टी<>डी पठरजध पर इंरा-डे जिकासी संिोधि प्रारूप-च इंरा-डे (डी-कदि) जिकासी सिं ोधि (टी<>डी पठरजध) क्रेता का िाम सिं ोधि सख्ं या जडलीिरी की जतजथ समय ब्लॉक एक कदि आग े ससं ोजधत मागं एलटीए एसटीओए एमटीओए जद्वपक्षीय ठटपपजणया ँ का मांग अिमु ाि (मेगा िाट ) 1 2 3 4 …. 96 कुल औसत न्‍दयिू तम अजधकतम एमडब्ल्यएू च ड-2.3 अन्‍दय िािकारी 1. एसिीएस के जलए क्षमता डेटा (सदं भ:ष अध्याय-9) आइटम क) िेिरेटर और आईपीपी सभी उत्पादि इकाइयों के जलए एसटीय ू को ििीितम क्षमता एसटीयू/एसएलडीसी से अिुरोध प्राप्त होिे पर। िक्र प्रस्ट्तुत करेंगे। ख) सीपीपी एसटीयू को िुद्ध ठरटिष क्षमता प्रस्ट्ततु करेंगे िो पारेर्ण प्रणाली स े एसटीयू/एसएलडीसी से अिुरोध प्राप्त होिे पर। जियातष /आयात के जलए उपलब्ध होगी70 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 2. एसिीएस के जलए आिजृ त्त पठरितिष पर प्रजतकक्रया (सदं भ:ष अध्याय-9)। आइटम क) आिृजत्त पठरितिष के जलए न्‍दयिू तम उत्पादि स े लेकर पंिीकृत क्षमता तक लोड एसटीयू/एसएलडीसी स े अिरु ोध प्राप्त के जिजभन्न स्ट्तरों पर मेगािाट म ेंप्राथजमक प्रजतकक्रया जिसके पठरणामस्ट्िरूप गििषर होिे पर। िाल्ि पूरी तरह से खलु िाता ह।ै ख) आिृजत्त पठरितषि के जलए मगे ािाट म ेंमाध्यजमक प्रजतकक्रया एसटीयू/एसएलडीसी स े अिरु ोध प्राप्त होिे पर। 3. एसएलडीसी के जलए उत्पादि की जिगरािी (सदं भ:ष अध्याय-9) । उत्पादि और जिकासी की जिगरािी (एसिीएस के जलए) आइटम क) एसिीएस एसएलडीसी को 15 जमिट का ब्लॉक-िार उत्पादि सारांि प्रदाि करेगा। िास्ट्तजिक समय के आधार पर िास्ट्तजिक समय के आधार पर ख) सीपीपी एसएलडीसी को 15 जमिट का ब्लॉक-िार जियाषत/आयात मेगािाट प्रदाि करेगा। आिश्यकता अिुसार ग) िेिरेटर की एसएलडीसी में लॉग की गई रीलडंग। आगामी माह के प्रथम सप्ताह में घ) माजसक आधार पर यूजिट ठरलपंग उत्पन्न करिे की जिस्ट्तृत ठरपोटष। 4. एसिीएस के जलए आिश्यक और गरै -आिश्यक लोड डेटा (सदं भ:ष अध्याय-11)। आकजस्ट्मकता योििा (एसएलडीसी के जलए) आइटम लोड िेलडंग के प्रयोििों के जलए प्रत्येक अलग लोड ब्लॉक पर आिश्यक और गैर- किेक्िि के बाद जितिी िल्दी हो सके आिश्यक लोड की अिुसूची। (पठरजिष्ट च: घटिा की ठरपोर्टिंग (दघु टष िाओं के अलािा) (सदं भ:ष अध्याय 13 परै ा 13.4) प्रथम ठरपोटष कदिाकं : _ _/_ _/_ _ _ _ समय:_______घंटा क्रम सख्ं या आइटम जििरण 1 घटिा की जतजथ और समय 2 घटिा का स्ट्थाि 3 घटिा का प्रकार 4 घटिा से पहले जसस्ट्टम पैरामीटर (िोल्टेि, आिृजत्त, प्रिाह, पीढीआकद) 5 प्राप्त हुए ठरले संकेत और सुरक्षा का प्रदिषि 6 उपकरण को िुकसाि 7 आपूर्तष बाजधत और अिजध, यकद लागू हो 8 यकद लागू हो तो िष्ट हुए िेिरेिि की मात्रा 9 िैकजल्पक आपूर्तष व्यिस्ट्था की संभाििा[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 71 10 सेिा पर लौटिे के समय का अिुमाि 11 घटिा का कारण 12 कोई अन्‍दय प्रासंजगक िािकारी और की गई उपचारात्मक कायषिाही 13 भजिष्य में सुधार/घटिा की पुिरािृजत्त के जलए जसफाठरिें 14 संगिि का िाम पठरजिष्ट छ: मीटटरंग डेटा (सदं भ:ष अध्याय 15) 1. मीटटरंग डेटा की प्रस्ट्तजु त आइटम जियत जतजथ/समय क) एसिीएस ख-1 में जिर्दष्टष उपखंड "सुरक्षा और जमटटरंग" के अिुसार िैसा कक जिस्ट्तृत योििा डेटा पर उिके द्वारा स्ट्थाजपत मीटटरंग उपकरण और योििाओं का जििरण प्रस्ट्तुत लाग ूहोता ह ै करेगा। ख) एसटीयू उिके द्वारा स्ट्थाजपत मीटटरंग उपकरण और योििाओं का िैसा कक जिस्ट्तृत योििा डेटा पर जििरण प्रस्ट्तुत काएगा िैसा की ख-2 म ें कदया गया ह।ै उपखडं "ठरलेइंग और लाग ूहोता ह ै मीटटरंग" के अतं गतष जिस्ट्तृत जसस्ट्टम डेटा, ककसी भी उपयोगकताष के संबंध में पारेर्ण 2. मीटर के मािक (क) भाग- I: सभी प्रकार के मीटरों के जलए सामान्‍दय मािक 1. ये मािक मीटरों की जिजिष्टता, बाहरी कारकों से प्रजतरक्षा, सीललगं लबंद ुऔर कायाषत्मक आिश्यकताओं को प्रदाि करते ह ैं िो जियामक दजृ ष्टकोण स ेआिश्यक ह।ैं जिस्ट्ततृ तकिीकी जिजिदिे मीटर के क्रेता द्वारा तैयार ककया िाएगा। 2. मीटरों की जिजिष्टताए ँ मािक सदं भ षिोल्टेि आईएस के अिुसार िोल्टेि की सीमा आईएस के अिुसार मािक आिजृ त्त आईएस के अिुसार मािक मूल धारा आईएस के अिुसार (उपभोक्ता मीटरों की ितषमाि रेंि को इस प्रकार चुिा िाएगा कक स्ट्िीकृत लोड के अिुरूप लोड करंट को ठरकॉडष ककया िा सके) एक्यरू ेसी क्लास मीटर एक्यूरेसी क्लास की जिम्नजलजखत आिश्यकताओं को पूरा करेंगे इंटरफेस मीटर 0.2S उपभोक्ता मीटर 650 िोल्ट तक 1.0 या बेहतर 650 िोल्ट से ऊपर और 33 ककलो 0.5S या बेहतर िोल्ट तक 33 ककलो िोल्ट से ऊपर 0.2S ऊिा षलखे ांकि और लखे ापरीक्षा मीटर72 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] उत्पादि और पारेर्ण प्रणाली में मीटरों की सटीकता िगष 0.2S से कम िहीं होिी चाजहए। जितरण प्रणाली में मीटरों की सटीकता श्रेणी िहीं होगी 0.5S सटीकता िगष से कमतर हो। आरंजभक धारा और अजधकतम धारा आईएस के अिुसार पािर फैक्टर रेंि आईएस के अिुसार पािर फ़्रीक्वेंसी िोल्टेि को िहि करती है आईएस के अिुसार 1.2/50 माइक्रो सेकंड के जलए आिेग िोल्टेि आईएस के अिुसार का सामिा करि ेका परीक्षण मािक सदं भ षिोल्टेि आईएस के अिुसार 3. मीटर म ेंमीटर रीलडंग इंस्ट्ूमेंट (एमआरआई) के माध्यम से मीटर ककए गए डेटा को डाउिलोड करि ेकी सुजिधा होगी। 4. बाहरी कारकों के प्रजत प्रजतरक्षा मीटर चुंबकीय प्रेरण, कंपि, इलेक्रोस्ट्टैठटक जडस्ट्चाि,ष जस्ट्िलचंग रांजसएंट, सिष िोल्टेि, जतरछा जिलंबि और हामोजिक्स िैसे बाहरी प्रभािों से प्रजतरजक्षत होगा और संबंजधत मािक के अिुसार आिश्यक परीक्षण ककए िाएंगे। 5. सीललंग पिाइंट- सीललंग जिम्नजलजखत लबंदओंु पर की िाएगी (िैसा लाग ूहो): (क) मीटर बॉडी या किर; (ख) मीटर टर्मषिल किर; (ग) मीटर परीक्षण टर्मषिल ब्लॉक; (घ) मीटर कैजबिेट। 6. करंट रांसफामषर (सीटी) और िोल्टेि रांसफामषर (िीटी) की सटीकता श्रेणी संबंजधत मीटरों स े कम िहीं होिी चाजहए। इि जिजियमों का अिुपालि िहीं करिे िाले मौिूदा सीटी और िीटी को खराबीपूणष, गैर-कायाषत्मक पाए िािे पर या उपयुक्त आयोग के जिदेिों के अिुसार िए सीटी और िीटी द्वारा प्रजतस्ट्थाजपत ककया िाएगा। यकद िगह की कमी के कारण मीटर के समाि सटीकता िगष के सीटी और िीटी को मीटटरंग क्यूजबकल या पैिल में समायोजित िहीं ककया िा सकता ह,ै तो अगले जिचले सटीकता िगष के सीटी और िीटी को स्ट्थाजपत ककया िा सकता है। 7. िोल्टेि रांसफामषर इलेक्रो-मैग्नेठटक िीटी या कैपेजसठटि िोल्टेि रांसफामषर (सीिीटी) होंगे। ख. भाग- II: इंटरफेस मीटर के जलए मािक 1. कायात्ष मक आिश्यकताएँ: (क) एबीटी के जलए उपयक्तु इंटरफेस मीटर स्ट्थैजतक प्रकार, जमजश्रत मीटर, सकक्रय और प्रजतकक्रयािील ऊिा ष के माप के जलए स्ट्ि-जिजहत उपकरणों के रूप म ेंहोंगे, और जिम्नजलजखत परै ािाफ में िर्णतष कुछ अन्‍दय पैरामीटर होंगे। मीटर 110 िी के रेटेड सेकेंडरी लाइि-टू-लाइि िोल्टेि िाल े िोल्टेि रांसफामषर (िीटी) और आईए (मॉडल-ए: 3 एलीमेंट) के रेटेड सेकेंडरी करंट िाल े ितषमाि रासं फामषर (सीटी) स े सीधे किेक्ट होि े के जलए उपयक्तु होंगे। 4 तार या मॉडल सी: 2 एलीमेंट, 3 तार) या 5ए (मॉडल-बी: 3 एलीमेंट, 4 तार या मॉडल डी: 2 एलीमेंट 3 तार)। संदभष आिृजत्त 50 हर्टि ष होगी। (ख) मीटर में एक गैर-िाष्पिील मेमोरी होगी जिसमें जिम्नजलजखत को स्ट्िचाजलत रूप से संिहीत ककया िाएगा: i) प्रत्येक क्रजमक 15 जमिट के ब्लॉक के जलए औसत आिृजत्त, दो अकं ों के कोड के रूप म ें(49.0 से 51.0 हर्टि षआिृजत्त 00 से 99 तक) ii) प्रत्येक क्रजमक 15 जमिट के ब्लॉक के दौराि, दसू रे दिमलि तक, पलस/माइिस जचनि के साथ िेट डब्ल्यू एच रांसजमटल। iii) प्रत्येक मध्यराजत्र म ेंएक दिमलि सजहत छह अंकों म ेंसंचयी डब्ल्यू एच संचारण।[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 73 iv) िोल्टेि उच्च जस्ट्थजत के जलए सचं यी िीएआरएच रांसजमटल, प्रत्येक मध्यराजत्र म,ें एक दिमलि सजहत छह अंकों में। v) िोल्टेि कम जस्ट्थजत के जलए सचं यी िीएआरएच रांसजमटल, प्रत्येक मध्यराजत्र म,ें एक दिमलि सजहत छह अंकों में। vi) ककसी भी फेि पर िीटी आपूर्तष की जिफलता की जतजथ और समय ब्लॉक, एक स्ट्टार (*) जचनि के रूप में। (ग) मीटर उपरोक्त सभी सूचीबद्ध डेटा को कम से कम दस कदिों की अिजध के जलए अपिी मेमोरी में संिहीत करेगा। दस कदि से अजधक पुरािा डेटा अपिे आप जमट िाएगा। प्रत्येक मीटर के सामिे एक ऑजपटकल पोटष होगा, जिससे उसकी मेमोरी में संिहीत सभी डेटा को हाथ से पकडे िाि े िाले डेटा संिह उपकरण का उपयोग करके टैप ककया िा सके। मीटर उजचत संचार माध्यम का उपयोग करके डेटा को दरू स्ट्थ स्ट्थाि पर प्रसाठरत करिे के जलए उपयुक्त होगा। (घ) सकक्रय ऊिाष (डब्ल्यूएच) माप आईईसी-104 687/आईईसी-62053-22 के िगष 0.2 एस के अिुसार सटीकता के साथ 3-फेि, 4-तार जसद्धांत पर ककया िाएगा। मॉडल-ए और सी में, ऊिाष की गणिा सीधे सीटी और िीटी माध्यजमक मात्रा में की िाएगी, और िाट-घंटे में इंजगत की िाएगी। मॉडल-बी और मॉडल डी म,ें ऊिाष प्रदिषि और ठरकॉर्डगिं सीटी और िीटी माध्यजमक मात्रा में गणिा की गई डब्ल्यूएच का पांचिां जहस्ट्सा होगी। (ड) िार और प्रजतकक्रयािील ऊिाष माप भी आईईसी-62053-23 या बेहतर की कक्षा 2 के अिुसार सटीकता के साथ 3- फेि, 4-तार जसद्धांत पर होगा। मॉडल-ए या मॉडल सी म,ें िार और िीएआरएच गणिा सीधे सीटी और िीटी माध्यजमक मात्रा में होगी। मॉडल-बी या मॉडल डी म,ें उपरोक्त मात्राओं को सीटी और िीटी माध्यजमक मात्राओं म ें गणिा की गई मात्राओं के पांचिें जहस्ट्से के रूप में प्रदर्िषत और ठरकॉडष ककया िाएगा। दो प्रजतकक्रयािील ऊिाष रजिस्ट्टर होंगे, एक उस अिजध के जलए िब औसत आरएमएस िोल्टेि 103% से ऊपर ह ै और दसू रा उस अिजध के जलए िब िोल्टेि 97% से िीचे ह।ै (च) सबस्ट्टेिि बस बारों से िुद्ध डब्ल्यू एच जियाषत होिे पर 15-जमिट डब्ल्यू एच में +ve जचनि होगा, और िुद्ध डब्ल्यू एच आयात होिे पर -ve जचनि होगा। डब्ल्यू एच और िीएआरएच के जलए एकीकृत (संचयी) रजिस्ट्टर सबस्ट्टेिि बसबारों स े डब्ल्यू एच/िीएआरएच जियाषत होिे पर आगे बढेंगे, और आयात होिे पर पीछे की ओर बढेंगे। (छ) मीटर बारी-बारी से (मांग पर) जिम्नजलजखत परै ामीटर भी प्रदर्िषत करेगा: (i) मीटर की जिजिष्ट पहचाि सख्ं या (ii) कदिांक (iii) समय (iv) संचयी डब्ल्यू एच रजिस्ट्टर रीलडंग (v) जपछले 15 जमिट के ब्लॉक की औसत आिृजत्त (vi) जपछले 15 जमिट के ब्लॉक में +/- जचन्‍दह के साथ िेट व्ह रासं जमटल (vii) औसत प्रजतित िोल्टेि (viii) +/- जचनि के साथ प्रजतकक्रयािील जिद्युत (ix) िोल्टेि-उच्च िीएआरएच रजिस्ट्टर रीलडंग (x) िोल्टेि-कम िीएआरएच रजिस्ट्टर रीलडंग। (ि) तीि लाइि-टू-न्‍दयूरल िोल्टेि की लगातार जिगरािी की िाएगी, और यकद इिमें स े कोई भी 70% से कम हो िाता ह,ै तो जस्ट्थजत को उपयक्तु रूप से इंजगत ककया िाएगा और ठरकॉड ष ककया िाएगा। मीटर ककसी सहायक जबिली आपूर्त ष की आिश्यकता के जबिा, िीटी सेकेंडरी सर्कषट से ली गई जबिली स े संचाजलत होंगे। प्रत्येक मीटर म ें एक अतं र्िषर्मतष कैलेंडर और घडी होगी, जिसकी सटीकता प्रजत माह 30 सेकंड या उससे बेहतर होगी। (झ) मीटर पूरी तरह से सीलबंद और छेडछाड-रोधी होंग,े प्रजतबंजधत घडी सुधार को छोडकर, साइट पर ककसी भी समायोिि की कोई संभाििा िहीं होगी। डब्ल्य ू एच, Var, और िीएआरएच को मापते समय हामोजिक्स को कफल्टर ककया िाएगा, और केिल मौजलक आिृजत्त मात्रा को मापा/गणिा ककया िाएगा। (ञ) मुख्य मीटर और चेक मीटर सीटी और िीटी के एक ही कोर से िुडे होंगे।74 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] (ग) भाग-III: उपभोक्ता मीटर के जलए मािक 1. मापि ेके परै ामीटर (क) उपभोक्ता मीटर उपभोक्ता द्वारा उपयोग की गई संचयी सकक्रय ऊिाष के माप के जलए उपयक्तु होगा। (ख) उपभोक्ता मीटर में उपभोक्ताओं की जिजभन्न श्रेजणयों के जलए टैठरफ आिश्यकता के आधार पर जिम्नजलजखत में स े एक या अजधक मापदडं ों को मापिे, ठरकॉडष करिे और प्रदर्ितष करि े की सुजिधाएं हो सकती ह।ैं तात्काजलक जिद्युत मापदंडों को छोडकर सभी मापदंडों को भी मेमोरी में सिं हीत ककया िाएगा। (i) संचयी प्रजतकक्रयािील ऊिा ष (ii) औसत िजक्त कारक (iii) ऊिाष के उपयोग का समय (iv) प्रत्यक्ष जबिली (v) अजधकतम मांग (vi) फेि िोल्टेि और लाइि धाराएँ 2. सभी तीि फेि के मीटरों म ेंगरै -िाष्पिील मेमोरी म ेंकम से कम 35 कदिों के जलए डेटा भडं ारण क्षमता होिी चाजहए। 3. छेडछाड रोधी जििर्े ताए ं (क) ककसी भी फेि और न्‍दयूरल की अदला-बदली होिे पर भी मीटर क्षजतिस्ट्त िहीं होगा या जिजष्क्रय िहीं होगा। (ख) मीटर तब भी ऊिाष दिष करेगा िब लोड करंट का ठरटि ष माग ष मीटर पर िापस समाप्त िहीं होता ह ै और ऐसे मामले म ें सर्कषट अथ ष के माध्यम से पूरा ककया िाएगा। धाजत्िक जिकायों के मामले में, अथष टर्मषिल को बाहर लाया िाएगा और जडब्बे के बाहर प्रदाि ककया िाएगा। (ग) मीटर आपूर्तष के फेि अिुक्रम (केिल पॉली फेि के जलए) के बाििूद सही ढंग से काम करेगा। (घ) 3 फेि, 3 तार मीटर के मामल े में भल े ही संदभ ष िाई फेि हटा कदया गया हो, मीटर काम करिा िारी रखगे ा। 3 फेि, 4 तार प्रणाली के मामल े म,ें मीटर ककन्‍दहीं दो तारों की उपजस्ट्थजत म ें भी काम करता रहगे ा, अथाषत न्‍दयूरल और ककसी एक फेि या ककन्‍दहीं दो फेि की अिुपजस्ट्थजत म ेंभी। (ङ) संपूणष करंट मीटर और एलिी सीटी संचाजलत मीटर के मामले में, मीटर सही ढंग से ऊिाष ठरकॉडष करिे में सक्षम होगा, भले ही इिपुट और आउटपुट टर्मषिल आपस में बदल गए हों। (च) पंिीकरण अिश्य होिा चाजहए चाह े इिपुट चरण या तटस्ट्थ तार िीक से िुडे हों या िे इिपुट टर्मषिलों पर परस्ट्पर िुडे हों। (छ) मीटर फैक्री कैजलिेटेड होगा और प्रेर्ण स ेपहले उपयक्तु रूप स ेसील कर कदया िाएगा। (ि) मीटर गुम क्षमता (केिल िीटी संचाजलत मीटरों के जलए) की घटिाओं को ठरकॉड ष करि े में सक्षम होगा और उपरोक्त अिजध के दौराि ऐसी घटिाओं की कुल संख्या और अिजध के साथ पहली ऐसी घटिा और अजं तम बहाली की जतजथ और समय के साथ इसकी बहाली होगी। सभी चरण. (झ) अजतठरक्त छेडछाड-रोधी सुजिधाएँ, जििमें टैम्पसष की लॉलगगं िैस े करंट सर्कषट ठरिसषल, करंट सर्कषट िॉट ष या ओपि और असामान्‍दय चुंबकीय क्षेत्र की उपजस्ट्थजत िाजमल ह,ै उजचत आयोग के जियमों या उपयुक्त सरकार के जिदेिों के अिुसार या सुधार कायषक्रम के अिुसार प्रदाि की िा सकती ह।ै (घ) भाग-IV: ऊिा षलखे ाकं ि और ऑजडट मीटर के जलए मािक 1. ऊिाष लेखांकि और ऑजडट मीटर कदिांक और समय के साथ संचयी सकक्रय ऊिा ष के माप, ठरकॉर्डिंग और प्रदििष के जलए उपयुक्त होंगे। 2. ऊिाष लेखांकि और ऑजडट मीटर में ऊिाष लेखांकि और ऑजडट आिश्यकता के आधार पर जिम्नजलजखत म ें से एक या अजधक मापदंडों को मापि,े ठरकॉडष करिे और प्रदर्िषत करिे की सुजिधा भी हो सकती ह।ै तात्काजलक जिद्युत मापदंडों को छोडकर सभी मापदंडों को भी मेमोरी में संिहीत ककया िाएगा।[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 75 (क) प्रत्यक्ष जिद्धुत (ख) चरम केिीए पर चरणिार ककलोिाट (ग) चरम केिीए पर फेि िार केिीए (प्रजतकक्रयािील)। (घ) चरम केिीए पर फेि िार िोल्टेि (ङ) जबिली बंद होिे का समय (च) औसत िजक्त कारक (छ) लाइि धाराए ँ (ि) फेि िोल्टेि (झ) कदिांक और समय (ञ) छेडछाड की घटिाए ं 3. ऊिाष लेखांकि और ऑजडट मीटर में गरै -िाष्पिील मेमोरी में कम से कम 35 कदिों के जलए डेटा भडं ारण क्षमता होिी चाजहए। 4. ऊिाष लेखांकि और ऑजडट मीटर में मीटर रीलडंग उपकरणों के माध्यम से मापदंडों को डाउिलोड करिे के साथ-साथ संचार िेटिकष पर डेटा के ठरमोट पारेर्ण की सुजिधा होगी। पठरजिष्ट ि: आकजस्ट्मकता के जलए मािदडं (संदभष: अध्याय 11) जिम्नजलजखत सामान्‍दय जसद्धांतों को ध्याि म ेंरखत े हुए पारेर्ण प्रणाली की योििा बिाई िाएगी: 1. जिड के सामान्‍दय संचालि ('एि-0') म,ें अध्ययि के समय जक्षजति म ें सभी तत्ि सेिा में उपलब्ध होि े के साथ, यह आिश्यक ह ैकक िोल्टेि, लोलडंग, आिृजत्त िैसे सभी जसस्ट्टम परै ामीटर अिुमेय सामान्‍दय सीमा के अंदर रह।ें 2. हालाँकक, जिड ककसी तत्ि के आउटेि/िुकसाि के अधीि हो सकता ह ै और यह आिश्यक ह ै कक एक तत्ि ('एि-1' या एकल आकजस्ट्मकता) के िुकसाि के बाद, िोल्टेि, लोलडंग, आिृजत्त िैसे सभी जसस्ट्टम पैरामीटर अिुमेय सीमा के अंदर हों। 3. ककसी तत्ि के आउटेि/िुकसाि के अंतगषत जिड को एक और आकजस्ट्मकता का अिुभि हो सकता ह,ै हालांकक कम संभाििा होती ह ै ('एि-1-1'), जिसमें कुछ उपकरण उिकी आपातकालीि सीमा तक लोड ककए िा सकते ह।ैं जसस्ट्टम मापदंडों को उिकी सामान्‍दय सीमा के अदं र िापस लाि े के जलए, लोड िेलडंग/िेिरेिि का पिु र्िषधाषरण या तो मैन्‍दयुअल रूप से या स्ट्िचाजलत जसस्ट्टम सुरक्षा योििाओं (एसपीएस) के माध्यम से करिा पड सकता ह।ै ऐसे उपाय आम तौर पर गडबडी के एक घंटे के अंदर लागू ककए िाएगं े। जिश्वसिीयता मािदंड 1. कोई आकजस्ट्मकता िहीं ('एि-0') (क) जसस्ट्टम का परीक्षण सभी लोड-ििरेिि पठरदश्ृ यों उच्च/जिम्न पिि, उच्च/िून्‍दय सौर, उच्च/जिम्न हाइड्रो उत्पादि, उच्च मांग, कम मांग और उिके संयोिि के जलए ककया िाएगा। (ख) योििा प्रयोिि के जलए सभी उपकरण अपिी सामान्‍दय थमलष लोलडंग और िोल्टेि रेटटंग के अदं र रहगें े। (ग) आसन्न बसों के बीच कोणीय पथृ क्करण 30 जडिी से अजधक िहीं होिा चाजहए। 2. एकल आकजस्ट्मकता ('एि-1') (क) जस्ट्थर अिस्ट्था: i. जिम्नजलजखत तत्िों म ें स े ककसी एक के आउटेि/िुकसाि (जिसे एकल आकजस्ट्मकता या 'एि-1' कहा िाता ह)ै के बाद पारेर्ण प्रणाली के सभी उपकरण अपिी सामान्‍दय थमलष और िोल्टेि रेटटंग के अदं र रहगें े, लेककि लोड िेलडंग/उत्पादि के पुिर्िधष ाषरण के जबिा: - 132 केिी लसंगल सर्कषट का आउटेि, - 220 केिी लसंगल सर्कषट का आउटेि,76 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] - 400 केिी एकल सर्कषट का आउटेि (जिजित श्रृंखला कैपेजसटर के साथ या उसके जबिा), इंटर-किेलक्टंग रांसफामषर (आईसीटी)/पािर रांसफामषर का खराब होिा, 765 केिी लसंगल सर्कषट का आउटेि एचिीडीसी बाइपोल के एक पोल का खराब होिा ii. 'एि-1' के अंतगषत आसन्न बसों के बीच कोणीय पृथक्करण 30 जडिी से अजधक िहीं होगा। iii. एफ ए सी टी एस उपकरणों के जलए 'एि-1' मािदंड पर जिचार िहीं ककया िा सकता ह,ै हालाकं क एफ ए सी टी एस उपकरणों के बंद होि े की जस्ट्थजत म ें स्ट्थािांतरण क्षमता म ें कमी, िेिरेिि जिकासी पर प्रजतबधं आकद िैस े मुद्दों के समाधाि के जलए अध्ययि ककया िा सकता ह।ै (ख) क्षजणक-अिस्ट्था: आमतौर पर, गडबडी एक क्षजणक कारण बिती ह ै िो प्रकृजत म ें दोलििील होती ह,ै लेककि यकद प्रणाली जस्ट्थर ह,ै तो दोलि कम हो िाएंगे। उस प्रणाली को जस्ट्थर कहा िाता ह ैजिसम ेंतल्ु यकाजलक मिीि ेंबाजधत होि ेपर, या तो अपिी मलू जस्ट्थजत म ें िापस आ िाएगं ी, अगर जबिली के आदाि-प्रदाि म ेंकोई बदलाि िहीं होता ह ैया तुल्यकालि खोए जबिा असम्बद्ध रूप से िई जस्ट्थजत प्राप्त कर लेगी। जिम्नजलजखत आउटेि/िुकसाि म ेंसे ककसी एक के अधीि होि ेके बाद पारेर्ण प्रणाली जस्ट्थर होगा: (क) जसस्ट्टम बस के ििदीक 765 केिी लाइि पर स्ट्थायी तीि चरण की िाउंड फॉल्ट से बचि ेमें सक्षम होगा जिसे 100 एमएस में साफ ककया िाएगा। (ख) जसस्ट्टम बस के ििदीक 765 केिी लाइि पर स्ट्थायी लसंगल फेि टू िाउंड फॉल्ट स े बचि े म ें सक्षम होगा। तदिुसार, खराबीपूणष फेि के एकल पोल ओपलिगं (100 एमएस) और असफल पिु : समापि (समय 1 सके ंड) के बाद खराबीपूण ष लाइि के 3-पोल ओपलिगं (100 एमएस) पर जिचार ककया िाएगा। (ग) जसस्ट्टम बस के ििदीक 400 केिी लाइि पर स्ट्थायी तीि फेि की िाउंड फॉल्ट से बचि ेमें सक्षम होगा जिसे 100 एमएस में साफ ककया िाएगा। (घ) जसस्ट्टम बस के ििदीक 400 केिी लाइि पर स्ट्थायी लसंगल फेि टू िाउंड फॉल्ट स े बचिे म ें सक्षम होगा। तदिुसार, खराबीपूणष चरण के एकल पोल ओपलिगं (100 एमएस) और असफल पुि: समापि (समय 1 सेकंड) के बाद खराबीपूणष लाइि के 3-पोल ओपलिगं (100 एमएस) पर जिचार ककया िाएगा। (ङ) 220 केिी/132 केिी िेटिकष के मामले म,ें जसस्ट्टम 3-पोल ओपेलिंग पर 160 एमएस (8 चक्र) के फाल्ट जििारण समय के साथ, बस के ििदीक एक सर्कषट पर स्ट्थायी तीि फेि के फाल्टसे बचि े में सक्षम होगा। (च) जसस्ट्टम एचिीडीसी कन्‍दिटषर स्ट्टेिि में खराबी से बचिे में सक्षम होगा, जिसके पठरणामस्ट्िरूप एचिीडीसी बाइपोल का एक पोल स्ट्थायी रूप से बंद हो िाएगा। (छ) उत्पादि की हाजि: जसस्ट्टम एकल सबसे बडी उत्पादि इकाई या एक महत्िपूणष उत्पादि इकाई के िुकसाि के दौराि जस्ट्थर रहगे ा (महत्िपूण षउत्पादि इकाई का जिकल्प पारेर्ण योििाकार पर छोड कदया गया ह)ै (ि) एकल लबंद ुपर िडु े सबसे बडे रेजडयल लोड का िुकसाि। 3. दसू री आकजस्ट्मकता ('एि-1-1') 'एकल आकजस्ट्मकता' के जलए ऊपर पठरभाजर्त पठरदश्ृ य के अंतगतष जसस्ट्टम एक और आकजस्ट्मकता का अिुभि कर सकता ह ै(जिस े'एि-1-1' कहा िाता ह)ै : (क) जसस्ट्टम बस के ििदीक 765 केिी लाइि पर अस्ट्थायी लसंगल फेि टू िाउंड फॉल्ट से बचिे में सक्षम होगा। तदिुसार, खराबीपूणष फेि के एकल पोल ओपेलिगं (100 एमएस) और सफल पुिः समापि (डेड टाइम 1 सेकंड) पर जिचार ककया िाएगा। (ख) जसस्ट्टम बस के ििदीक 400 केिी लाइि पर स्ट्थायी लसंगल फेि टू िाउंड फॉल्ट स े बचिे म ें सक्षम होगा। तदिुसार, खराबीपूणष फेि के एकल पोल ओपेलिगं (100 एमएस) और असफल पुि: समापि (डेड समय 1 सेकंड) के बाद खराबीपूणष लाइि के 3-पोल ओपलिगं (100 एमएस) पर जिचार ककया िाएगा। (ग) 220 केिी/132 केिी िेटिकष के मामले में, जसस्ट्टम 3-पोल ओपलिंग पर 160 एमएस (8 चक्र) के खराबी जििारण[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 77 समय के साथ, बस के ििदीक एक सर्कषट पर स्ट्थायी तीि फेि की खराबी से बचि े में सक्षम होगा। िैसा कक ऊपर कहा गया ह,ै 'एि-1-1' म,ें यकद कोई अस्ट्थायी खराबी ह,ै तो जसस्ट्टम खराबी दरू होि े के बाद दसू रा तत्ि िहीं खोएगा, बजल्क गडबडी से सफलतापूिषक बच िाएगा। स्ट्थायी खराबी के मामले म,ें जसस्ट्टम खराबी जििारण के पठरणामस्ट्िरूप दसू रा तत्ि खो देगा और उसके बाद, समकाजलकता खोए जबिा असम्बद्ध रूप से एक िई जस्ट्थर जस्ट्थजत तक पहुचं िाएगा। इस िई जस्ट्थजत में, जसस्ट्टम पैरामीटर (अथाषत िोल्टेि और लाइि लोलडंग) आपातकालीि सीमा से अजधक िहीं होंगे, हालांकक, जसस्ट्टम पैरामीटर को सामान्‍दय सीमा के अंदर लाि े के जलए लोड िेलडंग/िेिरेिि के पुिर्िषधाषरण की आिश्यकता हो सकती ह।ै जिड के साथ रेजडयल रूप स ेिडु ा ििे रेिि ििरेटर(रों) को जिड स ेरेजडयल रूप से िोडिे िाली पारेर्ण प्रणाली के जलए, जिम्नजलजखत मािदंड लागू होंगे: (क) रेजडयल प्रणाली जस्ट्थर-अिस्ट्था और क्षजणक-अिस्ट्था दोिों के जलए ऊपर कदए गए 'एि-1' जिश्वसिीयता मािदंडों को पूरा करेगी। (ख) बाद की आकजस्ट्मकता के जलए अथाषत, 'एि-1-1' (दसू री आकजस्ट्मकता), रेजडयल प्रणाली के जलए केिल अस्ट्थायी खराबी पर जिचार ककया िाएगा। (ग) यकद 'एि-1-1' आकजस्ट्मकता स्ट्थायी प्रकृजत की ह ै या ककसी गडबडी/आकजस्ट्मकता के कारण मुख्य जिड से ऐसे ििरेटर का आइसोलिे ि हो िाता है, तो िेर् मिे जिड ििे रेिि के िुकसाि के जबिा लसंक्रोजिज़्म की एक िई जस्ट्थर जस्ट्थजत में पहुचं िाएगा। इस िई जस्ट्थजत म ें जसस्ट्टम परै ामीटर आपातकालीि सीमा से अजधक िहीं होंगे। हालांकक, जसस्ट्टम पैरामीटर को सामान्‍दय सीमा के अंदर लाि े के जलए लोड िेलडंग/ििे रेिि के पिु र्िषधाषरण की आिश्यकता हो सकती ह।ै (घ) 'एि-1' मािदंड आईएसटीएस/इंरा-एसटीएस जिड के साथ ििीकरणीय िेिरेिि की तत्काल किेजक्टजिटी प्रणाली अथाषत, उत्पादि पठरयोििा जस्ट्िचयाडष को जिड स े िोडिे िाली लाइि और जिड पर स्ट्टेप-अप रांसफामषर स्ट्टेिि पर लाग ूिहीं ककया िा सकता ह।ै बिते कक, 'एि-1' मािदंड भडं ारण के साथ ििीकरणीय उत्पादि पठरयोििाओं के मामले में लागू होंगे, िो प्रकृजत में दढृ ह ैंऔर परू ी तरह से प्रेर्ण योग्य ह।ैं (ङ) बिते कक, ििीकरणीय उत्पादि स्ट्टेििों के क्षमता कारक पर जिचार करिे के बाद 1000 मेगािाट से अजधक की ििीकरणीय ऊिाष आधाठरत उत्पादि के जलए आईएसटीएस / एसटीयू पूललंग स्ट्टेििों पर आईसीटी के जलए 'एि- 1' जिश्वसिीयता मािदंड पर जिचार ककया िा सकता ह।ै JOINT ELECTRICITY REGULATORY COMMISSION (FOR THE UT OF J&K THE UT OF LADAKH) NOTIFICATION Jammu, the 29th November, 2023 No. JERC-JKL/Reg/2023/19.—In exercise of the powers conferred by Section 181 read with section 86 (1) (h) of the Electricity Act, 2003 (36 of 2003) and all other powers enabling it in this behalf, the Joint Electricity Regulatory Commission for the UT of Jammu & Kashmir and the UT of Ladakh hereby makes the following Regulations. CHAPTER -1: GENERAL 1.1 Short Title, Extent and Commencement 1. These Regulations may be called the “Joint Electricity Regulatory Commission for the UT of Jammu & Kashmir and the UT of Ladakh (State Grid Code) Regulations, 2023”. 2. These Regulations shall come into force from the date of its publication in the official gazette. 3. These Regulations shall extend to the UT of Jammu & Kashmir and the UT of Ladakh.78 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 1.2 Definitions 1. In these Regulations the following words and expressions shall, unless the subject matter or context otherwise requires or is inconsistent therewith, bear the following meanings: Act The Electricity Act, 2003 (Act No. 36 of 2003) as amended from time to time; Accredited Test A test laboratory accredited by National Accreditation Board for Testing and Laboratory Calibration Laboratories (NABL); Active Energy The electrical energy produced, flowing or supplied by an electric circuit during a time interval, being the integral with respect to time of the instantaneous power, measured in units of watt-hours or standard multiples thereof, Active Power The product of voltage and the in-phase component of alternating current measured in units of watts and standard multiples thereof, Alert State means the state in which the operational parameters of the power system are within their respective operational limits, but a single n-1 contingency leads to violation of system security; Apparatus All the electrical apparatus like machines, fittings, accessories and appliances in which electrical conductors are used. Apparent Power The product of voltage and alternating current measured in unit of volt- amperes and standard multiples thereof, Appropriate The “Central Transmission Utility” (CTU) or the “State Transmission Utility” Transmission Utility (STU), as case may be; Area of Supply Area within which a Distribution Licensee is authorized by his license to supply electricity. Authority Central Electricity Authority (CEA) referred to in sub-section (1) of Section 70 of the Act. Automatic Voltage A continuously acting automatic excitation control system to control the voltage Regulator (AVR) of a Generating Unit measured at the generator terminals. Availability Based Tariff A tariff structure based on availability of generating units and having (ABT) components, viz., Capacity Charges (CC), Energy Charges (EC) or Variable Charges (VC) and charges for Unscheduled Interchange (UI). Bulk Consumer A Consumer who avails supply at voltage of 33 kV or above. Buyer Any generating company or licensee or consumer whose system receives electricity from the system of generating company or licensee. Captive Power Plant A Power Plant set up by any person to generate electricity for his own use and (CPP) includes a power plant set up by any co-operative society or association of persons for generating electricity primarily for use of members of such co- operative society or association. Central Commission Central Electricity Regulatory Commission (CERC) referred to in sub-Section (1) of section 76 of the Act. Central Transmission Any Government Company which the Central Government may notify under Utility (CTU) sub section (1) of section 38 of the Act. Check Meter A meter, which shall be connected to the same core of the Current Transformer (CT) and Voltage Transformer (VT) to which main meter is connected and shall be used for accounting and billing of electricity in case of failure of main meter.[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 79 Commission Joint Electricity Regulatory Commission for the UT of Jammu & Kashmir and the UT of Ladakh. Connection The electric power lines and electrical equipment used to affect a connection of a user’s system to the Transmission System. Connection conditions Those conditions mentioned in Chapter 4 (“connection conditions”) which have to be fulfilled before the User’s System is connected to the Grid. Connection point An electrical point of connection between the Transmission System and the User’s System. Consumer Any person who is supplied with electricity for his own use by a licensee or the Government or by any other person engaged in the business of supplying electricity to public under the Act or any other law for the time being in force and includes any person whose premises are for the time being connected for the purpose of receiving electricity with the works of a licensee, the Government or such other person, as the case may be. Control Area A control area is an electrical system bounded by interconnections (tie lines) metering and telemetry which controls its generation and / or load to maintain its interchange schedule with other control areas whenever required to do so and contributes to frequency regulation of the synchronously operating system. Demand The demand of Active Power in MW and Reactive Power in MVAR of electricity unless otherwise stated. Demand control Any of the following methods of achieving a load reduction: a) Consumer Load Management initiated by Users. b) Consumer Load reduction by Disconnection initiated by Users (other than following an instruction from Load Despatch Centre). c) Consumer Load reduction instructed by the Load Despatch Centre. d) Automatic under Frequency Load Disconnection. e) Emergency manual Load Disconnection. Distribution system The system of wires and associated facilities between the delivery points on the transmission lines or the generating station connection and the point of connection to the installation of the consumers. Drawl The import / export of electrical energy from / to the grid; Energy Accounting & Meters used for accounting of the electricity to various segments of electrical Audit Meters system so as to carry out further analysis to determine the consumption and loss of energy therein over a specified time period; Extra High Voltage Voltage exceeding 33000 volts under normal subject to the percentage variation (EHV) or Extra High allowed by the Authority. Tension (EHT) Forced Outage Forced outage of a generating unit or a transmission facility due to a fault or other reason which has not been planned. Generating company Any company or body corporate or association or body of individuals, whether incorporated or not, or artificial juridical person, which owns or operates or maintains a generating station. Generating station Any station for generating electricity, including any building and plant with step- up transformer, switchyard, switch gear, cables or other appurtenant equipment, if any, used for that purpose and the site thereof, a site intended to be used for a generating station, and any building used for housing the operating staff of a generating station and where electricity is generated by water – power, includes, penstocks, head and tail works, main and regulatory reservoirs, dams and other hydraulic works, but does not in any case include any substation.80 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] Grid High Voltage back bone system of inter-connected Transmission Lines, Sub Stations and Generating plants. State Grid Code These Regulations specify the philosophy and the responsibilities for planning and operation of the Power system for the UT of Jammu & Kashmir and the UT of Ladakh. Indian Electricity Grid Indian Electricity Grid Code (IEGC), specified by the Central Commission under Code (IEGC) clause (h) of sub section (1) of Section 79 of the Act. Grid Standards Grid Standards specified by the Central Electricity Authority under Clause (d) of section 73 of the Act. High voltage (HV) or Voltage greater than 400 V and does not exceed 33000 volts under normal High Tension (HT) conditions subject to the percentage variation allowed by the Authority. Independent Power Power Station owned by a generator who is not a part of Power and Electricity Producer Department. Indian Standards Those Standards and specifications approved by the Bureau of Indian Standards. Instrument The Current Transformer (CT), Voltage Transformer (VT) and Capacitor Voltage Transformer Transformer (CVT); Interconnecting Transformer connecting EHV lines of different voltage systems. Transformer Interface Meter A meter used for accounting and billing of electricity, connected at the point of interconnection between electrical systems of generating company, licensee, and consumers, directly connected to the Inter-State Transmission System or Intra – State Transmission system who have to be covered under ABT and has been permitted open access by the Appropriate Commission. Inter-State Transmission Inter-State Transmission System includes: System i) Any system for the conveyance of electricity by means of a main Transmission Line from the territory of one State to another State; ii) The conveyance of electricity across the territory of an intervening State as well as conveyance within a State, which is incidental to such inter-state transmission of electricity. iii) The transmission of electricity within the territory of a State built, owned, operated maintained or controlled by the Central Transmission Utility. Intra–State Any system for transmission of electricity other than an Inter - State Transmission System Transmission System. Isolation The disconnection of EHV / HV Apparatus from the remainder of the System in which that EHV / HV Apparatus is situated. Lean Period That period in a day when the electrical power demand is lowest. License A license granted under section 14 of the Act. Licensee This means a person who has been granted a license under section 14 of the Act. Load The Active, Reactive or Apparent power as the context requires, is generated, transmitted or distributed. Low Voltage or LV Voltage not exceeding 440 volts. Main Meter A meter which would primarily be used for accounting and billing of electricity. Main protection Protection equipment or system is expected to have priority in initiating either a fault clearance or an action to terminate an abnormal condition in a power system. Open Access The non-discriminatory provision for the use of transmission lines or distribution[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 81 systems or associated facilities with such lines or system by any licensee or consumer or a person engaged in generation in accordance with the regulations specified by the Appropriate Commission. Operation A scheduled or planned action relating to the operation of a system. Operational procedure Management instructions and procedures, both for the safety rules and for the local and remote operation of plant and apparatus, issued in connection with the actual operation of plant and/or apparatus at or from a connecting site. Outage A total or partial regulation in availability due to repair and maintenance of the Transmission or Distribution or Generation facility or defect in Auxiliary System. Part Load The condition of a generating station, which is loaded but is not running at its declared availability. Partial shutdown A shutdown of a part of the system resulting in failure of power supply, either from external connections or from the healthy part of the system. Peak period That period in a day when the electrical power demand is highest. Person Any company or body corporate or association or body of individuals, whether incorporated or not, or artificial juridical person. Planned outage An outage of generating plant or part of the Transmission system, or part of a User’s System coordinated by SLDC. Power factor The ratio of Active Power (KW) to Apparent Power (KVA) Power System Power system means all aspects of generation, transmission, distribution and supply of electricity and includes one or more of the following namely: a) Generating Station b) Transmission or main transmission lines c) Sub-stations d) Tie-lines e) Load despatch activities f) Mains or distribution mains g) Electric supply lines h) Overhead lines i) Service lines j) Works Protection The scheme and apparatus for detecting abnormal conditions on a system and initiating fault clearance or actuating signals or indications. Rated MW The “Name plate” MW output of a Generating machine, being that output up to which the Generating machine is designed to operate. Reactive Power The product of voltage and current and the sine of the phase angle between them measured in units of volt-amperes reactive and standard multiples thereof; Requester A person such as Generating Company including captive generating plant or Transmission Licensee (excluding State Transmission Utility) or Distribution Licensee or Bulk Consumer, who is seeking connection of his new or expanded electrical plant in the Grid at Voltage level exceeding 33 kV. Safety Rules The rules framed by the Users and the transmission licensee to ensure safety to persons working on plant / apparatus. Start – Up The action of bringing a generating unit from shutdown to synchronous speed. State Generating The generating plant that is required to be scheduled by SLDC in Station accordance with IEGC as issued by CERC from time to time. State Transmission This means the Board or the Government Company specified as such by the Utility appropriate Government under sub-section (1) of section 39. Sub station Station for transforming or converting electricity for the transmission or82 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] distribution thereof and includes transformers, converters, switchgears, capacitors, synchronous condensers, structures, cable and other appurtenant equipment and any buildings used for that purpose and the site thereof. Supervisory Control and The communication links and data processing systems, which provide information Data Acquisition or to enable implementation of requisite supervisory and control actions. (SCADA) Supplier Any generating company or licensee from whose system electricity flows into the system of another generating company or licensee or consumer Synchronized Those conditions where an incoming generating unit or system is connected to the bus bars of another system so that the frequencies and phase relationships of that generating unit or system as the case may be, and the system to which it is connected are identical. Transmission licensee A licensee authorized to establish and operate transmission lines Transmission lines All high-pressure cables and overhead lines (not being an essential part of the distribution system of a licensee) transmitting electricity from a generating station to another generating station or a substation, together with any step-up and step- down transformers, switch-gear and other works necessary to and used for the control of such cables or overhead lines, and such buildings or part thereof as may be required to accommodate such transformers, switch-gear and other works. Transmission system The system consisting of high-pressure cables and overhead lines of transmission licensee including electrical sub-stations, for transmission of electrical power from the generating station up to connection point / interface point with the distribution system. This shall not include any part of the distribution system. Under Frequency An electrical measuring relay intended to operate when its characteristic quantity Relay reaches the relay settings by decrease in frequency. User A person such as a Generating Company including Captive Generating Plant or Transmission Licensee (other than STU) or Distribution Licensee or Bulk Consumer within the State, whose electrical plant is connected to the Intra-State Transmission system at voltage level exceeding 33 kV. 2. Words and expressions used and not defined in these Regulations but defined in the Act shall have the meanings assigned to them in the Act. Expressions used herein but not specifically defined in these Regulations or in the Act but defined under any law passed by a competent legislature and applicable to the electricity industry in the state shall have the meaning assigned to them in such law. Subject to the above, expressions used herein but not specifically defined in these Regulations or in the Act or any law passed by a competent legislature shall have the meaning as is generally assigned in the electricity industry. 3. ABBREVIATION ABT Availability Based Tariff BIS Bureau of Indian Standards BS British Standards CEA Central Electricity Authority CERC Central Electricity Regulatory Commission CPP Captive Power Plant CT Current Transformer CTU Central Transmission Utility EHT Extra High Tension HT High Tension ICT Inter Connecting Transformer IEC International Electro-Technical Commission Standards IEGC Indian Electricity State Grid Code[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 83 IPP Independent Power Producer ISTS Inter State Transmission System KV Kilo Volt LCP Line Clear Permit NABL National Accreditation Board of Testing and Calibration Laboratories PGCIL Power Grid Corporation of India Ltd. PTW Permit to Work RLDC Regional Load Despatch Centre SCADA Supervisory Central and Data Acquisition SGC State grid code SGS State Generating Station SLDC State Load Despatch Centre STS State Transmission System STU State Transmission Utility VT Voltage Transformer 1.3 Introduction 1. The State Grid Code lays down the rules, guidelines and standards to be followed by all Users of the State Transmission System, to operate and maintain an efficient and coordinated power system in the for the UT of Jammu & Kashmir and the UT of Ladakh in coordination with the concerned Regional Grids as per the provisions of Indian Electricity Grid Code (IEGC) issued by Central Electricity Regulatory Commission (CERC) as amended from time to time and also in line with the National Electricity policy. 2. State Transmission Utility: The Administration of the UT of Jammu & Kashmir and the UT of Ladakh shall notify their respective Electricity Departments which are deemed licensees in terms of section 14 of the Electricity Act 2003, to act as State Transmission Utilities (STUs). Provided they shall not engage in the business of trading in electricity. The State Transmission Utilities shall discharge the functions as stipulated under Section 39 (2) of the Electricity Act, 2003. 3. (a) Establishment of SLDC: The Administration of the UT of Jammu & Kashmir and the UT of Ladakh shall establish a centre to be known as the State Load Despatch Centre (SLDC) in the UT of Jammu & Kashmir and the UT of Ladakh. The State Load Despatch Centre shall be operated by a Government company or any Authority or Corporation established or constituted by or under any State Act, as may be notified by Appropriate Government. Until a Government company or any authority or corporation is notified by the Appropriate Government, the State Transmission Utility shall operate the State Load Despatch Centre. (b) Functions of SLDC: State Load Despatch Centre shall discharge the functions as stipulated under Sections 32 (2) and 33 of the Act. (c) Manning of SLDC: i) SLDC shall be manned by qualified and experienced Engineers who are well acquainted with State Transmission System and grid operation. ii) Periodical Training shall be imparted to the personnel of the State Load Despatch Centre to update their skills in order to enable them to discharge their functions stipulated under Section 32 (2) & 33 of the Act. 1.4 Objectives of State Grid Code The State Grid Code governs the boundary between State Transmission Utility (STU) and Users as well as establishes guidelines for operation of facilities for those who are connected and will use the State Transmission System. It lays down both the information requirements and procedures governing the relationship between STU and Users. The principal objectives of the State Grid Code are: (a) To provide clarity in the functions of the STU, State Generation Companies, Distribution Licensees, IPPs / CPPs within the UT of J&K and the UT of Ladakh and open access customers connected to the State Grid by specifying their respective roles, responsibilities and obligations with respect to the operation of the State Grid.84 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] (b) To improve the grid stability and achieve minimum standards of system performance. (c) To specify the transmission connectivity requirement for new entrants i.e., future new generating companies, distribution/trading licensees, open access customers and consumers. (d) To document the normal practices in grid operation for easy reference and for compliance. (e) To elicit data from generators on the performance characteristics of their plant to meet the connectivity requirements. (f) To provide a mechanism for clear and consistent disclosure of all information between the utilities concerned. (g) To indicate how generation is to be scheduled and despatched. (h) To actually enforce what is verbally agreed. 1.5 Applicability The State Grid Code shall be applicable to all Users, Requesters, State Transmission Utility and SLDC who are connected to the transmission network. 1.6 Implementation of the State Grid Code: 1. The State Transmission Utility shall be responsible for implementation of the State Grid Code. All the Users shall comply with the provisions of this State Grid Code and assist the State Transmission Utility in all aspects. The Users must provide all the required information required for implementation of the State Grid Code. 2. If any User has any difficulty in complying with or any of the provisions of the State Grid Code, he shall, without delay, inform the same to the State Transmission Utility for guidance in complying with the provision. 3. The operation of the State Grid shall be reviewed regularly by the State Grid Code Review Committee in accordance with the provisions of the relevant section of the State Grid Code. 4. Users shall provide such reasonable cooperation and assistance to STU / SLDC as may be sought for and required by them. The STU / SLDC shall however refer all such cases for ratification in the next meeting of the review panel. 1.7 Non - Compliance by User 1. If any User fails to comply with any provision of the State Grid Code, the STU shall inform the State Grid Code Review Committee without delay the reasons for its non-compliance and ensure its compliance promptly. 2. SLDC shall report to the State Grid Code Review Committee, instances of serious violation of any provisions of the SGC and incidences of persistent non-compliance with the directions of the SLDC issued in order to exercise supervision and control required for ensuring the stability of grid operations. 3. Consistent failure to comply with the State Grid Code provisions may lead to disconnection of the User’s plant and/or facilities from the grid. The responsibility for the consequences of disconnection, including payment of damages and compensation to consumers, rests with the User who consistently violates the State Grid Code. 1.8 Code Responsibilities 1. In discharging its duties under the State Grid Code, STU has to rely on information, which Users shall supply regarding their requirements and intentions. 2. STU shall exercise strict supervision over the Users to ensure compliance with the instructions issued by SLDC for efficient discharge of the grid operations. 1.9 Confidentiality 1. Under the terms of the State Grid Code, STU will receive information from Users relating to their intentions in respect of their Generation or Supply businesses. 2. STU shall not, other than as required by the State Grid Code, disclose such information to any person other than Central or State Government without the prior written consent of the provider of the information. 1.10 Directives The appropriate Government may issue policy directives in any matter to STU or SLDC as the case may be, to take such measures as may be necessary for maintaining smooth and stable transmission and supply of electricity to any region of State as per section 37 of the Electricity Act 2003. STU shall promptly inform the Commission and all Users of the requirement of such directives. The Users, subject to the relevant sections of the Act, shall comply with all such directives.[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 85 1.11 Compatibility with Indian Electricity State Grid Code This State Grid Code shall be consistent / compatible with the IEGC. However, in matters relating to inter-State transmission, if any provisions of the State Grid Code are inconsistent with the provisions of the IEGC, then the provisions of IEGC as approved by CERC shall prevail. 1.12 The Power Department functioning as an integrated Utility The functions of STU, SLDC, generating stations, and Distribution Licensees shall be performed by the concerned officers authorized by the Electricity Department as long as it continues to function as an integrated Utility. 1.13 Structure of the UT of J&K and the UT of Ladakh State Grid Code The State Grid Code for the UT of J&K and the UT of Ladakh consists of the following chapters: Chapter-1: General; Chapter-2: Management of State Grid Code Chapter-3: System Planning; Chapter-4: Connection Conditions; Chapter-5: System Security Aspects; Chapter-6: Frequency and Voltage Management; Chapter-7: Protection; Chapter-8: Operation Planning; Chapter-9: Monitoring of Generation and Drawal; Chapter-10: Outage Planning; Chapter-11: Contingency Planning; Chapter-12: Inter User Boundary Safety; Chapter-13: Operational Event Information Reporting; Chapter-14: Scheduling and Load Despatch; Chapter-15: Metering; Chapter-16: Safety and Line Clear Permits; Chapter-17: Data Registration; Chapter-18: Miscellaneous. CHAPTER –2 MANAGEMENT OF STATE GRID CODE 2.1 Objective The State Transmission Utility (STU) is required to implement and comply with the State Grid Code and to carry out periodic review and amendments of the same with the approval of the Commission. A State Grid Code Review Committee shall be constituted by STU, as required in this Chapter, comprising of the representatives of the Users of the Transmission System. 2.2 State Grid Code Review Committee 1. The State Grid Code Review Committee shall be established separately by each STU. 2. The Chairperson of the State Grid Code Review Committee shall be an Engineer of the STU not below the rank of Executive Engineer. The Member Secretary of the Review Committee shall also be nominated by STU. The Review Committee shall consist of the following members as recommended by the heads of the respective organizations: a. One engineering representative at executive level from Transmission Licensee. b. One representative at executive level from the concerned Regional Load Despatch Centre c. One representative at executive level from the State Load Despatch Centre. d. One representative at executive level from Distribution Licensee(s) of the State.86 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] e. One representative at executive level from state generating company and IPP(s). f. One member from the State Government connected with Electricity Affairs of the State. g. Any other member co-opted / nominated by the Commission. 3. The Member Secretary nominated by STU shall be the convener and he shall coordinate the functioning of the committee. 4. STU shall inform all the Users, the names and addresses of the Review Committee Chairperson and the Member Secretary. Any subsequent changes shall also be informed to all the Users by STU. Similarly, each User shall inform the names and designations of their representatives to the Member Secretary of the Review Committee. 2.3 Functions of the State Grid Code Review Committee The functions of the Review Committee are as follows: a. Implementation of the State Grid Code, and continuous scrutiny and review. b. Consideration of all requests for review proposed by any User and publication of the recommendations for changes in the State Grid Code together with reasons for such changes. c. Consideration of the problems raised by any User as well as resolution of the problems. d. Review and analyze the reasons for failure of protection system in case of any grid disturbances and recommend methods for improvement. e. Ensuring that the changes / modifications proposed in the State Grid Code are consistent and compatible with Indian Electricity Grid Code (IEGC). f. Such other matters as may be directed by the Commission from time to time. The State Grid Code Review Committee may hold any number of meetings as required subject to the condition that at least one meeting shall be held once every twelve (12) months. Sub-meetings may be held by STU with the Users to discuss individual requirements to prepare proposals for Review Committees consideration. 2.4 Review and Revisions 1. The State Grid Code shall be reviewed by the State Grid Code Review Committee at least once in every twelve (12) months. 2. No change in the State Grid Code, shall be made without being deliberated and agreed by the State Grid Code Review Committee and approved by the Commission. 3. The Users seeking any amendment to the State grid code shall send written requests to the Member Secretary of the State grid code Review Committee. 4. The Member Secretary shall place all the proposed revisions for the State grid code to the Review Committee for its consideration. 5. After discussion in the review meeting, the State grid code Review Committee shall send a report to the STU and to the Commission, providing information regarding: (i) Outcome of the review; (ii) Any proposed revisions to the State grid code; and (iii) All written representations submitted by the Users; 6. The STU shall send the report along with its recommendations regarding the proposed modification(s) / amendment(s) along with all the related correspondence to the Commission for approval. 7. Amendments to the State Grid Code shall be finalized and notified by the Commission duly adopting the prescribed procedure followed for regulations issued by the Commission. 8. After the approval by the Commission, the STU shall publish revisions to the State grid code and forward copies of approved amendments to all Users. 9. STU shall maintain copies of the State grid code with the latest amendments and shall make them available at a reasonable cost to any person requiring it. This may also be made available on the website as soon as feasible. The STU shall keep an up-to-date list of recipients of all copies of the State Grid Code, to ensure that the latest version of State grid code reaches to all concerned.[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 87 10. The Commission, may, on the application by the User or otherwise, call the emergency meeting of the State grid code Review Committee as and when required and make such alterations or amendments in the State grid code as it thinks fit. CHAPTER –3 SYSTEM PLANNING 3.1 Objective This Chapter formulates the procedures for the ‘System Planning’ to enable STU in consultation with the Users, to ensure an efficient, coordinated, secure and economical State Transmission System to satisfy requirements of future demand. 3.2 Development of State Transmission System 1. Reinforcement or extension of the State Transmission system arises due to many reasons of which a few are mentioned below: i) Developments / changes occurring on a user’s system already connected to the State Transmission System. ii) Introduction of a new connection point between the User’s system and the State Transmission System. iii) System of evacuation of power from generating stations within or outside the State iv) Reactive power compensation. v) Need to increase system capacity, to remove operational constraints and to maintain standards of security to accommodate a general increase in the demand. vi) Transient and steady state stability considerations. vii) Cumulative effect of any combination of the above. viii) Any other need to effect changes in the State Transmission System. The reinforcement or extension of the State Transmission System may involve work at an entry or exit point (connection point) of a User to the State Transmission System. 2. Development of State Transmission system must be planned well in advance to ensure consents and way leaves to be obtained and detailed engineering design / construction work to be completed. To this effect, the planning code imposes time lines for exchange of necessary information between STU and Users. 3.3 Planning Policy 1. STU would develop a perspective transmission plan for next 10 years for the State Transmission System. These perspective transmission plans shall be updated every year to take care of any revisions / modifications in load projections, generation capacity additions etc. The perspective plans shall be submitted to the Commission for approval. 2. STU shall carryout network studies and review fault levels to plan strengthening and augmentation of the State Transmission System. 3. STU shall follow the following steps in planning: i) Forecast the demand for power within the area of supply based on the load forecasts provided by Distribution Licensees. These shall include details of demand forecasts, data methodology and assumptions on which forecasts are based. These forecasts would be annually reviewed and updated, and also whenever major changes are required in the existing system. ii) Prepare a transmission plan for the State Transmission System compatible with the above load forecast and generation plan, Reactive Power (VAR) compensation needed etc. iii) To prepare and submit a long term (10 years) plan to the Commission for State Transmission System expansion to fully meet both energy and peak demand. iv) To extend full support to CTU to finalize the annual planning. Corresponding to a 5 year forward term for identification of major interstate transmission system including inter - regional schemes which shall fit in with the long-term plan developed by CEA. v) The State Transmission Utility shall, also submit its investment plan based on the identified intra-State transmission schemes and system strengthening schemes projected in the transmission system plan. vi) The cost of the transmission system planning study undertaken in accordance with this Regulation shall be allowed in the determination of the charges of the State Transmission Utility88 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 4. All Users shall supply to STU the planning data prescribed as in Appendix A and Appendix B of Data Registration Chapter within 6 months from the date of notification of the State Grid Code and thereafter such data shall be furnished by 31st March every year to enable STU to formulate and finalize the updated plan by 30th September each year for the next 5 years. 3.4 Planning Criterion 1. The planning criterion shall be based on the security philosophy on which both Inter State Transmission System (ISTS) and the State Transmission System (STS) has been planned. The security philosophy shall be as per the Transmission Planning criteria and other guidelines as laid down by CEA in the CEA (Grid Standards) Regulations 2010 as amended from time to time. The STU shall carry out appropriate system studies while developing the transmission system plan. 2. The State Transmission System, as a general rule, shall be capable of withstanding and be secured against the following contingency outages without necessitating load shedding or rescheduling of generation during steady state operations: a. Outage of a D/C line of voltage above 66 kV, below 400 kV, b. Outage of S/C line of voltage of 400 kV and above, c. Outage of a single Inter Connecting Transformer, d. Outage of a one pole of HVDC Bipole line or, e. Outage of a 765kV S/C line. The above contingencies shall be considered assuming a pre – contingency system depletion (Planned outage) of another 220 KV D/c line or 400 KV S/c line in another corridor and not emanating from same sub-station. 3. All the generating Units may operate within their reactive capability curves and the network voltage profile shall also be maintained within voltage limits specified. 4. The State Transmission System (STS) shall be capable of withstanding the loss of most severe single system in feed without loss of stability. 5. Any one of the events defined in sub para 3.4 (2) above shall not cause: (i) Loss of supply; (ii) Prolonged operation of the system frequency below and above specified limits; (iii) Unacceptable high or low voltage; (iv) System instability; (v) Unacceptable overloading of ISTS / STS elements 6. In all extra high voltage sub-stations suitable number (at least two) and appropriate capacity transformers shall be provided to have reliability. In HVDC substations, at least one spare converter/inverter transformer shall be kept ready to use at any time. 7. STU shall carry out planning studies for Reactive Power compensation of State Transmission System including reactive power consumption requirement at the State Generating Stations switchyard. 3.5 Planning responsibility 1. The primary responsibility of load forecasting within distribution licensee’s area of supply rests with the respective Distribution Licensees. The Distribution Licensee shall determine peak load and energy forecast of their areas for each category of loads for each of the succeeding 5 years and submit the same annually by 31st March to STU along with details of demand forecasts, data, methodology and assumptions on which forecasts are based along with their proposals for transmission system augmentation. The load forecasts shall be made for each of the prevalent as well as proposed inter connection points between STU and Distribution Licensees and shall include annual peak load and energy projections. The demand forecasts shall be updated annually or whenever major changes are made in the existing forecasts or planning. While indicating requirements of single consumers with large demands (1 MW or higher) the Distribution Utility/ Licensee shall satisfy itself as to the degree of certainty of the demand materialising. 2. Generating stations shall provide their generation capacity to STU for evacuating power from their power stations for each of the succeeding 5 years along with their proposals for augmentation of transmission proposals and submit the same annually by 31st March to STU. 3. The planning for strengthening the State Transmission System for evacuation of power from outside state stations shall be initiated by STU.[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 89 3.6 Planning data 1. State Generating Companies / IPPs / licensees shall supply following types of data to STU for the purpose of developing transmission plan: (i) Standard Planning Data (ii) Detailed Planning Data Standard Planning Data: - i) Standard Planning data shall consist of details which are expected to be normally sufficient for the STU to investigate the impact on the State Transmission System (STS) due to User / Transmission Licensee development. ii) The Users and Transmission Licensee shall provide the following data to STU from time to time (a) preliminary project planning data, (b) committed project planning data and (c) connected planning data. Detailed Planning data: - Detailed Planning data shall consist of detailed data required by STU to assess the impact of User / Transmission Licensee development on the State Transmission System. The detailed planning data shall be furnished by the Users and Transmission Licensees as and when requested by STU. Formats: The formats for submission of the above data are given in Appendices in the Data Registration Chapter - 17 2. The one-time data shall be submitted by all the Users and Transmission Licensees to STU within six (6) months from the date of notification of this State Grid Code. 3. STU shall also furnish to all the Users, the Annual Transmission Planning Report, Grid Map and any other information as the Commission may specify. 3.7 Implementation of Transmission Plan The actual programme of implementation of State transmission lines, inter – connecting transformers, reactors/capacitors and other transmission elements will be determined by STU in consultation with the concerned agencies. The completion of these works within time frame shall be ensured by STU through the concerned agencies. CHAPTER – 4: CONNECTION CONDITIONS 4.1 Objective The objective of this Chapter is to ensure the following: 1. All Users and prospective users are to be treated equally. 2. Any new or modified connection when established shall not impose any adverse effect on the existing Users and new connections shall not suffer adversely due to existing user connection. 3. A system of acceptable quality is ensured by specifying minimum design and operational criteria, to assist the Users in their requirement to comply with the license obligations. 4. The ownership and responsibility for all equipment is clearly specified in a schedule “(Site Responsibility Schedule)” for every site, where a Connection is made. 4.2 Procedure for connection to State Transmission System 1. Application for new or modification of existing arrangement of connection to the STS shall be submitted by the concerned User to the State Transmission Utility. The format for application shall be developed by State Transmission Utility and shall be made available at its office and in its website within two (2) months of notification of this State Grid Code. 2. The above application shall be submitted along with the following details: (i) Purpose of the proposed connection or modification, transmission licensee to whose system connection is proposed, connection point, description of apparatus to be connected or modification of the apparatus already connected and beneficiaries of the proposed connection; (ii) Construction schedule including completion date, and90 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] (iii) Confirmation that the User shall abide by the provisions of State Grid Code. 3. The STU shall forward a copy of the application to the Transmission Licensee in whose system the connection is being sought and to the State Load Despatch Centre for their comments. 4. The Transmission licensee, in whose system the connection is being sought, may carry out the power system studies as considered appropriate before allowing any new connection. 5. The STU shall, within thirty (30) days, from the receipt of an application and after considering all suggestions and comments received from the parties identified under para (3) above accept the application with such modification or such conditions as may be specified by the STU. 6. On acceptance of an application, the STU shall make a formal offer to the applicant for consent, specifying any works required for the extension or reinforcement of the State Transmission System necessitated by the applicant’s proposal. A copy of the offer shall be forwarded to the concerned Transmission Licensee. 7. The STU shall, upon compliance of the required conditions by the User, shall notify the concerned User, that it can be connected to the STS. 8. The applicant and the concerned Transmission Licensee or STU, in whose system the connection is being sought, shall finalize a Connection Agreement on acceptance of the offer by the applicant. A copy of the Connection Agreement shall be provided to the STU and SLDC. 4.3 Rejection of application 1. STU shall be entitled to reject any application for connection to the State Transmission System for reasons, to be recorded in writing, if such application is not in accordance with the provisions of the State Grid Code. 2. In the event of any dispute with regard to rejection of application by STU, the User may approach the Commission 4.4 Connection Agreement 1. All Users connected to or seeking connections to the STU shall enter into a connection agreement with the STU. 2. A connection agreement, shall include within its terms and conditions, the following: (i) A condition requiring both parties to comply with the provisions of the State Grid Code. (ii) Details of connection, technical requirements and commercial arrangements. (iii) Details of any capital related expenditure arising from reinforcement or extension of the system, data communication etc, and demarcation of the same between the concerned parties. (iv) Details of Plants and equipments to be connected. (v) A Site Responsibility Schedule. (vi) General philosophy, guidelines, etc. on protection. (vii) Any other information considered appropriate by the STU. 4.5 Site Responsibility Schedule 1. For every connection to the State Transmission System for which a connection agreement is required, the User shall prepare a schedule called ‘Site Responsibility Schedule’ indicating the following for each item of equipment installed at the connection site. i) Ownership of the equipment ii) Responsibility for control of equipment iii) Responsibility for maintenance of equipment iv) Responsibility for operation of equipment v) Responsibility for all matters relating to safety of any person at the connection / interface site. vi) Management of the Connection / Interface site. 2. The format to be used in the preparation of Site Responsibility Schedule is given in Appendix – C in the Data Registration Chapter.[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 91 4.6 System Performance 1. The Design and Construction of all the equipment connected to the State Transmission System shall satisfy the relevant Indian Standard Specifications. In case of equipment for which Indian Standard Specifications do not exist, the appropriate IEC, or IEEE or other International Standards shall apply. 2. Installation of all electrical equipment shall comply with IE Rules, 1956 which are in force for time being or as replaced by new rules made under Electricity Act, 2003. 3. For every new / modified connection sought the STU shall specify the connection point, technical requirements and the voltage to be used, along with protection and metering requirements as specified in the Protection Code (Chapter-7) and Metering Code (Chapter-15). 4. Insulation coordination of the User’s equipment shall conform to those applicable as per Indian Standards. Rupturing capacity of the switchgear shall not be less than that specified as per Indian Standards. 5. Protection schemes and metering schemes shall be as detailed in the Protection Code and Metering Code Chapter. 6. The State Transmission System rated frequency shall be 50.00 Hz and shall normally be controlled within the limits as per Regulations issued by the Authority. 7. The User shall be subject to the Grid discipline prescribed by SLDC and RLDC. 8. In the event of Grid disturbances in the Regional Grid, SLDC shall not be liable to maintain system parameters within the normal range of voltage and frequency. 4.7 Connection Points / Interface points 1. State Generating Station (SGS) / IPPs / CPPs:  The voltage at the Connection point / Interface point with the State Transmission System may be 220/132/110/66 KV or as agreed with STU.  Unless specifically agreed with STU, the Connection point with generating station shall be the terminal isolator provided just before the outgoing gantry of the feeders.  SGS shall operate and maintain all terminals, communication and protection equipment provided within the generating station.  The provisions for the metering between generating station and STU system shall be as per the Metering Code.  Respective Users shall maintain their equipment from the outgoing feeders’ gantry onwards emanating from generating station. 2. Distribution Licensee:  The voltage at the Connection Point / Interface Point to State Transmission System may be as specified by the Distribution Licensee or as agreed with STU. For EHV consumer directly connected to the transmission system, voltage may be 220kV or 132kV.  Unless specifically agreed with Distribution Licensee, the Connection point with STU shall be the outgoing feeder gantry, from STU substation.  STU shall operate and maintain all terminals, communication and protection equipment provided within its sub- station.  The provisions for the metering between Distribution Licensee and STU systems shall be as per the Metering Code.  Respective Users shall maintain their equipment beyond the outgoing gantry of feeders emanating from STU sub-station onwards. 3. Regional Transmission System:  The Connection, protection scheme, metering scheme and the voltage shall be in accordance with the provisions of IEGC. 4. EHV Consumers and Open Access Customers:  The voltage may be 220/132/110/66 KV or as agreed with STU.  The Connection point shall be just before the feeder gantry in their premises. The metering point shall be Connection point / Interface Point with their system.92 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 4.8 Connectivity of renewable energy generating station to the grid General Conditions for Connectivity of Renewables General Conditions for Connectivity of Renewable sources can be connected at the distribution level (not exceeding 33 kV) or transmission level (above 33 kV) of the State which can be amended as and when required. 4.9 Data Requirements:  Users shall provide STU with data as specified in the Data Registration Chapter.  Unless otherwise agreed in the Connection Agreement, the equipment for data transmission and communication shall be operational and maintained by the User in whose premises it is installed irrespective of its ownership. CHAPTER – 5: SYSTEM SECURITY ASPECTS 5.1 Objective All Users shall endeavour to operate their respective power systems and generating stations in synchronism with each other at all times, such that the State Grid operates as synchronized system and integrated part of Concerned Regional Grid. The STU shall endeavour to operate the interstate links in such a way that transfer of power can be achieved smoothly when required. Security of the power system and safety of power equipment shall enjoy priority over economically optimal operations. 5.2 Scope The System Security relates to entire inter–connected power system including that of Users. The operation of the State Transmission System will be supervised and regulated by SLDC as per directions and instructions of RLDC. 5.3 System Security 1. All switching operations, whether affected manually or automatic, will be based on policy guidelines of: i) IEGC ii) RLDC’s instructions/guidelines under IE Rules iii) State Grid Code 2. No part of the State Transmission System shall be deliberately isolated from the integrated grid except under the following conditions; i) Under emergency conditions in which such isolation would prevent a total grid collapse and / or would enable early restoration of power supply ii) When serious damage to a costly equipment is imminent and such isolation would prevent it and iii) When such isolation is specifically instructed by SLDC. 3. In case of isolating of any important element of the STS under an emergency situation, the same shall be intimated to SLDC at the earliest possible time after the event. 4. Complete synchronization of grid shall be restored as soon as the conditions permit it. The restoration process shall be supervised by SLDC. 5. Any tripping, whether manual or automatic of transmission lines of 66 KV and above or power transformers of 66 KV shall be promptly reported to the SLDC at the earliest along with the reasons for such tripping and the likely time required for restoration. While restoring the tripped equipment / line, SLDC shall be informed and get the clearance. 6. Each User and Transmission Licensee shall provide adequate and reliable communication facility internally and with State Load Despatch Centre, other Users and other Transmission Licensees to ensure exchange of data/information necessary to maintain reliability and security of the grid. 7. All generating units, which are synchronized with the GRID, irrespective of their ownership, type and size, shall have their governors in normal operation at all times. If any generating unit of over fifty (50) MW size is required to be operated without its governor in normal operation, the NRLDC through SLDC shall be immediately advised about the reason and duration of such operation. The exemption from free governor mode operation in respect of run of river hydro stations without any pondage steam turbine of thermal and gas-based power stations not having free governor mode facility shall be sought from CERC under clause 1.6 of IEGC. Such petitions for exemption shall be preceded by a study preferably by CEA.[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 93 8. System operator shall make all efforts to evacuate the available Solar and Wind Power and treat as a must-run station. However, System operator may instruct solar/wind generator to back down generation on consideration of safety of any equipment or personnel is endangered and Solar/wind generator comply with the same. 9. User and State Transmission Utility shall send the requested information/data including disturbance recorder/sequential event recorder output etc to State Load Despatch Centre for the purpose of analysis of any grid disturbance/event. CHAPTER -6: FREQUENCY AND VOLTAGE MANAGEMENT 6.1 Objective The objectives of this chapter are as follows: 1. To define the responsibilities of all Users in contributing to frequency and voltage management. 2. To define actions required to enable SLDC and STU to maintain the State Transmission System voltages and frequency within acceptable levels in accordance with IEGC guidelines as well as Planning and Security Standards for the Inter-State Transmission System specified by the Central Commission, if any. 6.2 Frequency Management 1. The rated frequency of the system shall be 50 Hz and shall normally be controlled within the limits specified by the Central Electricity Authority or the Indian Electricity Grid Code as amended from time to time. 2. The STU & SLDC shall make all possible efforts to ensure that grid frequency remains within 49.9 - 50.05 Hz band. However, under conditions of falling and rising frequency following measures needs to be adopted; a) Falling frequency Under falling frequency conditions, SLDC shall take appropriate action to issue instructions, in co-ordination with RLDC to arrest the falling frequency and restore frequency within permissible range. Such instructions may include despatch instruction to SGS to increase generation and/or instruction to the Distribution Licensees and Open Access Customers to reduce load demand by appropriate manual and/or automatic load shedding. b) Rising Frequency Under rising frequency conditions, SLDC shall take appropriate action to issue instructions to SGS in co- ordination with RLDC to arrest the rising frequency and restore frequency within the permissible range. SLDC shall also issue instructions to Distribution Licensees and Open Access Customers in coordination with RLDC to lift Load shedding (if exists) in order to take additional load. In case of a Load Crash, SLDC shall take steps as per Para 8.4 of this Code. 6.3 Voltage Management 1. Users using the State Transmission System and STU shall make all possible efforts to ensure that the grid voltage always remains within the limits specified in IEGC at clause 5.2 (r). Voltage (kV rms) Nominal Maximum Minimum 400 420 380 220 245 198 132 145 122 The Minimum voltages are revised from 360 to 380 kV for 400 kV, 200 to 198 kV for 220 kV and 120 to 122 kV for 132 kV in the latest IEGC. Similarly, considering the same percentage voltage variations as above, the maximum and minimum limits of 110 kV and 66 kV voltages will be as given below. Nominal Maximum Minimum 110 121 102 66 72 6194 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 2. STU and/or SLDC shall carry out load flow studies based on operational data from time to time to predict where voltage problems may be encountered and to identify appropriate measures to ensure that voltages remain within the defined limits. On the basis of these studies, SLDC shall instruct SGS to maintain specified voltage level at interconnecting points. SLDC shall continuously monitor 220 KV, 132 KV, 110 KV and 66 KV voltage levels at strategic sub-stations. 3. SLDC shall take appropriate measures to control State Transmission System Voltages, which may include transformer tap changing, capacitor / reactor switching and capacitor switching by Distribution Licensees at 110 KV, 66 kV or 33 KV substations, and use of MVAr reserves with SGS within technical limits agreed to between STU and Generators. Generators shall inform SLDC of their reactive reserve capability promptly on request. 4. SLDC will ensure that there is minimum reactive power flow on transmission network. Reactive energy demand would be met by installation of capacitor banks at suitable sub-stations as per load flow study. 5. Distribution Licensees and Open Access Customers shall participate in voltage management by providing Local VAR compensation (as far as possible in low voltage system close to load points) such that they do not depend upon EHV grid for reactive support. CHAPTER –7: PROTECTION 7.1 Objective 1. The objective of this Chapter is to define the minimum protection requirements for any equipment connected to the State Transmission System to safe guard from faults and thereby minimize any disruption due to faults. 2. Minimum protection requirements are prescribed because inadequate protection or mal-operation of protection system of any entity may result in far-reaching consequences, disturbances and even damages to the system of other entities. 7.2 General Principles 1. No item of electrical equipment shall be allowed to remain connected to the State Transmission System unless it is covered by minimum specified protection relay settings aimed at reliability, selectivity, speed, stability and sensitivity. 2. All Users shall co-operate with STU to ensure correct and appropriate settings of protection to achieve effective, discriminatory removal of faulty equipment within the target clearance time specified in this section. 3. Protective Relay settings shall not be altered, or protection relays bypassed and/or disconnected without consultation and agreement between all affected Users. In a case where protection is bypassed and/or disconnected by an agreement, then the cause must be rectified and the protection restored to normal condition as quickly as possible. If an agreement has not been reached, that electrical equipment not having protection shall be removed from service forthwith. 7.3 Protection Coordination 1. The State Grid Code Review Committee constituted as per Chapter-2 of the State Grid Code and shall also be responsible for all the protection coordination functions. 2. The settings of protective relays starting from the generating unit up to the remote end of 110kV/66kV/33 KV line shall be such that only the faulty section is isolated under all circumstances. 3. The STU shall notify the initial settings and any subsequent changes approved by the Committee to the Users from time to time. Periodical testing of all the protective relays shall be conducted once in six months. 4. Malfunctioning of any protective relay shall be intimated to the State Grid Code Review Committee immediately for analyzing and to recommend necessary corrective actions. 5. A separate cell headed by an engineer of executive level, having experience in protection of system and consisting of necessary supporting technical and no-technical staff shall be established by the STU, for testing and maintenance of protection relays, meters and other connected instruments. 6. At all places where protection schemes are installed, they have to be exhibited in single line diagram. 7. Copies of the specifications of all the protection relays installed shall be provided at all places where such relays are installed. 7.4 Fault Clearance Times 1. The fault clearance time when all equipment operates correctly, for a three-phase fault (close to the bus bars) on user equipment directly connected to State Transmission System and for a three-phase fault (close to bus bars) on State Transmission Connected to the user’s equipment, shall not be more than;[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 95 a) 100 milliseconds for 400 kV class of voltage b) 160 milliseconds for 220 kV, 132 kV and 110 kV class of voltage c) 300 milliseconds for 66 kV class of voltage 2. Lesser fault clearance time than the above are preferable. 3. Lower fault clearance times for faults on a user’s system may be agreed to but only if, in STU’s opinion, system conditions allow this. STU shall specify the required opening time and rupturing capacity of the circuit breakers at various locations for STU and Distribution Licensees / Open Access Customers directly connected to Transmission System. At generating stations, line faults should be cleared at the generation station end within the critical clearing time so that the generators remain in synchronism. 7.5 Generator Requirements 1. All Generating Units and all associated electrical equipment of the Generating Units connected to the State Transmission System shall have adequate protection and backup protection system approved by the Protection Coordination Committee so that the State Transmission System does not suffer due to any disturbances originating from the Generation units. 2. The guidelines mentioned in the Manual on protection of generators, Generator Transformers etc. vide publications No. 274 of CBIP shall also be kept in view. 7.6 Transmission Line Requirements 1. General Every EHT line taking off from a Generating Station or a sub-station or a switching station shall have adequate protection and back up protection approved by the Protection Coordination Committee. Switchgear equipment and Relay Panels for the protection of lines of STU taking off from a Generating Station shall be owned and maintained by the Generator. Any transmission line related relay settings or any change in relay settings will be carried out by the Generator in close co-ordination and consultation with STU. Carrier cabinets / equipment, Line matching units including wave traps and communication cable shall be owned and maintained by STU. All Generators shall provide space, connection facility, and access to STU for such purpose. The guidelines mentioned in the Manual on protection of 220 kV and 400 kV network etc. vide publication No. 274 of CBIP shall also be kept in view. 2. 400kV Transmission Lines All 400kV transmission lines owned by STU shall have two fast acting protection schemes, the voltage of the two relays shall be fed from two different cores of the line CVT and the currents of the two relays shall be fed from two different cores of the line CTs. Main 1 protection scheme shall be numerical, three zone, non-switched fast acting distance protection scheme with permissible inter-trip at remote end (in case of zone-2 fault). Main 2 protection scheme shall be either similar type of numerical, three zone, non-switched fast acting distance protection scheme with permissible inter-trip at remote end (in case of zone-2 fault) or a unit protection scheme employing transient wave detection, directional comparison or phase comparison carrier relaying scheme. One pole tripping and single shot auto-reclosing with adjustable dead-time shall be provided. All 400kV sub-station shall have bus-bar differential protection scheme along with LBB and auto-reclosures for transmission lines 3. 220 KV Transmission Lines All 220 KV transmission lines owned by STU shall have two fast acting protection schemes. Main 1 protection scheme shall be numeric, three zone, non-switched fast acting distance protection scheme with permissible inter-trip at remote end (in case of zone-2 fault). The scheme shall have power swing blocking, location of fault recording, disturbance recording, event logger, communication port, single and three shot auto reclosing as well as Local Breaker Backup (LBB). Main 2 protection scheme shall be static/ numeric, three zone, switched/ non-switched fast acting distance protection scheme having all features as in Main- 1 except auto reclosing and Local Breaker Backup (LBB). For back-up protection, three directional IDMTL over current relays and unidirectional earth fault relay shall be provided. 4. 132 KV/110 KV/66 KV Lines96 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] A single scheme three zone, non-switched numeric distance protection with standard built in features like single and three phase tripping, carrier inter-tripping, IDMT over current and earth fault, power swing blocking and LBB protection shall be provided as main protection. The backup protection shall be at least two directional IDMTL over current relays and one directional earth fault relay. For short transmission radial lines, appropriate alternative protection schemes may be adopted. 7.7 Transformer Requirements 1. The protection of Power Transformers shall be as approved by the Protection Coordination Committee. The guidelines mentioned in the manual on transformers published by the Central Board of Irrigation and Power (CBIP) Publication No. 275 shall also be kept view. The following minimum protections shall be ensured for transformers: (i) All 220 KV class power transformers shall be provided with numeric fast acting differential, REF, open delta (Neutral Displacement Relay) and over-fluxing relays. In addition, there shall be back up IDMTL over current and earth fault protection. For parallel operation, such back up protection shall have inter-tripping of both HV and LV breakers. For protection against heavy short circuits, the over current relays should incorporate a high set instantaneous element. In addition to electrical protection, transformer own protection viz. Buchholz, OLTC oil surge, gas operated relays, winding temperature protection, oil temperature protection, PRV relay shall be provided for alarm and trip functions. (ii) For 132 KV, 110 KV and 66 KV class power transformers of capacity of 10MVA and above; the protection shall be same as mentioned in 7.7 (1) (i) above except over-fluxing, REF and PRV relays. (iii) For 132 KV, 110 KV and 66 KV class power transformers of capacity less than 10 MVA, over-current with high set instantaneous element along with auxiliary relays for transformer trip and alarm functions as per transformer requirements, shall be provided. 2. In addition to electrical protection, gas operated relays, winding temperature protection and oil temperature protection shall be provided. 7.8 Sub-Station Fire Protection Adequate precautions shall be taken and protection shall be provided against fire hazards to all apparatus and other assets confirming to relevant Indian Standard Specification and provisions in I.E. Rules. The firefighting equipment installed shall be maintained in good working condition and shall be inspected daily and recorded in the maintenance log book by the concerned in charge person. The single line schematic diagram of the five- protection arrangement shall be displayed in the sub-station control room. 7.9 Calibration and Testing The protection scheme shall be tested at each 220 KV, 132 KV, 110 KV, 66 KV sub-station by STU and Users once in six months or immediately after any major fault, whichever is earlier. Testing and calibration of all protection schemes pertaining to generating units/stations shall be the responsibility of respective SGS. 7.10 Data Requirements: Users shall provide to the STU and SLDC with data as specified in Appendix-D in the Data Registration Chapter. CHAPTER –8: OPERATION PLANNING 8.1 Objective This Chapter describes the process by which the SLDC carries out the operational planning and demand control procedures. The detailed procedure is required to enable SLDC to reduce overloading to avoid operating problems on all parts of the State Transmission System. SLDC will utilize demand control in a manner, which does not unduly indiscriminate against any one or group of consumers. 8.2 Demand Estimation 1. The long-term demand estimation and load forecast (for more than 1 year) shall be done by STU. SLDC shall be provided with a copy of the same as and when it is finalized. 2. It shall be the responsibility of all Distribution Licensees to fully cooperate with STU in preparation of demand estimation and load forecast for the entire state.[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 97 3. The Distribution Licensees shall provide to the STU their estimates of demand for the year ahead on month-basis at each inter connection point for the next financial year by 31st January of each year. Distribution Licensees shall also provide daily demand on the month ahead at each inter connection point by 25th for the next month. 4. Based on the data furnished by the Distribution Licensees, STU shall make monthly peak and lean period demand estimates for year ahead and daily peak and lean period demand estimates for the month ahead and furnish the same to SLDC. 5. The Distribution Licensee shall provide to SLDC estimates of loads that may be shed when required, in discreet blocks with details of arrangements of such load shedding. 6. Distribution Licensees shall also furnish realistic category-wise demand along with details of essential loads, supply lines to be maintained in rural areas, details of power cuts imposed or to be imposed, etc to STU and SLDC. 7. The SLDC would up to date the demand forecast (in MW as well as KWh) on a quarterly, monthly, weekly, and ultimately on a daily basis which would be used in day–ahead scheduling. 8.3 Demand Control 1. Automatic load shedding shall be resorted to by means of installation of the Under Frequency Relays at the sub stations of the STU as per the directions of the SLDC to preserve the overall integrity of the power system. The number and size of the discrete blocks using Automatic under Frequency Relays for Load Shedding shall be determined on rotational basis in consultation with every Distribution Licensee. The frequency settings of these relays shall be coordinated in consultation with the RLDC. 2. Whenever restoration of large portions of the total demand disconnection effected by the automatic load shedding is not possible within a reasonable time, the SLDC shall implement additional disconnection manually, to restore an equivalent amount of demand disconnected. Each Distribution Licensee shall help the SLDC in identifying such load blocks. Load shed by the operation of automatic load shedding devices shall not be restored without specific directions from the SLDC. 3. Planned manual load shedding shall be implemented by the SLDC when there is a shortfall in generation, or constraints in Transmission System, or reduction of imports through external connection etc., requiring demand control to control the over-drawl of power from ISGS. In such cases a rotational load shedding scheme shall be adopted to ensure equitable treatment for all consumers as far as practicable. 4. Emergency manual load shedding to deal with unacceptable voltage and frequency levels etc. shall be implemented by the SLDC when loss of generation, mismatch of generation with the demand, constraints in the transmission system, over-drawal from the grid in excess of respective schedule affecting the frequency of the regional grid below 49 Hz, requiring load shedding at short notice or no notice, to maintain a regulating margin. 5. These control measures shall not be withdrawn till the system frequency improves and when the SLDC issues such instructions after review of the situation. 8.4 Load Crash 1. In the event of load crash in the system due to weather disturbance or any other reasons, the situation would be controlled by SLDC by the following methods in descending priorities: i) Lifting of the load restrictions, if any ii) Exporting the power to neighbouring regions/ states iii) Backing down of thermal stations with a time lag of 5-10 minutes for short period in merit order. iv) Closing down of hydel units (subject to non-spilling of water and effect on irrigation) keeping in view the inflow of water into canals and safety of canals/hydel channels. The above methodology shall be reviewed from time to time. 2. While implementing the above, the system security aspects should not be violated as per provisions in para 5.3 in Chapter 5 of the State Grid Code. CHAPTER –9: MONITORING OF GENERATION AND DRAWAL 9.1 Objective The objective of this chapter is to define the responsibilities of all State Generation Stations (SGS) in monitoring of Generating Unit reliability and performance, and STU’s / User’s compliance with the scheduled drawal to assist SLDC in managing voltage and frequency and in improving system performance and Grid discipline.98 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 9.2 Monitoring of Generation 1. For effective operation of the State Transmission System, it is important that a SGS’s declared availability is realistic and that any departures from the availability are invariably reported to the SLDC. 2. The SLDC shall continuously monitor Generating Unit outputs and Bus voltages. More stringent monitoring may be performed at any time when there is reason to believe that a SGS’s declared availability may not match the actual availability or declared output does not match the actual output. 3. SLDC will ensure that all thermal units with capacity 200 MW & above within the State are operated with free governor made of operation. 4. SLDC can ask for putting a generating station to demonstrate the declared availability by instructing the generating station to come up to the declared availability within time specified by generators. 5. SLDC shall inform a SGS, in writing, if the continual monitoring demonstrates an apparent persistent or material mismatch between the despatch instructions and the Generating Unit output or breach of the Connection Conditions. Continued discrepancies shall be resolved by the State Grid Code Review Committee with a view to either improve performance in future, providing more realistic declarations or initiate appropriate action for any breach of Connectivity Conditions. Continued default by the generating stations entails penalty as may be determined by the Commission. 6. SGS shall provide to SLDC 15-minute block-wise generation summation outputs wherever telemetry data is not available through SCADA/RTU equipment. CPPs shall provide to SLDC 15-minute block-wise export / import (MW and MVAr). 7. The SGS shall provide any other logged readings that SLDC may reasonably require, for monitoring purposes where SCADA data is not available. 9.3 Monitoring of Drawal 1. SLDC shall continuously monitor actual drawal (in MW) by Distribution Licensees and other Users against their schedule through use of SCADA equipment wherever available, or otherwise using available metering. SLDC shall request RLDC and adjacent States as appropriate, to provide any additional data required to enable this monitoring to be carried out. 2. SLDC shall continuously monitor the actual MVAr drawal to assist in voltage management of the State Transmission System. 9.4 Generating Unit Trippings 1. SGS shall promptly inform SLDC of the tripping of a Generating Unit, with reasons, SLDC shall intimate RLDC about the trippings and their revival. SLDC shall keep a written log of all such trippings, including the reasons with a view to demonstrating the effect on system performance and identifying the need for remedial measures. 2. SGS shall submit a more detailed monthly report of tripping of their Generating Units to SLDC. 9.5 Data Requirement SGS, IPPs and REGs shall submit data to SLDC as listed in Appendix-E (E-5) of Data Registration Chapter-17. CHAPTER –10: OUTAGE PLANNING 10.1 Objective The objective of this Chapter is to define the process, which will allow STU to optimize the planned Transmission Outages in State Generating Stations and Distribution Licensee’s outages while maintaining system security to the extent possible. 10.2 Outage Planning Process 1. Each User shall provide their outage programme for ensuing financial year to the SLDC for preparing an overall outage plan for the State Transmission System as a whole. SLDC shall be responsible for analyzing the outage schedules of all Users including SGS, Distribution Licensees, and STU schedules for outage of Transmission network and preparing a draft annual Outage Plan for the State Transmission System in coordination with the Outage Plan prepared for the region by RLDC. The Users shall furnish the information to SLDC as listed in Appendix-E of Data Registration Chapter-17. 2. However, SLDC is authorized to defer the planned outage in case of any of the following events: a. Major grid disturbance b. System Isolation[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 99 c. Black out in the State d. Any other event in the system that may have an adverse impact on system security by the proposed outage. 3. Each User shall obtain approval of SLDC, prior to availing the Outage. SLDC while releasing any circuit for outage shall issue specific code. Similarly, no inter user boundary circuits shall be connected back to the State Transmission System without specific code/approval by SLDC. This restriction shall however not be applicable to individual Generating Unit(s) of a CPP. 4. In case of emergency in the system, viz. loss of generation, breakdown of transmission line affecting the system, grid disturbance, system isolation, SLDC may conduct studies again before clearance of planned outage. 10.3 Annual Outage Planning 1. Scheduled outage of power stations and EHV lines as notified by SLDC from time to time, will be subject to annual planning. 2. SGS and CPPs connected to the State Grid shall furnish their proposed Outage programme for the next financial year in writing by 15th November each year. 3. SGS outage programme shall contain details like identification of unit, reason for outage, generation availability affected due to such outage, outage start date and duration of outage. SLDC shall review the outage programme received from SGS on monthly basis to chalk out the outage of the State Transmission System. 4. SLDC shall also obtain from STU the proposed outage programme for Transmission lines, equipment’s and sub- stations etc. for next financial year by 15th November each year. STU outage programme shall contain identification of lines/ substations, reasons for outage, outage start date and duration of outage. 5. In case of hydro generating stations such a plan shall also endeavour to maximize the utilization of water for the purpose of power generation subject to applicable constraints related to alternate use of such water. Provided further that outage of wind generator may be planned during lean wind season, outage of solar, if required during the rainy season and outage of run-of-the-river hydropower plant in the lean water season. 6. All Users and STU shall follow annual outage plans published by SLDC. If any deviation is required, the same shall be obtained with the prior permission of SLDC. The outage planning of run-of-the-river hydro plant, wind and solar power plant and its associated evacuation network shall be planned to extract maximum power from these renewable sources of energy 7. Transmission Outage Planning shall be harmonized with Generation Outage Planning and Distribution System Outage Planning shall be harmonized with Generation and Transmission Outage Planning 8. In respect of scheduled outage referred in this section a calendar shall be formulated in respect of annual outage planning for the ensuing financial year. 9. SLDC shall have the authority to defer any planned outage in case of occurrence of following events: (a) Major grid disturbances (e.g., partial/total blackout); (b) System isolation; and (c) Any other event in the system that may have an adverse impact on the system security by the proposed outage. 10. In case of emergency in the system, which may include events like loss of generation, breakdown of the transmission line, grid disturbances and system isolation, SLDC may appropriately review the situation before clearance of the planned outage: Provided that scheduled outage of power stations of 10 MW capacity and above as notified by SLDC from time to time, will be subject to annual planning. 11. SLDC shall prepare and submit to RPC its outage plan in writing for the next financial year by 31st December for each year. These shall contain identification of each Generating Unit/Transmission Line/Interconnecting Transformer for which outage is being planned, reasons for the outage, the preferred date for each outage and its duration and where there is flexibility, the earliest start date and latest finishing date. SLDC shall submit Load Generation Balance Report for peak as well as off-peak scenario by 31st October for the next financial year to RPC. The annual plans for managing deficits/surpluses shall be clearly indicated in the Load Generation Balance Report (LGBR). 12. Scheduled outage of power stations and EHV transmission lines affecting regional power system shall be affected only with the approval of RLDC in coordination with SLDC.100 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 13. SLDC would ensure that State’s generating units are taken out for annual maintenance during the low power demand period of the year. 14. SLDC shall upload quarterly, half-yearly, yearly outage reports on its website. 10.4 Availing of shutdowns schedule 1. SLDC would review on daily basis proposed the outage schedule for the next two days and in case of any contingency or conditions such as grid disturbances, system isolation, partial black out or any other event in the system that may have an adverse impact as the system security by the proposed outage, it may defer any planned outage stating the reasons thereof. The revised dates in such cases would be finalized in consultation with the User. 2. STU and User shall obtain approval of SLDC prior to availing the outage. 3. Where interruption of power supply is caused to Consumers due to availing the planned outage, the Distribution Licensee shall obtain the prior approval of the Commission and also give prior information to the consumers by publishing in the daily newspaper regarding the interruption of supply timings. CHAPTER – 11: CONTINGENCY PLANNING 11.1 Objective The objective of this chapter is to define the responsibilities of all Users to achieve the fastest possible recovery in the event of the State Transmission System or Regional System blackout, taking into account essential loads, generating stations capabilities and operational constraints of the State Transmission System. 11.2 Contingency Planning Procedure 1. SLDC shall efficiently handle the following types of contingencies and restoration of system back to normal: a. Partial system blackout in the UT of Jammu & Kashmir and the UT of Ladakh due to multiple tripping of the Transmission lines emanating from power stations/sub-stations b. Total black out in the UT of Jammu & Kashmir and the UT of Ladakh c. System islands / System split 2. Diesel generating (DG) sets of sufficient capacity shall be provided at each power station to meet the start-up power. 3. Synchronizing facility shall be available at all power stations and 220 KV, 132 KV, 110 K and 66 KV sub- stations having inter-connection with Inter State Transmission System. 4. In case of partial blackout in the system/state, priority is to be given for early restoration of power station units, which have tripped. 5. In case of total regional blackout, SLDC shall co-ordinate and follow the instructions of Regional Load Despatch Centre (RLDC) for early restoration of the entire grid. 6. For safe and fast restoration of supply, SLDC shall formulate the proper sequence of operations for major generating units, lines, transformers and load within the state. The sequence of operations shall include opening, closing/tripping of circuit breakers, isolators, on-load tap-changers etc 11.3 Restoration Procedure 1. Detailed and procedure for restoration of the State Grid under partial / total blackout shall be developed by SLDC in consultation with RLDC and all Users and shall be in conformity to the System Restore Procedure prescribed under IEGC. The procedure shall be reviewed / updated annually. 2. Detailed procedures for restoration under partial / total blackout of each User’s system within the State will be finalized by the concerned User in coordination with SLDC. 3. List of generating stations with black start facility, inter-state / inter regional ties, synchronizing points and essential loads to be restored on priority, shall be available with SLDC. 4. All communication channels required for restoration process shall be used for operational communication only till grid normalcy is restored. 5. The contingency planning shall be done in accordance with aforesaid principles and also as per the CEA Manual on Transmission Planning Criteria 2023 as updated from time to time. The brief procedure and concepts of Criteria for Contingency is provided at Annexure-H.[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 101 11.4 Special Considerations applicable to contingency planning 1. During the process of restoration of the State Transmission System or Regional System blackout conditions, the normal standards of voltage and frequency need not be insisted and may left to the discretion of the SLDC. 2. Distribution Licensees shall separately identify non-essential loads, which may be kept off during system contingent conditions. They shall also draw up an appropriate schedule with corresponding load blocks in each case. The non-essential loads can be put on only when system normalcy is restored or as advised by SLDC. 3. All Users shall pay special attention in carrying out the procedures to prevent secondary collapse of the system due to undue haste or inappropriate loading operation of conditions. 4. Despite the urgency of the situation, prompt and complete logging of all operations and operational messages shall be ensured by all Users to facilitate subsequent investigation into the incident and reviewing of the efficiency of the restoration process. Such investigation shall be conducted after the incident, and placed before the State Grid Code Review Committee in its next meeting. 11.5 Post Disturbance Analysis SLDC as per guidelines and instructions from RLDC shall carry out the post-analysis of disturbance occurrence of all major grid disturbances resulting into total or partial system blackout and out of synchronization of any part of the state grid. All users shall enable SLDC, analyse the system disturbance and furnish report to RLDC. CHAPTER – 12: INTER USER BOUNDARY SAFETY 12.1 Objective The objective of this chapter is to achieve an agreement and consistency on the principles of safety as prescribed in the Indian Electricity Rules 1956 which are in force for the time being and will be replaced by the rules made under Electricity Act, 2003 when working across the inter user boundary (cross boundary) between one User and another User. 12.2 Designated Persons STU and all Users shall nominate and notify authorized persons to be responsible for the co-ordination of safety across their boundary. These persons shall be referred to as Designated Officer. 12.3 Procedure to work on Inter User Boundary Circuits 1. STU shall issue a list of Designated persons’ names, designations and telephone numbers to all Users who have a direct inter user boundary with him. This list shall be updated promptly, whenever there is a change of name, designation or telephone number of any designated persons named in the list. 2. All Users with a direct inter user boundary with STU shall issue a similar list of their Designated persons to STU. This list shall be updated promptly whenever there is any change of name etc in the list. 3. Whenever any work across an inter-user boundary is to be carried out by the User or the STU, the Designated officer of the User or STU as the case may be, wishing for Line Clear Permit / Permit to Work (PTW) shall personally contact the other relevant Designated officer. If the Permit to Work cannot be obtained personally, the Designated officer shall contact through telephone and exchange Code word or secrete code to ensure correct identification of both agencies. 4. If the work extends beyond than one shift, the Designated officer shall ensure that the Relieving Designated Officer is fully briefed on the nature of the work and the code words in operation. 5. The Designated Officer(s) shall co-operate to establish and maintain the precautions necessary for the required work to be carried out in a safe manner. Both the established isolation and the established earth shall be kept in locked position with “Men Working” tag, where such facilities exist, and shall be clearly identified. 6. Work shall not commence until the Designated Officer in charge of the work of the User including, wishing to carry out, is satisfied that all the safety precautions have been established. This Designated Officer shall issue approved safety documentation and work permit (PTW) to the working party to allow work to commence. The Permit to Work in respect of specified EHV lines and other interconnections shall be issued with the consent of SLDC. 7. When work is completed and safety precautions are no longer required, the Designated Officer who has been responsible for the work being carried out shall make direct contact with the other Designated Person to return the Permit to Work and removal of those safety precautions. Return of Permit to Work in respect of specified EHV lines and interconnections shall be informed to SLDC.102 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 8. The equipment shall only be considered as suitable for connecting back to service when all safety measures are confirmed as removed, by direct communication using code word contact between the two Designated Officers, and after ensuring that the return of Permit to Work from the working party has been taken place. 9. STU shall develop an agreed written procedure for inter-user boundary safety and continuously update it. 10. Any dispute concerning inter-user boundary safety shall be resolved at the level of STU, if STU is not a party. In case STU is a party, the dispute shall be referred to the State Grid Code Review Committee for resolving the dispute. 12.4 Special Consideration 1. For the inter-user boundary between STU and other Users’ circuits, all Users shall comply with the approved safety rules, which must be in accordance with IE Rules. 2. Each Designated Officer shall maintain a legibly written safety log, in chronological order, of all operations and messages relating to safety coordination sent and received by him. All safety logs shall be retained for a period of not less than 10 years. CHAPTER -13: OPERATIONAL EVENT INFORMATION REPORTING 13.1 Objective This Chapter defines the incidents to be reported, the reporting route to be followed and the information to be supplied to ensure a consistent approach to the reporting of incidents / events. 13.2 Reportable Events 1. All events in the State Transmission System having an operational effect on the User’s system shall be reported by the STU to SLDC and to Users whose systems are affected. 2. All events in the User’s system having an operational effect on the State Transmission System shall be reported by the User to the STU and SLDC and who in turn shall intimate the other Users on whose system the event may have an operational effect. 3. Any of the following incidents/events that could affect the State Transmission System requires reporting: a. Blackout/partial system blackout b. System islanding/system split c. Exceptionally high / low system voltage or frequency. d. Serious equipment problem, relating to major circuit breaker, transformer or bus bar. e. Failure of major Generating Unit. f. System split, State Transmission System breakaway or Black Start. g. Tripping of transmission Line, ICT (Inter connecting transformer) and capacitor banks. h. Major fire incidents. i. Major failure of protection equipment. j. Equipment and Transmission Line overload. k. Accidents-Fatal and Non-Fatal. l. Load Crash / Loss of Load m. Excessive drawal deviations. n. Minor equipment alarms. o. Violation of security standards p. Any other event as stipulated by the Commission from time to time The last two reportable incidents which are of lesser consequence, but which still have effect on the State Transmission System and can be reasonably classed as minor. They require prompt corrective action. 13.3 Reporting Procedure 1. All incidents occurring on lines and equipment above 33 kV and all the lines on which there is the inter user flow affecting the State Transmission System shall immediately be reported orally on telephone or through power line carrier communication etc by the User or STU whose equipment has experienced the incident to SLDC. The[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 103 reporting User or STU shall submit a confirmation report by Telephone message / Fax / E-mail to SLDC within one hour of such oral report. The reporting User shall submit a written report within 2 (two) days of occurrences of the incident to the SLDC by e-mail or by courier or by certified post. 2. SLDC shall suo-moto call for a report from any User on any incident affecting other Users or STU. However, this shall not relieve any User from the obligation to report events in accordance with provisions of the State Grid Code to SLDC / STU. 3. A written report containing the following details confirming the oral report, shall be sent to SLDC by the User or STU. (i) Location of incident. (ii) Time and date of incident. (iii) Plant and equipment directly involved. (iv) Details of relay indications with nature of fault implications. (v) Demand / Transmission or Generation (in MV) interrupted and duration of interruption. (vi) Brief description and cause of incident / event. (vii) Estimated time to return to service. (viii) Possibility of alternate arrangement made for restoration of supply (ix) Sequence of tripping with time (x) Details of Red Flags with remedial measures (xi) Any other relevant information including copies of records of all recording instruments, event logger, DAS, etc. 13.4 Reporting Form The standard reporting form, other than for accidents, shall be as approved from time to time by the State Grid Code Review Committee. The standard reporting form shall be made available on the website of STU and SLDC. A typical form is attached (APPENDIX-F) in the Data Registration Chapter-17. 13.5 Major Failure Whenever a major failure such as tripping of generating unit or EHV transmission line, System frequency or Voltage outside statutory limits, system overload, accidents take place, the User shall inquire and establish the cause of such failure to STU / SLDC / Commission. The STU shall submit the report to State Grid Code Review Committee within one month for further analysis. On demand by the Commission a detailed report on major failures shall be submitted to the Commission. 13.6 Accident Reporting If any accident occurs in connection with the Generation, Transmission, Distribution of supply or use of electricity or in connection with any part of electric lines or electrical plant of any person and the accident results or is likely to have resulted in the loss of human or animal life or any injury to a human being or an animal, the same shall be dealt with in accordance with Section 161 of the Electricity Act, 2003. CHAPTER – 14: SCHEDULING AND LOAD DESPATCH 14.1 Objective This Chapter details the actions and responsibilities of SLDC in preparing and issuing a daily schedule of generation and the responsibilities of Users to supply the necessary data and to comply with the schedules. 14.2 General 1. SLDCs shall have the total responsibility for (i) Scheduling / despatching generation of State Generating Stations (including generation of their embedded licensees), (ii) Regulating the demand in its control area, (iii) Scheduling their drawal from the ISGS (within their share in the respective plant’s expected capability) (iv) Permitting long-term, medium-term and short-term open access transactions for embedded generators / consumers, in accordance with the contracts, and104 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] (v) Regulating the net drawal in their control area from the regional grid in accordance with the respective Regulations of the CERC. 2. The following specific points shall be taken into consideration while preparing and finalizing the schedules: (i) SLDC will issue despatch instructions required to regulate all generation and imports according to the 15- minute day ahead generation schedule. In the absence of any despatch instruction by SLDC, SGS can generate/ export according to the day-ahead generation schedule and intimate the same to the SLDC to regulate the supply for the needy Users. (ii) The SLDC shall regulate the overall state generation in such a manner that generation from following types of power stations having energy potential, if unutilized, goes waste shall not be curtailed. a) Run of river (without storage) or canal based hydro stations. b) Run of river with pondage and storage type hydro-stations when water level is at peak reservoir level or expected to touch peak reservoir level as per inflows. c) Wind and Solar based generating sources. d) Hybrid solar power stations with minimum generation from conventional fuel required to utilize available solar power. (iii) Despatch instructions to SGS shall be communicated in standard format by SLDC. 14.3 Scheduling and Despatch Procedure 1. The procedure for scheduling of ISGS and SGS/IPP/CPP shall be as described below: i) Each day starting from 00.00 hours will be divided into 96 time blocks of 15-minute iintervals. ii) By 9:00 AM every day each, SGS shall intimate the SLDC the station wise ex- power plant MW and MWh capabilities foreseen for the next day i.e., between 00.00 to 24.00 hrs of the following day. iii) By 9:00 AM every day each Distribution Licensee shall intimate SLDC the overall requirement in MW and MWh for the next day i.e., between 00.00 to 24.00 hours of the following day. iv) By 10:00 AM every day, the above information along with the entitlements of the State in various Inter State Generating stations given by RLDC, the SLDC shall compile the aggregate generating capability of SGS, entitlement from ISGS bilateral interchange, if any, vis-à-vis the Distribution Licensee requirement. v) By 3:00 PM, SLDC shall finalize generation schedule of SGS and drawal schedule of each Distribution Licensees, convey to RLDC the net drawal schedule from each of the ISGS along with the bilateral exchanges agreed or intended to be had with the other state / states and the estimates of demand / availability in the state and additional power required to be obtained. vi) By 6:00 PM, RLDC shall convey to SLDC the drawal schedule for the State from each of the ISGS vii) By 7:00 PM, SLDC shall convey, a) The ex-power plant despatch schedule to each of SGS, in MW for different hours, for the next day b) The “net drawal schedule” to the distribution licensee in MW for different hours, for next day. viii) SGS and Distribution Licensees shall inform any modifications / changes, if any, to be made, in the above station wise drawal schedule to SLDC by 9:00 PM or preferably earlier. ix) SLDC after considering the same shall convey revised schedule to RLDC by 10:00 PM. 2. SLDC may also give the required data to the RLDC such that the RLDC itself may decide the best drawal schedules for the State. 3. SLDC shall prepare the day ahead generation schedule keeping in view the followings i) Transmission System constraints from time to time. ii) 15-minute load requirements as estimated by SLDC. iii) The need to provide operating margins / reserves required to be maintained. iv) The availability of generation from SGS, Central Sector Generators and others together with any constraint in each case. 4. During the day of operation, the generation schedule may be revised under following conditions:[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 105 i) In case of forced outage of a unit of any SGS, SLDC may revise the generation schedule on the basis of revised declared capability by the affected SGS. The revised declared capability and the revised schedule shall become effective from the 4th time block, counting the time block in which the revision is advised by the ISGS or SSGS to be the first one. ii) In case of any grid disturbance, scheduled generation of all the SGS and scheduled drawal of all the beneficiaries shall be deemed to have been revised to be equal to their actual generation/drawal for all the time blocks affected by the grid disturbance. Certification of grid disturbance and its duration shall be done by the SLDC. iii) Revision of declared capability by the SGS(s) and requisition by beneficiary (ies) for the remaining period of the day shall also be permitted with advance notice. Revised schedules/declared capability in such cases shall become effective from the 6th time block, counting the time block in which the request for a revision has been received in the SLDC to be the first one. iv) If, at any point of time, the SLDC observes that there ia s need for revision of the schedules in the interest of better system operation, it may do so on its own, and in such cases, the revised schedules shall become effective from the 4th time block, counting the time block in which the revised schedule is issued by the SLDC to be the first one. v) To discourage frivolous revisions, SLDC may, at its sole discretion, refuse to accept scheduling/capability changes of less than two (2) percent of the previous schedule/capability. vi) After the operating day is over at 2400 hours, the schedule finally implemented during the day (taking into account all changes in dispatch schedule of generating stations and drawal schedule of the States) shall be issued by SLDC. These schedules shall be the datum for commercial accounting. The average ex-bus capability for each SGS shall also be worked out based on all before-the-fact advice to SLDC. vii) SLDC shall properly document all above information i.e., station-wise foreseen ex-power plant capabilities advised by the generating stations, the drawal schedules advised by beneficiaries, all schedules issued by the SLDC, and all revisions/updating of the above. viii) The procedure for scheduling and the final schedules issued by SLDC shall be open to all constituents for any checking/verification, for a period of 5 days. In case any mistake/omission is detected, the RLDC shall forthwith make a complete check and rectify the same. ix) Scheduling of solar and wind generation should follow below outlines: a) Scheduling of Solar and wind power generation plants would have to be done for the purpose of computing deviation where the sum of generation capacity of such plants are clubbed at a Pooling Station and connected through a line(s) at the connection point to the transmission or distribution system is 10 MW and above and connection point is 33 KV and above, and where PPA has not yet been signed. For capacity and voltage level below this, as well as for old Wind farms (A wind farm is collection of wind turbine generators that are connected to a common connection point commonly known as a Pooling Station), it could be mutually decided between the Wind Generator and the transmission or distribution utility, as the case may be, if there is no existing contractual agreement to the contrary. The schedule by wind power generating stations (excluding collective transactions) may be revised by giving advance notice to SLDC. The revisions by wind power generating stations and solar power generating stations shall be effective from 4th time block, the first being the time-block in which notice was given. There may be one revision for each time slot of 1.5 hours starting from 00:00 hours of a particular day subject to a maximum of 16 revisions during the day or as specified in CERC (Forecasting, Scheduling, Deviation settlement and related matters for solar and wind Generation sources) Regulations, issued and amended from time to time. b) The schedule of solar generation shall be given by the generator based on availability of the generator, weather forecasting, season and normal solar generation curve and shall be vetted by the SLDC. If SLDC is of the opinion that the schedule is not realistic, it may ask the solar generator to modify the schedule. c) SLDC shall maintain the record of schedule from renewable power generating stations based on type of renewable energy sources i.e., wind or solar from the point of view of grid security. While scheduling generating stations in the State, system operator shall aim at utilizing available solar and wind energy fully.106 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 14.4 Drawal Scheduling SLDC is responsible for collection, examination and compilation of drawal Schedule for each Distribution Licensees at the prescribed time. Each Distribution Licensee shall supply to SLDC 15-minute average demand estimates in MW for the day ahead. 14.5 Generation Despatch 1. SGS shall comply promptly with a despatch instruction issued by SLDC. SGS shall promptly inform SLDC in the event of any unforeseen difficulties in carrying out an instruction. 2. Despatch instructions shall be issued by E-Mail /Fax/ telephone, confirmed by an exchange of name of operators sending and receiving the same and logging the same at each end. All oral instructions shall be complied forthwith and written confirmation shall be issued promptly by FAX, tele-printer, or otherwise. 14.6 Responsibilities 1. SLDC shall monitor actual power drawal against the demand for scheduled power and internal generation. SLDC shall also monitor reactive power drawal and availability of capacitor banks. 2. Generating Stations within state shall follow the despatch instructions issued by SLDC. 3. Distribution Licensees and Open Access Customers shall comply with the instructions of SLDC for managing load & reactive power drawal as per system requirement. 14.7 Data Requirement Users shall provide SLDC with data as specified in Appendix – E2, Generation Scheduling Data in the Data Registration Chapter –17. CHAPTER -15: METERING 15.1 Objective This Chapter defines minimum acceptable standards of metering equipment which shall provide proper metering of the various operating system parameters for the purpose of accounting, commercial billing and settlement of electrical energy and to provide information which shall enable to operate the system in economic manner. 15.2 Scope 1. This Metering covers the practices that shall be employed and the facilities that shall be provided for the measurement and recording of various parameters like active/reactive/apparent power/energy, power factor, voltage, frequency etc. 2. This Metering sets out or refers to the requirements of metering at generating stations, sub-stations and interfaces for tariff and operational metering. 3. This Metering also specifies the requirement for calibration, testing and commissioning of metering equipments viz. energy meters with associated accessories, current transformers and voltage transformers. The Metering broadly indicates the technical features of various elements of the metering, data communication and testing system. 15.3 Applicability This Metering shall be applicable to meters installed and to be installed by all: a) STU/Transmission Licensees, b) Generating Stations connected to the State Transmission System, c) Distribution Licensees connected to the State Transmission System, d) EHV Consumers of Distribution Licensee(s) directly connected to the State Transmission System, e) Open Access Customers availing Open Access on State Transmission system, and f) Captive Generators connected to the State Transmission System 15.4 Type of meters 1. All interface meters, User meters and energy accounting and audit meters shall be of static type. 2. The meters not complying with the specified type shall be replaced by the STU on his own or on request of the User. 3. The meters may also be replaced as per the regulations or directions of the Commission or pursuant to the reforms programme of the Government.[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 107 15.5 Standards. - All interface meters, and energy accounting and audit meters shall: a) Comply with the relevant standards of Bureau of Indian Standards (BIS). If BIS Standards are not available for a particular equipment or material, the relevant British Standards (BS), International Electro-Technical Commission (IEC) Standards, or any other equivalent Standard shall be followed: Provided that whenever an international Standard or IEC Standard is followed, necessary corrections or modifications shall be made for nominal system frequency, nominal system voltage, ambient temperature, humidity and other conditions prevailing in India before actual adoption of the said Standard; b) Conform to the standards on ‘Installation and Operation of Meters’ as specified in Schedule annexed to Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006 and as amended from time to time. 15.6 Ownership of meters 1. Interface meters a) All interface meters installed at the points of interconnection with Inter- State Transmission System (ISTS) for the purpose of electricity accounting and billing shall be owned by CTU. b) All interface meters installed at the points of interconnection with State Transmission System excluding the system covered under sub-clause (a) above for the purpose of electricity accounting and billing shall be owned by STU. c) All interface meters installed at the points of inter connection between the two licensees excluding those covered under sub-clauses (a) and (b) above for the purpose of electricity accounting and billing shall be owned by the respective licensee of each end. d) All interface meters installed at the points of inter connection for the purpose of electricity accounting and billing not covered under sub clauses (a), (b) and (c) above shall be owned by supplier of the electricity. 2. Energy accounting and audit meters Energy accounting and audit meters shall be owned by the generating company or STU, as the case may be. 15.7 Locations of meters. - 1. The location of interface meters, and energy accounting and audit meters shall be as per the Table given below: S.No. Stages Main Meter Check Standby Meter Meter A. Generating On all outgoing feeders. On all (i) High Voltage (HV) side of Station outgoing Generator Transformers feeders. ii) High Voltage (HV) side of all Station Auxiliary Transformers (Explanation: The location of main, check and standby meters installed at the existing generating stations shall not be changed unless permitted by the Authority) B. Transmission At one end of the line between the su b- There shall be no separate and stations of the same licensee, and at both standby meter. Meter installed Distribution ends of the line between sub-stations of at other end of the line in case System two different licensees. Meters at both of two different ends shall be considered as main meters licensees shall work as standby for respective licensees. meter. C. Inter- High Voltage (HV) side of ICT. Low Voltage (LV) side Connecting of ICT. Transformer (ICT) 2. The generating companies or licensees may install meters at additional locations in their systems depending upon the requirement. 3. Interface Meters108 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] i) Users who have interconnection with the Inter-State Transmission System or State Transmission System and have been permitted open access by the Commission shall be provided with interface meters. ii) For Users connected to distribution system and permitted open access, by provision of interface meters may be made as per the regulations or of the Commission shall be provided with interface meters. 4. Energy accounting and audit meters Energy accounting and audit meters shall be installed at such locations so as to facilitate accounting for the energy generated, transmitted, distributed in the various segments of the power system and the energy loss. The location of these meters shall be as under: (i) Generating Stations 1) at the stator terminal of the generator; 2) on HV and LV sides of the station and the unit auxiliary transformers; 3) on feeders to various auxiliaries. (ii) Transmission System All incoming and outgoing feeders (If the interface meters do not exist). (iii) Distribution System 1) all incoming feeders (11 kV and above); 2) all outgoing feeders (11 kV and above); 15.8 Accuracy Class of meters Every meter shall meet the requirement of accuracy class as specified in the standards are given in the Schedule annexed to Central Electricity Authority “Installation and Operation of Meters” Regulations, 2006 (Annexure). 15.9 Installation of meter 1. Generating company or STU, as the case may be, shall examine, ,test and regulate all meters before installation and only correct meters shall be installed. 2. The meter shall be installed at locations, which are easily accessible for installation, testing, commissioning, reading, recording and maintenance. 3. In case CTs and VTs form part of the meters, the meter shall be installed as near the instrument transformers as possible to reduce the potential drop in the secondary leads. 15.10 Operation, Testing and Maintenance of Meters The operation, testing and maintenance of all types of meters shall be carried out by the generating company or the STU, as the case may be. 15.11 Access to meter The owner of the premises where, the meter is installed shall provide access to the authorized representative(s) of the STU for installation, testing, commissioning, reading and recording and maintenance of meters. 15.12 Sealing of meters 1. Sealing Arrangements a. All meters shall be sealed by the manufacturer at its works. In addition to the seal provided by the manufacturer at its works, the sealing of all meters shall be done as follows at various sealing points as per the standards given in the Schedule annexed to Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006 b. Sealing of interface meters, shall also be done by both the supplier and the buyer. i) Sealing of User meters shall be done by the STU. ii) Sealing of energy accounting and audit meters shall be done by the STU or generating company as the case may be. c. Seal shall be unique for each utility and the name or logo of the utility shall be clearly visible on the seals. d. Only the patented seals (seal from the manufacturer who has the official right to manufacture the seal) shall be used.[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 109 e. Polycarbonate or acrylic seals or plastic seals or holographic seals or any other superior seal shall be used. f. Lead seals shall not be used in the new meters. Old lead seals shall be replaced by new seals in a phased manner and the time frame of the same shall be submitted by the STU to the Commission for approval. 2. Removal of seals from meters (a) Interface meters Whenever seals of the interface meters have to be removed for any reason, advance notice shall be given to other party for witnessing the removal of seals and resealing of the interface meter. The breaking and re- sealing of the meters shall be recorded by the party, who carries out the work, in the meter register, mentioning the date of removal and resealing, serial numbers of the broken and new seals and the reason for removal of seals. (b) Energy accounting and audit meters Seal of the energy accounting and audit meter shall be removed only by the generating company or the STU who owns the meter. 15.13 Safety of meters 1. The supplier or buyer in whose premises the interface meters are installed shall be responsible for their safety. 2. The User shall, as far as circumstances permit, take precautions for the safety of the meter installed in his premises belonging to the STU or Distribution licensee. 3. The generating company or the STU who owns the energy accounting and audit meters shall be responsible for its safety. 15.14 Meter reading and recording 1. Interface meters It shall be the responsibility of the Appropriate Transmission Utility or Distribution licensee to take down the meter reading and record the metered data, maintain database of all the information associated with the interface meters and verify the correctness of metered data and furnish the same to various agencies. 2. Energy accounting and audit meters It shall be the responsibility of the generating company or STU to record the metered data, maintain database of all the information associated with the energy accounting and audit meters and verify the correctness of metered data. Each generating company or STU shall prepare quarterly, half-yearly and yearly energy account for its system for taking appropriate action for efficient operation and system development. 15.15 Meter failure or discrepancies 1. Interface meters a. Whenever the difference between the readings of the Main meter and the Check meter for any month is more than 0.5%, the following steps shall be taken: i) Checking of CT and VT connections; ii) Testing of accuracy of interface meter at site with reference standard meter of accuracy class higher than the meter under test. If the difference exists even after such checking or testing, then the defective meter shall be replaced with a correct meter. b. In case of conspicuous failures like burning of meter and erratic display of metered parameters and when the error found in testing of meter is beyond the permissible limit of error provided in the relevant standard, the meter shall be immediately replaced with a correct meter. c. In case where both the Main meter and Check meter fail, at least one of the meters shall be immediately replaced by a correct meter. d. Billing for the failure period: i) The SLDC / STU shall develop a procedure for assessment of consumption of defective meter during the failure period of the meter and submit the same to the Commission for its approval. The billing for the failure period of the meter shall be done as per this approved procedure. ii) Readings recorded by Main, Check and Standby meters for every time slot shall be analysed, cross checked and validated by the SLDC. The discrepancies, if any, noticed in the readings shall be informed by SLDC in writing to the energy accounting agency for proper accounting of energy. SLDC shall also110 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] intimate the discrepancies to the State Transmission Utility or the User, who shall take further necessary action regarding testing, calibration or replacement of the faulty meters in accordance with the provisions laid down. e. The defective meter shall be immediately tested and calibrated. 2. Energy accounting and audit meters Energy accounting and audit meters shall be rectified or replaced by the generating company or licensee immediately after notice of any of the following abnormalities: a. the errors in the meter readings are beyond the limits prescribed for the specified Accuracy Class; b. meter readings are not in accordance with the normal pattern of the load demand; c. meter tampering, or erratic display or damage. 15.16 Anti-tampering features of meters The meters shall be provided with such anti-tampering features as per the Standards on Installation and Operation of Meters given in the Schedule annexed to Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006 15.17 Quality assurance of meters 1. The STU shall set up appropriate number of accredited testing units or utilize the services of other accredited testing laboratories. The STU shall take immediate action to get the accreditations of their existing meter testing laboratories from NABL, if not already done. 2. The generating company or STU shall ensure that all type, routine and acceptance tests are carried out by the manufacturer complying with the requirement of the relevant BIS or BS or IEC as the case may be. 15.18 Calibration and periodical testing of meters. – 1. Interface meter a. At the time of commissioning, each interface meter shall be tested by the STU at site for accuracy using standard reference meter of better accuracy class than the meter under test. b. All interface meters shall be tested at least once in five years. These meters shall also be tested whenever the energy and other quantities recorded by the meter are abnormal or inconsistent with electrically adjacent meters. Whenever there is unreasonable difference between the quantity recorded by interface meter and the corresponding value monitored at the billing centre via communication network, the communication system and terminal equipment shall be tested and rectified. The meters may be tested using NABL accredited mobile laboratory or at any accredited laboratory and recalibrated if required at manufacturer’s works. c. Testing and calibration of interface meters may be carried out in the presence of the representatives of the supplier and buyer by giving due notice of testing in advance. 2. Energy accounting and audit meters Energy accounting and audit meters shall be tested at site at least once in five years or whenever the accuracy is doubtful or whenever the readings are inconsistent with the readings of other meters, e.g., check meters, standby meters. The testing must be carried out without removing the CTs and VTs connection. Testing may be carried out through NABL accredited mobile laboratory using secondary injection kit, measuring unit and phantom loading or at any accredited test laboratory and recalibrated if required at manufacturer’s works. 15.19 Data Requirements State Generating Station (SGS) and State Transmission Utility (STU) shall provide data to each other and SLDC as specified in Appendix – G of Data Registration Chapter –17. CHAPTER – 16: SAFETY AND LINE CLEAR PERMITS 16.1 This Chapter deals with safety to the working personnel of STU / Distribution Licensee and the Users and maintenance of proper records for the issue of Line Clear Permits for allowing the working personnel to carry out the works. 16.2 Safety Standards: 1. STUs shall prepare their own "Safety Manual" for the maintenance of Transmission Lines, and Substations and got vetted by an accredited agency. Copies of this safety manual shall be provided at all the substations, concerned departments of STU and Users. For the guidance of the Shift Operators, "Operation and Maintenance Manuals" for each Substation shall be prepared by the STU and Users containing all the maintenance and[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 111 operation schedules based on the recommendations of the manufacturers of the various equipments installed in the Substation. These manuals shall be periodically reviewed based on the experience gained and replacement of equipments. A maintenance register for all the equipments including the station batteries shall be maintained at the respective Substations. These shall be updated as and when the maintenance work is carried out and shall be periodically reviewed by the Commission. Similar registers shall be maintained for the Transmission and Sub- Transmission Lines. 2. The ‘Operation and Maintenance Manual’ shall clearly specify the details of isolation and earthing to be provided for allowing work on the equipments. The ‘Single Line Diagram’ of the Substation indicating the positions of various isolating devices shall be prominently displayed in the station. Charts showing the clearances from live parts (section clearance) for working on the isolated equipments where workmen are allowed to work shall be displayed prominently at each Substation. 3. STUs and Users shall affix the "Danger" boards (of a design as per relevant ISS No. 2551) prominently displayed at a conspicuous place at all the locations as required in the IE Rules. 4. All the equipments including the system batteries in the receiving stations and Substations shall be maintained in good condition as per the manufacturers' manuals and also as per relevant Indian and / or international standards. The DC system provided in all these stations shall be properly maintained with no appreciable leakage current. On-line monitoring system for monitoring of leakage and detection of ground faults shall be adopted. 16.3 Line Clear Permit (LCP): The formats enclosed shall be used while issuing and returning line clear permit. The Format - I designated as "Requisition for Line Clear Permit" shall be used by the requesting Safety Coordinator who is an authorized person. The Format - 2 designated as "Line Clear Permit" shall be used at the time of issue of Line Clear Permit. The Format -3 designated as "Line Clear Return" shall be used for the return of the Line Clear Permit after the work is completed for which the Line Clear Permit is taken. FORMAT – 1 Serial No. xxxxxxx REQUISITION FOR LINE CLEAR PERMIT Date …………………………… Time ………………… I Shri/Shrimati ---------------------- request Line Clear Permit on the following EHT / HT Line/Equipment. EHT / HT Apparatus/Line Identification: Details of works to be carried out: Estimated time required for completion: …………………………………………………………………………………………. (Person Requesting Line Clear Permit) ( In charge of the Crew) Designation…………………………….……………………….…… Date…………………….…………… (FOR USE IN SUBSTATION FROM WHERE LINE CLEAR PERMIT WILL BE ISSUED) Name and Signature a) Line Clear Permit issued: Yes/No b) Number and Date of Issue (Code No.): c) Time of Issue: d) Date & Time of Return: e) Remarks: See Check List LCP - F RECEIPT OF LCP I have received confirmation from …………………………….. (Name of Issuing Safety Coordinator) at …………………………….(location) that the safety precautions have been established and the instructions will not be issued at his location for their removal until his LCP is cancelled. Name and Signature…………………………………… (Person Requesting Line Clear Permit) In charge of the Crew at ……………………….. (Time) on ……………………(Date)112 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] FORMAT – 2 Serial No. xxxxxx LINE CLEAR PERMIT LCP Number……………………………. Dated………………………………………Time.................. CHECK LIST OF THE LINE CLEAR PERMIT: (a) Name of location for which line clear is issued. (b) Reference and Authority requisitioning line clear: (Indicate serial number of LCP requisition). (c) Identity of HV Apparatus. (d) Sources from which the Line/Equipment is charged. (e) No./name of Circuit Breaker/Isolating Switch open at each of above sources. (f) Whether confirmed that the Line is disconnected at both ends. (g) Whether line is Earthed at both ends. (h) Whether the Circuit Breaker truck removed in case of indoor switchgear controlling the Feeder/Equipment for which line clear is given. (i) Whether Isolating Switches controlling the feeder/equipment for which line clear is given are locked and kept in safe custody. (j) Time of issue of Line Clear Permit and LCP No. (k) Name of requesting Safety Coordinator on whom LCP is issued. (l) Approximate Time for returning LCP as ascertained from the Requesting Coordinator. Name and Signature………………………………………………………….. (Issuing Safety Coordinator) Designation……………………………………………………………………. LINE CLEAR PERMIT LCP No……………………. I Sri/Srimati ------------- (Issuing Safety Coordinator) do hereby issue permission to Sri/Srimati-------------- (Requesting Safety Coordinator) for carrying out works as per requisition No………………..date………………..Time ........ The EHT/ HT Line/equipment herein described is declared safe. The permission is subject to the conditions given on backside of this Permit. Name and Signature…………………………………….. (Person issuing Line Clear Permit) Designation………………………………………………. (To be printed on the reverse of LCP: Format-2) CONDITIONS: (a) This permit is valid only for working on the Feeder/Equipment mentioned herein and not in any other Feeder/Equipment. (b) Only authorized persons are allowed to work on Feeder / Equipment for which the permit has been issued. (c) Works as per requisition only should be carried out. (d) Before touching any part of the Feeder / Equipment it should be ensured that earthing at two points on either side through standard discharge rods connected with good Earths. Temporary Earths may be removed after completion of all works and after all the men have come down from the Feeder/Equipment. (e) Work should be so planned that the Line Clear is returned before or at the time indicated. If unavoidable delay is anticipated advance information should be given to the location from where the Line Clear is issued.[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 113 (f) Before return of the Line Clear, it should be ensured that all the men, materials, tools/tackles etc. on line have returned and reported that all temporary earths are removed. There should also be a check on the material, Tools and Plant issued for the work to ensure that nothing is left behind on the Line or Equipment. (g) Only authorized persons should return Line Clear. (h) In case the Line Clear cannot be returned in person, the same may be returned to the Line Clear Issuing Authority over Telephone by naming the Code Words assigned and the telephone number which is used for naming the Code Words assigned. In case two or more different Code Words are issued to the two or more persons in whose favour the permit is given, those persons must jointly return the Line Clear by naming their own Code Words. The Line Clear Return will not be accepted unless returned by all these persons. (i) The Line Clear issuing authority should go through the checklist of Line Clear Return before accepting it. (j) If Line Clear is returned over telephone, the Line Clear Return Form duly filled and signed should be sent to the Line Clear Issuing Authority by post immediately for record. (k) Control persons should keep all the required data of LCP issued & LCR received. He should monitor and keep specific note in log sheet when more than one LCP are issued on same line/ equipment / bay along with code words. FORMAT – 3 Serial No. xxxxxxxxx LINE CLEAR RETURN LCP Number…………………………………. Date ………………………………………………. Time.............. I Shri/Shrimati --------------- hereby return the LCP no -----at (time) ------- issued for the following HT/EHT Line/Apparatus. I declare that all the crew who were sent on work have been withdrawn, temporary earth(s) removed, all repair tools and materials checked and the Feeders/Equipments mentioned below are safe to be energized. (a) EHT / HT Apparatus/Line Identification: (b) Safety Precaution no longer required: (c) Isolation [State locations and each point of Isolation indicating means by which Isolation was achieved.] (d) Earthing [State location at which Earthing was established and identify each point of Earthing means, which achieved Earthing.] (e) Details of work done CHECK LIST TO BE TICKED OFF: (a) Whether all men withdrawn: Yes (b) Whether all temporary Earth removed: Yes (c) Whether materials, Tools and Plant used in the work have been checked: Yes (d) Code Number (If used when Line Clear is returned over phone) ----------------- Name and Signature…………………………………………. (Person Requesting Line Clear Permit) Designation…………………………………………………… In-charge of the Crew ------------------------ (Designation) CHAPTER -17: DATA REGISTRATION 17.1 This Chapter deals with listing out all the data required to be provided by Users to STU and/or SLDC and vice versa, in accordance with the provisions of the State Grid Code.114 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 17.2 Responsibility 1. All Users are responsible for submitting the required up-to-date data to STU/ SLDC in accordance with the provisions of the State Grid Code. 2. All Users shall provide STU and SLDC, the names, addresses and telephone numbers of the persons responsible for sending the data. 3. Responsibility for the correctness of the data rests with the concerned User providing the data. 4. STU shall inform all Users and SLDC, the names, addresses, and telephone numbers of the persons responsible for receiving data. 5. STU shall provide up-to-date data to Users as provided in the relevant Chapters of this State Grid Code. 17.3 Data to be registered Data required to be registered/exchanged has been listed in the Appendices to this chapter under various categories. The data so far applicable to the particular User need only to be registered and exchanged with STU or SLDC. 17.4 Changes in User’s Data Whenever any User becomes aware of a change to any items of data that is registered with STU, the User must promptly notify the STU of the changes. STU on receipt of intimation of the changes shall promptly correct the database accordingly. This shall also apply to any data compiled by STU regarding its own system. 17.5 Method of Submitting Data 1. The data shall be furnished in the standard formats for data submission and such formats must be used for the written submission of data to SLDC and STU. Where standard formats are not enclosed, they would be developed by SLDC or STU in consultation with Users. 2. All data to be submitted under the Schedule(s) must be submitted to SLDC / STU or to such other department and/or entity as STU may from time to time notify to Users. The name of the person who is submitting each schedule of data shall be indicated. 3. Where a computer data link exists between a User and SLDC/ STU, data may be submitted via this link. The data shall be in the same format as specified for paper transmission. The User shall specify the method to be used in consultation with the SLDC/ STU and resolve issues such as protocols, transmission speeds etc. at the time of transmission. 17.6 Data not supplied All Users are obliged to supply data as referred to in the individual Chapters of this State Grid Code and listed out in this Data Registration Chapter Appendices. In case any data is not supplied by any User or is not available, STU or SLDC may, acting reasonably, if and when necessary, estimate such data depending upon the urgency of the situation. Similarly, in case any data is not supplied by STU, the concerned User may, acting reasonably, if and when necessary, estimate such data depending upon urgency of the situation. Such estimates will in each case, be based upon corresponding data for similar Plant or Apparatus or upon such other information, the User or STU or SLDC, as the case may be, deems appropriate. 17.7 Special Considerations SLDC and any other User may at any time make reasonable request to STU for extra data as necessary. STU shall supply data, required/requested. CHAPTER – 18: MISCELLANEOUS 18.1 Dispute Redressal: Any dispute regarding interpretation of any provision of the State Grid Code, shall be addressed to Secretary to the Commission. The decision of the Commission shall be taken as final and binding on all concerned. 18.2 Power to Remove Difficulties: If any difficulty arises in giving effect to any of the provisions of the Gird Code, the Commission may, by general or specific order, make such provisions not inconsistent with the provisions of the Act, as may appear to be necessary for removing the difficulty.[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 115 18.3 Power to Relax The Commission may by general or special order, for reasons to be recorded in writing and after giving an opportunity of hearing to the parties likely to be effected by grant of relaxation, may relax any of the provisions of the State Grid Code on its own motion or on an application made before it by an interested person. 18.4 Power to Amend The Commission may, at any time, vary, alter, modify or amend any provision of State grid code. By Order of the Commission. V. K. DHAR, Secy. [ADVT.-III/4/Exty./612/2023-24] APPENDIX A: STANDARD PLANNING DATA (Reference to: Chapter 3 para 3.3 (4), para 3.6 (1,2,3) and Chapter 4 para 4.2 (6)) A.1 STANDARD PLANNING DATA (GENERATION) For SGS – Thermal A-1.1 THERMAL (COAL/GAS/FUEL LINKED) 1. GENERAL i Site Furnish location map to scale showing roads, railway lines, Transmission lines, canals, pondage, and reservoirs if any. ii Coal linkage/ Fuel (Like Liquefied Natural Give information on means of coal transport / carriage. In case of other Gas, Naphtha etc.) linkage fuels, give details of source of fuel and their transport. iii Water Sources Give information on availability of water for operation of the Power Station. iv Environmental State whether forest or other land areas are affected. v Site Map (To Scale) Showing area required for Power Station coal linkage, coal yard, water pipe lines, ash disposal area, colony etc. vi Approximate period of construction 2. CONNECTION i Point of Connection Furnish single line diagram of the proposed Connection with the system. ii Step up voltage for Connection (kV) 3. STATION CAPACITY i Total Generating Station capacity (MW) State whether development will be carried out in phases, and if so, furnish details. ii No. of units & unit size (MW) 4. GENERATING UNIT DATA i Steam Generating Unit State type, capacity, steam pressure, steam temperature etc. ii Steam turbine State type, capacity. iii Generator Type Rating (MW) Speed (RPM)116 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] Terminal voltage (KV) Rated Power Factor Reactive Power Capability (MVAr) in the range 0.95 of leading and 0.85 lagging Short Circuit Ratio Direct axis (saturated) transient reactance (% on MVA rating) Direct axis (saturated) sub-transient reactance (% on MVA rating) Auxiliary Power Requirement MW and MVAr Capability curve Ramp-up and ramp-down rate Generator Characteristics curve iv Generator Transformer Make Phases Type Rated capacity (MVA) Voltage Ratio (HV/LV) Tap change Range (+ % to - %) Percentage Impedance (Positive Sequence at Full load) A-1.2 HYDRO ELECTRIC (For SGS) 1. GENERAL i Site Give location map to scale showing roads, railway lines, and transmission lines. ii Site map (To scale) Showing proposed canal, reservoir area, water conductor system, fore-bay, power house etc. iii Submerged Area Give information on area submerged, villages submerged, submerged forest land, agricultural land etc. iv Whether storage type or run of river type v Whether catchment receiving discharges from other reservoir or power plant. vi Full reservoir level vii Minimum draw down level. viii Tail race level ix Design Head x Reservoir level v/s energy potential curve xi Restraint, if any, in water discharges xii Approximate period of construction. 2. CONNECTION i Point of Connection Give a single line diagram proposed Connection with the Transmission System. ii Step up voltage for Connection (KV) 3. STATION CAPACITY[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 117 i Total Power Station capacity (MW) State whether development is carried out in phases and if so, furnish details. ii No. of units & unit size (MW) 4. GENERATING UNIT DATA i Operating Head (in Meters) a. Maximum: __________________ b. Minimum: ___________________ c. Average: ____________________ ii Hydro Unit Capability to operate as synchronous condenser. Water head versus discharges curve (at full and part load) Power requirement or water discharge while operating as synchronous condenser iii Turbine State Type and capacity iv Generator Type Rating (MVA) Speed (RPM) Terminal voltage (KV) Rated Power Factor Reactive Power Capability (MVAr) in the range 0.95 of leading and 0.85 of lagging MW & MVAr capability curve of generating unit Short Circuit Ratio Direct axis transient (saturated) reactance (% on rated MVA) Direct axis sub-transient (saturated) reactance (% on rated MVA) Auxiliary Power Requirement (MW) v Generator- Transformer Type Make Phases Rated Capacity (MVA) Voltage Ratio HV/LV Tap change Range (+% to -%) Percentage Impedance (Positive Sequence at Full Load). A-2 STANDARD PLANNING DATA (TRANSMISSION) For STU and Transmission Licensees STU shall make arrangements for getting the required data from different Departments of STU/other transmission licensees (if any) to update its Standard Planning Data in the format given below: i) Name of line (Indicating Power Stations and substations connected) ii) Voltage of line (KV). iii) No. of circuits iv) Route length (Km) v) Conductor sizes118 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] vi) Line parameters (PU values) a. Resistance/km b. Inductance/km c. Susceptance/km vii) Approximate power flow expected- MW & MVAr viii) Terrain of the route- Give information regarding nature of terrain i.e., forest land, fallo w land, agricultural and river basin, hill slope etc. ix) Route map (to scale) - Furnish topographical map showing the route showing existing power lines and telecommunication lines. x) Purpose of Connection- Reference to Scheme, wheeling to other States etc. xi) Approximate period of Construction A-3 STANDARD PLANNING DATA (DISTRIBUTION) For Distribution Licensees 1. GENERAL i Area Map (to scale) Furnish map of the UT of Jammu & Kashmir and the UT of Ladakh duly marked with the area of supply relevant for the Distribution Licensee. ii Consumer Data Furnish categories of consumers, their numbers and connected loads. iii Reference to Electrical Divisions presently in charge of the Distribution. 2. CONNECTION i Points of Connection Furnish single line diagram showing points of Connection ii Voltage of supply at points of Connection iii Names of Grid Sub-Station feeding the points of Connection 3. LINES AND SUBSTATIONS i Line Data Furnish lengths of line and voltages within the Area. ii Sub-station Data Furnish details of 132/33 KV sub-stations, 33/11 KV sub-station etc. 4. LOADS i Loads drawn at points of Connection. ii Details of loads fed at EHV, if any. Give the name of the consumer, voltage of supply, contract demand/load and the name of the Grid Sub-station from which line is drawn, length of EHV line from Grid Sub-station to consumer's premises. iii Reactive Power compensation installed 5. DEMAND DATA (FOR ALL LOADS 1 MW AND ABOVE) i Type of load State whether furnace loads, rolling mills, traction loads, other industrial loads, pumping loads etc. ii Rated voltage and phase[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 119 iii Electrical loading of equipment State number and size of motors, types of drive and control arrangements. iv Sensitivity of load to voltage and frequency of supply. v Maximum Harmonic content of load. vi Average and maximum phase unbalance of load. vii Nearest sub-station from which load is to be fed. viii Location map to scale Showing location of load with reference to lines and sub- stations in the vicinity. 6. LOAD FORECAST DATA i Peak load and energy forecast for each category of loads for each of the succeeding 5 years. ii Details of methodology and assumptions on which forecasts are based. iii Details of loads 1 MW and above. a. Name of prospective consumer. b. Location and nature of load. c. Sub-Station from which to be fed. d. Voltage of supply. e. Phasing of load. APPENDIX B: DETAILED PLANNING DATA (Reference to: Chapter 3 para 3.3 (4), para 3.6 (1,2,3) and Chapter 4 para 4.2 (6)) B-1 DETAILED PLANNING DATA (GENERATION) B-1.1 THERMAL POWER STATIONS (For SGS) 1. GENERAL i. Name of the Power Station. ii. Number and capacity of Generating Units (MW). iii. Ratings of all major equipment (Boilers and major accessories, Turbines, Alternators, Generator Unit Transformers etc). iv. Single line Diagram of Power Station and switchyard. v. Relaying and metering diagram. vi. Neutral Grounding of Generating Units. vii. Excitation control- (What type is used?) e.g., Thyristor, Fast Brushless Exciters) viii. Earthing arrangements with earth resistance values. 2. PROTECTION AND METERING i. Full description including settings for all relays and protection systems installed on the Generating Unit, Generator unit Transformer, Auxiliary Transformer and electrical motor of major equipment etc. ii. Full description including settings for all relays installed on all outgoing feeders from Power Station switchyard, Tie circuit breakers, and incoming circuit breakers. iii. Full description of inter-tripping of circuit breakers at the point or points of Connection with the Transmission System.120 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] iv. Most probable fault clearance time for electrical faults on the User's System. v. Full description of operational and commercial metering schemes. 3. SWITCHYARD i. In relation to interconnecting transformers: 1. Rated MVA. 2. Voltage Ratio. 3. Vector Group. 4. Positive sequence reactance for maximum, minimum, normal Tap. (% on MVA). 5. Positive sequence resistance for maximum, minimum, normal Tap. (% on MVA). 6. Zero sequence reactance (% on MVA). 7. Tap changer Range (+% to -%) and steps. 8. Type of Tap changer. (off/on load). ii. In relation to switchgear including circuit breakers, isolators on all circuits connected to the points of Connection: 1. Rated voltage (KV). 2. Type of circuit breaker (MOCB/ABCB/SF6). 3. Rated short circuit breaking current (KA) 3 phase. 4. Rated short circuit breaking current (KA) 1 phase. 5. Rated short circuit making current (KA) 3 phase. 6. Rated short circuit making current (KA) 1-phase. 7. Provisions of auto reclosing with details. iii. In relation to the Lightning Arresters – Technical data iv. In relation to Communication – Details of communication equipment installed at points of Conn connection. v. In relation to the Basic Insulation Level (KV) - 1. Bus bar. 2. Switchgear. 3. Transformer bushings. 4. Transformer windings. 4. PARAMETERS OF GENERATING UNITS i. Rated terminal voltage (KV). ii. Rated MVA. iii. Rated MW. iv. Speed (rpm) or number of poles. v. Inertia constant H (MW Sec./MVA). vi. Short circuit ratio. vii. Direct axis synchronous reactance (% on MVA) Xd. viii. Direct axis (saturated) transient reactance (% on MVA) Xd'. ix. Direct axis (saturated) sub-transient reactance (% on MVA) Xd". x. Quadrature axis synchronous reactance (% on MVA) Xq .[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 121 xi. Quadrature axis (saturated) transient reactance (% on MVA) Xq'. xii. Quadrature axis (saturated) sub-transient reactance (% on MVA) Xq". xiii. Direct axis transient open circuit time constant (Sec) T'do. xiv. Direct axis sub-transient open circuit time constant (See) T"do. xv. Quadrature axis transient open circuit time constant (Sec) T’qo. xvi. Quadrature axis sub-transient open circuit time constant (Sec) T’'qo. xvii. Stator Resistance (ohm)Ra. xviii. Neutral grounding details. xix. Stator leakage reactance (ohm) X1. xx. Stator time constant (Sec). xxi. Rated Field current (A). xxii. Open Circuit saturation characteristic for various terminal Voltages giving the compounding current to achieve the same. xxiii. MW and MVAr Capability curve. 5. PARAMETERS OF EXCITATION CONTROL SYSTEM: i. Type of Excitation. ii. Maximum Field Voltage. iii. Minimum Field Voltage. iv. Rated Field Voltage. v. Details of excitation loop in block diagrams showing transfer functions of individual elements using I.E.E.E. symbols. vi. Dynamic characteristics of over - excitation limiter. vii. Dynamic characteristics of under-excitation limiter. 6. PARAMETERS OF GOVERNOR: i. Governor average gain (MW/Hz). ii. Speeder motor setting range. iii. Time constant of steam or fuel Governor valve. iv. Governor valve opening limits. v. Governor valve rate limits. vi. Time constant of Turbine. vii. Governor block diagram showing transfer functions of individual elements using I.E.E.E. symbols. 7. OPERATIONAL PARAMETERS: Minimum notice required to synchronize a Generating Unit from de- synchronization. i. Minimum time between synchronizing different Generating Units in a Power Station. ii. The minimum block load requirements on synchronizing. iii. Time required for synchronizing a Generating Unit for the following conditions: 1. Hot 2. Warm 3. Cold iv. Maximum Generating Unit loading rates for the following conditions: 1. Hot 2. Warm122 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 3. Cold v. Minimum load without oil support (MW). 8. GENERAL STATUS i. Detailed Project report. ii. Status Report 1. Land 2. Coal 3. Water 4. Environmental clearance 5. Rehabilitation of displaced persons iii. Techno-economic approval by Central Electricity Authority (CEA). iv. Approval of State Government/Government of India. v. Financial Tie-up. 9. CONNECTION i. Reports of Studies for parallel operation with the State Transmission System. ii. Short Circuit studies iii. Stability Studies. iv. Load Flow Studies. v. Proposed Connection with the State Transmission System. a. Voltage b. No. of circuits c. Point of Connection. B-1.2 HYDRO - ELECTRIC STATIONS (For SGS) 1. GENERAL i. Name of the Power Station. ii. No. and capacity of units. (MVA) iii. Ratings of all major equipment. a. Turbines (HP) b. Generators (MVA) c. Generator Transformers (MVA) d. Auxiliary Transformers (MVA) iv. Single line diagram of Power Station and switchyard. v. Relaying and metering diagram. vi. Neutral grounding of Generator. vii. Excitation control. viii. Earthing arrangements with earth resistance values. ix. Reservoir Data. a. Salient features b. Type of Reservoir c. Multipurpose[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 123 d. For Power e. Operating Table with x. Area capacity curves and xi. Unit capability at different net heads 2. PROTECTION i. Full description including settings for all relays and protection systems installed on the Generating Unit, Generator transformer, auxiliary transformer and electrical motor of major equipment included etc. ii. Full description including settings for all relays installed on all outgoing feeders from Power Station switchyard, tie breakers, and incoming breakers. iii. Full description of inter-tripping of breakers at the point or points of Connection with the Transmission System. iv. Most Probable fault clearance time for electrical faults on the User's System. 3. SWITCHYARD i. Interconnecting transformers: 1. Rated MVA 2. Voltage Ratio 3. Vector Group 4. Positive sequence reactance for maximum, minimum and normal Tap (% on MVA). 5. Positive sequence resistance for maximum, minimum and normal Tap (% on MVA). 6. Zero sequence reactance (% on MVA) 7. Tap changer range (+% to -%) and steps. 8. Type of Tap changer (off/on load). 9. Neutral grounding details. ii. Switchgear (including circuit breakers, Isolators on all circuits connected to the points of Connection). 1. Rated voltage (KV). 2. Type of Breaker (MOCB/ABCB/SF6). 3. Rated short circuit breaking current (KA) 3 phase. 4. Rated short circuit breaking current (KA) 1 phase. 5. Rated short circuit making current (KA) 3 phase. 6. Rated short circuit making current (KA) 1 phase. 7. Provisions of auto reclosing with details. iii. Lightning Arresters Technical data iv. Communications Details of Communications equipment installed at points of connections. v. Basic Insulation Level (KV) 1. Bus bar. 2. Switchgear. 3. Transformer Bushings 4. Transformer windings.124 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 4. GENERATING UNITS i. Parameters of Generator 1. Rated terminal voltage (KV). 2. Rated MVA. 3. Rated MW 4. Speed (rpm) or number of poles. 5. Inertia constant H (MW sec./MVA). 6. Short circuit ratio. 7. Direct axis synchronous reactance Xd (% on MVA). 8. Direct axis (saturated) transient reactance (% on MVA) X'd. 9. Direct axis (saturated) sub-transient reactance (% on MVA) X"d. 10. Quadrature axis synchronous reactance (% on MVA) Xq. 11. Quadrature axis (saturated) transient reactance (% on MVA) X'q. 12. Quadrature axis (saturated) sub-transient reactance (% on MVA) X"q. 13. Direct axis transient open circuit time constant (sec) T'do. 14. Direct axis sub-transient open circuit time constant (sec) T"do. 15. Quadrature axis transient open circuit time content (sec) T'qo. 16. Quadrature axis transient open circuit time constant (sec) T"qo. 17. Stator Resistance (ohm) Ra. 18. Stator leakage reactance (ohm) X1. 19. Stator time constant (sec). 20. Rated Field current (A). 21. Neutral grounding details. 22. Open Circuit saturation characteristics of the Generator for various terminal voltages giving the compounding current to achieve this. 23. Type of Turbine. 24. Operating Head (meters) 25. Discharge with full gate opening (cumecs) 26. Speed Rise on total Load throw off (%). 27. MW and MVAr Capability curve ii. Parameters of excitation control system: iii. Parameters of governor: iv. Operational parameter: 1. Minimum notice required to Synchronise a Generating Unit from de- synchronisation. 2. Minimum time between Synchronising different Generating Units in a Power Station. 3. Minimum block load requirements on Synchronising. 5. GENERAL STATUS i. Detailed Project Report. ii. Status Report. 1. Topographical survey 2. Geological survey 3. Land[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 125 4. Environmental Clearance 5. Rehabilitation of displaced persons. iii. Techno-economic approval by Central Electricity Authority. iv. Approval of State Government/Government of India. v. Financial Tie-up. 6. CONNECTION i. Reports of Studies for parallel operation with the State Transmission System. 1. Short Circuit studies 2. Stability Studies. 3. Load Flow Studies. ii. Proposed Connection with the State Transmission System. 1. Voltage 2. No. of circuits 3. Point of Connection. 7. RESERVOIR DATA i. Dead Capacity ii. Live Capacity B-1.3 GAS POWER STATIONS (For SGS) 1. GENERAL i. Name of the Power Station ii. Number and capacity of Generating Units (MVA). iii. Ratings of all major equipments (Turbines, Alternators, Heat Recovery Boiler Generator Unit Transformer etc). iv. Single line Diagram of Power Station and switchyard. v. Relaying and metering diagram. vi. Neutral Grounding of Generating Units. vii. Excitation control- (What type is used?) e.g., Thyristor, Fast Brushless Exciters viii. Earthing arrangements with earth resistance values. ix. Start-up Engine x. Turbine Details 2. PROTECTION AND METERING i. Full description including settings for all relays and protection systems installed on the Generating Units, Generator Unit Transformer, Auxiliary Transformer and Electrical motor of major equipment. ii. Full description including settings for all relays installed on all outgoing feeders from Power Station switchyard, Tie circuit breakers, and incoming circuit breakers. iii. Full description of inter – tripping of circuit breakers at the point or points of Connection with the Transmission System. iv. Most probable fault clearance time for electrical faults on the User’s system. v. Full description of operational and commercial metering schemes. 3. SWITCHYARD a. In relation to interconnecting transformers: i. Rated MVA. ii. Voltage Ratio iii. Vector Group126 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] iv. Positive sequence reactance for maximum, minimum, and normal Tap. (% on MVA) v. Positive sequence resistance for maximum, minimum, and normal Tap. (% on MVA). vi. Zero sequence reactance (% on MVA). vii. Tap changer Range (=% to -%) and steps. viii. Type of Tap changer. (off/on load). b. In relation to switchgear including circuit breakers, and isolators on all circuits connected to the points of connection: i. Rated Voltage (KV) ii. Type of circuit breaker (MOCB/ABCB/SF6). iii. Rated short circuit breaking current (KA) 3 phase iv. Rated short circuit breaking current (KA) 1 phase. v. Rated short circuit making current (KA) 3 phase. vi. Rated short circuit making current (KA) 1-phase. vii. Provisions of auto reclosing with details. c. Lightning Arresters – Technical data d. Communication – Details of communication equipment installed at points of connections. e. Basic Insulation Level (kV) – i. Bus bar. ii. Switchgear iii. Transformer bushings iv. Transformer windings 4. GENERATING UNITS a) Parameters of Generating Units: i. Rated terminal voltage (kV) ii. Rated MVA iii. Rated MW iv. Speed (rpm) or number of poles v. Inertia constant H (MW Sec./MVA) vi. Short circuit ratio. vii. Direct axis synchronous reactance (% on MVA) Xd. viii. Direct axis (saturated) transient reactance (% on MVA) Xd’. ix. Direct axis (saturated) sub-transient reactance (% on MVA) Xd”. x. Quadrature axis synchronous reactance (% on MVA) Xq xi. Quadrature axis (saturated) transient reactance (% on MVA) Xq’ xii. Quadrature axis (saturated) sub-transient reactance (% on MVA) Xq”. xiii. Direct axis transient open circuit time constant (Sec) Tdo. xiv. Direct axis sub-transient open circuit time constant (Sec) T”do. xv. Quadrature axis transient open circuit time constant (Sec) T’qo. xvi. Quadrature axis sub-transient open circuit time constant (Sec) T”qo.[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 127 xvii. Stator Resistance (ohm) Ra. xviii. Neutral grounding details. xix. Stator leakage reactance (ohm) X1. xx. Stator time constant (sec). xxi. Rated Field current (A). xxii. Open Circuit saturation characteristic for various terminal Voltages giving the compounding current to achieve the same. xxiii. MW and MVAr Capability curve. b) Parameters of excitation control system: i. Type of Excitation. ii. Maximum Field Voltage. iii. Minimum Field Voltage. iv. Rated Field Voltage. v. Details of excitation loop in block diagrams showing transfer functions of individual elements using I.E.E.E symbols. vi. Dynamic characteristics of over – excitation limiter. vii. Dynamic characteristics of under – excitation limiter. c) Parameter of governor: i. Governor average gain (MW/Hz) ii. Speeder motor setting range. iii. Time constant of steam or fuel Governor valve. iv. Governor valve opening limits. v. Governor valve rate limits. vi. Time constant of Turbine. vii. Governor block diagram showing transfer functions of individual elements using I.E.E.E symbols. d) Operational parameters: i. Minimum notice required synchronising a Generating unit from desynchronization. ii. Minimum time between synchronizing different Generating Units in a Power Station. iii. The minimum block load requirements on synchronizing. iv. Time required for synchronizing a Generating unit for the following conditions: a. Hot b. Warm c. Cold v. Maximum Generating unit loading rates for the following conditions: a. Hot b. Warm c. Cold vi. Minimum load without oil support (MW). 5. GENERAL STATUS i. Detailed project report ii. Status Report a. Land128 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] b. Gas/Liquid Fuel c. Water d. Environmental Clearance e. Rehabilitation of displaced persons iii. Approval of State Government/ Government of India. iv. Financial Tie – up. 6. CONNECTION i. Reports of Studies for parallel operation with State Grid. a. Short Circuit Studies b. Stability Studies c. Load Flow Studies ii. Proposed Connection with the State Grid. a. Voltage b. No. of circuits c. Point of Connection. B-2 DETAILED SYSTEM DATA-TRANSMISSION For STU and Transmission Licensees 1. GENERAL i. Single line diagram of the Transmission System down to 66KV,33KV bus at Grid Sub-station detailing: 1. Name of Sub-station. 2. Power Station connected. 3. Number and length of circuits. 4. Interconnecting transformers. 5. Sub-station bus layouts. 6. Power transformers. 7. Reactive compensation equipment. ii. Sub-station layout diagrams showing: 1. Bus bar layouts. 2. Electrical circuitry, lines, cables, transformers, switchgear etc. 3. Phasing arrangements. 4. Earthing arrangements. 5. Switching facilities and interlocking arrangements. 6. Operating voltages. 7. Numbering and nomenclature: 8. Transformers. 9. Circuits. 10. Circuit breakers. 11. Isolating switches. 2. LINE PARAMETERS (for all circuits) i. Designation of Line.[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 129 1. Length of line (Km). 2. Number of circuits Per Circuit values. 3. Operating voltage (KV). 4. Positive Phase sequence reactance (pu on 100 MVA) X1 5. Positive Phase sequence resistance (pu on 100 MVA) R1 6. Positive Phase sequence susceptance (pu on 100 MVA) B1 7. Zero Phase sequence reactance (pu on 100 MVA) X0 8. Zero Phase sequence resistance (pu on 100 MVA) R0 9. Zero Phase sequence susceptance (pu on 100 MVA) B0 3. TRANSFORMER PARAMETERS (For all transformers) i. Rated MVA ii. Voltage Ratio iii. Vector Group iv. Positive sequence reactance, maximum, minimum and normal (pu on 100 MVA) X1 v. Positive sequence resistance, maximum, minimum and normal (pu on 100 MVA) R1 vi. Zero sequence reactance (pu on 100 MVA). vii. Tap change range (+% to -%) and steps. viii. Details of Tap changer. (Off/On-load). 4. EQUIPMENT DETAILS (For all substations) i. Circuit Breakers ii. Isolating switches iii. Current Transformers iv. Potential Transformers/CVTs 5. RELAYING AND METERING i. Protection relays installed for all transformers and feeders along with their settings and level of co- ordination with other Users. ii. Metering Details. 6. SYSTEM STUDIES i. Load Flow studies (Peak and lean load for maximum hydro and maximum thermal generation). ii. Transient stability studies for three-phase fault in critical lines. iii. Dynamic Stability Studies iv. Short circuit studies (three-phase and single phase to earth) v. Transmission and Distribution Losses in the Transmission System. 7. DEMAND DATA (For all substations) Demand Profile (Peak and lean load) for next 5 years. 8. REACTIVE COMPENSATION EQUIPMENT i. Type of equipment (fixed or variable). ii. Capacities and/or Inductive rating or its operating range in MVAr. iii. Details of control. iv. Point of Connection to the System.130 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] B-3 DETAILED PLANNING DATA (DISTRIBUTION) For Distribution Licensees 1. GENERAL i. Distribution map (To scale). Showing all lines up to 11KV and sub-stations belonging to the Supplier. ii. Single line diagram of Distribution System (showing distribution lines from points of Connection with the Transmission System, 132/33 KV sub stations, 33/11KV 110/22-11 KV substations, and consumer bus in case of consumers fed directly from the Transmission System). iii. Numbering and nomenclature of lines and sub-stations (Identified with feeding Grid sub-stations of the Transmission and concerned 220/132/33/11KV, 132/33/11KV, and 33/11KV 110/22-11 KV sub- stations of Licensee). 2. CONNECTION i. Points of Connection (Furnish details of existing arrangement of Connection). ii. Details of metering at points of Connection. 3. LOADS i. Details of major loads of 1 MW and above to be contracted for next 5 years. ii. Demand profile of Distribution System (Current & forecast). APPENDIX C: SITE RESPONSIBILITY SCHEDULE (Reference to: Chapter 4 para 4.5 (2)) Name of Power Station / Sub – Station: __________________________________________________________________________________________________________________________________ Site Owner: _____________________________ Site Manager: _________________________________________ Tel. Number: ____________________________ Fax Number: __________________________________________ e-mail id: ________________________________ Item of Plant / Plant Safety Control Operation Maintenance Remarks Apparatus Owner responsibility responsibility responsibility responsibility KV Switchyard All equipment including bus bars Feeders Generating units Station/Unit-1 Station/Unit-2 Station/Unit-3[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 131 APPENDIX D: PROTECTION DATA (Reference to: Chapter 7) PROTECTION: ITEM DUE DATE/TIME a) Generators/CPPs/IPPs shall submit details of protection requirement and As applicable to Detailed schemes installed by them as referred to in B-1. Detailed planning Data Planning Data under sub-section “Protection and Metering” b) The STU shall submit details of protection equipment and schemes As applicable to Detailed installed by them as referred to in B-2. Detailed system Data, Planning Data Transmission under sub-section “Relaying and Metering” in relation to Connection with any User. APPENDIX E: OPERATIONAL PLANNING DATA (Reference to: chapter 10 para 10.3 (1)) E.1 OUTAGE PLANNING DATA 1. Demand Estimates (For Distribution Licensees) Item Due date/ Time a) Estimated aggregate month-wise annual sales of Energy in Million Units 15th November of current year and peak and lean demand in MW & MVAr at each Connection point for the next financial year. b) Estimated aggregate day-wise monthly sales of Energy in million Units and 25th of current month peak and lean demand in MW & MVAr at each Connection point for the next month. c) 15 Minute block-wise demand estimates for the day ahead. 09.00 Hours every day. 2. Estimates of Load Shedding for Distribution Licensee Item Due date / Time a) Details of discrete load blocks that may be shed to comply with instructions Soon after connection is made. issued by SLDC when required, from each connection point. 3. Year ahead outage program (For the financial year) (a) Generator outage program for (SGS) Item Due date / Time a) Identification of Generating Unit. 15th November each year b) MW, which will not be available as a result of Outage. c) Preferred start date and start-time or ranges of start dates and start times and period of outage. d) If outages are required to meet statutory requirement, then the latest – date by which outage must be taken.132 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] (b) Affecting Intra – State Transmission System Item Due date / Time a) MW, which will not be available as a result of Outage from imports through 15th November each year external connections. b) Start date and start time and period of Outage. (c) Year ahead CPP’s outage program (Affecting Intra – State Transmission System) Item Due date / Time a) MW, which will not be available as a result of Outage from Imports through 15th November each year external connections. b) Start date and start time and period of Outage. (d) Year ahead Distribution Licensees outage program Item Due date / Time a) Loads in MW not available from any connection point. Identification of 15th November each year connection point. b) Period of suspension of drawal with start date and start time. (e) STU’s Overall outage program Item Due date / Time a) Report on proposed outage program 15th February each year b) Release of finally agreed outage plan E-2 GENERATION SCHEDULING DATA (Reference to: Chapter 14) SCHEDULE AND DESPATCH (For SGS, IPPs and CPPs) Item Due date/ Time Day ahead 15 Minute block-wise MW/MVAr availability (00.00 - 24.00 09.00 hrs Hours). a) Status of Generating Unit Excitation AVR in service (Yes/No). 09.00 hrs b) Status of Generating Unit Speed Control System. Governor in service 09.00 hrs (Yes/No). c) Spinning reserve capability (MW). 09.00 hrs d) Backing down capability with/without oil support (MW). 09.00 hrs Hydro reservoir levels and restrictions. 09.00 hrs a) Generating Units 15 Minute block-wise summation outputs (MW). 09.00 hrs b) Day ahead 15 Minute block-wise MW entitlements from Central Sector 09.0 hrs Generation Power Stations. Formats for sharing information provided in Section E-2.2 belo[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 133 E-2.1 DAY AHEAD DRAWAL SCHEDULE Format-A Submission of Day Ahead Drawal Schedule at T<>D Periphery by Buyer to SLDC Format-A Day Ahead (D-1 day) Drawal of Buyer (at T<>D Periphery) Name of Entity/Buyer Buyer Code Delivery Date Revision No. (In case of Revision in Schedule) Time Block Projected Demand Short Term OA Medium Term OA Bilateral Contract MW MWh MW MWh MW MWh MW MWh 1 2 3 4 …. 96 TOTAL Average Min Max Note: 1. In Day Ahead (D-1)- D is the delivery date. 2. In case of any ‘Revision’ in Schedule, the above format would be applicable. E-2.2 UNIT WISE EX-BUS DAY AHEAD AVAILABILITY Format-B Submission of Unit Wise Ex-bus Day Ahead Availability by Seller Format-B Day Ahead (D-1 day) Declared Capacity (DC) at Ex-bus (Unit Wise) Name of Seller Unit wise134 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] Seller Code Delivery Date Revision No. (In case of Revision of DC) Time Block Day Ahead LTOA (MW) STOA (MW) MTOA (MW) Collective (MW) DC (MW) Intra-state Intra-state Intra-state Buyer 1 Buyer 2 Buyer 1 Buyer 2 Buyer 1 Buyer 2 1 2 3 4 …. 96 TOTAL Average Min Max Note: 1. In Day Ahead (D-1)- D is the delivery date. 2. In case of any ‘Revision’ in Schedule, the above format would be applicable. Format-C Submission of Unit Wise Ex-bus Day Monthly Availability by Seller (Hydro) Format-C (Hydro) For Day Ahead (D-1) Declared Capacity at Ex-Bus Unit Wise to be submitted by Hydro Generator Name of Seller Seller Code (Unit wise) Revision No. Delivery date Month wise water availability (in MCum and TMC) Lake level (in meters) as on date Statutory restrictions of Tribunal/WRD for water[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 135 utilisation if any Consent of Beneficiary having PPA with Hydro Plant DC for the days of the month (MW) Time Block 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Remark 1 2 … 96 Total Avg. Min. Max. Water utilisation (MCum / TMC) Note: 1. In case of Pumped Hydro, the same format would be applicable Format-D Day Ahead Drawal Schedule declaration based on MOD by SLDC Format-D Day Ahead Drawal Schedule of Buyer- XXXXX (Based on De-centralised MOD at T<>D Periphery) Name of Buyer Buyer Code Delivery Date Time Block Gen 1 Gen 2 Gen 3 Gen 4 Gen 5 Gen n Total Drawal 1 2 3 4 …. 96 Format-E Intra-Day Drawal Revision at T<>D periphery by Buyer Format-E Intra-day (D-Day) Drawal Revision (T<>D Periphery) Name of Buyer Revision No. Delivery Date136 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] Time Block Day Ahead Revised LTA (MW) STOA MTOA Bilateral Remarks Projected Demand (MW) (MW) (MW) (MW) Demand (MW) 1 2 3 4 …. 96 TOTAL Average Min Max MWh E-2.3 OTHER INFORMATION 1. Capability Data (Ref: Chapter-9) For SGS Item a) Generators and IPPs shall submit to STU up-to-date capability curves for all On receipt of request from STU / SLDC. Generating Unit. b) CPPs shall submit to STU net return capability that shall be available for export On receipt of request from STU / SLDC. /import from Transmission System 2. Response to Frequency Change (Ref: Chapter-9) For SGS Item a) Primary Response in MW at different levels of loads ranging On receipt of request from STU / from minimum generation to registered capacity for frequency SLDC. changes resulting in fully opening of governor valve. b) Secondary response in MW to frequency change On receipt of request from STU / SLDC. 3. Monitoring of Generation (Ref: Chapter-9) For SLDC Monitoring Of Generation and Drawal (For SGS) Item a) SGS shall provide 15-minute block-wise generation Real time basis summation to SLDC. Real time basis b) CPPs shall provide 15-minute block-wise export / import MW to SLDC. As required c) Logged readings of Generators to SLDC. In the first week of the succeeding month d) Detailed report of generating unit tripping on monthly basis.[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 137 4. Essential and Non-Essential Load Data (Ref: Chapter-11) For SGS Contingency Planning (For SLDC) Item Schedule of essential and non-essential loads on each As soon as possible discrete load block for purposes of load shedding. after connection APPENDIX F: INCIDENT REPORTING (OTHER THAN ACCIDENTS) (Reference to: chapter 13 para 13.4) First Report: Date: _ _/_ _/_ _ _ _ Time: _ _: _ _ Hrs Sr. No. Item Details 1 Date and time of incident 2 Location of incident 3 Type of incident 4 System parameters before the incident (voltage, frequency, flows, generation etc.) 5 Relay indications received and performance of protection 6 Damage to equipment 7 Supplies interrupted and duration, if applicable 8 Amount of generation lost, if applicable 9 Possibility of alternate supply arrangement 10 Estimate of time to return to service 11 Cause of incident 12 Any other relevant information and remedial action taken 13 Recommendations for future improvement / repeat incident 14 Name of the organization APPENDIX G: METERING DATA (Reference to: chapter 15) 1. Metering Data to be furnished Item Due date/Time a) SGS shall submit details of metering equipment and schemes installed by As applicable to Detailed them as referred in B-1. Detailed Planning Data under sub-section Planning Data “Protection and Metering” b) STU s shall submit details of metering equipment and schemes installed by As applicable to Detailed them as referred in B-2. Detailed System Data, Transmission under sub- Planning Data section “Relaying and Metering” in relation to connection with any User 2. Standards of Meters (a) Part-I: Common Standards to All Type of Meters 1. These standards provide for specification of meters, immunity to external factors, sealing points and functional requirements that are required from regulatory perspective. Detailed technical specification shall be prepared by the purchaser of the meter.138 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 2. Specifications of meters Standard Reference Voltage As per IS Voltage Range As per IS Standard Frequency As per IS Standard Basic Current As per IS (Current range of consumer meters shall be so chosen as to record the load current corresponding to the sanctioned load) Accuracy Class Meters shall meet the following requirements of Accuracy Class: Interface Meters 0.2S Consumer Meters Up to 650 volts 1.0 or better Above 650 volts and up to 0.5S or better 33 kilo volts Above 33 kilo volts 0.2S Energy accounting and audit meters The accuracy class of meters in generation and transmission system shall not be inferior to that of 0.2S Accuracy Class. The accuracy class of meters in distribution system shall not be inferior to that of 0.5S Accuracy Class. Starting Current and Maximum Current As per IS Power Factor Range As per IS Power Frequency Withstand Voltage As per IS Impulse Voltage Withstand Test for 1.2/50 As per IS micro sec Power Consumption As per IS 3. Meter shall have downloading facilities of metered data through Meter Reading Instrument (MRI). 4. Immunity to External Factors The meter shall be immune to external influences like magnetic induction, vibration, electrostatic discharge, switching transients, surge voltages, oblique suspension and harmonics and necessary tests shall be carried out in accordance with relevant standard. 5. Sealing Points Sealing shall be done at the following points (as applicable): (a) Meter body or cover; (b) Meter terminal cover; (c) Meter test terminal block; (d) Meter cabinet. 6. The accuracy class of Current transformers (CTs) and Voltage transformers (VTs) shall not be inferior to that of associated meters. The existing CTs and VTs not complying with these regulations shall be replaced by new CTs and VTs, if found defective, non-functional or as per the directions of the Appropriate Commission. In case the CTs and VTs of the same Accuracy Class as that of meters cannot be accommodated in the metering cubicle or panel due to space constraints, the CTs and VTs of the next lower Accuracy Class can be installed. 7. The Voltage Transformers shall be electro-magnetic VT or Capacitive Voltage Transformer (CVT).[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 139 (b) Part-II: Standards for interface meters 1. Functional Requirements: (a) The Interface meters suitable for ABT shall be static type, composite meters, as self –contained devices for measurement of active and reactive energy, and certain other parameters as described in the following paragraphs. The meters shall be suitable for being connected directly to voltage transformers (VTs) having a rated secondary line-to-line voltage of 110 V, and to current transformers (CTs) having a rated secondary current of IA (Model-A :3 element 4 wire or Model C: 2 elements, 3 wire) or 5A (model-B: 3 elements, 4 wire or Model D: 2 element 3 wire). The reference frequency shall be 50Hz. (b) The meters shall have a non-volatile memory in which the following shall be automatically stored: i) Average frequency for each successive 15-minute block, as a two-digit code (00 to 99 for frequency from 49.0 to 51.0Hz). ii) Net Wh transmittal during each successive 15-minute block, upto second decimal, with plus/minus sign. iii) Cumulative Wh transmittal at each midnight, in six digits including one decimal. iv) Cumulative VArh transmittal for voltage high condition, at each midnight, in six digits including one decimal. v) Cumulative VArh transmittal for voltage low condition, at each midnight, in six digits including one decimal. vi) Date and time blocks of failure of VT supply on any phase, as a star (*) mark. (c) The meters shall store all the above listed data in their memories for a period of at least ten days. The data older than ten days shall get erased automatically. Each meter shall have an optical port on its front for tapping all data stored in its memory using a hand-held data collection device. The meter shall be suitable for transmitting the data to remote location using appropriate communication medium. (d) The active energy (Wh) measurement shall be carried out on 3- phase, 4-wire principle, with an accuracy as per class 0.2 S of IEC- 104 687/IEC-62053-22. In model-A and C, the energy shall be computed directly in CT and VT secondary quantities, and indicated in watt-hours. In Model-B and Model D, the energy display and recording shall be one fifth of the Wh computed in CT and VT secondary quantities. (e) The Var and reactive energy measurement shall also be on 3- phase, 4-wire principle, with an accuracy as per class 2 of IEC-62053- 23 or better. In model-A or Model C, the Var and VArh computation shall be directly in CT and VT secondary quantities. In Model-B or Model D, the above quantities shall be displayed and recorded as one-fifth of those computed in CT and VT secondary quantities. There shall be two reactive energy registers, one for the period when average RMS voltage is above 103% and the other for the period the voltage is below 97%. (f) The 15-minute Wh shall have a +ve sign when there is a net Wh export from substation busbars, and a –ve sign when there is a net Wh import. The integrating (cumulative) registers for Wh and Varh shall move forward when there is Wh/Varh export from substation busbars, and backward when there is an import. (g) The meters shall also display (on demand), by turn, the following parameters: (i) Unique identification number of the meter (ii) Date (iii) Time (iv) Cumulative Wh register reading (v) Average frequency of the previous 15-minute block (vi) Net Wh transmittal in the previous 15-minute block, with +/- sign (vii) Average percentage voltage (viii) Reactive power with +/- sign (ix) Voltage-high VArh register reading (x) Voltage-low VArh register reading. (h) The three line-to-neutral voltages shall be continuously monitored, and in case any of these falls below 70%, the condition shall be suitably indicated and recorded. The meters shall operate with the power drawn from140 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] the VT secondary circuits, without the need for any auxiliary power supply. Each meter shall have a built-in calendar and clock, having an accuracy of 30 seconds per month or better. (i) The meters shall be totally sealed and tamper-proof, with no possibility of any adjustment at site, except for a restricted clock correction. The harmonics shall be filtered out while measuring Wh, Var, and VArh, and only fundamental frequency quantities shall be measured/computed. (j) The Main meter and the Check meter shall be connected to same core of CTs and VTs. (c) Part-III: Standards for Consumer Meters 1. Measuring Parameters (a) The consumer meter shall be suitable for measurement of cumulative active energy utilized by the consumer. (b) The consumer meter may have the facilities to measure, record and display one or more of the following parameters depending upon the tariff requirement for various categories of consumers. All parameters excluding instantaneous electrical parameters shall also be stored in memory. (i) Cumulative reactive energy (ii) Average power factor (iii) Time of use of energy (iv) Apparent power (v) Maximum demand (vi) Phase voltage and line currents 2. All the three phase meters shall have data storage capacity for at least 35 days in a non-volatile memory. 3. Anti-Tampering Features (a) The meter shall not get damaged or rendered non-functional even if any phase and neutral are interchanged. (b) The meter shall register energy even when the return path of the load current is not terminated back at the meter and in such a case the circuit shall be completed through the earth. In case of metallic bodies, the earth terminal shall be brought out and provided on the outside of the case. (c) The meter shall work correctly irrespective of the phase sequence of supply (only for poly phase). (d) In the case of 3 phase, 3 wire meter even if reference Y phase is removed, the meter shall continue to work. In the case of 3 phase, 4 wire system, the meter shall keep working even in the presence of any two wires i.e., even in the absence of neutral and any one phase or any two phases. (d) In case of whole current meters and LV CT operated meter, the meter shall be capable of recording energy correctly even if input and output terminals are interchanged. (e) The registration must occur whether input phase or neutral wires are connected properly or they are interchanged at the input terminals. (f) The meter shall be factory calibrated and shall be sealed suitably before despatch. (g) The meter shall be capable of recording occurrences of a missing potential (only for VT operated meters) and its restoration with date and time of first such occurrence and last restoration along with total number and duration of such occurrences during the above period for all phases. (h) Additional anti-tampering features including logging of tampers such as current circuit reversal, current circuit short or open and presence of abnormal magnetic field may be provided as per the regulations or directions of the Appropriate Commission or pursuant to the reforms programme of the Appropriate Government. (d) Part-IV: Standards for energy accounting and audit meters 1. The energy accounting and audit meters shall be suitable for measurement, recording and display of cumulative active energy with date and time. 2. The energy accounting and audit meters may also have the facility to measure, record and display one or more of the following parameters depending upon the energy accounting and audit requirement. All parameters excluding instantaneous electrical parameters shall also be stored in memory. (a) Apparent power (b) Phase wise kilowatt at peak KVA[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 141 (c) Phase wise KVA (reactive) at peak KVA (d) Phase wise voltage at peak KVA (e) Power down time (f) Average power factor (g) Line currents (h) Phase voltages (i) Date and time (j) Tamper events 3. The energy accounting and audit meter shall have data storage capacity for at least 35 days in a non-volatile memory. 4. Energy accounting and audit meters shall have facility to download the parameters through meter reading instruments as well as remote transmission of data over communication network. APPENDIX H: CRITERIA FOR CONTINGENCY (Reference to: chapter 11) The transmission system shall be planned considering following general principles: 1. In normal operation (‘N-0’) of the grid, with all elements to be available in service in the time horizon of study, it is required that all the system parameters like voltages, loadings, frequency should remain within permissible normal limits. 2. The grid may however be subjected to outage / loss of an element and it is required that after loss of an element (‘N-1’ or single contingency), all the system parameters like voltages, loadings, frequency shall be within permissible normal limits. 3. Under outage / loss of an element, the grid may experience another contingency, though less probable (‘N-1-1’), wherein some of the equipment may be loaded up to their emergency limits. To bring the system parameters back within their normal limits, load shedding/re-scheduling of generation may have to be done, either manually or through automatic system protection schemes (SPS). Such measures shall generally be applied within one hour after the disturbance. Reliability criteria 1. No contingency (‘N-0’) a. The system shall be tested for all the load-generation scenarios high/low Wind, high/nil Solar, high/low Hydro generation, high demand, low demand and combinations thereof. b. For the planning purpose all the equipment shall remain within their normal thermal loadings and voltage ratings. c. The angular separation between adjacent buses shall not exceed 30 degrees. 2. Single contingency (‘N-1’) a) Steady-state: i. All the equipment in the transmission system shall remain within their normal thermal and voltage ratings after outage / loss of any one of the following elements (called single contingency or ‘N-1’), but without load shedding / rescheduling of generation: - Outage of a 132 kV single circuit, - Outage of a 220 kV single circuit, - Outage of a 400 kV single circuit (with or without fixed series capacitor), - Outage of an Inter-Connecting Transformer (ICT) / power transformer, - Outage of a 765 kV single circuit - Outage of one pole of HVDC bipole ii. The angular separation between adjacent buses under ‘N-1’ shall not exceed 30 degrees.142 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] iii. ‘N-1’ criteria for FACTS devices may not be considered, however studies may be carried out to address the issues like reduction in transfer capability, restriction on generation evacuation etc. in case of outage of FACTS devices. b) Transient-state: Usually, perturbation causes a transient that is oscillatory in nature, but if the system is stable, the oscillations will be damped. The system is said to be stable in which synchronous machines, when perturbed, will either return to their original state, if there is no change in exchange of power or will acquire new state asymptotically without losing synchronism. The transmission system shall be stable after it is subjected to one of the following outage / losses: a) The system shall be able to survive a permanent three phase to ground fault on a 765 kV line close to the bus to be cleared in 100 ms. b) The system shall be able to survive a permanent single phase to ground fault on a 765 kV line close to the bus. Accordingly, single pole opening (100 ms) of the faulted phase and unsuccessful re-closure (dead time 1 second) followed by 3-pole opening (100 ms) of the faulted line shall be considered. c) The system shall be able to survive a permanent three phase to ground fault on a 400 kV line close to the bus to be cleared in 100 ms. d) The system shall be able to survive a permanent single phase to ground fault on a 400 kV line close to the bus. Accordingly, single pole opening (100 ms) of the faulted phase and unsuccessful re-closure (dead time 1 second) followed by 3-pole opening (100 ms) of the faulted line shall be considered. e) In case of 220 kV / 132 kV networks, the system shall be able to survive a permanent three phase fault on one circuit, close to a bus, with a fault clearing time of 160 ms (8 cycles) assuming 3-pole opening. f) The system shall be able to survive a fault in HVDC convertor station, resulting in permanent outage of one of the poles of HVDC Bipole. g) Loss of generation: The system shall remain stable under the loss of single largest generating unit or a critical generating unit (choice of candidate critical generating unit is left to the transmission planner). h) Loss of largest radial load, connected at single point. 3. Second contingency (‘N-1-1’) Under the scenario as defined above for ‘Single Contingency’ the system may experience another contingency (called ‘N-1-1’): a) The system shall be able to survive a temporary single phase to ground fault on a 765 kV line close to the bus. Accordingly, single pole opening (100 ms) of the faulted phase and successful re-closure (dead time 1 second) shall be considered. b) The system shall be able to survive a permanent single phase to ground fault on a 400 kV line close to the bus. Accordingly, single pole opening (100 ms) of the faulted phase and unsuccessful re-closure (dead time 1 second) followed by 3-pole opening (100 ms) of the faulted line shall be considered. c) In case of 220 kV / 132 kV networks, the system shall be able to survive a permanent three phase fault on one circuit, close to a bus, with a fault clearing time of 160 ms (8 cycles) assuming 3-pole opening. In the ‘N-1-1’ as stated above, if there is a temporary fault, the system shall not lose the second element after clearing of fault but shall successfully survive the disturbance. In case of permanent fault, the system shall lose the second element as a result of fault clearing and thereafter, shall asymptotically reach to a new steady state without losing synchronism. In this new state, the system parameters (i.e., voltages and line loadings) shall not exceed emergency limits, however, there may be requirement of load shedding / rescheduling of generation so as to bring system parameters within normal limits. Radially connected generation with the grid For the transmission system connecting generator(s) radially with the grid, the following criteria shall apply: a) The radial system shall meet ‘N-1’ reliability criteria as given above for both the steady-state as well as transient-state. b) For subsequent contingency i.e., ‘N-1-1’ (second contingency), only temporary fault shall be considered for the radial system.[भाग III—खण् ड 4] भारत का रािपत्र : असाधारण 143 c) If the ‘N-1-1’ contingency is of permanent nature or any disturbance/contingency causes disconnection of such generator(s) from the main grid, the remaining main grid shall asymptotically reach to a new steady state without losing synchronism after loss of generation. In this new state the system parameters shall not exceed emergency limits, however, there may be requirement of load shedding / rescheduling of generation so as to bring system parameters within normal limits. d) The ‘N-1’ criteria may not be applied to the immediate connectivity system of renewable generations with the ISTS/Intra-STS grid i.e., the line connecting the generation project switchyard to the grid and the step-up transformers at the grid station. Provided that, ‘N-1’ criteria shall be applicable in case of renewable generation projects with storage, which are firm in nature and fully dispatchable. Provided that, ‘N-1’ reliability criteria may be considered for ICTs at the ISTS / STU pooling stations for renewable energy based generation of more than 1000 MW after considering the capacity factor of renewable generating stations. Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064 and Published by the Controller of Publications, Delhi-110054

Continue your research