रजिस्ट्री स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99
सी.जी.-डी.एल.-अ.-25032025-261941
xxxGIDHxxx
CG-DL-E-25032025-261941
xxxGIDExxx
असाधारण
EXTRAORDINARY
भाग III—खण् ड 4
PART III—Section 4
प्राजधकार स ेप्रकाजित
PUBLISHED BY AUTHORITY
स.ं 238] नई दिल्ली, मगं लिार, मार् च25, 2025/र्त्रै 4, 1947
No. 238] NEW DELHI, TUESDAY, MARCH 25, 2025/CHAITRA 4, 1947
ubZ fnYyh] 5 ekpZ] 2025
.—Þforj.k vuqKfIr/kkfj;ks a }kjk ÅtkZ dh mikfIRk ds fy, cksyh çfØ;k }kjk
VSfjQ dk vo/kkj.k dju s gsrq ekxZn'kZd fl)karß ls lacaf/kr fo|qr ea=ky; dh le;≤ ij ;Fkkla'kksf/kr
rkjh[k 19-01-2005 dh vf/klwpuk ds [kaM 5-6 ¼vi½ ds vuqlj.k eas] dsUnzh; fo|qr fofu;ked vk;ksx dk s fo|qr ea=ky; ds
i= fnukad 13-04-2022 vkSj **'kfDr ¼Hkkjr eas dks;yk] ikjn'khZ :Ik eas vkcafVr dju s oky s vkSj gkusZflax ds fy, ;kstuk½
uhfr** fnukad 06-03-2019 ds ch¼I½] ch¼III½ vkSj ch¼IV½ ds v/khu dk;s y s ds vkcaVu lfgr ekWMy cksyh nLrkostks a ds v/khu
;FkkçnÙk fMtkbu] fuekZ.k] foÙk] LokfeRo vkSj çpkyu ¼Mhch,Qvksvks½ vk/kkj vkSj lzksr bZa/ku ij LFkkfir FkeZy ikoj
LVs'kuks a ls fo|qr dh nh?kZdkfyd mikfIr ds fy, ekxZfunsZ'k** ds la'kks/ku ij fnukad 11-07-2022 ds çLrko ds vuqlj.k eas]
dsfofovk Hkqxrku ds iz;kstu ds fy, fuEufyf[kr o`f) njks a dks vf/klwfpr djrk gSA
1- vk;kfrr dks;y s ds fy, o`f) nj (-)3.85%
2- vk;kfrr dks;y s ds ifjogu ds fy, o`f) nj 6.23%
3- vk;kfrr dks;y s dh varnZs'kh; mBkbZ&/kjkbZ ds fy, o`f) nj (-)0.12%
gjizhr flag çqFkh] lfpo
[जिज्ञापन-III/4/असा./1096/2024-25]
2028 GI/2025 (1)2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4]
CENTRAL ELECTRICITY REGULATORY COMMISSION
NOTIFICATION
New Delhi, the 5th March, 2025
No. Eco-M2/2025-CERC.—In pursuance of Clause 5.6 (vi) of the Ministry of Power (MOP) Notification on
“Guidelines for Determination of Tariff by Bidding Process for Procurement of Power by Distribution Licensees”
dated 19.01.2005 as amended from time to time, MOP communication to the Central Electricity Regulatory
Commission (CERC) dated 13.04.2022, and MOP Resolution dated 11.07.2022 on an amendment to the “Guidelines
for long term Procurement of Electricity from Thermal Power Stations set up on Design, Build, Finance, Own and
Operate (DBFOO) basis and sourcing fuel as provided under Model Bidding Documents including allocation of coal
under B (I), B(III) and B(IV) of SHAKTI (Scheme for Harnessing and Allocating Koyala (Coal) Transparently in
India) Policy” dated 6.03.2019, the CERC notifies the following escalation rates for the purpose of payment.
Monthly Escalation Rates applicable for February 2025 for the purpose of payment for Procurement of Power
by Distribution Licensees as per the Power Purchase Agreement entered into under the Guidelines mentioned
above:
Sr. Description Monthly Escalation Rates
No. for Payment
1 Escalation rate for imported coal (-)3.85%
2 Escalation rate for transportation of imported coal 6.23%
3 Escalation rate for inland handling of imported coal (-)0.12%
HARPREET SINGH PRUTHI, Secy.
[ADVT.-III/4/Exty./1096/2024-25]