2866. SHRI BABUBHAI JESANGBHAI DESAI
Will the Minister of New and Renewable Energy be pleased to state:
(a) the State-wise current status of India’s installed renewable energy capacity, including solar, wind,
green hydrogen and bio-energy and the progress made towards achieving the 2030 clean energy targets;
(b) the initiatives undertaken to promote domestic manufacturing under the Production Linked
Incentive scheme for solar modules and battery storage systems in the country;
(c) whether Government has introduced policy measures to strengthen grid integration, storage
solutions and round-the-clock renewable power supply; and
(d) the manner in which these initiatives are contributing to energy security, reduction in carbon
emissions and generation of green employment opportunities across the country?
ANSWER
THE MINISTER OF STATE FOR NEW & RENEWABLE ENERGY AND POWER
(SHRI SHRIPAD YESSO NAIK)
(a) Ministry of New and Renewable Energy (MNRE) is working towards achieving 500 GW of
installed electricity capacity from non-fossil fuel-based sources by 2030. As on 28.02.2026, a total of
266.68 GW renewable energy capacity has been installed in the country. The source-wise and State-
wise details are given at Annexure-I.
Further, the Government is implementing the National Green Hydrogen Mission (NGHM) with an
objective to make India a global hub of production, usage and export of green hydrogen and its
derivatives. The Mission aims to establish green hydrogen production capacity of 5 Million Metric
tonnes per annum by 2030. As per available information, around 8000 tonnes per annum of green
hydrogen production capacity has been commissioned in the country till February 2026. The location-
wise details are given at Annexure-II.
(b) The Government is implementing the Production Linked Incentive (PLI) Scheme for High
Efficiency Solar PV Modules, for achieving domestic manufacturing capacity of Giga Watt (GW) scale
in High Efficiency Solar PV modules, with an outlay of Rs. 24,000 crore. Under the Scheme, Letters
of Award have been issued for setting up of 48,337 MW of fully/ partially integrated solar PV module
manufacturing units.
Further, Ministry of Heavy Industries is having a Production Linked Incentive (PLI) scheme, ‘National
Programme on Advanced Chemistry Cell (ACC) Battery Storage’ for implementation of giga-scale
ACC manufacturing facilities in India, for 50 GWh with a total budgetary outlay of ₹18,100 crore.
(c) Government has taken various initiatives for development of the Energy Storage capacity in the
country which include, inter alia, the following:
(i) Notified Guidelines for Procurement and Utilization of Battery Energy Storage System
(BESS) as part of Generation, Transmission and Distribution assets, along with Ancillary
Services.(ii) Issued National Framework to promote Energy Storage Systems in the country.
(iii) Issued Guidelines to promote Pumped Storage Projects (PSP).
(iv) Granted 100% waiver of Inter-State Transmission System (ISTS) charges for PSP for which
construction work is awarded on or before June 30, 2028
(v) Granted 100% ISTS charges waiver for co-located BESS projects, commissioned on or
before 30th June 2028, with certain conditions.
(vi) Approved a Viability Gap Funding (VGF) Scheme for the development of large-scale BESS
with an outlay of ₹3,760 crore for the development of 13,220 MWh. Approved another
VGF Scheme for 30 GWh, funded through ₹5,400 crore from the Power System
Development Fund (PSDF.
(vii) Issued an Advisory on ‘Co-locating Energy Storage Systems with Solar Power Projects to
enhance grid stability and cost efficiency’.
Further, the various measures taken to strengthen grid integration are as under:
(i) Central Electricity Authority (CEA) has published a plan for Transmission System for
Integration of over 500 GW renewable energy capacity by 2030 covering all renewable
energy rich States.
(ii) Ministry of New & Renewable Energy is implementing Green Energy Corridor scheme in
two phases, i.e. Phase-I & Phase-II, in ten States, viz., Andhra Pradesh, Gujarat, Himachal
Pradesh, Karnataka, Kerala, Madhya Pradesh, Maharashtra, Rajasthan, Tamil Nadu and
Uttar Pradesh for enabling smooth evacuation of 44GW of renewable energy (RE).
(iii) Central Electricity Authority (Technical Standards for Connectivity to the Grid)
Regulations lay down the minimum technical requirements for the RE generating plants to
ensure safe, secure and reliable operation of the grid. The compliances to the said
regulations by RE plants are verified jointly by Central Transmission Utility (CTUIL) and
Grid-India/Regional Load Despatch Centres (RLDCs) before granting connectivity/
interconnection to the national grid.
(iv) Indian Electricity Grid Code mandates that RE plants participate in the primary and
secondary frequency control in case of contingencies.
(v) Establishment of Renewable Energy Management Centres (REMCs) for real-time
forecasting, scheduling, and monitoring of RE generation across 12 RE-rich regions.
Further, Ministry of Power vide Resolution no. 23/03/2023-R&R dated 9th June, 2023 issued the
Guidelines for Tariff Based Competitive Bidding Process for Procurement of Firm and Dispatchable
Power from Grid Connected Renewable Energy Power Projects with Energy Storage Systems. These
Guidelines enables the DISCOMs to procure round-the clock /demand based renewable power.
(d) The initiatives undertaken by the Government for promotion of renewable energy, domestic
manufacturing, grid integration and energy storage are aimed at strengthening the country’s energy
security by diversifying the energy mix and reducing dependence on fossil fuels. These measures are
expected to facilitate greater deployment of clean energy technologies, which in turn may contribute
to reduction in carbon emissions. Further, the expansion of renewable energy capacity, manufacturing
ecosystem and associated supply chains is likely to generate employment opportunities across various
segments such as manufacturing, project development, installation, operations and maintenance.
*****Annexure-I
Annexure-I referred to in reply of part (a) of the Rajya Sabha Unstarred Question
No. 2866 to be answered on 17.03.2026
Source-wise and State-wise Renewable Energy installed capacity as on 28.02.2026
(In Megawatt)
Sl. STATES / UTs Small Wind Bio- Solar Large Total
No. Hydro Power Power Power Hydro
Power
1 Andhra Pradesh 164.51 4415.78 594.02 7208.18 3290.00 15672.49
2 Arunachal Pradesh 140.61 0.00 15.44 1615.00 1771.05
3 Assam 34.11 2.00 533.47 346.00 915.58
4 Bihar 70.70 140.22 435.34 646.26
5 Chhattisgarh 100.90 285.42 1755.40 120.00 2261.72
6 Goa 0.05 1.94 76.24 78.23
7 Gujarat 113.30 15197.19 129.85 27486.27 1990.00 44916.61
8 Haryana 73.50 326.71 2584.78 2984.99
9 Himachal Pradesh 1013.46 10.20 346.28 11421.02 12790.96
10 Jammu & Kashmir 189.93 0.00 79.48 3360.00 3629.41
11 Jharkhand 4.05 20.14 242.39 210.00 476.58
12 Karnataka 1284.73 8500.54 1917.05 11029.95 3689.20 26421.47
13 Kerala 276.52 71.52 2.50 2150.25 2008.15 4508.94
14 Ladakh 45.79 0.00 12.02 89.00 146.81
15 Madhya Pradesh 123.71 3610.15 155.46 5893.84 2235.00 12018.16
16 Maharashtra 384.28 5873.01 2998.30 19364.16 3047.00 31666.75
17 Manipur 5.45 0.00 17.52 105.00 127.97
18 Meghalaya 55.03 13.80 4.28 322.00 395.11
19 Mizoram 45.47 0.00 33.69 60.00 139.16
20 Nagaland 32.67 0.00 3.34 75.00 111.01
21 Odisha 140.63 64.22 779.32 2154.55 3138.72
22 Punjab 176.10 576.59 1566.91 1096.30 3415.90
23 Rajasthan 23.85 5229.15 207.52 38728.22 412.50 44601.24
24 Sikkim 55.11 0.00 7.56 2282.00 2344.67
25 Tamil Nadu 123.05 12102.76 1046.62 12352.49 2203.20 27828.12
26 Telangana 89.67 128.10 221.67 5065.10 2405.60 7910.14
27 Tripura 16.01 0.00 35.41 51.42
28 Uttar Pradesh 50.60 2310.39 3846.45 501.60 6709.04
29 Uttarakhand 233.82 149.57 837.89 4785.35 6006.63
30 West Bengal 98.50 351.86 320.62 1341.20 2112.18
31 A&N Islands 5.25 0.00 32.12 37.37
32 Chandigarh 0.00 78.85 78.85
33 Dadra & Nagar Haveli 3.75 134.90 138.65
and Daman & Diu
34 Delhi 85.17 413.90 499.07
35 Lakshadweep 0.00 6.57 6.57
36 Puducherry 0.00 80.71 80.71
37 Others 4.30 0.00 45.01 49.31
Total 5171.36 55132.50 11614.97 143604.37 51164.67 266687.85Annexure-II
Annexure-II referred to in reply of part (a) of the Rajya Sabha Unstarred Question
No. 2866 to be answered on 17.03.2026
Location-wise details of green hydrogen production plants commissioned in the country
Sl. Company Name Capacity Location
No. (Tonnes per
Annum)
1 ACME Cleantech Solutions Pvt. Ltd 175 Bikaner, Rajasthan
2 Bharat Petroleum Corporation Ltd. 780 Bina Refinery, Madhya Pradesh
3 National Institute of Solar Energy 7.8 Gurugram, Haryana
4 INOX India Limited 190 Chittorgarh, Rajasthan
5 Hygenco Green Energies Pvt. Ltd. 16 Ujjain, Madhya Pradesh
6 Hygenco Green Energies Pvt. Ltd. 78 Hisar, Haryana
7 Hygenco Green Energies Pvt. Ltd. 230 Chhatrapati Sambhajinagar,
Maharashtra
8 SJVN Limited 5 NJHPS, Jhakri, Himachal
Pradesh
9 THDC India Limited 18.25 Rishikesh, Uttarakhand
10 Larsen & Toubro Limited 15 Hazira, Gujarat
11 Oil India Limited 10.95 Jorhat, Assam
12 Hero Future Energies 25 Tirupati, Andhra Pradesh
13 GAIL (India) Limited 1,752 Vijaipur, Madhya Pradesh
14 Adani New Industries Limited 876 Kutch, Gujarat
15 NTPC Limited 0.87 Kawas township, Surat, Gujarat
16 NTPC Limited 29.2 Leh, Ladakh
17 Deen Dayal Port Authority 80 Kandla, Gujarat
18 Torrent Power 72 Gorakhpur, Uttar Pradesh
19 V.O Chidambaranar (VOC) Port 7.8 V. O. Chidambaranar Port,
Tamil Nadu
20 JSW Steel 3600 Ballari, Karnataka
Total Capacity 7968.87