GOVERNMENT OF INDIA
MINISTRY OF NEW AND RENEWABLE ENERGY
LOK SABHA
UNSTARRED QUESTION NO. 507
ANSWERED ON 22.07.2026
AGRIPHOTOVOLTAIC PROJECTS IN ANDHRA PRADESH
507. SHRI TANGELLA UDAY SRINIVAS
Will the minister of new and renewable energy be pleased to state:
(a) the current status of implementation of the Pradhan Mantri Kisan Urja Suraksha evam
Utthaan Mahabhiyaan (PM-KUSUM) in Andhra Pradesh including the number of solar pumps
installed, farmers benefitted and funds utilised, year and district-wise particularly in Kakinada;
(b) the number of Agriphotovoltaic projects sanctioned in coastal Andhra Pradesh, the
agricultural land covered and the average income enhancement per acre reported in any
assessment;
(c) whether the Government has assessed the potential of offshore wind energy in the Bay of
Bengal coastal zone adjacent to Kakinada and if so, the details of findings and proposed action
thereof; and
(d) the steps taken by the Government to promote rooftop solar adoption among small
traders, fishermen households and youth entrepreneurs in Kakinada district under the Pradhan
Mantri Surya Ghar Muft Bijli Yojana (PM-SGMBY)?
ANSWER
THE MINISTER OF STATE FOR NEW & RENEWABLE ENERGY AND POWER
(SHRI SHRIPAD YESSO NAIK)
(a) PM-KUSUM is a demand driven scheme. The capacities are allocated based on demand
received from the States/UTs. Based on the demand received from the state, a total of 2,93,587
pumps are allocated under Component C (Feeder Level Solarization). However, no progress
has been reported by the state so far.
There is no demand received from the State of Andhra Pradesh for standalone solar pumps
under Component B of the PM KUSUM scheme.
(b) Component A of the PM KUSUM scheme allows for setting up of decentralized ground
mounted grid connected solar power plants in stilt fashion (also known as Agrivoltaics) by
farmers on their land. There is no demand received from the State of Andhra Pradesh for
installation of decentralized plants under Component A of the scheme.
(c) No specific assessment/study has been carried out in the Bay of Bengal coastal zone
adjacent to Kakinada for offshore wind potential.
(d) To promote rooftop solar adoption among all, including small traders, fishermen households
and youth entrepreneurs, the Ministry has taken various steps, which inter-alia includes:• Creating awareness about the scheme, through awareness and outreach program such
as print advertising in leading newspapers, TV commercials campaigns, Radio
campaigns across FM stations, including regional channels, etc., in the country.
• Online process from application to disbursal of subsidy directly into the bank account
of the residential consumer through National Portal.
• Availability of collateral free loan from nationalized banks at concessional interest rate
of repo-rate plus 50 bps i.e. 5.75% per annum for the present, with tenure of 10 years.
• Simplified the regulatory approval process by waiving technical feasibility requirement
and introducing auto load enhancement upto 10 kW.
• Net metering agreement has been made part of application in the National Portal.
• Simplified process for registration of vendors to ensure sufficient and qualified vendors
are available.
• Capacity building and training programmes are being conducted for creating skilled
manpower.
• Established a grievance redressal mechanism for the timely resolution of grievances. A
Call Centre with telephone number 15555 is operational in 12 languages.
*****