GOVERNMENT OF INDIA
MINISTRY OF NEW AND RENEWABLE ENERGY
LOK SABHA
UNSTARRED QUESTION NO. 1611
ANSWERED ON 29.07.2026
GREEN ENERGY CORRIDOR IN KARNATAKA
1611. DR. K SUDHAKAR:
SHRI ANURAG SINGH THAKUR:
Will the Minister of NEW AND RENEWABLE ENERGY be pleased to state:
(a) The current status of pending intra-State Green Energy Corridor Phase-I and Phase-II transmission
components in Karnataka and Himachal Pradesh which are among the States facing delays primarily
due to Right-of-Way (RoW) issues in difficult mountainous terrain forest clearance and land
acquisition issues along with the steps taken including Central intervention and financial support to
expedite their completion;
(b) the details of the integration plan for Pumped Storage Projects (PSPs) being developed by
Karnataka Power Corporation Limited (KPCL), Satluj Jal Vidyut Nigam Limited (SJVNL), National
Hydroelectric Power Corporation Limited (NHPC) and National Thermal Power Corporation Limited
(NTPC) and other developers in the said States with the Pumped Storage capacity targets envisaged
under the National Electricity Plan for 2029-30;
(c) whether the Government proposes to prepare a dedicated transmission master plan for Himachal
Pradesh and Karnataka considering its seismic vulnerability, recurring flood-induced damage and high
maintenance requirements and rapid renewable energy expansion in Koppal, Ballari, Vijayapura,
Gadag and Raichur rising grid congesion and the need for additional evacuation infrastructure
respectively and if so, the details thereof;
(d) the present status of transmission infrastructure proposed through Himachal Pradesh for evacuation
of power from the 13 GW Ladakh Renewable Energy project, including the expected timeline for its
completion; and
(e) the status, transmission capacity, estimated cost and expected timeline of high-capacity Inter-State
Transmission System projects proposed for evacuation of renewable energy from Karnataka's
Renewable Energy Zones?
ANSWER
THE MINISTER OF STATE FOR NEW & RENEWABLE ENERGY AND POWER
(SHRI SHRIPAD YESSO NAIK)
(a) Under the Intra-State Transmission System (InSTS) Green Energy Corridor (GEC) Phase-I scheme,
all sanctioned projects have been completed in both Himachal Pradesh and Karnataka.
Under InSTS GEC Phase-II, 08 packages have been sanctioned to Himachal Pradesh for creation of
transmission infrastructure for evacuation of 262 MW of renewable energy with Central Financial
Assistance (CFA) of Rs. 237.52 crore. As on 30.06.2026, 03 packages have been tendered and awarded.Under InSTS GEC Phase-II, 10 packages have been sanctioned to Karnataka for creation of
transmission infrastructure for evacuation of 2,640 MW of renewable energy with Central Financial
Assistance (CFA) of Rs. 341.96 crore. As on 30.06.2026, all 10 packages have been tendered and
awarded.
(b) As per Central Electricity Authority (CEA), the following Pumped Storage Projects (PSPs) have
been envisaged in National Electricity Plan for state of Karnataka:
• Saundatti PSP (1600 MW)-Integration plan includes power evacuation through Saundatti PSP-
Gadag II Substation and Saundatti PSP- Dhoni Substation (Karnataka Power Transmission
Company Limited).
• Shravathy PSP (2000 MW) (KPCL)- Integration plan includes power evacuation through the
Intra-state transmission system of Karnataka.
(c) Details of the transmission system identified for integration and evacuation of RE power from
Koppal, Ballari, Vijayapura and Gadag areas is provided at Annexure-I.
There is no separate dedicated transmission master plan exclusively on the basis of seismic or flood
vulnerability, suitable engineering measures are incorporated during planning, design and
implementation of transmission projects.
(d) In the Inter-State Green Energy Corridor Phase-II Scheme for 13 GW of RE evacuation project in
Ladakh, Front End Engineering and Design study has been completed. 300 acres of land has been
acquired at Leh by Power grid. A tender was floated under the competitive bidding mode. Only one bid
has been received. The completion period for the scheme is up to financial year 2029 -30.
(e) The high-capacity Inter-State Transmission System (ISTS) projects in Karnataka have been
implemented to integrate renewable energy (RE) generation across key zones like Tumkur, Koppal,
Gadag, Bidar, Bijapur, Davanagere, and Bellary. Details are given at Annexure-II.
*****Annexure-I to Lok Sabha Unstarred Question No. 1611 to be replied on 29/07/2026
Details of ISTS transmission system identified for integration and evacuation of RE power from
Koppal, Ballari, Vijayapura, Gadag and Raichur areas in Karnataka are as given below:
Sl. Name of the Transmission Project
No.
Transmission Scheme for integration of Renewable Energy Zone (Phase-II) in Koppal-II
1. (Phase-A) & (Phase-B) and Gadag-II (Phase- A) in Karnataka
System strengthening at Koppal-II and Gadag-II for integration of RE generation projects
2.
Transmission Scheme for integration of Bijapur REZ in Karnataka
3.
Transmission Scheme for integration of Davanagere / Chitradurga REZ
4.
Transmission Scheme for integration of Bellary REZ
Augmentation of transformation capacity by 2x500MVA (7th & 8th), 400/220kV ICTs at
5.
Tumkur (Pavagada) 400/220kV PS
Transmission system strengthening for integration of additional RE potential at
6. Davanagere (0.25 GW) and Bellary (2.75 GW)Annexure-II to Lok Sabha Unstarred Question No. 1611 to be replied on 29/07/2026
The details of ISTS transmission system under implementation for integration of RE
generations projects in Karnataka are as given below:
Sl. Name of the Transmission Project
No.
Transmission System for Ultra Mega Solar Power Park at Tumkur, Karnataka
1. (Phase-I & Phase-II)
Augmentation of Transformation Capacity by 1x500 MVA, 400/220kV ICT (6th) and
2.
common facility works at Pavagada (Tumkur) PS
Evacuation of power from RE sources in Koppal Wind Energy Zone (Karnataka)
3. (2500MW)
Augmentation of transformation capacity by 1x500 MVA, 400/220kV ICT (6th) at
4.
400/220kV Koppal PS in Karnataka
Transmission Scheme for Solar Energy Zone in Gadag (1000 MW & 1500 MW),
5. Karnataka-Part A: Phase-I & Phase-II
Augmentation of 1x500 MVA (6th), 400/220 kV transformation capacity at Gadag
6.
PS in Karnataka
ISTS Network Expansion scheme in Western Region & Southern Region for export
7. of surplus power during high RE scenario in Southern Region
Transmission Scheme for integration of Renewable Energy Zone (Phase-II) in
8.
Koppal-II (Phase-A) & (Phase-B) and Gadag-II (Phase- A) in Karnataka
System strengthening at Koppal-II and Gadag-II for integration of RE generation
9. projects
Transmission Scheme for Solar Energy Zone in Bidar (2500 MW)
10.
Augmentation of transformation capacity by 3x500 MVA, 400/220kV ICTs (6th - 8th)
11. and 1x1500 MVA,765/400kV ICT (4th) at Bidar PS
Transmission Scheme for integration of Tumkur-II REZ in Karnataka (1.5 GW
12. Solar)
Transmission Scheme for integration of Bijapur REZ in Karnataka
13.Sl. Name of the Transmission Project
No.
Transmission Scheme for integration of Davanagere / Chitradurga REZ
14.
Transmission Scheme for integration of Bellary REZ
Transmission system strengthening at Davanagere for integration of RE
15.
generation
Augmentation of transformation capacity by 2x500MVA (7th & 8th), 400/220kV ICTs
16.
at Tumkur (Pavagada) 400/220kV PS
Augmentation of transformation capacity by 2x500 MVA (9th & 10th), 400/220 kV
ICTs at Tumkur (Pavagada) 400/220 kV Pooling Station in Karnataka and
17.
Implementation of 1 Nos. of 220 kV line bay at Tumkur (Pavagada) 400/220 kV PS
for providing Connectivity to RE generation project
Inter-Regional Strengthening between SR Grid and WR Grid
18.
Transmission System for integration of additional RE capacity at Tumkur-II REZ
19. (2.7 GW)
Transmission system strengthening for integration of additional RE potential at
20. Davanagere (0.25 GW) and Bellary (2.75 GW)
Augmentation of transformation capacity by 1x500 MVA, 400/220 kV ICT (9th) at
21.
Davanagare PS
****