**Executive Summary**
The Ministry of New and Renewable Energy (MNRE) supports Bioenergy Projects under the National Bioenergy Programme (NBP), Phase-I, notified on November 2, 2022, with a budget of Rs. 998 Crore for 2022-23 to 2025-26. The announcement, made in Lok Sabha on December 17, 2025, details the Central Financial Assistance (CFA) provided for setting up bioenergy projects. Annexure-II provides details on bioenergy projects installed state-wise in the last ten years.
**Key Points / Main Content**
* **National Bioenergy Programme (NBP) Phase-I**
* Supports Bioenergy Projects with a budget outlay of Rs. 998 Crore for the period 2022-23 to 2025-26.
* **Central Financial Assistance (CFA) for Bioenergy Projects (Annexure-I):**
* **Biogas generation:** Rs 0.25 Crore per 12000 cum/day.
* **BioCNG generation:**
* Rs 4.0 Crore per 4800 kg/day (for BioCNG generation from new biogas plant).
* Rs 3.0 Crore per 4800 kg/day (for BioCNG generation from existing biogas plant).
* **Power generation based on Biogas:**
* Rs 0.75 Crore/MW (for power generation from new biogas plant).
* Rs 0.5 Crore/MW (for power generation from existing Biogas plant).
* **Power based on bio & agro-industrial waste:** Rs 0.4 Crore/MW.
* **Biomass Gasifier:** Rs. 2,500 per kWe with dual fuel engines for electrical application, Rs. 15,000 per kWe with 100% gas engines for electrical application, Rs. 2 lakh per 300 kWth for thermal applications.
* **Biomass Programme:**
* **Briquette manufacturing plants:** Rs. 9.00 Lakhs/ TPH (Maximum CFA- Rs. 45.00 Lakh per project).
* **Non-Torrefied Pellet manufacturing plant:** Rs. 21 lakhs/MTPH production capacity or 30% of the capital cost, whichever is lower (Maximum Rs. 105 lakhs per project).
* **Torrefied Pellet manufacturing plant:** Rs. 42 lakhs/MTPH production capacity or 30% of the capital cost, whichever is lower (Maximum Rs. 210 lakhs per project).
* **Non-Bagasse Cogeneration Projects:** Rs. 40 Lakhs/ Megawatt (Maximum CFA- Rs. 5.00 Crore per project).
* **Biogas Programme:**
* **Small biogas plants (1-25 cubic meter/day):** Rs. 9,800/- to Rs. 70,400/- per plant based on size.
* **Power generation and thermal application (25 - 2500 cubic meter/day):** Rs. 35,000/- to Rs. 45,000/- per kilowatt for power generation and Rs. 17,500/- to Rs. 22,500/- per kilowatt equivalent for thermal applications.
* 20% higher than Standard CFA in for NER, Island, Registered Gaushalas and SC/ST beneficiaries.
* **Installed Bioenergy Projects (Annexure-II):** State-wise capacity (MW) for biomass projects, capacity (MWe) for waste to energy projects and number of biogas plants.
**Impact Analysis**
**Bioenergy Project Developers**
* **Impact**: The announcement provides clarity on the available financial assistance for setting up new bioenergy projects or expanding existing ones.
* **Action Required**: Review the CFA details to assess project viability and submit applications as appropriate.
**Existing Bioenergy Plant Operators**
* **Impact**: The details on central financial assistance can help in expansion of existing plants or diversifying into new bioenergy projects.
* **Action Required**: Review the CFA details to assess project viability and submit applications as appropriate.
**Lok Sabha**
* **Impact**: The information provides an update on the progress of bioenergy projects in the country for the last ten years.
* **Action Required**: Review Financial Assistance for Bio-Energy Programme answered on 17.12.2025.
Key Entities Referenced
National Bioenergy Programme (NBP), Phase-I: Scheme supporting installation of Bioenergy Projects in India, notified on 02.11.2022, with a budget of Rs. 998 Crore for 2022-23 to 2025.26.
Ministry of New and Renewable Energy: The central ministry supporting the installation of bioenergy projects.
National Biogas and Manure Management Programme (NBMMP): A Scheme supporting Bioenergy Projects during 12th Five Year Plan.
New National Biogas & Organic Manure Programme (NNBOMP): A Scheme supporting Bioenergy Projects during 2018-19 to 2020-21.
Lok Sabha: Parliamentary house where the information regarding the bioenergy projects was submitted.
Ministry of New and Renewable Energy
India Adds 2,361 MW Biomass Capacity, 228
MWe Waste-to-Energy and 2.88 Lakh Biogas
Plants in Last Ten Years
प्रव तथ: 17 DEC 2025 12:45PM by PIB Delhi
Ministry of New and Renewable Energy supports installation of Bioenergy Projects in the country under
National Bioenergy Programme (NBP), Phase-I, which was notified on 02.11.2022, with a budget outlay
of Rs. 998 Crore, for the period 2022-23 to 2025.26. The details of Central Financial Assistance (CFA)
provided is given at Annexure-I.
During the last ten years, the Government has been supporting Bioenergy Projects through various
Schemes, namely National Biogas and Manure Management Programme (NBMMP) during 12th Five
Year Plan, New National Biogas & Organic Manure Programme (NNBOMP) from 2018-19 to 2020-21,
Scheme to support promotion of Grid interactive Biomass Power and Bagasse cogeneration in sugar mills
during 12th Plan Period, Programme on Energy from Urban, Industrial and Agricultural Wastes /Residues
during 12th Plan period, Scheme to support Promotion of Biomass based Cogeneration in Sugar Mills and
other Industries in the Country from 2018-19 to 2020-21.
The details of bioenergy projects installed in the country during the last ten years, State-wise, is given at
Annexure-II. Further, new bioenergy projects are being promoted under the NBP Phase-I.
This information was submitted by Union Minister of State for New and Renewable Energy Shri Shripad
Yesso Naik in a written reply in Lok Sabha today.
Annexure-I
The existing CFA Support for setting up of Bioenergy Projects in the country under National
Bioenergy Programme is given as under:
Waste to Energy Programme CFA in Rs Crore
Biogas generation Rs 0.25 Crore per 12000cum/day
BioCNG generation Rs 4.0 Crore per 4800 kg/day (for BioCNG generation from new
biogas plant)
Rs 3.0 Crore per 4800 kg/day (for BioCNG generation from
existing Biogas plant)
Power generation based on Rs 0.75 Crore/MW (for power generation from new biogas plant)
Biogas
Rs 0.5 Crore/MW (for power generation from existing Biogas plant)Power based on bio & agro- Rs 0.4 Crore/MW
industrial waste
Biomass Gasifier Rs. 2,500 per kWe with dual fuel engines for electrical application
Rs. 15,000 per kWe with 100% gas engines for electrical application
Rs. 2 lakh per 300 kWth for thermal applications
Biomass Programme CFA
Briquette manufacturing plants Rs. 9.00 Lakhs/ TPH
(Maximum CFA- Rs. 45.00 Lakh per project).
Non-Torrefied Pellet Rs. 21 lakhs/MTPH production capacity or 30% of the capital cost
manufacturing plant considered for plant and machinery of 1 TPH plant, whichever is
lower (Maximum Rs. 105 lakhs per project)
Torrefied Pellet manufacturing Rs. 42 lakhs/MTPH production capacity or 30% of the capital cost
plant considered for plant and machinery of 1 TPH plant, whichever is
lower (Maximum Rs. 210 lakhs per project)
Non-Bagasse Cogeneration Rs. 40 Lakhs/ Megawatt
Projects
Maximum CFA- Rs. 5.00 Crore per project).
Biogas Programme CFA
For small biogas plants (1-25 Rs. 9,800/- to Rs. 70,400/- per plant based on size of the plant in
cubic meter/day plant capacity): cubic meter
For Power generation and Rs. 35,000/- to Rs. 45,000/- per kilowatt for power generation
thermal application (25 - 2500
Rs. 17,500/- to Rs. 22,500/- per kilowatt equivalent for thermal
cubic meter/day plant capacity):
applications.
Note: 20% higher than Standard CFA in for NER, Island, Registered
Gaushalas and SC/ST beneficiaries);
Annexure-II
REFERRED TO IN REPLY TO THE LOK SABHA UNSTARRED QUESTION NO. 2809, Part (d)
TO BE ANSWERED ON 17.12.2025 on ‘Financial Assistance for Bio-Energy Programme’.The details of bioenergy projects installed in the country during the last ten years is given as under:
Biomass Projects Waste to Energy Biogas Plants
Projects
Sl No State Capacity (MW) Capacity (MWe) Nos
1 Andhra Pradesh 35.1 35.95 28505
2 Arunachal Pradesh 0 0 349
3 Assam 2 0 23612
4 Bihar 39.8 0.32 236
5 Chhattisgarh 54 0 11030
6 Goa 0 1 140
7 Gujarat 12 15.2 5427
8 Haryana 87.4 17.39 3487
9 Himachal Pradesh 1.5 0 294
10 Jharkhand 14.8 1.04 545
11 Karnataka 536.81 8.41 34657
12 Kerala 1.55 0.23 9639
13 Madhya Pradesh 31.2 5.86 32120
14 Maharashtra 1073.5 24.26 71653
15 Manipur 0 0 25
16 Meghalaya 0 0 867
17 Mizoram 0 0 648
18 Nagaland 0 0 102
19 Odisha 0.6 0 596620 Punjab 140.29 21.77 19288
21 Rajasthan 19.85 1.19 2404
22 Sikkim 0 0 170
23 Tamil Nadu 112.55 8.68 1740
24 Telangana 4.03 9.79 11159
25 Tripura 0 0 546
26 Uttarakhand 12.5 6.89 8362
27 Uttar Pradesh 146.6 41.34 3594
28 West Bengal 31.6 4.06 851
29 Andaman and Nicobar 0 0 0
Islands
30 Chandigarh 0 0 0
31 Dadra and Nagar 3.75 0 18
Haveli and Daman &
Diu
32 NCT of Delhi 0 24.17 0
33 Jammu & Kashmir 0 0 101
34 Ladakh 0 0 0
35 Lakshadweep 0 0 0
36 Puducherry 0 0 0
37 Others 0 0 10544
Total 2361.43 227.56 288079
***