GOVERNMENT OF INDIA
MINISTRY OF COAL
RAJYA SABHA
STARRED QUESTION NO. 105
ANSWERED ON 09.02.2026
COAL BLOCK ALLOCATION UNDER COMMERCIAL COAL MINING POLICY
*105. SHRI RAGHAV CHADHA:
Will the Minister of COAL be pleased to state:
(a) details on the number of coal blocks allocated by Government under the commercial coal
mining policy;
(b) whether these blocks have achieved actual production within the scheduled timelines and
if so, the details thereof;
(c) whether Government has reviewed any delays or under performance in these coal blocks
and if so, the details thereof; and
(d) whether Government plans to strengthen monitoring and ensure the policy achieves
its intended outcomes and if so, the details thereof?
ANSWER
MINISTER OF COAL & MINES
(SHRI G. KISHAN REDDY)
(a) to (d): A statement is laid on the Table of the House.
Page 1 of 3STATEMENT REFERRED TO IN REPLY TO PARTS (A) TO (D) IN RESPECT OF
RAJYA SABHA STARRED QUESTION NO. 105 FOR REPLY ON 09.02.2026
REGARDING COAL BLOCK ALLOCATION UNDER COMMERCIAL COAL
MINING POLICY ASKED BY SHRI RAGHAV CHADHA.
(a) The Ministry of Coal has introduced auction of commercial coal mines in June 2020.
Till January 2026, 131 blocks have been successfully allocated. The state wise list of allocated
mines is as under:
State Number of Mines
Jharkhand 35
Madhya Pradesh 30
Odisha 25
Chattisgarh 23
Maharashtra 11
West Bengal 3
Assam 2
Arunachal Pradesh 2
Total 131
(b) Till January 2026, 21 coal blocks have received Mine Opening Permissions. Out of 22
coal blocks having scheduled date of Mine Opening Permission by January, 2026, 16 coal
blocks have received Mine Opening Permissions. 5 coal blocks having scheduled date of Mine
Opening Permission after January, 2026 have also received Mine Opening Permissions ahead
of schedule. The development activities in the mines start after the grant of Mine Opening
Permission. In case of opencast mines, the coal production start after the removal of overburden
and in case of underground mines, inclines or shaft are completed and thereafter coal
production starts. Out of the 21 coal blocks, 11 blocks have started coal production. The
details of yearly coal production from commercial mines are as under:
Year Coal Production (in Million Tonne)
2021-22 1.15
2022-23 7.23
2023-24 12.55
2024-25 23.50
2025-26 (till Jan 2026) 20.59
Total 65.02
(c) Yes, the allocated coal blocks are regularly reviewed and monitored through meetings.
These meetings are attended by all relevant stakeholders, including officials from State
Governments and the Ministry of Environment, Forest and Climate Change (MoEF&CC).
During these meetings, the challenges encountered in the operationalization/progress of the
Page 2 of 3mines are examined in detail to facilitate timely resolution and ensure timely progress in the
mine.
The allocation agreement prescribes specific timelines for the completion of various
milestones. In cases where a milestone is not achieved within the stipulated time-frame, show-
cause notices are issued to the concerned allottee. To examine the issue of delay in achievement
of milestone, a Scrutiny Committee has been constituted. The Committee deliberates upon the
reply of the allottee and also the allottees are given an opportunity to represent their cases
before the committee.
Based on the allottee’s submissions and deliberations in the meeting, the Committee
recommends for imposition of penalty wherever it finds the allottee responsible for the delay
in achievement of milestone or condone where the allottee is not found responsible for the
delay. Based on the recommendation of the Committee, Ministry takes the necessary actions.
(d) The Government, with the implementation of the Commercial Coal Mining Policy in June
2020, has taken significant steps towards achievement of Aatmanirbharta in domestic coal
production. The Ministry has a robust monitoring mechanism in place and strengthens it
whenever the need arises. The salient features of the monitoring mechanism are as follows:
i. Regular review meetings with coal block allottees and State Governments to monitor
progress and resolve issues related to land acquisition, statutory clearances, and
infrastructure development.
ii. Implementation of a transparent Single Window System for Ease of Doing Business,
expediting mines operationalization and redressal of grievances of project proponents.
iii. Policy reforms aimed at expediting operationalization, such as removal of several
approval requirements, streamlining of procedures, and active coordination with the
Ministry of Environment, Forest and Climate Change (MoEF&CC) to fast-track
environmental and forest clearances.
iv. The Ministry has appointed a Project Monitoring Unit (PMU) for constant review and
support to project proponents for early operationalization of mines.
v. Constitution of a Scrutiny Committee comprising coal industry experts and
representatives from Central and State Governments to transparently evaluate delays,
examine allottee representations, and recommend penalties or condonation, as
applicable.
******