GOVERNMENT OF INDIA
DEPARTMENT OF SPACE
LOK SABHA
UNSTARRED QUESTION NO. 4157
TO BE ANSWERED ON WEDNESDAY, MARCH 18, 2026
DEVELOPMENT OF SATELLITE LAUNCH FACILITIES IN INDIA
4157. SHRI TANGELLA UDAY SRINIVAS:
Will the PRIME MINISTER be pleased to state:
(a) the number of new satellite launch facilities and launch pads
approved, under construction and operational in the country
during the last five years along with their designed payload
capacities and expected timelines for full commissioning, year
and State-wise;
(b) the funds sanctioned, released and utilised for establishment
or expansion of such facilities during the said period;
(c) the details of upcoming launch missions planned from these
facilities including the types of launch vehicles and payload
categories;
(d) whether any proposal for the development of such facilities
from States including Andhra Pradesh for a launch facility near
Kakinada is under consideration of the Government;
(e) if so, the status thereof including approvals, payload capacity
and funding pattern;(f) whether private participation and Foreign Direct Investment
(FDI) have been permitted in development of launch
infrastructure; and
(g) if so, the details thereof including regulatory safeguards
adopted?
ANSWER
MINISTER OF STATE IN THE MINISTRY OF PERSONNEL, PUBLIC
GRIEVANCES & PENSIONS AND IN THE PRIME MINISTER’S OFFICE
(DR. JITENDRA SINGH):
****
(a) As of now, two launch pads i.e. First Launch Pad (FLP) and
Second Launch Pad (SLP) are operational at Satish Dhawan
Space Centre (SDSC), Sriharikota, Andhra Pradesh. FLP caters
to the launches of PSLV & SSLV and SLP caters to the
launches of PSLV, GSLV & LVM3. Establishment of a Third
Launch Pad (TLP) at Satish Dhawan Space Centre, Sriharikota
has been approved by the Government of India in the year
2025 which will cater to the launch of Next Generation Launch
vehicles of ISRO. TLP is targeted to be established by 2029-30
timeframe.
In order to carry out the launches of Small Satellite Launch
Vehicle to Sun-synchronous Polar Orbit (SSPO) that is mostly
preferred for Earth Observation, a second launch site i.e.,
SSLV Launch Complex (SLC) in Kulasekarapattinam, Tamil
Nadu is being established. The second launch site is expected
to be commissioned during FY 2026-27 timeframe.(b) The funds sanctioned, released and utilised for establishment
or expansion of launch pad and related facilities during the
last five years is as in Annexure-I.
(c) Three missions each of PSLV and SSLV, mostly earth
observation satellites are planned to be launched from First
Launch Pad (FLP) during 2026-27 timeframe. Two missions
each of GSLV and LVM3, mostly for communication &
navigation satellites are planned to be launched during 2026-
27 timeframe.
The first developmental flight of NGLV from TLP is planned
during 2031-32 timeframe. The launches of SSLV from the
Second launch site at Kulasekarapattinam, Tamil Nadu is
expected during 2027-28 timeframe.
(d) & (e)
As of now, the Department of Space (DoS) has no proposal to
establish any other launch site elsewhere in the country.
(f) Yes. The Space sector reforms announced by the Government
of India during June, 2020 permits end to end space activities
including development of launch infrastructure. Following
these Indian National Space Promotion and Authorization
Centre (IN-SPACe) was created in Department of Space for
promoting, authorizing and overseeing the activities of Non-
Governmental Entities (NGEs) in Space sector. Foreign Direct
Investment (FDI) is permitted in development of launch
infrastructure as notified by Gazette notification dated
16.04.2024 by Department of Economic Affairs, Ministry of
Finance.(g) IN-SPACe has brought out the Norms, Guidelines and
Procedures (NGP) for Implementation of Indian Space Policy-
2023 in respect of Authorization of Space Activities, which
provides guidelines and criteria for authorization including
accountability, national security, sustainable and safe space
operations, and provides transparency and predictability to
the non-government entities seeking authorisation from
IN-SPACe. Guidelines and Standard Operating Procedure
including regulatory safeguards to be followed in automatic
as well as government routes for Foreign Direct Investment
(FDI) in space sector are already issued by the Department.
****Annexure-I
ANNEXURE REFERRED TO IN REPLY TO PART (b) OF LOK SABHA UNSTARRED QUESTION NO. 4157 TO BE ANSWERED ON
18.03.2026
Financial year 2020-21 to 2022-23
(Rs. in crore)
Sl. Name of Project
2020-21 2021-22 2022-23
No.
BE RE Actuals BE RE Actuals BE RE Actuals
1 Realization of Second 1000.00 1000.00 999.94 0.00 0.00 0.00 0.00 0.00 0.00
Vehicle Assembly
Building
2 Solid Propellant Space 8000.00 5000.00 5499.88 8000.00 6500.00 6299.99 3500.00 3900.00 3899.98
Booster Plant
3 PSLV Integration 11000.00 6000.00 5499.70 8000.00 4500.00 3679.14 4000.00 4000.00 3246.07
Facility
4 Launch Pad for SSLV 10000.00 584.00 78.74 11700.00 15482.00 15549.63 10000.00 1000.00 1172.99
5 Third Launch Pad 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 Augmentation of 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Infrastructure towards
enhancement of
launched capacity of
LVM 3Financial year 2023-24 to 2025-26
(Rs. in crore)
Sl. Name of Project
2023-24 2024-25 2025-26
No.
Actuals
BE RE Actuals BE RE Actuals BE RE (Feb 2026)
1 Realization of Second 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Vehicle Assembly
Building
2 Solid Propellant Space 2450.00 2450.00 2106.13 550.00 700.00 499.39 100.00 14.50 13.84
Booster Plant
3 PSLV Integration 4000.00 1500.00 711.41 2280.00 1700.00 930.91 100.00 7.00 5.31
Facility
4 Launch Pad for SSLV 10000.00 1000.00 36.78 10883.00 16270.00 13896.56 30000.00 230.00 148.65
5 Third Launch Pad 0.00 0.00 0.00 0.00 0.00 0.00 100.00 3.00 0.80
6 Augmentation of 0.00 0.00 0.00 0.00 0.00 0.00 2375.00 29.00 2.33
Infrastructure towards
enhancement of
launched capacity of
LVM 3