Home India Central Electricity Regulatory Commission In pursuance of Clause 5 6 vi of the Ministry of Power MOP N...
Date: 07-Feb-2024 Category: Extra Ordinary State: Union Government Country: India

In pursuance of Clause 5 6 vi of the Ministry of Power MOP Notification on Guidelines for Determination of Tariff by Bidding Process for Procurement

Issued by Central Electricity Regulatory Commission · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task

Executive Summary & Key Takeaways

What it means

  • The notification issued by the Central Electricity Regulatory Commission (CERC) announces the escalation rates applicable for January 2024, which will be used for payments related to power procurement by distribution licensees. These rates pertain to imported coal, its transportation, and inland handling.

Key Changes

  • The escalation rate for imported coal is set at -2.08%.
  • The escalation rate for the transportation of imported coal is set at -10.33%.
  • The escalation rate for the inland handling of imported coal is set at 0.53%.
  • These rates are applicable for payments made under Power Purchase Agreements (PPAs) as per the guidelines issued by the Ministry of Power (MOP).

Impact Analysis

Distribution Licensees

  • Action Item: Distribution licensees should update their payment calculations for January 2024 to reflect these revised escalation rates as per their PPAs.

Thermal Power Plants

  • Action Item: Thermal power plants should review their contracts and financial models to assess the impact of these escalation rates on their profitability.

Consumers

  • Action Item: Monitor tariff adjustments by distribution licensees to understand the direct impact on consumer electricity bills.

Key Entities Referenced

Central Electricity Regulatory Commission (CERC): The regulatory body that issued the notification and determines the escalation rates for power procurement. Ministry of Power (MOP): The government ministry that issued the original guidelines for tariff determination and long-term power procurement, and communicated with CERC regarding the escalation rates. Distribution Licensees: Entities responsible for procuring and distributing electricity to consumers. Thermal Power Stations: Power plants that generate electricity using thermal energy, particularly those that rely on imported coal. SHAKTI (Scheme for Harnessing and Allocating Koyala (Coal) Transparently in India) Policy: A policy related to the allocation of coal in India. Guidelines for Determination of Tariff by Bidding Process for Procurement of Power by Distribution Licensees: Guidelines issued by the Ministry of Power (MOP) on 19.01.2005, as amended from time to time, regarding the determination of tariff by bidding process for procurement of power by distribution licensees Guidelines for long term Procurement of Electricity from Thermal Power Stations set up on Design, Build, Finance, Own and Operate (DBFOO) basis: Guidelines for long term Procurement of Electricity from Thermal Power Stations set up on Design, Build, Finance, Own and Operate (DBFOO) basis and sourcing fuel as provided under Model Bidding Documents including allocation of coal under B (I), B(III) and B(IV) of SHAKTI (Scheme for Harnessing and Allocating Koyala (Coal) Transparently in India) Policy” dated 6.03.2019
Official Source Record View Original Source →
See Full Document Text
रजिस्ट्री स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99 ससीी..जजीी..--डडीी..एएलल..--अअ..--0077002222002244--225511992233 xxxGIDHxxx CCGG--DDLL--EE--0077002222002244--225511992233 xxxGIDExxx असाधारण EXTRAORDINARY भाग III—खण्ड 4 PART III—Section 4 प्राजधकार स ेप्रकाजित PUBLISHED BY AUTHORITY स.ं 85] नई दिल्ली, बुधिार, फरिरी 7, 2024/माघ 18, 1945 No. 85] NEW DELHI, WEDNESDAY, FEBRUARY 7, 2024/MAGHA 18, 1945 ubZ fnYyh] 28 tuojh] 2024 .—Þforj.k vuqKfIr/kkfj;ksa }kjk ÅtkZ dh mikfIRk ds fy, cksyh çfØ;k }kjk VSfjQ dk vo/kkj.k djus gsrq ekxZn'kZd fl)karß ls lacaf/kr fo|qr e=a ky; dh le;≤ ij ;Fkkla'kksf/kr rkjh[k 19-01-2005 dh vf/klwpuk ds [kaM 5-6 ¼vi½ ds vulq j.k esa] dsUnhz; fo|qr fofu;ked vk;ksx dk s fo|qr e=a ky; ds i= fnukad 13-04-2022 vkSj **'kfDr ¼Hkkjr eas dks;yk] ikjn'khZ :Ik eas vkcafVr djus okys vkSj gkusZflax ds fy, ;kstuk½ uhfr** fnukad 06-03-2019 ds ch¼I½] ch¼III½ vkSj ch¼IV½ ds v/khu dk;s ys ds vkcaVu lfgr ekWMy cksyh nLrkostks a ds v/khu ;FkkçnÙk fMtkbu] fuekZ.k] foÙk] LokfeRo vkSj çpkyu ¼Mhch,Qvksvks½ vk/kkj vkSj lzksr bZa/ku ij LFkkfir FkeyZ ikoj LVs'kuks a ls fo|qr dh nh?kZdkfyd mikfIr ds fy, ekxZfunsZ'k** ds la'kk/s ku ij fnukad 11-07-2022 ds çLrko ds vuqlj.k eas] dsfofovk Hkqxrku ds iz;kstu ds fy, fuEufyf[kr o`f) njks a dks vf/klwfpr djrk gSA 1- vk;kfrr dks;ys ds fy, o`f) nj (-)2.08% 2- vk;kfrr dks;ys ds ifjogu ds fy, o`f) nj (-)10.33% 3- vk;kfrr dks;ys dh varnZ's kh; mBkbZ&/kjkbZ ds fy, o`f) nj 0.53% gjizhr flag çqFkh] lfpo [जिज्ञापन-III/4/असा./738/2023-24] 853 GI/2024 (1)2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] CENTRAL ELECTRICITY REGULATORY COMMISSION NOTIFICATION New Delhi, the 28th January, 2024 No. Eco-M01/2024-CERC.—In pursuance of Clause 5.6 (vi) of the Ministry of Power (MOP) Notification on “Guidelines for Determination of Tariff by Bidding Process for Procurement of Power by Distribution Licensees” dated 19.01.2005 as amended from time to time, MOP communication to the Central Electricity Regulatory Commission (CERC) dated 13.04.2022, and MOP Resolution dated 11.07.2022 on an amendment to the “Guidelines for long term Procurement of Electricity from Thermal Power Stations set up on Design, Build, Finance, Own and Operate (DBFOO) basis and sourcing fuel as provided under Model Bidding Documents including allocation of coal under B (I), B(III) and B(IV) of SHAKTI (Scheme for Harnessing and Allocating Koyala (Coal) Transparently in India) Policy” dated 6.03.2019, the CERC notifies the following escalation rates for the purpose of payment. Monthly Escalation Rates applicable for January 2024 for the purpose of payment for Procurement of Power by Distribution Licensees as per the Power Purchase Agreement entered into under the Guidelines mentioned above: Sr. No. Description Monthly Escalation Rates for Payment 1 Escalation rate for imported coal (-)2.08% 2 Escalation rate for transportation of imported coal (-)10.33% 3 Escalation rate for inland handling of imported coal 0.53% HARPREET SINGH PRUTHI, Secy. [ADVT.-III/4/Exty./738/2023-24] Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064 and Published by the Controller of Publications, Delhi-110054.