See Full Document Text
रजिस्ट्री स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99
सी.जी.-डी.एल.-अ.-07122023-250473
xxxGIDHxxx
CG-DL-E-07122023-250473
xxxGIDExxx
असाधारण
EXTRAORDINARY
भाग III—खण् ड 4
PART III—Section 4
प्राजधकार स ेप्रकाजित
PUBLISHED BY AUTHORITY
स.ं 818] नई दिल्ली, बुधवार, दिसम्बर 6, 2023/अग्रहायण 15, 1945
No. 818] NEW DELHI, WEDNESDAY, DECEMBER 6, 2023/AGRAHAYANA 15, 1945
dsUæh; fo|qr fofu;ked vk;ksx
अजधसचू ना
नई दिल्ली, 27 नवम् बर, 2023
l-abZdks&,e11@2023&dsfofovk Þforj.k vuqKfIr/kkfj;ks a }kjk ÅtkZ dh mikfIRk ds fy, cksyh çfØ;k }kjk VSfjQ
—
dk vo/kkj.k djus gsrq ekxZn'kZd fl)karß ls lacaf/kr fo|qr ea=ky; dh le;≤ ij ;Fkkla'kksf/kr
rkjh[k 19-01-2005 dh vf/klwpuk ds [kaM 5-6 ¼vi½ ds vuqlj.k esa] dsUnzh; fo|qr fofu;ked vk;ksx dks fo|qr ea=ky;
ds i= fnukad 13-04-2022 vkSj **'kfDr ¼Hkkjr esa dks;yk] ikjn'khZ :Ik es a vkcafVr djus okys vkSj gkuZsflax ds fy,
;kstuk½ uhfr** fnukad 06-03-2019 ds ch¼I½] ch¼III½ vkSj ch¼IV½ ds v/khu dks;ys ds vkcaVu lfgr ekWMy cksyh
nLrkostksa ds v/khu ;FkkçnÙk fMtkbu] fuekZ.k] foÙk] LokfeRo vkSj çpkyu ¼Mhch,Qvksvks½ vk/kkj vkSj lzksr bZa/ku ij
LFkkfir FkeZy ikoj LVs'kuks a ls fo|qr dh nh?kZdkfyd mikfIr ds fy, ekxZfuns'Z k** ds la'kks/ku ij fnukad 11-07-2022 ds
çLrko ds vuqlj.k esa] dsfofovk] Hkqxrku ds iz;kstu ds fy, fuEufyf[kr o`f) njks a dks vf/klwfpr djrk gSA
mijkäs ekxZfunsZ'kkas ds varxZr gq, ÅtkZ Ø; djkj ds vuqlkj forj.k vuqKfIr/kkfj;ks a }kjk ÅtkZ dh mikfIRk ds
fy, lank; ds ç;kstu ds fy, uoEcj] 2023 gsrq ykxw ekfld o`f) njs%a
Ø-l-a fooj.k Hkqxrku grs q ekfld o`f) nj
1- vk;kfrr dks;ys ds fy, o`f) nj 9.47%
2- vk;kfrr dks;ys ds ifjogu ds fy, o`f) nj 0.72%
3- vk;kfrr dks;ys dh varnZs'kh; mBkbZ&/kjkbZ ds fy, o`f) nj 0.03%
gjizhr flag çqFkh] lfpo
[जवज्ञापन-III/4/असा./600/2023-24]
7534 GI/2023 (1)2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4]
CENTRAL ELECTRICITY REGULATORY COMMISSION
NOTIFICATION
New Delhi, the 27th November, 2023
No. Eco-M11/2023-CERC—In pursuance of Clause 5.6 (vi) of Ministry of Power (MOP) Notification on
“Guidelines for Determination of Tariff by Bidding Process for Procurement of Power by Distribution Licensees”
dated 19.01.2005 as amended from time to time, MOP communication to the Central Electricity Regulatory
Commission (CERC) dated 13.04.2022, and MOP Resolution dated 11.07.2022 on amendment to the “Guidelines for
long term Procurement of Electricity from Thermal Power Stations set up on Design, Build, Finance, Own and
Operate (DBFOO) basis and sourcing fuel as provided under Model Bidding Documents including allocation of coal
under B (I), B(III) and B(IV) of SHAKTI (Scheme for Harnessing and Allocating Koyala (Coal) Transparently in
India) Policy” dated 6.03.2019, the CERC notifies the following escalation rates for the purpose of payment.
Monthly Escalation Rates applicable for November 2023 for the purpose of payment for Procurement of Power
by Distribution Licensees as per the Power Purchase Agreement entered into under the Guidelines mentioned
above:—
Sr. No. Description Monthly Escalation Rates
for Payment
1 Escalation rate for imported coal 9.47%
2 Escalation rate for transportation of imported coal 0.72%
3 Escalation rate for inland handling of imported coal 0.03%
HARPREET SINGH PRUTHI, Secy.
[ADVT.-III/4/Exty./600/2023-24]