*473. SHRI PRAVEEN PATEL:
DR. SANJAY JAISWAL:
Will the Minister of COAL be pleased to state:
(a) the current status of the Coal Trading Exchange (CTE) across the country including Jharkhand and
Jammu;
(b) the number of coal blocks which have commenced actual production till date out of the 131 coal blocks
allocated under the Commercial Coal Mining Policy especially the number of coal blocks in Jharkhand,
Odisha, Chhattisgarh particularly in Surguja region along with actual production being made by them;
(c) the details of penalties imposed for delays in achieving the milestones;
(d) whether the Government has completed the revised Jharia Master Plan for rehabilitation and if so, the
details thereof along with the new technologies being deployed to manage long-standing underground mine
fires and landslides in Jharkhand particularly in Hazaribagh and Ramgarh districts;
(e) whether similar measures are being considered for other coal-producing regions including Surguja in
Chhattisgarh; and
(f) whether the Government has assessed the impact of commercial coal mining and related infrastructure
development in Odisha particularly in Keonjhar Lok Sabha Constituency and if so, the details thereof?
ANSWER
MINISTER OF COAL AND MINES
(SHRI G. KISHAN REDDY)
(a) to (f): A STATEMENT IS LAID ON THE TABLE OF THE HOUSE.
1STATEMENT REFERRED TO IN REPLY TO PARTS (A) TO (F) OF LOK SABHA STARRED
QUESTION NO. *473 FOR ANSWER ON 25.03.2026 ASKED BY SHRI PRAVEEN PATEL AND
DR. SANJAY JAISWAL REGARDING COAL TRADE EXCHANGE.
(a): Ministry of Coal has initiated the process of setting up of Coal Exchange (s) in the country in pursuance
of the legislative provisions of the Mines and Minerals (Development and Regulation) Amendment Act,
2025. Section 18B of the Mines and Minerals (Development and Regulation) Amendment Act, 2025
empowers the Central Government to frame the rules for the purpose of Coal Exchange (s). In pursuance
of the provisions, Ministry of Coal has initiated the process of formulation of the Coal Exchange Rules,
which shall provide for the objectives and structure of the Coal Exchange (s) to be established in the
country.
(b): Out of the 131 coal blocks allocated under the Commercial Coal Mining Policy, 21 coal blocks have
obtained Mine Opening Permission and 12 coal blocks have commenced production as on 28th February,
2026. District wise details of these 12 coal blocks along with production details is as below:
Production
Production
Sl. Name of the (FY 25-26) till
State District Allottee (FY 24-25)
No. Coal Mine 28.02.2026
in MT
in MT
Gare Palma Jindal Power
1. 7.195 6.803
IV/1 Limited
Sarda
Gare Palma
2. Energy And 1.722 1.699
IV/7
Minerals Ltd.
Raigarh
Gare Palma
3. 4.001 3.345
IV/6
Chhattisgarh Jindal Steel
Gare Palma
And Power
4 & IV/2 and
Limited 6.236 6.231
5. Gare Palma
IV/3
Prakash
6. Surajpur Bhaskarpara Industries 0.077 0.940
Ltd.
Rajhara
Fairmine
North
7. Jharkhand Palamau Carbons 0.006 0.314
(Eastern &
Private Ltd
Central)
Gotitoria
Boulder
8 & Madhya (East) &
Narsinghpur Stone Mart 0.253 0.229
9. Pradesh Gotitoria
Private Ltd.
(West)
Takli-Jena-
Bellora Aurobindo
(North) & Reality And
10. Maharashtra Chandrapur 0.732 0.377
Takli-Jena- Infrastructure
Bellora Private Ltd.
(South)
Jindal Steel
11. Odisha Angul Utkal C And Power 3.362 3.384
Limited
Arunachal Namchik Coal Pulz
12. Changlang - 0.011
Pradesh Namphuk Private Ltd.
2(c): The details of penalties imposed against coal blocks allocated under commercial auction scheme post
2020 is at the Annexure.
(d): Government has approved the Revised Jharia Master Plan (JMP) in June, 2025 for dealing with Fire,
Subsidence & Rehabilitation of affected families of Jharia Coalfield. The initial phase of Revised JMP is
applicable to 81 most vulnerable sites and the initial phase is to be completed by December, 2028.
The fire is being extinguished by digging out through excavation or blanketing by overburden (OB). To
monitor the success of this process, Bharat Coking Coal Limited periodically conducts surveys through the
National Remote Sensing Centre (NRSC), Hyderabad, for delineation of surface fires.
As per the NRSC survey report of the year 2017-18, the surface fire area was 3.26 sq. km, which has
reduced to 1.53 sq. km in the year 2024-25. Further, as per the survey of the year 2020-21, there were 27
fire locations, out of which 17 have been dealt with by excavation and blanketing through OB as on date.
Mines of Argada, Barka-Sayal, Kuju, Hazaribagh and Rajrappa Areas of Central Coalfields Ltd. (CCL) are
located in Hazaribagh and Ramgarh districts of the State of Jharkhand, which are not a part of Jharia Master
Plan. Long-standing underground mine fire exists in Kuju Colliery, Kuju area, of CCL, located in Ramgarh
district of Jharkhand. Drone based Scientific study using Thermal Infra-Red Sensor (TIR Survey) has been
conducted by Central Mine Planning & Design Institute Limited (CMPDIL) to map the extent of mine fire.
Based upon this study, Mining Plan is under preparation at CMPDIL, to dig out the existing fire through
opencast working. In other Areas of CCL located in Ramgarh and Hazaribagh districts, there is no case of
long standing underground mine fire and landslides.
(e): South Eastern Coalfields Limited (SECL) has presently only one mine namely Amera OC situated in
Sarguja district of Chhattisgarh, where so far challenges as mentioned in Jharia master plan have not arisen.
(f): No coal block has been allocated in Keonjhar Lok Sabha Constituency since inception of Commercial
coal mining in 2020. However, Ministry of Coal has auctioned 26 coal mines in the State of Odisha under
commercial coal mine auction policy. These 26 coal mines have cumulative Peak Rated Capacity (PRC)
of 150.63 MTPA. These mines once operationalized are expected to provide an annual revenue of Rs
18,344 crore, attract capital investment of Rs 22,594 crore and provide employment to 2,03,652 persons.
****
3Annexure
(LOK SABHA STARRED QUESTION NO. 473 ANSWERED ON 25.03.2026)
Details of Performance Bank Guarantee deductions
Sl. Coal Allottee Non-Achievement of Appropriatio Appropriation Appropriated Not
No Mines Milestones n/ Amount (Rs) Appropriated
. Termination due to Court
order date Case
1 Marki M/s Yazdani Approval of Mining Plan 06-11-2023 ₹ 2,28,30,958.00 ₹ 2,28,30,958.00 ₹ 0.00
Mangli-II International Private
Limited
2 Marki M/s Sobhagya MS-II, Approval of Mine 22.05.2025 ₹ 8,84,17,773.98 ₹ 8,84,17,773.98 ₹ 0.00
Mangli Mercantile Limited Plan
IV
3 Dahegaon M/s Ambuja Cements MS-2, Approval of Mining 26.02.2026 ₹ 2,29,83,095.00 ₹ 2,29,83,095.00 ₹ 0.00
Gowari Limited Plan
4 Dhirauli Stratatech Mineral Environment Clearance- 29/02/2024 ₹ 46,91,68,386.87 ₹ 46,91,68,386.87 ₹ 0.00
Resources Private MS-3
Limited
5 Sahapur Sarda Energy & Environment Clearance- 29/02/2024 ₹ 6,88,95,341.57 ₹ 0.00 ₹ 6,88,95,341.57
West Minerals Limited MS-3
6 Sahapur M/s Chowgule and Delay in Environment 27/03/2024 ₹ 10,48,64,923.00 ₹ 0.00 ₹ 10,48,64,923.00
East Company Private Clearance
Limited.
7 Gondbahe M/s Mahan Energen Delay in Preparation of GR 15/02/2025 ₹ 1,69,04,063.00 ₹ 1,69,04,063.00 ₹ 0.00
ra Ujheni Ltd. (MS-1)
East
8 Beheraba Auro Coal Pvt. Ltd Delay in Preparation of GR 14/02/2025 ₹ 2,32,68,750.00 ₹ 2,32,68,750.00 ₹ 0.00
ndh North (MS-1)
Extension
4Details of Performance Bank Guarantee deductions
Sl. Coal Allottee Non-Achievement of Appropriatio Appropriation Appropriated Not
No Mines Milestones n/ Amount (Rs) Appropriated
. Termination due to Court
order date Case
9 Marwatol JSW Cement Limited Approval of Mining Plan 18/06/2025 ₹ 17,95,32,287.00 ₹ 0.00 ₹ 17,95,32,287.00
a VI (MS-2)
10 Choritand M/s Rungta Metals Mining Plan Approval 04.12.2025 ₹ 4,36,33,188.00 ₹ 0.00 ₹ 4,36,33,188.00
Tiliaya Private Limited
11 Patal East M/s RCR Steel Mining Plan Approval 23.12.2025 ₹ 1,25,25,322.30 ₹ 0.00 ₹ 1,25,25,322.30
Eastern Works Private
Part Limited
12 Jogeshwa South West Pinnacle 1.Prospecting License or 20.11.2023 ₹ 30,37,500.00 ₹ 30,37,500.00 ₹ 0.00
r & Khas Exploration Limited Notification under section 4
Jogeshwa of the CBA Act, 1957, as
r applicable
2.Completion of
Drilling/Exploration
3.Preparation of Geological
Report (GR) MS-1
13 Jogeshwa South West Pinnacle Preparation of Geological 10.02.2025 ₹ 30,37,500.00 ₹ 30,37,500.00 ₹ 0.00
r & Khas Exploration Limited Report (GR) not done
Jogeshwa within 24 months from
r allotment order date MS-1
14 Basantpur Goquest Solutions Preparation of Geological 11.03.2025 ₹ 23,47,407.00 ₹ 23,47,407.00 ₹ 0.00
Private Limited Report (GR)not done within
(Formerly known as 15 months from allotment
Gangaramchak order date MS-1
Mining Pvt. Ltd.)
15 Rauta Shreesatya Mines Preparation of Geological 10.06.2025 ₹ 14,17,500.00 ₹ 14,17,500.00 ₹ 0.00
Closed Private Limited Report (GR)not done within
24 months from allotment
order date MS-1
5Details of Performance Bank Guarantee deductions
Sl. Coal Allottee Non-Achievement of Appropriatio Appropriation Appropriated Not
No Mines Milestones n/ Amount (Rs) Appropriated
. Termination due to Court
order date Case
16 Rauta Shreesatya Mines 1.Prospecting License or 08.03.2024 ₹ 14,17,500.00 ₹ 14,17,500.00 ₹ 0.00
Closed Private Limited Notification under section 4
of the CBA Act, 1957, as
applicable
2.Completion of
Drilling/Exploration
3.Preparation of Geological
Report (GR) MS-1
17 Burakhap Shreesatya Mines Approval of Mine Plan, MS 12.06.2025 ₹ 10,87,79,469.00 ₹ 10,87,79,469.00 ₹ 0.00
Small Private Limited II
Patch
18 Urma M/s Auro Infra Preparation of Geological 01.08.2024 ₹ 2,16,00,000.00 ₹ 2,16,00,000.00 ₹ 0.00
Paharitola Private Limited Report (GR) not done
within 15 months from
allotment order date
19 Gondulpa M/s Adani Approval of Mine Plan, MS 03.08.2024 ₹ 18,78,73,420.00 ₹ 18,78,73,420.00 ₹ 0.00
ra Enterprises Limited II
20 Brinda & Dalmia Cement Approval of Mine Plan, MS 28.10.2025 ₹ 5,04,14,418.23 ₹ 5,04,14,418.23 ₹ 0.00
Sasai Bharat Limited II
21 Chakla Hindalco Industries Environment Clearance, MS 06.11.2024 ₹ 24,18,99,473.30 ₹ 0.00 ₹ 24,18,99,473.30
Ltd. (HIL) III
22 Jitpur Terri Mining Pvt. Approval of Mine Plan, MS 26.02.2026 ₹ 7,07,95,123.000 ₹ 7,07,95,123.000 ₹ 0.00
Ltd. II
23 Binja Assam Mineral Preparation of Geological 22.05.2025 ₹ 58,80,000.00 ₹ 58,80,000.00 ₹ 0.00
Development Corp. Report (GR) not done
Limited within 15 months from
allotment order date
6Details of Performance Bank Guarantee deductions
Sl. Coal Allottee Non-Achievement of Appropriatio Appropriation Appropriated Not
No Mines Milestones n/ Amount (Rs) Appropriated
. Termination due to Court
order date Case
24 Binja Assam Mineral Preparation of Geological 25.02.2026 ₹ 58,80,000.00 ₹ 58,80,000.00 ₹ 0.00
Development Corp. Report (GR) not done
Limited within 24 months from
allotment order date
25 Datima Shree Cement Mining Plan Approval 26.06.2025 ₹ 3,63,51,707.00 ₹ 3,63,51,707.00 ₹ 0.00
Limited
26 Kasta Jitusol Developers Approval of mine plan -MS 06.03.2024 ₹ 2,55,27,988.55 ₹ 2,55,27,988.55 ₹ 0.00
East Private Limited - 2
27 Utkal C JSPL Approval of mine plan -MS 14.02.2025 ₹ 27,06,30,820.00 ₹ 27,06,30,820.00 ₹ 0.00
- 2
28 Radhikap Vedanta Ltd Environment Clearance 21.07.2025 ₹ 29,23,55,117.68 ₹ 0.00 ₹ 29,23,55,117.68
ur West
29 Bankhui M/s Yazdani Preparation of Geological 21.10.2025 ₹ 58,85,625.00 ₹ 58,85,625.00 ₹ 0.00
International Private Report (GR) not completed
Limited within 15 months from
allocation
30 Bijahan M/s Mahanadi Mines Approval of mine plan -MS 05.02.2026 ₹ 21,59,52,375 ₹ 21,59,52,375 ₹ 0.00
and Minerals - 2
Private Limited
31 Garampa Assam Mineral Approval of mine plan -MS 08.03.2024 ₹ 4,39,26,310.13 ₹ 4,39,26,310.13 ₹ 0.00
ni Development - 2
Corporation
32 Koilajan Assam Mineral Approval of mine plan -MS 06.03.2024 ₹ 27,75,823.07 ₹ 27,75,823.07 ₹ 0.00
Development - 2
Corporation
Total ₹ 2,65,08,09,165.68 ₹ 1,70,71,03,512.83 ₹ 94,37,05,652.85