GOVERNMENT OF INDIA
MINISTRY OF PORTS, SHIPPING AND WATERWAYS
RAJYA SABHA
STARRED QUESTION NO.*106
ANSWERED ON 10.02.2026
BALAGARH PROJECT OF KOLKATA PORT
*106. SHRI SAMIK BHATTACHARYA:
Will the Minister of PORTS, SHIPPING AND WATERWAYS be pleased to state:
(a) whether Government has approved and initiated implementation of the Balagarh
Project of Syama Prasad Mookerjee Port, Kolkata for setting up a new cargo handling
facility on Balagarh Island, about 85 km upstream from Kolkata;
(b) the objectives of the project, including decongestion of the Kolkata Dock System
andimprovement of inland waterway connectivity;
(c) the present status of land acquisition, environmental and other statutory clearances
and tendering;
(d) the estimated project cost, funding pattern and timelines; and
(e) the proposed cargo handling capacity, trade benefits and employment potential
envisaged upon commissioning?
ANSWER
MINISTER OF PORTS, SHIPPING AND WATERWAYS
(SHRI SARBANANDA SONOWAL)
(a) & (e) A statement is laid on the Table of the House.STATEMENT REFERRED TO IN REPLY TO PART (a) TO (e) OF THE RAJYA
SABHA STARRED QUESTION NO.*106 FOR ANSWER ON 10.02.2026, RAISED BY
SHRI SAMIK BHATTACHARYA REGARDING “BALAGARH PROJECT OF
KOLKATA PORT”
(a) Yes.
(b) To accommodate anticipated traffic growth and reduce intra-city cargo
movement, Syama Prasad Mookerjee Port Authority (SMPA) is developing dedicated
container and coal berths at Balagarh.The project also seeks to promote cargo
transportation through National Waterway-1, thereby, strengthening inland waterway
connectivity and enhancing overall logistics efficiency.
(c) Land is already available with the SMPA and environmental clearance was
received on 24.01.2025. Under the Engineering Procurement and Construction (EPC)
component of the project, the tender for road construction was opened on 02.02.2026
and the work order for construction of the Road Over Bridge (ROB) has been issued on
09.01.2026.
(d) The estimated cost of the project is ₹ 539.17 crore including the Engineering
Procurement and Construction (EPC) component of Rs.131.97 crore and Public Private
Partnership (PPP) component of ₹ 407.20 crore. The EPC component is to be funded
by the Inland Waterways Authority of India, while the PPP component is to be financed
and implemented by the selected concessionaire.The EPC part of project, except
dredging part, is scheduled for completion by 31.03.2028. The dredging activities will be
taken up by IWAI immediately before commencement of construction of Jetties by PPP
operators. Construction of facilities under the PPP component is to be completed within
three years from the award of concession.
(e) The proposed cargo handling capacity under the project is 2.7 million metric
tonnes per annum (MMTPA). The project is expected to provide trade benefits by
reducing congestion arising from cargo movement within city areas, lowering logistics
costs, and facilitating development of an alternate trade hub.The project is expected to
generate around 2,600 employment opportunities through both direct and indirect
avenues which will also create significant employment opportunities for the local
population, thereby contributing to regional socio-economic development.
*****