Home India Ministry of Railways Parliament Question: Amrit Bharat Station Scheme for Uttar P...
Date: 2025-07-23 Category: Not Applicable State: Union Government Country: India

Parliament Question: Amrit Bharat Station Scheme for Uttar Pradesh

Issued by Ministry of Railways · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task

Executive Summary & Key Takeaways

Executive Summary: The Ministry of Railways launched the Amrit Bharat Station Scheme (ABSS) for the development and upgradation of railway stations across Indian Railways. As part of this scheme, 157 stations in Uttar Pradesh have been identified for development. The scheme focuses on improving amenities, integrating stations with the city, and implementing sustainable solutions. Development and upgradation of stations is an ongoing process, depending on the availability of funds and project viability. Key Points / Main Content: Amrit Bharat Station Scheme (ABSS) * 1,337 stations identified for development under ABSS across Indian Railways. * 157 stations located in Uttar Pradesh are included in the scheme. * Phase I works completed at 20 stations. * Phase I/Phase II works underway at 130 stations. * 9 stations are at the master planning/tendering stage. * The scheme focuses on long-term station development and continuous improvement of amenities. Stations Identified in Uttar Pradesh * Specific stations in Uttar Pradesh, including those in Baghpat, Sitapur, and Jaunpur constituencies, have been selected for development. * Stations include Modi Nagar (Baghpat), Sitapur Junction, Jaunpur City, and Jaunpur Junction. Progress of Development Works * Various works are in progress at stations like Modi Nagar, Sitapur Junction, Jaunpur Junction, Jaunpur City, Lucknow Charbagh Junction, Prayagraj, and Ghaziabad, including station building improvements, platform upgrades, and construction of new facilities. * Phase I works of 20 stations in the state of Uttar Pradesh have been completed under this scheme. Funding and Expenditure * Development is funded under Plan Head 53 Customer Amenities. * The state of Uttar Pradesh is covered under the jurisdiction of five railway zones, namely East Central Railway, North Central Railway, Northern Railway, North Eastern Railway, and West Central Railway. * Allocations and expenditures under Plan Head 53 are maintained Zonal Railway-wise, not station-wise or state-wise. * Allocations and expenditures for the five railway zones for the last five financial years are detailed in the document. Project Timelines and Challenges * No specific time frame can be indicated due to the complexity of railway projects and various statutory clearances required. * Progress is affected by challenges such as shifting utilities, brownfield constraints, and operational requirements. New Rail Line Project * Survey for Meerut-Panipat New Rail Line (104 Km) has been sanctioned for preparing DPR. * Sanctioning of project requires consultation with various stakeholders including State Governments and necessary approvals viz. appraisal of NITI Aayog,Ministry of Finance etc. Ongoing Railway Projects in Uttar Pradesh * As of 01.04.2025, 49 Railway projects including 10 New Line, 02 Gauge Conversion and 37 Doubling, of total length of 3,808 Km costing 62,360 crore falling fullypartly in the State of Uttar Pradesh are sanctioned, out of which 1,323 Km length has been commissioned and an expenditure of 30,611 crore has been incurred upto March 2025. Security, Cleanliness, and Passenger Facilities * The government is taking steps to ensure security, cleanliness, and improvement in passenger facilities at railway stations. * Security measures include CCTV surveillance, Rail Madad Portal, helpline number 139, and coordination with GRP and RPF. * Cleanliness measures include integrated housekeeping contracts, mechanized cleaning, dustbins for waste segregation, bio-toilets, and plastic bottle crushing machines. Impact Analysis: Ministry of Railways: * Impact: Responsible for implementing the Amrit Bharat Station Scheme, allocating funds, and overseeing the development and upgradation of railway stations. * Action Required: Continue to allocate funds, monitor progress, and address challenges in project implementation. Passengers: * Impact: Will benefit from improved amenities, enhanced security, and cleaner railway stations. * Action Required: Utilize available facilities and report any issues or concerns to railway authorities. Railway Staff: * Impact: Required to manage and maintain the upgraded facilities, as well as ensure passenger safety and security. * Action Required: Adapt to new infrastructure and procedures, and prioritize passenger service and safety. State Governments (especially Uttar Pradesh): * Impact: Collaboration is required for land acquisition, statutory clearances, and cost-sharing of projects. * Action Required: Provide necessary support for project implementation, including timely land acquisition and clearances. Contractors and Vendors: * Impact: Opportunities for contracts related to construction, maintenance, and provision of services at railway stations. * Action Required: Execute projects according to specifications and timelines, while adhering to safety and quality standards.

Key Entities Referenced

Amrit Bharat Station Scheme: A scheme by the Ministry of Railways for the development and upgradation of railway stations over Indian Railways. Uttar Pradesh: A state in India where 157 railway stations have been identified for development under the Amrit Bharat Station Scheme. Ministry of Railways: The government ministry responsible for the development and management of railways in India. Panipat-Meerut New Rail Line: A proposed new railway line between Panipat, Haryana and Meerut, Uttar Pradesh for which a survey has been sanctioned for preparing a Detailed Project Report (DPR). Lucknow Charbagh NR: A railway station in Lucknow, Uttar Pradesh, where structural works are underway as part of the Amrit Bharat Station Scheme. Prayagraj Jn: A railway station in Prayagraj, Uttar Pradesh, where structural work is underway as part of the Amrit Bharat Station Scheme. Ghaziabad: A railway station in Ghaziabad, Uttar Pradesh, where structural work is underway as part of the Amrit Bharat Station Scheme. Railway Protection Force: Supplements the efforts of GRPDistrict Police to provide better protection and security to railway property, passenger area passengers and for matters connected therewith.
Official Source Record View Original Source →
See Full Document Text
GOVERNMENT OF INDIA MINISTRY OF RAILWAYS LOK SABHA UNSTARRED QUESTION NO. 481 TO BE ANSWERED ON 23.07.2025 AMRIT BHARAT STATION SCHEME FOR UTTAR PRADESH 481. MS IQRA CHOUDHARY: SHRI PUSHPENDRA SAROJ: SHRI RAKESH RATHOR: SHRI BABU SINGH KUSHWAHA DR. RAJKUMAR SANGWAN: Will the Minister of RAILWAYS be pleased to state: (a) the number of railway stations selected under Amrit Bharat Station Scheme (ABSS) in Uttar Pradesh particularly in Baghpat, Sitapur and Jaunpur Lok Sabha Constituencies; (b) the amount allocated, sanctioned and disbursed and spent for station redevelopment works in the said State under the ABS scheme during the last five years, year-wise, district-wise and station-wise; (c) the number of selected stations where Master Plans have been sanctioned; (d) the number of selected stations where DPR has been sanctioned along with the details of financial and physical progress of the work;(e) the status of DPR of Panipat-Meerut new railway line including the date of its submission; (f) whether the said project has received approval from the Ministry of Railways or any related authorities such as the Gati Shakti Unit and if so, the details thereof; (g) whether any timeline has been fixed for the commencement and completion of the railway line and if not, the reasons for the delay; (h) the estimated project cost and budgetary provisions made so far for the said line; and (i) the steps taken/being taken by the Government to ensure security, cleanliness and improvement in passenger facilities at railway stations under the said scheme? ANSWER MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND ELECTRONICS & INFORMATION TECHNOLOGY (SHRI ASHWINI VAISHNAW) (a) to (i) Ministry of Railways has launched Amrit Bharat Station Scheme for development / upgradation of stations over Indian Railways. So far, 1337 stations have been identified for development under Amrit Bharat Station Scheme, out of which 157 stations are located in the state of Uttar Pradesh. Out of which, phase-I works have been completed at 20stations, Phase-I/Phase-II works have been taken up at 130 stations and 9 stations are at master planning / tendering stage. The names of stations identified for development under Amrit Bharat Station Scheme in the state of Uttar Pradesh are as following: No. of Amrit State Names of Amrit Stations Stations Uttar 157 Achnera, Agra Cantt., Agra Fort, Aishbagh Pradesh Jn, Akbarpur Jn, Aligarh, Amethi, Amroha, Anand Nagar Jn., Aonla, Ayodhya Dham Junction, Azamgarh, Babatpur, Bachhrawan, Badaun, Badshahnagar, Badshahpur, Baheri, Bahraich, Balamau Jn., Ballia, Balrampur, Banaras, Banda, Barabanki Jn, Bareilly, Bareilly City, Barhni, Basti, Belthara Road, Bhadohi, Bharatkund, Bhatni, Bhuteshwar, Bijnor, Bulandsahar, Chandauli Majhwar, Chandausi, Chilbila, Chitrakut dham karwi, Chopan, Chunar Jn., Daliganj, Darshannagar, Deoria Sadar, Dhampur, Dildarnagar, Etawah Jn., Farrukhabad, Fatehabad, Fatehpur, Fatehpur Sikri, Firozabad, Gajraula, Garhmuktesar, Gauriganj, Ghatampur, Ghaziabad, Ghazipur City, Gola Gokarnath, Gomtinagar, Gonda, Gorakhpur, Govardhan, Govindpuri, Gursahaiganj, Haidergarh, Hapur, Hardoi, Hathras City, Idgah Agra Jn,Izzatnagar, Janghai Jn, Jaunpur City, Jaunpur Jn, Kannauj, Kanpur Anwarganj, Kanpur Bridge Left Bank, Kanpur Central, Kaptanganj Jn, Kasganj Jn, Kashi, Khalilabad, Khorason road, Khurja Jn., Kosi Kalan, Kunda Harnamganj, Lakhimpur, Lalganj, Lalitpur Jn, Lambhua, Lohta, Lucknow (Charbagh) NR, Lucknow city, Lucknow Jn. (NER), Maa Belha Devi Pratapgarh Junction, Maghar, Maharaja Bijli Pasi, Mahoba Jn, Mailani Jn, Mainpuri Jn, Malhaur, Manak Nagar, Manikpur Jn, Mariahu, Mathura Jn, Mau Jn, Meerut City Jn, Mirzapur, Modinagar, Mohanlalganj, Moradabad Jn, Muzaffarnagar, Nagina, Najibabad Jn, Orai, Panki Dham, Phaphamau Jn, Phulpur, Pilibhit Jn, Pokhrayan, Prayag Jn, Prayagraj Jn, Pt. Deen Dayal Upadhyay Jn , Rae Bareli Jn, Raja Ki Mandi, Ramghat Halt, Rampur Jn, Renukoot, Saharanpur Jn., Salempur, Seohara, Shahganj Jn, Shahjahanpur, Shamli, Shikohabad Jn., Shivpur, Siddharth nagar, Sitapur Jn., Sonbhadra, Sri Krishna Nagar, Sultanpur Jn, Suraimanpur, Swaminarayan Chappia, Takia, Tulsipur, Tundla Jn., Ujhani, Unchahar, Unnao Jn, Utraitia Jn, VaranasiCantt., Varanasi City, Vindhyachal, Virangana Lakshmibai, Vyasnagar, Zafarabad Modi Nagar station under Baghpat Parliamentary Constituency, Badshahpur, Janghai Junction, Jaunpur City, Jaunpur Junction, Shahganj Junction, Sri Krishna Nagar, Zafarabad stations under Jaunpur Parliamentary Constituency and Sitapur Junction station under Sitapur Parliamentary Constituency have been identified for development under Amrit Bharat Station Scheme. Development works at railway stations under Amrit Bharat Station Scheme in the state of Uttar Pradesh have been taken up at a good pace. Till now, phase-I works of 20 stations (Ayodhya Dham, Balrampur, Bareily City, Bijnor, Fatehabad, Gola Gokarnath Gomti Nagar, Govardhan, Govindpuri, Hathras City, Idgah Agra Jn., Izzatnagar, Mailani, Pokhrayan, Ramghat Halt, Saharanpur Jn., Siddharth Nagar, Suraimanpur, Swaminarayan Chappia, Ujhani) in the state of Uttar Pradesh have been completed under this scheme. The works at other stations have also been taken up at good pace and progress of some of above stations is as given below:  At Modi Nagar station, work of improvement to station building, improvement to waiting area and toilets, 12m wide Foot Over Bridge, new platform shelters, have been completed and work of minor finishing items of building, platform surfacing, signage, improvement to circulating area and parking have been taken up. At Sitapur Junction station, work of construction of old station building façade, platform flooring, platform shelter, circulating area boundary wall have been completed and works of construction of new station building foundation, pay & use toilet renovation, circulating area road, parking etc. have been taken up.  At Jaunpur Junction station, structural work of new station building, platform shelter and toilet block have been taken up.  At Jaunpur City station, work of platform shelters has been taken up. ● At Lucknow (Charbagh & Junction) station, the structural works of the second entry station building, TTE Running Hostel, Store Depot have been completed and masonry work including other finishing works, concourse, Foot Over Bridge, second entry circulating area, main entry external development and platform no. 10/11 works have been taken up. ● At Prayagraj station, structural work of second entry side, Rail Mail Service & arrival, parcel & arrival buildings, and basement plaza at second entry, Electrical substation have been completed and finishing work of these structures have been taken up. Extension work of Foot Over Bridge no. 2 has been completed. Work of roof plaza and relocated structures have been taken up. ● At Ghaziabad station, structural work of station building at main entry side and second entry side, foundation work of Foot Over Bridge, roof plaza,electrical substation at main entry side and second entry side,Magistrate building, Government Railway Police and Railway Protection Force buildings have been taken up. Further development / redevelopment / upgradation / modernisation of stations on Indian Railways is a continuous and ongoing process and works in this regard are undertaken as per requirement, subject to inter- se priority and availability of funds. The priority for development / redevelopment / upgradation / modernisation of stations is accorded to higher category of station over lower category of station while sanctioning and executing the works. Master planning is an iterative process requiring optimization and the time frame and other details for such optimization cannot be indicated at this stage. Amrit Bharat Station Scheme envisages development of stations on a continuous basis with a long-term approach.It involves preparation of master plans and their implementation in phases to improve the amenities at the stations like improvement of station access, circulating areas, waiting halls, toilets, lift/escalators as necessary, platform surfacing and cover over platform, cleanliness, free Wi-Fi, kiosks for local products through schemes like ‘One Station One Product’, better passenger information systems, executive lounges, nominated spaces for business meetings, landscaping, etc. keeping in view the necessity at each station.The scheme also envisages improvement of building, integrating the station with both sides of the city, multimodal integration, amenities for Divyangjans, sustainable and environment friendly solutions, provision of ballastless tracks, etc. as per necessity, phasing and feasibility and creation of city centre at the station in the long term. Development / upgradation / modernisation of stations including under Amrit Bharat Station Scheme is generally funded under Plan Head-53 ‘Customer Amenities’. The details of allocation and expenditure under Plan Head-53 are maintained Zonal Railway-wise and not work-wise, or station wise or state-wise. The state of Uttar Pradesh is covered under the jurisdiction of five railway zones, namely East Central Railway, North Central Railway, Northern Railway, North Eastern Railway, and West Central Railway. For these zones, the allocations and expenditures made over the last five financial years are as follows: in 2021–22, ₹707 crore was allocated and ₹632 crore expended; in 2022–23, ₹1,278 crore was allocated and ₹866 crore expended; in 2023–24, ₹3,888 crore was allocated and ₹2,915 crore expended; in 2024–25, ₹4,188 crore was allocated and ₹4,143 crore expended; and in 2025–26, ₹4,358 crore has been allocated, with an expenditure(up to June, 2025) of ₹877 crore incurred so far. Development / upgradation of railway stations is complex in nature involving safety of passengers & trains and requires various statutory clearances such as fire clearance, heritage, tree cutting, airport clearance etc. The progress also gets affected due to brownfield related challenges such as shifting of utilities (involving water/sewage lines,optical fibre cables, gas pipe lines, power/signal cables, etc.), infringements, operation of trains without hindering passenger movement, speed restrictions due to works carried out in close proximity of tracks and high voltage power lines, etc. and these factors affect the completion time. Therefore, no time frame can be indicated at this stage. Railway projects are survey/ sanctioned/ executed Zonal Railway wise and not State-wise/UT wise/District wise as the Railway projects may span across State/UT/District boundaries. Railway projects are sanctioned on the basis of remunerativeness, traffic projections, last mile connectivity, missing links and alternate routes, augmentation of congested/saturated lines, demands raised by State Governments, Central Ministries, Member of Parliament, other public representatives, Railway’s own operational requirement, socio-economic considerations etc. depending upon throwforward of ongoing projects and overall availability of funds. The Survey for Meerut-Panipat New Rail Line (104 Km) has been sanctioned for preparing Detailed Project Report. However, Panipat and Meerut are well connected with existing rail network via Delhi- Ghaziabad. After firming up of Detailed Project Report (DPR), sanctioning of project requires consultation with various stake-holders including State Governments and necessary approvals viz. appraisal of NITI Aayog,Ministry of Finance etc. As sanctioned of projects is a continuous and dynamic process, exact timelines cannot be fixed. As on 01.04.2025, 49 Railway projects (10 New Line, 02 Gauge Conversion and 37 Doubling), of total length of 3,808 Km costing ₹62,360 crore falling fully/partly in the State of Uttar Pradesh are sanctioned, out of which 1,323 Km length has been commissioned and an expenditure of ₹30,611 crore has been incurred upto March 2025. The Status of work is summarized as under:- Plan Head No. of Total Length Length Expenditure Projects (in Km) Commissioned upto March (in Km) 2025 (₹in Cr) New Lines 10 1227 340 10517 Gauge 2 67 0 281 Conversion Double 37 2513 983 19813 Multitracking Total 49 3808 1323 30611 Budget allocation for infrastructure projects and safety works, falling fully/partly in Uttar Pradesh is as under: Period Outlay 2009-14 ₹1,109 crore/year 2025-26 ₹19,858 Cr. (nearly 18 times)The completion of any Railway project depends on various factors like quick land acquisition by state government, forest clearance by officials of forest department, deposition of cost share by State Government in cost sharing projects, priority of projects, shifting of infringing utilities, statutory clearances from various authorities, geological and topographical conditions of area, law and order situation in the area of project(s) site, number of working months in a year for particular project site due to climate conditions etc. Police’ and ‘Public Order’ are state subject under the Seventh Schedule to the Constitution of India and therefore, State Governments are responsible for prevention, detection, registration, and investigation of crime and maintenance of law and order of Railways through their law enforcement agencies viz. Government Railway Police (GRP)/District Police. Railway Protection Force (RPF) supplements the efforts of GRP/District Police to provide better protection and security to railway property, passenger area passengers and for matters connected therewith. The following steps are being taken by the Railway in coordination with GRP for the security of passengers in trains and at stations:-  Surveillance is kept through CCTV cameras provided in number of coaches and at railway stations.  For immediate assistance passengers can make complaint on Rail Madad Portal directly or through Helpline Number 139 [integrated with Emergency Response Support System (ERSS) No. 112]. Railways are in regular touch with passenger through various social media platforms like twitter & facebook to enhance security of passengers and to address their security concern.  Frequent announcements are made through Public Address System to educate passengers to take precautions against theft, snatching drugging etc.  State Level Security Committee of Railways (SLSCR) have been constituted for all State/Union Territories under the Chairmanship of respective Director General of Police/Commissioner of State/Union Territories for regular monitoring and review of security arrangements of the Railways.  RPF has established more than 750 Anti Human Trafficking Units (AHTUs) over the Indian Railways at Post (Thana) level to counter trafficking through Indian Railways.  In coordination with Ministry of Women and Child Development (MoWCD), Child Help desks (CHDs) have been setup at selected railway station across the Indian Railway to safeguard children in need of care and protection. These CHDs are being operated by District Child Protection Units (DCPUs) at district level. Cleanliness is a continuous process, and every endeavour is made to keep the station's premises in a properly maintained and clean condition. Various measures have been taken for improving cleanliness at stations (including those covered under the Amrit Bharat Scheme), which include:  Integrated housekeeping contracts at major stations. Mechanized cleaning and provision of two bin-type dustbins at several locations for segregation of biodegradable and non- biodegradable wastes.  Rag picking contracts and/or garbage disposal contracts are available at major stations.  Prevention of falling of fecal matter on railway tracks by fitting bio-toilets in all passenger coaches, thereby ensuring cleaner railway stations.  Installation of plastic bottle crushing machines at major stations. *****

Continue your research