UNSTARRED QUESTION NO.2052
ANSWERED ON 30.07.2026
ALLOCATION OF POWER FROM CENTRAL POWER PROJECTS TO
UTTAR PRADESH
†2052. SHRI ARUN KUMAR SAGAR:
Will the Minister of POWER
be pleased to state:
(a) whether the Union Government has taken any steps to ensure the allocation
of power from central power projects to the State of Uttar Pradesh in
accordance with its requirements and to ensure uninterrupted power supply in
the Scheduled Caste dominated Shahjahanpur Parliamentary Constituency; and
(b) if so, the details thereof?
A N S W E R
THE MINISTER OF STATE IN THE MINISTRY OF POWER
(SHRI SHRIPAD NAIK)
(a) & (b): The Government of India has allocated 11,520.53 MW of power to
Uttar Pradesh from Central Sector Generating Station (CGS), as on 30.06.2026,
which comprises 11,269.93 MW of firm power and 250.6 MW power from
unallocated quota.
Electricity being a concurrent subject, the supply and distribution of
electricity to the various categories of consumers/areas/districts in a State/UT
is looked after by the respective Power Utility/State Government. Further, The
Central Government supplements the efforts of the State Governments by
establishing power plants through Central Public Sector Undertakings (CPSUs)
and allocate power from them to the various States / UTs.
To ensure generation capacity remains ahead of projected demand, all
the States, in consultation with CEA, have prepared their “Resource Adequacy
Plans (RAPs)”, which are dynamic 10-year rolling plans and includes power
generation as well as power procurement planning.
The details of Power Supply Position for the State of Uttar Pradesh in
terms of Energy for the last three financial years and current year (upto June,
2026) is given at Annexure. The ‘energy supplied’ has been commensurate
with the ‘energy requirement’ with only a marginal gap which is generally on
account of constraints in the State transmission / distribution network.
………2.- 2 -
Following steps have been taken to support States/Distribution Utilities
to provide uninterrupted power supply in the States/UTs including the State of
Uttar Pradesh:
(i) Government of India launched “Revamped Distribution Sector Scheme
(RDSS) in July, 2021 with the objective of improving the quality of power
supply through a financially sustainable and operationally efficient
distribution sector. The scheme has a total outlay of Rs.3,03,758 crore,
including Gross Budgetary Support from the Central Government of
Rs.97,631 crore. The sunset date of the scheme is 31.03.2028. Under the
scheme, financial assistance is being provided to the Distribution
Utilities for loss reduction infrastructure works and smart metering
works. Loss reduction works include replacement of old conductors,
creation of new substations, upgradation of Substations, installation of
new Distribution Transformers (DTs), upgradation of DTs, feeder
segregation works etc. Under the scheme, loss reduction infrastructure
works amounting to Rs.21,782 crore and smart metering works
amounting to Rs.18,956 crore have been sanctioned for the State of
Uttar Pradesh. In Shahjahanpur Parliamentary Constituency, loss
reduction infrastructure works amounting to Rs.230.88 crore and smart
metering works amounting to Rs.234.02 crore have been sanctioned.
The loss reduction works have achieved physical progress of around
61%.
(ii) Government of India has supplemented the efforts of the States through
schemes namely Deen Dayal Upadhyaya Gram Jyoti Yojana (DDUGJY)
and Pradhan Mantri Sahaj Bijli Har Ghar Yojana (SAUBHAGYA) for
strengthening of the rural distribution network and electrification of
villages and households. As reported by the States, all the inhabited un-
electrified census villages in the country were electrified. A total of
18,374 villages were electrified during DDUGJY, including 1,498 villages
in the State of Uttar Pradesh. Under DDUGJY and thereafter during
SAUBHAGYA, electrification of all willing households was completed. A
total of 2.86 crore households were electrified during the SAUBHAGYA
period, including 91.8 lakh households in the State of Uttar Pradesh and
1,23,284 households in Shahjahanpur Lok Sabha Constituency. Both the
schemes stand closed as on 31.03.2022. Government of India is further
supporting States for grid electrification of left-out households, including
households belonging to Particularly Vulnerable Tribal Group (PVTG)
under PM-JANMAN (Pradhan Mantri Janjati Adivasi Nyaya Maha Abhiyan),
tribal households under DA-JGUA (Dharti Aaba Janjatiya Gram Utkarsh
Abhiyan), Scheduled Caste households under Pradhan Mantri Anusuchit
Jaati Abhyuday Yojna (PM-AJAY) and remote & border households under
Vibrant Village Program (VVP), under RDSS. Till date, under RDSS, works
have been sanctioned for electrification of 13.65 lakh households
including 2,58,700 households in the State of Uttar Pradesh and 2,924
households in Shahjahanpur Lok Sabha Constituency.
……..3.- 3 -
(iii) As per rule 10 of the Electricity (Rights of Consumers) Rules, 2020, the
distribution licensee shall supply 24x7 power to all consumers. However,
the State Commission may specify lower hours of supply for some
categories of consumers.
As reported by the State, the power supply as per the following roster is
provided for Shahjahanpur Parliamentary constituency.
District Head Quarter Tehsil Rural
(HQ) (HH:MM) (HH:MM)
(HH:MM)
24:00 21:30 18:00
**************ANNEXURE
ANNEXURE REFERRED IN REPLY TO PARTS (a) & (b) OF UNSTARRED QUESTION
NO. 2052 ANSWERED IN THE LOK SABHA ON 30.07.2026
*************
The details of actual Power Supply Position for the State of Uttar Pradesh in
terms of Energy for the last three financial years and current year (upto June,
2026)
Energy [in Million Unit (MU)]
Energy Energy
Financial Year Energy not Supplied
Requirement Supplied
(MU) (MU) (MU) ( % )
2023-24 1,48,791 1,48,287 504 0.3
2024-25 1,65,090 1,64,786 304 0.2
2025-26 1,63,501 1,63,475 26 0.0
2026-27 (upto June, 49,411 49,401 10 0.0
2026)
(*) Data for the month of June, 2026 is Provisional
***************