**Executive Summary**
This report, in response to Unstarred Question No. 383 answered on December 2, 2025, provides details regarding the completion of roads under the Pradhan Mantri Gram Sadak Yojana (PMGSY). It addresses complaints received, investigated, and resolved, specifically focusing on the State of Rajasthan. There is a timeline for completion of PMGSY-III is March 2026, and it states there is no cost overrun due to delay.
**Key Points / Main Content**
* **Grievance Redressal under PMGSY:**
* Timely redressal of grievances and their disposal have been prioritized through CPGRAM portal/PMO/VIP references and state governments.
* A dedicated grievance redressal App "MeriSadak" has been developed.
* Complaints are addressed on priority.
* **Complaint Statistics via CPGRAM Portal (Last Three Years):**
* **All India:** Total complaints: 5298, Resolved: 4986, Pending: 312.
* **Rajasthan:** Total complaints: 1010, Resolved: 954, Pending: 56.
* **Complaint Statistics via "MeriSadak" App (Last Three Years):**
* **All India:** Total complaints: 19,930, Resolved: 18,493, Pending: 1,273.
* **Rajasthan:** Total complaints: 1277, Resolved: 1277, Pending: 0.
* **PMGSY Road and Bridge Development in Rajasthan (Up to 26.11.2025):**
* 18,161 roads covering 78,267 km and 73 bridges have been sanctioned.
* 18,109 roads of 75,788 km and 65 bridges have been completed.
* **Project Details for Sri Ganganagar and Hanumangarh (Up to 27.11.2025):**
* **Sanctioned:**
* **Sri Ganganagar:** 178 Roads (1,178.165 km), 1 Bridge, Proposal Value: Rs. 318.51 Cr.
* **Hanumangarh:** 165 Roads (1,223.400 km), 0 Bridges, Proposal Value: Rs. 335.42 Cr.
* **Completed:**
* **Sri Ganganagar:** 177 Roads (1,158.06 km), 1 Bridge, Expenditure: Rs. 262.56 Cr.
* **Hanumangarh:** 165 Roads (1,184.88 km), 0 Bridges, Expenditure: Rs. 282.91 Cr.
* **Project Delays and Cost Overruns:**
* Only 1 road of 0.60 km length is pending under PMGSY-III in the district of Sri Ganganagar. The timeline for completion of PMGSY-III is March 2026.
* There is no cost overrun due to delay in the execution of projects.
**Impact Analysis**
**Ministry of Rural Development / Department of Rural Development**
* **Impact:** Requires the Department to address complaints and ensure timely disposal through various channels, including the "MeriSadak" app. They must also monitor project progress and completion rates under PMGSY.
* **Action Required:** Continue prioritizing grievance redressal, monitor project implementation, and ensure compliance with PMGSY guidelines. Access programme website "www.omms.nic.in ->Progress Monitoring ->State MPR Abstract Report" for detailed District wise report.
**State Government of Rajasthan**
* **Impact:** The state government is responsible for implementing PMGSY projects and addressing complaints within their jurisdiction.
* **Action Required:** Ensure timely completion of pending road projects, specifically the one road in Sri Ganganagar scheduled for completion by March 2026. Provide necessary compliance and ATRs (Action Taken Reports) regarding NQM (National Quality Monitors) inspections to the Central Government.
**Local Residents/Beneficiaries**
* **Impact:** Impacted by the timely and quality completion of road projects under PMGSY. Have access to a grievance redressal mechanism via the "MeriSadak" app.
* **Action Required:** Utilize the "MeriSadak" app to report any issues or complaints related to PMGSY road projects in their areas.
**Hon'ble MP Shri Bhajan LalJatav**
* **Impact:** Will be updated regarding the action taken in response to a complaint he raised.
* **Action Required:** Await communication on action taken regarding quality of PMGSY works.
Key Entities Referenced
Pradhan Mantri Gram Sadak Yojana (PMGSY): A rural road connectivity program aiming to provide all-weather access to eligible unconnected habitations.
Ministry of Rural Development: The central ministry responsible for implementing the PMGSY scheme.
Rajasthan: One of the states that the report focuses on
"MeriSadak" App: A grievance redressal application for complaints related to PMGSY.
O.I.H.
GOVERNMENT OF INDIA
MINISTRY OF RURAL DEVELOPMENT
DEPARTMENT OF RURAL DEVELOPMENT
LOK SABHA
UNSTARRED QUESTION NO. 383
ANSWERED ON 02/12/2025
COMPLETION OF ROADS UNDER PMGSY
383. Shri KuldeepIndora:
Will the Minister of RURAL DEVELOPMENT be pleased to state:
(a) the details and total number of complaints received through
public grievance portals or by State Governments regarding
corruption, use of substandard materials and misreporting of
completion dates in road projects under the Pradhan Mantri
Gram SadakYojana (PMGSY) during the last three years, State-
wise including Rajasthan;
(b) the details and total number of complaints have been
investigated, resolved and pending;
(c) the list of road developments and upgradation projects delayed
beyond their original deadlines in Rajasthan particularly in the
Sri Ganganagar-HanumangarhLokSabha Constituency; and
(d) the details of the cost overrun in these projects along with
their reasons for the delay?
ANSWER
MINISTER OF STATE IN THE MINISTRY OF RURAL DEVELOPMENT
(SHRI KAMLESH PASWAN)
(a) & (b): Under the Pradhan Mantri Gram SadakYojana (PMGSY)
timely redressal of grievances and their disposal has been
prioritized and grievances/complaints received through CPGRAM
portal/PMO/VIP references and through States in various categories
have been timely disposed of by the Department. Further, to bring
more transparency in the system a dedicated grievance redressal
App w.r.t. PMGSY has been developed in the Department viz.
"MeriSadak" App. Complaints received in various categories are
dynamic in nature and being disposed of as and when received on
priority after taking appropriate necessary action in timely manner.
Page 1 of 4One complaint by Shri BhajanLalJatav, Hon’ble MP
DholpurKarauli raised regarding quality in PMGSY Works of
Bharatpur, Dholpur&Karauli District was received during this period.
Department has taken immediate action and National Quality
Monitor (NQMs) were sent on field for immediate inspection which
was conducted in June & July 2025. The reports of the NQMs were
shared with State for providing necessary compliance. Upon receipt
of ATRs are from State Government, the action taken therein will be
apprised to Hon`ble MP.
Details of complaints received and disposed of in last three
years through the "CPGRAM Portal" including State of Rajasthan
under PMGSY is as per Table-1 below:
A: All India
Number of Final Reply
Financial Year Pendency
Complaints Received Provided
2022-23 1755 1605 150
2023-24 1623 1576 47
2024-25 1015 972 43
2025-26 (till
905 833 72
27.11.2025)
Total 5298 4986 312
B: State of Rajasthan
Number of Final Reply
Financial Year Pendency
Complaints Received Provided
2022-23 333 299 34
292
2023-24 286 6
2024-25 186 184 2
2025-26
199 185 14
(till 27.11.2025)
Total 1,010 954 56
Details of complaints received and disposed of in last three years
through the "MeriSadak" mobile application including State of
Rajasthan under PMGSY is as per Table-2 below:
Page 2 of 4Table:2
A: All India
Number of Complaints Final Reply
Financial Year Pendency
Received Provided
2022-23 2915 2455 460
2023-24 4905 4820 85
2024-25 8382 8162 220
2025-26 (till
3728 3056 508
27.11.2025)
Total 19,930 18,493 1,273
B: State of Rajasthan
Number of All disposed of.
Financial year
Complaints Received No pendency
2022-23 155 0
2023-24 386 0
2024-25 500 0
2025-26 (till
236 0
27.11.2025)
Total 1277 0
(c): Under PMGSY since its inception till date (26.11.2025), a total
of 18,161 roads covering 78,267 km of road length and 73 bridges
have been sanctioned under various interventions/verticals of the
PMGSY for the State of Rajasthan. Out of these, 18,109 roads of
75,788 km and 65 bridges have been completed by State. Details of
projects sanctioned and completed with expenditure in the district
of Sri Ganganagar and Hanumangarh of Rajasthan State till date (27-
11-2025) are as follows:-
District Name Sanctioned
No. of Road Length No. of Value of
Roads (Km) Bridges Proposal
(Rs. Cr.)
Sri 178 1,178.165 1 318.51
Ganganagar
Hanumangarh 165 1,223.400 - 335.42
Page 3 of 4District Name Completed
No. of Road No. of Expenditure including
Roads Length Bridges State share (Rs. Cr.)
(Km)
Sri 177 1,158.06 1 262.56
Ganganagar
Hanumangarh 165 1,184.88 - 282.91
Note: Only 1 road of 0.60 km length is pending under PMGSY-III in
the district of Sri Ganganagar. The timeline for completion of
PMGSY-III is March 2026. Detailed District wise report may be
accessed at programme website "www.omms.nic.in ->Progress
Monitoring ->State MPR Abstract Report".
(d): There is no cost overrun due to delay in execution of projects.
Hence, report may be treated as NIL.
*****