PIB Backgrounder
Ken-Betwa Link Project
Frequently Asked Questions (FAQs)
प्रव तथ: 21 AUG 2026 4:25PM by PIB Delhi
About the Project
1. What is the Ken-Betwa Link Project?
The Ken–Betwa Link Project (KBLP) is a major water-resources development project intended to
address the long-standing water scarcity and irrigation challenges of the Bundelkhand region of
Madhya Pradesh and Uttar Pradesh.
The project envisages transfer of water from the Ken basin to the Betwa basin through a system
comprising the Daudhan Dam, link canal and associated works. KBLP is the first priority project
under the National Perspective Plan for Interlinking of Rivers to enter the implementation stage.
2. What is the scheme of the project?
This project involves transfer of water from the Ken to the Betwa River through construction of
the 96.7 m high Daudhan Dam on the Ken River in Panna and Chhatarpur districts of Madhya
Pradesh, about 40 km from Khajuraho. A 216.465 km-long Ken–Betwa Link Canal will take off
near the Daudhan Dam and merge into Barua Sagar near Jhansi. Other components include the
Lower Orr Project, Kotha Barrage, and Bina Complex Multipurpose Project.
The Project also includes various irrigation and water infrastructure works to be implemented by
the Governments of Uttar Pradesh and Madhya Pradesh, including modernization and
strengthening of existing canal systems, renovation of tanks and weirs, construction of barrages,
development of pumping and pressurized pipe/micro-irrigation systems, stabilization and
development of new command areas, and implementation of associated water supply and irrigation
projects.
3. What is the total cost of the project
The total cost of the project is ₹44,605 crore.
4. What is the status of this project
The foundation stone of the project was laid by Hon’ble Prime Minister Shri Narendra Modi on
25th December 2024. The dam is under construction, while work on the canal is yet to begin. The
Lower Orr Project, Kotha Barrage, and Bina Complex Multipurpose Project are under
construction. Preparation of DPR of other state-specific projects of MP and UP is also under
finalisation stage. The Project is scheduled for completion in 2030.
5. Why is this project needed?Bundelkhand region has historically faced recurrent water scarcity, dependence on rainfall,
inadequate irrigation facilities, declining groundwater availability in several areas and vulnerability
of agriculture to drought.
The Ken Betwa Link Project is designed to provide more dependable water availability for
irrigation and drinking-water requirements while also generating renewable energy and supporting
broader regional development. The project is therefore not merely an irrigation project; it is
envisaged as a comprehensive water-security and regional-development initiative for
Bundelkhand.
6. What are the main benefits of the project?
The Project will provide irrigation to 10.62 lakh ha, drinking water to about 62 lakh people, and
generate 103 MW of hydropower and 27 MW of solar power. Thus, it will supply clean drinking
water, electricity, and reliable year-round irrigation across vast farmlands in Madhya Pradesh and
Uttar Pradesh, permanently resolving the long-standing water crisis in the Bundelkhand region.
7. Which areas will benefit from this project?
The project will benefit the water-starved Bundelkhand region across Madhya Pradesh and Uttar
Pradesh, covering districts such as Chhatarpur, Newari, Tikamgarh, Panna, Sagar, Damoh, Datia,
Vidisha, Shivpuri, and Raisen in M.P., and Banda, Mahoba, Jhansi and Lalitpur in U.P.
8. Will the Ken–Betwa Link Project create new jobs in the local area?
Yes. The Ken–Betwa Link Project (KBLP) is generating employment opportunities in the local
area, particularly during the ongoing construction phase. Employment is being generated in civil
construction, engineering, transportation, material supply, equipment operation, security, services
and other ancillary activities. Local shops, transporters, suppliers and service providers are alsobenefiting from increased economic activity. In the long term, improved irrigation and water
availability will support agriculture and allied activities, creating further livelihood and
employment opportunities in the region.
9. How will the Ken–Betwa Link Project improve agriculture in Bundelkhand?
The Ken–Betwa Link Project is providing more reliable irrigation water, reducing dependence on
uncertain rainfall and helping farmers plan agricultural activities with greater confidence. The
improved availability of irrigation water is expected to support increased cropping intensity, higher
crop productivity, crop diversification, cultivation of high-value crops, reduced vulnerability to
drought and improved farm incomes, thereby strengthening rural livelihoods in the Bundelkhand
region.
10. Will KBLP eliminate drought in Bundelkhand?
It would not be appropriate to claim that the project will completely eliminate drought.
Rather, KBLP is intended to substantially improve water security and drought resilience in its
command and beneficiary areas by providing dependable irrigation and drinking-water support.
11. Will groundwater levels improve?
The availability of surface water for irrigation and other uses can reduce excessive dependence on
groundwater in appropriate areas. The project also envisages rejuvenation/feeding of tanks along
the link canal, wherever technically feasible, which can contribute to groundwater recharge and
local water security.
Actual groundwater improvement will depend on local hydrogeological conditions and sustainable
groundwater-use practices.
12. How does the wider region gain from this development?
By protecting crops from drought, it will boost harvests, reduce losses, and raise family incomes
for farmers, while better utilities and transport links create new jobs and uplift everyday living
standards for the entire community. It is expected to boost socio-economic prosperity in this
backward region through increased agricultural activities, employment generation, and reduced
distress migration. Better infrastructure attracts new schools, healthcare clinics, commercial
markets, and agro-industries, transforming the area into a prosperous one.
13. Will downstream villages face any water shortage?
No. Continuous minimum environmental water release is strictly maintained around the year to
ensure that downstream farming, drinking water needs, and aquatic ecosystems remain
undisturbed. Similarly, the water infrastructure created under the region would also enhance the
groundwater in the region.
14. How are flood risks managed during heavy monsoons?
The dam will act as a cushion against floods. Its automated spillway gates and 24/7 control rooms
monitor water inflow to prevent sudden flooding in low-lying villages.
15. Are the benefits of KBLP greater than its impacts?
The project has been evaluated through the prescribed technical, economic, environmental and
social assessment processes. KBLP is intended to deliver large-scale benefits in irrigation, drinking
water and renewable energy while implementing mitigation and R&R measures for unavoidable
impacts.The appropriate approach is therefore not to ignore the impacts, but to minimize, mitigate,
compensate and responsibly manage them while delivering the intended public benefits.
16. Is the Ken–Betwa Link Project beneficial only to farmers?
No. The Ken–Betwa Link Project (KBLP) provides benefits beyond irrigation to farmers. It
supports farmers through irrigation facilities; rural and urban populations through drinking water
supply; the energy sector through hydropower generation; and local communities through
employment, infrastructure and increased economic activity. Overall, the project is strengthening
water security, agricultural development and socio-economic growth in the Bundelkhand region.
17. Will KBLP improve transportation infrastructure?
Major water infrastructure projects require construction and improvement of access roads, bridges,
approaches and other associated infrastructure. Where such infrastructure is developed or upgraded
as part of the project, it will facilitate improved connectivity to nearby areas.
18. Will project roads benefit local communities?
Project-related roads and connectivity infrastructure will facilitate secondary benefits to
surrounding communities and people at large such as:
movement of agricultural produce;
access to markets;
access to schools and healthcare;
construction and economic activities;
movement of people and goods; and
access to project facilities.
19. Will KBLP directly develop a new transport corridor?
KBLP is primarily a water-resource and energy project. Any transport-related benefit should
therefore be described in terms of project-associated roads, bridges and improved connectivity,
rather than presenting KBLP as a dedicated transport project unless a particular transport facility
has been formally approved as part of the project.
20. Why is drinking-water supply an important component of the Ken–Betwa Link Project
(KBLP)?
Drinking-water supply is an important component of KBLP because water security is essential not
only for agriculture but also for the well-being of rural and urban communities. Reliable drinking
water helps improve public health, sanitation and household security, reduces the time spent by
families, particularly women, in collecting water, and supports education, livelihoods and overall
quality of life. Thus, KBLP has both agricultural and human-development benefits.
Land, Villages and People Affected
21. Why is land required for the Ken–Betwa Link Project (KBLP)?
Land is required for construction and development of various permanent and temporary project
components of KBLP, including the Daudhan Dam and its appurtenant structures,
reservoir/submergence area, Ken–Betwa Link Canal, powerhouses, access roads, project
infrastructure, colonies, construction facilities and other ancillary works required for
implementation of the project.
22. How many villages are affected by the project in Madhya Pradesh?
22 villages are affected — 8 in Panna district and 14 in Chhatarpur district.23. Whether a public hearing was conducted for the Ken–Betwa Link Project?
Yes. Public hearings were conducted as part of the Environmental Clearance process for the Ken–Betwa
Link Project, in accordance with the provisions of the EIA Notification, 2006. The concerns and
suggestions raised by the local people and other stakeholders during the public hearing process were
considered while finalizing the environmental assessment and mitigation measures for the project.
24. Is land being taken without the consent of the people?
No. The Land acquisition is being taken as per the LARR Act 2013 and other state-applicable laws
of GoMP. The consents have been obtained as per the Act and accordingly the rehabilitation plan is
being implemented. Under this project, a comprehensive R&R package has been announced by
GoMP under which all R&R works are being undertaken. The rehabilitation plan is consent-based,
and all affected families were given a choice between compensation under the normal land
acquisition law or a more generous Special Package.
25. How will disputes regarding land ownership be handled?
Land ownership and entitlement issues are dealt with by competent revenue and land-acquisition
authorities headed by the District Collector. Where there are disputes regarding title, succession,
ownership or entitlement, the matter is processed in accordance with applicable law and
established administrative/judicial procedures.
Compensation and the Special Rehabilitation Package
26. Whether any special package for R&R under KBLP has been announced by GoMP?
Yes, the GoMP announced a Special Package for the Resettlement and Rehabilitation of Project
Affected Families (PAFs) in 2023. Under the Special Package, compensation for acquired land is
paid at either the rate determined by the Act or ₹12.50 lakh per hectare, whichever is higher, with
compensation for houses, trees, wells, tube wells and other immovable assets similarly determined
under the Act. Eligible families are receiving a grant of ₹7 lakh for a plot in rural areas (₹6.50 lakh
in urban areas), or lump-sum assistance of ₹12.50 lakh where a plot is not opted for; eligible
Scheduled Caste and Scheduled Tribe families in scheduled areas receive additional financial
assistance under the approved package.
27. Who is considered a Project Affected Family (PAF) for getting R&R assistance under the
LARR Act, 2013?
A Project Affected Family means a family whose land, house, property, forest rights, or main
source of livelihood is affected due to land acquisition for the project.
It includes:
Landowners whose land is acquired;
Persons whose livelihood is affected due to the acquisition;
Tenants, agricultural labourers and share-croppers whose livelihood is affected;
Scheduled Tribes and traditional forest dwellers whose recognised forest rights are affected; and
Other eligible families covered under Section 3(c) of the RFCTLARR Act, 2013.
Such families may be eligible for Rehabilitation & Resettlement (R&R) benefits as provided under
the Act and applicable rules.
28. How is a family unit counted for R&R benefits in KBLP?
As per Section 3(m) of the LARR Act, 2013, a family includes the person, his/her spouse, minor
children and dependent minor brothers and sisters.For R&R benefits, the following are treated as separate family units:
Adult sons or daughters (18 years or above), whether married or unmarried.
Widows, divorcees and women deserted by their families are treated as separate families.
Thus, in KBLP, the number of PAFs is determined by identifying the eligible family units as per
the LARR Act, 2013, based on the survey and verification of affected families.
29. What support is available under KBLP for families who do not own land but whose livelihood
is affected by the project?
Under the LARR Act, 2013, land ownership is not the only basis for R&R benefits. Eligible
landless families whose main source of livelihood is affected due to KBLP have also been
considered as Project Affected Families (PAFs), subject to the eligibility conditions under the Act
and applicable State Government provisions.
Such eligible families are provided R&R benefits as applicable under the approved R&R
provisions of KBLP.
30. How are people assisted in earning their livelihood after relocation?
Under various schemes, they are provided dedicated livelihood restoration programs that provide
vocational and skill-development training, financial grants for self-help groups, small business
assistance, and priority employment in project operations.
31. What compensation do people get for their land?
Families are paid either the rate fixed under the land acquisition law, or ₹12.50 lakh per hectare as
per the Special Package announced by GoMP, whichever amount is higher.
32. What about houses, trees and wells on the land?
Compensation for houses, trees, wells, tube wells and other fixed property is also given, calculated
as per the law.
33. What if a family wants a new house plot instead of just cash?
Eligible families can get a grant of ₹7 lakh for a plot in rural areas, or ₹6.50 lakh in urban areas.
34. What if a family does not want a plot at all?
They can instead choose a one-time lump-sum payment of ₹12.50 lakh per family.
35. Is there extra help for Scheduled Caste and Scheduled Tribe families?
Yes. Eligible SC and ST families living in Scheduled Areas get additional financial assistance on
top of the standard package.
36. Who approved this Special Package?
The Government of Madhya Pradesh approved it on 13 September 2023, following a decision of
the State Cabinet on 9 September 2023.
37. How much compensation has been paid so far?
As of the latest figures, awards worth about ₹360.66 crore have been passed, of which about
₹321.97 crore (around 89%) has already been paid to families. In village-habitation areas alone,
over 94% of the awarded amount has been distributed.
38. What about the total project-wide compensation figures?Across the project, awards worth about ₹629.87 crore have been passed for 5,039 affected
families, and about ₹604.745 crore (around 96%) has already been paid out. The remaining
amount will be released once the required legal formalities are completed.
39. How is land compensation calculated and paid out?
Compensation is calculated transparently based on official market rates plus statutory resettlement
allowances. Payments are transferred directly into verified bank accounts of landowners to prevent
middlemen and unnecessary delays.
40. Are there special healthcare and educational initiatives?
Yes. Regular free medical checkup camps, mobile health vans, school infrastructure upgrades, and
student scholarships are actively provided under ongoing community welfare programs.
41. What is KBLPA's approach towards affected families?
KBLPA recognizes that land acquisition affects not only land and property but also the lives and
livelihoods of affected families. Accordingly, KBLPA is focusing on timely compensation,
rehabilitation and resettlement, livelihood support, relocation wherever required, provision of basic
civic amenities at resettlement sites, consultation with affected persons and grievance redressal.
The objective is to ensure that Project Affected Families are treated with fairness, transparency and
dignity throughout the rehabilitation and resettlement process.
42. Will affected landowners receive compensation?
Yes, Eligible landowners and other persons having recognized rights/interests in land are entitled
to compensation and other admissible benefits in accordance with the applicable statutory
framework.
The compensation process is intended to ensure that affected persons receive the benefits to which
they are legally entitled.
Making Sure No One Is Left Out
43. What happens if someone's name was left out of the compensation list?
The district administration has re-surveyed affected villages in Chhatarpur and Panna at the request
of displaced families, and people who were earlier left out have now been added to the
compensation awards.44. Who checks that the process stays fair and accurate?
The District Administration continuously reviews land records. In addition, a National Monitoring
Committee, set up under the land acquisition law, oversees the entire rehabilitation process.
45. Who helps families with documentation and paperwork?
Dedicated Field Facilitation Officers visit villages weekly to assist families with entitlement
verification, banking paperwork, and application submissions at zero cost.
46. Can affected families still raise complaints or grievances?
Yes. Grievances are regularly received and resolved. For example, the administration has held
special camps to hear and settle complaints from displaced families in the affected villages.
47. What is KBLPA’s message to people affected by the project?
KBLPA’s message is clear: the development of Bundelkhand should go hand in hand with the
rights, dignity and welfare of Project Affected Families. KBLPA is working with the concerned
State Governments, district administrations and affected communities to implement land
acquisition, Rehabilitation & Resettlement (R&R), and environmental measures in accordance
with applicable laws, approved plans and prescribed procedures. The objective is to ensure
fairness, transparency and responsible implementation of the project.
Support for Displaced Families
48. Are the children of displaced families looked after?
Yes. Efforts are made to enrol their children in schools and Anganwadi centres so their education is
not disrupted.
49. Is healthcare support provided to displaced families?
Yes. Health camps have been organised where people are medically examined, medicines are
distributed, and drinking-water handpumps are repaired.
50. Do displaced families get access to other government welfare schemes?
Yes. Special camps are held so families can also benefit from other government schemes, such as
those related to livestock, social security, and welfare schemes for women and girls.
51. Does the government stay in touch with displaced families after they relocate?
Yes, Regular contact is maintained with displaced families so that any difficulty is quickly
identified and their grievances are resolved fairly and speedily.
Rights of Tribal and Forest-Dependent Communities
52. Are the rights of tribal communities protected in this project?
Yes. The rights of Scheduled Tribes and other forest-dependent communities are safeguarded under
the Forest Rights Act, 2006, through a statutory process of recognising and settling forest rights.
53. Was the consent of local communities taken before forest clearance?
The concerned District Collectors initiated the process for obtaining the free, prior and informed
consent of the relevant Gram Sabhas, as required under the Scheduled Tribes and Other Traditional
Forest Dwellers (Recognition of Forest Rights) Act, 2006. It was on this basis, and subject to
compliance with applicable statutory requirements, that Forest Clearance for the project was
accorded by MoEF&CC on 03.10.2023.Environmental and Legal Clearances
54. Has the project received all the required government clearances?
Yes. The project has received all the statutory clearances needed under law, including
Environmental Clearance (2017), Wildlife Clearance (2016), Clearance from the Ministry of Tribal
Affairs (2017), and Forest Clearance (2023).
55. Will KBLP have environmental impacts?
Like any major water-resources infrastructure project, KBLP has environmental impacts that
require careful assessment and management.
The project has therefore incorporated environmental safeguards and an Environmental
Management Plan (EMP), along with compliance with applicable environmental, forest and
wildlife-related requirements.
The approach is based on the principle that development and environmental protection must
progress together.
56. Whether the environmental impacts of KBLP were studied before implementation?
Yes. The environmental impacts of the Ken–Betwa Link Project (KBLP) were assessed through
detailed environmental studies as part of the statutory clearance process. Based on these
assessments, the project was granted Environmental Clearance on 25.08.2017, along with the
required Wildlife Clearance and Forest Clearance, subject to prescribed conditions and mitigation
measures.
The project is also implementing various environmental management, compensatory afforestation,
wildlife conservation and biodiversity protection measures to address and minimize the identified
environmental impacts.
57. How is the loss of forest area and biodiversity in the core area of Panna Tiger Reserve (PTR)
being compensated under KBLP?
The environmental impacts of KBLP, including unavoidable forest loss and impacts on
biodiversity, are being addressed through a combination of compensatory afforestation, wildlife
conservation and habitat management, catchment area treatment and implementation of the
Integrated Landscape Management Plan (ILMP) for the Greater Panna Landscape.
In addition, an equivalent area of non-forest land has been provided adjacent to the core area of
Panna Tiger Reserve for compensatory purposes, which will contribute to strengthening the habitat
and conservation landscape around the Reserve.
Funds have also been provided as per the conditions of the Forest and Wildlife Clearances for
implementing approved conservation and mitigation measures. These measures aim to compensate
for unavoidable forest loss, minimize ecological impacts and strengthen biodiversity and wildlife
conservation in the wider landscape.
58. What is the concern regarding Panna Tiger Reserve?
The project has significant environmental and wildlife considerations because of its proximity and
relationship with the Panna landscape. Accordingly, wildlife and forest-related safeguards have
been incorporated into project planning and implementation.
The Government has also undertaken landscape-level planning and conservation measures in
association with the project.59. What are the measures being taken to protect the environment and the wildlife
The project is aimed at not only providing water security in the Bundelkhand but also ensuring the
overall conservation of the region and especially for landscape-dependent species such as Tiger,
Vulture and Gharial. Apart from taking mitigation measures as per the approved Environmental
Management Plan, the Wildlife Institute of India (WII) has prepared a comprehensive Integrated
Landscape Management Plan (ILMP) for the conservation of wildlife and biodiversity not only in
Panna Tiger Reserve (PTR) but also in surrounding areas. The Integrated Landscape Management
Plan in Greater Panna Landscape (GPL) is one of the major and unique conservation measures
being initiated in the conservation history of India.
60. What is Greater Panna Landscape Council?
A comprehensive Integrated Landscape Management Plan (ILMP) has been prepared for the
conservation of wildlife and biodiversity in Panna Tiger Reserve (PTR) & surrounding areas. To
ensure systematic and time-bound implementation of the Greater Panna Landscape Management
Plan, the Greater Panna Landscape Council (GPLC) has been constituted under the chairmanship
of the Chief Secretary, Govt. of Madhya Pradesh, with members from all the stakeholders.
Adequate financial provisions have been earmarked for the implementation of Environment
Management Plan and Integrated Landscape Management Plan under the Ken-Betwa Link Project.
This model will be a template for future development.
61. What is compensatory afforestation?
Where forest land is diverted for approved project purposes, compensatory afforestation and other
prescribed measures are undertaken in accordance with applicable forest legislation and approvals.
These measures are intended to compensate for permitted diversion of forest land and contribute to
long-term ecological restoration.
62. Will KBLP affect biodiversity?
Environmental impacts on biodiversity have been considered as part of project planning. The
project incorporates mitigation and conservation measures intended to reduce, manage and
compensate for unavoidable impacts. Environmental monitoring will also be undertaken during
construction and operation.
Looking Ahead63. What is being done to make sure the project stays on track?
Compensation and rehabilitation work continues in a transparent, fair and time-bound manner,
with local officials in ongoing contact with affected families to resolve issues quickly.
64. What is the larger goal of the project going forward?
The goal is to balance the region's development needs with the rights and welfare of affected
families — completing rehabilitation with dignity while delivering long-term irrigation, drinking
water and power benefits to Bundelkhand.
65. Where can people get more information about the project?
More information is available on the official KBLPA website: www.kblpa.gov.in, the Ministry of
Jal Shakti and the District Administrations of Chhatarpur and Panna.