Will the Minister of NEW AND RENEWABLE ENERGY be pleased to state:
(a) whether it is a fact that solar energy projects that are on the books and waiting for
implementation are likely to be impacted by the Approved List of Cell Manufacturers (ALCM)
for solar cells notified by the Government and if so, the details thereof;
(b) whether it is also a fact that solar photovoltaic module manufacturers mandatorily use solar
PV cells only from those listed under the ALCM and if so, the details thereof;
(c) whether it is also a fact that the introduction of ALCM may create several challenges for
the Indian solar industry and if so, the details thereof;
(d) whether the notification of mandatory use of solar PV cells from ALCM has come into
force without ensuring adequate domestic cell manufacturing capacity and if so, the details
thereof;
(e) whether it is also a fact that India's module manufacturing capacity has reached
approximately 190 GW whereas domestic solar cell manufacturing capacity is only around 25
GW and if so, the details thereof; and
(f) whether it is also a fact that India's annual solar installation requirement is estimated at about
50 GW and if so, the details thereof?
ANSWER
THE MINISTER OF NEW & RENEWABLE ENERGY, CONSUMER AFFAIRS &
FOOD AND PUBLIC DISTRIBUTION AND EDUCATION.
(SHRI PRALHAD JOSHI)
(a) to (f) A Statement is laid on the Table of the House.
*****STATEMENT
Statement referred to in reply to parts (a) to (f) of the Lok Sabha Starred
Question No. 352 to be answered on 12.08.2026 regarding ‘Impact of ALCM Notification
on Solar Energy Projects’
(a) & (b) On 09.12.2024, Ministry of New & Renewable Energy (MNRE) had issued the
framework for implementation of Approved List of Models & Manufacturers (ALMM) List-II
for solar photovoltaic (PV) cells and as per various clarifications/ amendments issued thereto,
certain specified projects are mandated to use solar PV modules from ALMM List-I (for solar
PV modules) and solar PV cells from ALMM List-II (for solar PV cells) as per the terms and
conditions specified in this regard by MNRE, which are broadly summarised as follows:
(i) For projects awarded through bidding, if last date of bid submission is on or before the cut-
off date of 31.08.2025 (the date falling after one month of the publication of initial ALMM
List-II dated 31.07.2025), the projects are exempt from ALMM List-II (for solar cells), else
not. The applicability of this provision is to bids which were live as on 28.07.2025. However,
if the bid conditions in tenders where the last date of bid submission was between 09.12.2024
(the date of issuance of MNRE’s Office Memorandum No. 283/59/2024-GRID SOLAR dated
09.12.2024 for implementation of ALMM for solar PV cells) and 28.07.2025 (the date of
amendment to MNRE’s aforesaid Office Memorandum dated 09.12.2024, vide MNRE’s Office
Memorandum No. 283/59/2024-GRID SOLAR dated 28.07.2025), provided for usage of solar
PV cells from ALMM List-II for solar PV cells, such conditions will remain valid.
(ii) For Net-Metering & Open Access Projects, if commissioned by 31.12.2026, the projects
are exempt from ALMM List-II for solar cells, else not.
On 18.07.2026, Ministry of New & Renewable Energy has granted additional seven months’
time-extension beyond 31.05.2026, till 31.12.2026, to Net-Metering / Open Access renewable
power projects, for commissioning with exemption from ALMM List-II for solar PV cells.
Further, the projects which are awarded through bidding, were already covered under ALMM
List-II for solar PV cells, subject to specified conditions, even much prior to the aforesaid
extension and bidders for such projects would have duly taken into account the provisions
regarding compliance to ALMM List-II for solar PV cells, while submitting their bids for such
projects.
Thus, sufficient advance notice period has been provided in respect of implementation of
ALMM List-II for solar PV cells to avoid any challenges to projects under implementation.
Further, the Government has not issued any blanket order mandating that solar photovoltaic
module manufacturers mandatorily use solar PV cells only from those listed under ALMM
List-II.
(c) Overall policy for implementation of ALMM List-II for solar PV cells has been designed
keeping in view the overall interest of the solar sector and after duly taking into consideration
the interests of various stakeholders within the solar sector including solar power developers,
solar PV module manufacturers, solar cell manufacturers, Net-Metering/Open Access
renewable power project developers, etc. and aims at overall long-term benefit of the Indian
solar industry, while overcoming short-term challenges, if any.
(d) Projects availing Central Financial Assistance (CFA) under PM Surya Ghar: Muft Bijli
Yojana and components B & C of PM-KUSUM Scheme were already mandated to use
domestically manufactured solar PV modules and cells. Hence these were already included inthe past demand projections. Further, not all projects, which get commissioned after
31.12.2026, are mandated to use solar PV cells from ALMM List-II, with projects having
exemption from ALMM List-II for solar PV cells, including the following:
i. Projects with last date of bid submission on or prior to 09.12.2024, are already exempt
from ALMM List-II for solar PV cells, thereby creating a market for solar PV modules
which are in ALMM List-I (for solar PV modules) but do not use solar PV cells from
ALMM List-II (for solar PV cells)
ii. Residential rooftop solar projects under ‘Give-it-U p’ category of PM Surya Ghar: Muft
Bijli Yojana, opting for giving up Central Financial Assistance (CFA) under the
scheme, have also been exempted from ALMM List-II (for solar PV cells) till the end
of the scheme, i.e. 31st March 2027, subject to the condition that such applications are
made mandatorily through PMSG:MBY National Portal only.
iii. Private Behind-The-Meter solar power plants solely used for captive consumption by a
consumer or group of consumers, subject to specified conditions, are already exempt
from both ALMM List-I (for solar PV modules) as well as ALMM List-II (for solar PV
cells).
(e) As of 07.08.2026, the installed solar PV module manufacturing capacity in India, as
enlisted in ALMM List-I for solar PV modules, is around 213 GW and the installed solar PV
cell manufacturing capacity in India, as enlisted in ALMM List-II for solar PV cells, is around
32 GW.
(f) The capacity addition for solar power in India in FY 2025-26 was around 45 GW. The actual
requirement / demand may be somewhat higher than this on account of DC overloading
undertaken for some utility scale solar power projects.
*****