**Executive Summary**
The document provides answers to unstarred question No. 227 in Lok Sabha, answered on January 29, 2026, regarding the implementation of Pradhan Mantri Krishi Sinchayee Yojana (PMKSY) in Andhra Pradesh. The question addresses the number of proposals, funds utilized, physical progress, beneficiaries, and monitoring activities under various components of PMKSY. Annexures provide detailed data on specific projects and assistance.
**Key Points / Main Content**
* **PMKSY Components and Implementation:**
* PMKSY is an umbrella scheme with components implemented by the Ministry of Jal Shakti, the Department of Land Resources, and the Department of Agriculture and Farmers Welfare.
* **New Proposals and Approvals:**
* No new proposals were received or approved under AIBP, HKKP-SMI, and CADWM in Andhra Pradesh during the last five years.
* **HKKP-RRR:**
* Rejuvenation of 135 water bodies was sanctioned under HKKP-RRR with a total estimated cost of Rs. 70.72 crore, including Rs. 42.432 crore of central assistance.
* **PMKSY-PDMC:**
* 305.279 thousand hectares have been brought under micro irrigation with central assistance of Rs. 946.42 crore.
* **WDC Component:**
* Central assistance of Rs. 380.76 crore was released for 59 projects in 13 districts.
* Andhra Pradesh government utilized Rs. 360.02 crore from 2021-22 to date.
* **Monitoring and Evaluation:**
* The Central Water Commission (CWC) monitors projects under AIBP, CADWM, and SMI-RRR.
* Third-party monitoring is in place for WDC-PMKSY.
* National Institute of Rural Development and Panchayati Raj, Hyderabad, conducted a mid-term evaluation of WDC-PMKSY projects.
* Evaluation of the PDMC Component was taken up by the NITI Aayog during 2020-21.
**Impact Analysis**
**Government of Andhra Pradesh**
* **Impact:** Responsible for project implementation, fund utilization, and potential for improved irrigation and water management.
* **Action Required:** Utilize released funds effectively and ensure proper project monitoring and evaluation.
**Farmers/Farmer Groups/SHGs in Andhra Pradesh**
* **Impact:** Beneficiaries of the PMKSY scheme through improved irrigation facilities, water availability, and enhanced agricultural productivity.
* **Action Required:** Participate in the PMKSY projects, adopt efficient irrigation practices, and monitor the progress of implemented projects.
**Ministry of Jal Shakti, Department of Land Resources, and Department of Agriculture and Farmers Welfare**
* **Impact:** Responsible for overseeing the implementation of PMKSY components.
* **Action Required:** Ensure timely release of funds, monitor project progress, conduct evaluations, and address implementation challenges.
Key Entities Referenced
Pradhan Mantri Krishi Sinchayee Yojana (PMKSY): A central government scheme to enhance water efficiency and improve water management in agriculture.
Ministry of Jal Shakti: The central government ministry responsible for water resources, river development, and Ganga rejuvenation; key implementer of PMKSY.
Andhra Pradesh: Indian state where the implementation of PMKSY is being discussed.
Accelerated Irrigation Benefit Programme (AIBP): A major component under PMKSY implemented by the Ministry of Jal Shakti.
Har Khet Ko Pani (HKKP): A major component under PMKSY implemented by the Ministry of Jal Shakti.
GOVERNMENT OF INDIA
MINISTRY OF JAL SHAKTI
DEPARTMENT OF WATER RESOURCES, RIVER DEVELOPMENT & GANGA REJUVENATION
LOK SABHA
UNSTARRED QUESTION NO. 227
ANSWERED ON 29.01.2026
IMPLEMENTATION OF PMKSY IN ANDHRA PRADESH
227. SHRI PUTTA MAHESH KUMAR:
SHRI MAGUNTA SREENIVASULU REDDY:
Will the Minister of JAL SHAKTI be pleased to state:
(a) the details regarding the total number of proposals received and approved under each component of
Pradhan Mantri Krishi Sinchayee Yojana (PMKSY) during the last five years, yearwise and State-wise
including district-wise in Andhra Pradesh;
(b) the details regarding the total amount of funds approved, released and utilised under each component of
PMKSY during the last five years, year-wise, State-wise and district-wise in Andhra Pradesh;
(c) the details regarding physical progress including projects under approval stage for Andhra Pradesh,
year-wise, component-wise and district-wise;
(d) the details regarding the number of beneficiaries (farmers/farmer groups/SHGs) covered under each
component, year-wise, State-wise and district-wise in Andhra Pradesh; and
(e) the details regarding monitoring, evaluation and audit actions taken (Central/State monitoring visits,
third-party evaluations or other audit observations) for PMKSY projects in Andhra Pradesh during the said
period and the remedial measures taken thereon?
ANSWER
THE MINISTER OF STATE FOR JAL SHAKTI
(SHRI RAJ BHUSHAN CHOUDHARY)
(a) to (d) PMKSY is an umbrella scheme, consisting of two major components being implemented by
Ministry of Jal Shakti, namely, Accelerated Irrigation Benefit Programme (AIBP), and Har Khet Ko Pani
(HKKP). HKKP, in turn, consists of Command Area Development and Water Management (CADWM),
Surface Minor Irrigation scheme (SMI), Repair-Renovation-Restoration of water bodies (RRR), and
Ground Water Management. However, during approval for continuation of PMKSY during 2021-26,
Ground Water Management Component was only approved for committed liabilities.
In addition, Watershed Development component (WDC) of PMKSY is being implemented by
Department of Land Resources. Further, Per Drop More Crop (PDMC) was implemented by Department of
Agriculture and Farmers Welfare (DoA& FW) under the umbrella of PMKSY during 2016-22, which is
now being implemented by DoA& FW under Rashtriya Krishi Vikash Yojana (RKVY).
Under AIBP, HKKP-SMI and CADWM, no new proposal received and approved during the last
five year in Andhra Pradesh.
1Further under HKKP-RRR, the rejuvenation of 135 water bodies at a total estimated cost of Rs. 70.72
crore with Rs. 42.432 Crore Central Assistance were sanctioned during 2021-22. The details are annexed as
Annexure-I.
Apart from the above, under PMKSY-PDMC, 305.279 thousand hectare area has been brought under
micro irrigation in Andhra Pradesh with central assistance of Rs. 946.42 Crore during last five years. The
details are annexed as Annexures-II.
Similarly, under WDC component of PMKSY, the Central Assistance of Rs. 380.76 Crore was
released for 59 projects in 13 districts of Andhra Pradesh. Out of Rs. 380.76 Crore, Andhra Pradesh
government has utilized Rs. 360.02 Crore from 2021-22 to till date. The details are annexed as Annexures-
III.
(e) Central Water Commission (CWC) regularly monitors the projects under three components of PMKSY
namely AIBP, CADWM & SMI-RRR. The concurrent evaluation by an independent agency and audit of
the scheme, to be undertaken by the State Government, which has not been carried out by the Government
of Andhra Pradesh.
Under WDC-PMKSY, a third-party agency has been engaged through AP Procurement tenders and
the agency is regularly submitting the field observation reports as per the prescribed MoU norms. Further,
Department of Land Resources at Central level has engaged National Institute of Rural Development and
Panchayati Raj, Hyderabad for Mid-Term evaluation of WDC-PMKSY projects across all States/UTs
including Andhra Pradesh. The evaluation of the PDMC Component was taken up by the NITI Aayog
during 2020-21.
***
2ANNEXURE-I
ANNEXURE REFERRED TO IN REPLY TO PART (a) to (d) OF UNSTARRED QUESTION NO.
227 TO BE ANSWERED IN LOK SABHA ON 29.01.2026 REGARDING “IMPLEMENTATION
OF PMKSY IN ANDHRA PRADESH”.
Details under PMKSY-RRR
Sl.No. Year Project District Estimated Expenditure incurred Physical progress and
cost (in till November 25 (in number of
Crore) Crore) beneficiaries
1 2021-22 RRR of 80 WB’s-70.72 Nil expenditure. Nil
135 Prakasam However, Mother
Water District, sanction of Rs. 4.5 Crore
Bodies 33 WB’s - issued during 2025-26
Anantapur
District,
22 WB’s-
NelloreDistrict
3ANNEXURE-II (a)
ANNEXURE REFERRED TO IN REPLY TO PART (a) to (d) OF UNSTARRED QUESTION NO.
227 TO BE ANSWERED IN LOK SABHA ON 29.01.2026 REGARDING “IMPLEMENTATION
OF PMKSY IN ANDHRA PRADESH”.
District wise area covered under Micro Irrigation in Andhra Pradesh through PDMC
Area in Ha
S.No District 2020-21 2021-22 2022-23 2023-24 2024-25 Total
1 Ananthapuramu - 3687 13697 12404 17642 47430
2 YSR Kadapa - 2893 9982 10578 13045 36498
3 Prakasam - 1437 8851 9725 10406 30419
4 Chittoor - 1483 6681 4936 10065 23165
5 Kurnool - 1350 4509 4692 5653 16204
6 Annamayya - - 10782 7753 12153 30688
7 Sri Satya Sai - - 9348 7629 12046 29023
8 SPSR Nellore - 398 3437 2675 4554 11064
9 East Godavari - 561 2941 2228 3634 9364
10 West Godavari - 746 162 115 282 1305
11 Eluru - - 4658 3711 6648 15017
12 Nandyal - - 4438 3688 5058 13184
13 Guntur - 445 560 570 574 2149
14 Krishna - 251 280 225 415 1171
15 Palnadu - - 1582 2963 1925 6470
16 NTR - - 1803 1703 1871 5377
17 Tirupathi - - 1632 1586 2406 5624
18 Vizianagaram - 432 891 624 982 2929
19 Srikakulam - 591 539 608 1658 3396
20 Bapatla - - 1209 1072 1417 3698
21 Visakhapatnam - 380 68 22 100 570
22 Kakinada - - 1053 773 1511 3337
23 Anakapalli - - 832 829 1391 3052
24 Parvathipuramu Manyam - - 552 490 1535 2577
25 Alluri Sitharama Raju - - 244 274 816 1334
26 Konaseema - - 44 97 93 234
Total - 14654 90775 81970 117880 305279
ANNEXURE-II (b)
ANNEXURE REFERRED TO IN REPLY TO PART (a) to (d) OF UNSTARRED QUESTION NO.
227 TO BE ANSWERED IN LOK SABHA ON 29.01.2026 REGARDING “IMPLEMENTATION
OF PMKSY IN ANDHRA PRADESH”.
Central Assistance released under PDMC during last 5 years in the state of Andhra Pradesh
States 2020-21 2021-22 2022-23 2023-24 2024-25 Total
Andhra Pradesh 100.00 180.00 222.82 105.75 337.85 946.42
4ANNEXURE-III (a)
ANNEXURE REFERRED TO IN REPLY TO PART (a) to (d) OF UNSTARRED QUESTION NO.
227 TO BE ANSWERED IN LOK SABHA ON 29.01.2026 REGARDING “IMPLEMENTATION
OF PMKSY IN ANDHRA PRADESH”.
The list of watershed development projects approved under the WDC-PMKSY in Andhra Pradesh
No. of Projects sanctioned
Sl. No. Name of the District
during FY2021-22
1 Ananthapuramu 7
2 Sri Sathya Sai 3
3 Chittoor 7
4 Annamayya 10
5 YSR Kadapa 9
6 Kurnool 5
7 Nandyal 2
8 Prakasam 8
9 Visakhapatnam 1
10 Anakapalli 2
11 Alluri Sitharama Raju 1
12 Vizianagaram 3
13 Parvathipuram Manyam 1
Total 59
ANNEXURE-III (b)
ANNEXURE REFERRED TO IN REPLY TO PART (a) to (d) OF UNSTARRED QUESTION NO.
227 TO BE ANSWERED IN LOK SABHA ON 29.01.2026 REGARDING “IMPLEMENTATION
OF PMKSY IN ANDHRA PRADESH”.
The details regarding the total amount of funds approved, released and utilised under WDC-
PMKSY in Andhra Pradesh
(Rs. in crore)
Funds utilized
Sl. Funds Funds F.Y F.Y F.Y F.Y F.Y
District
No. approved released 2021-2022-2023-2024- 2025- Total
22 23 24 25 26
1 ALLURI SITHARAMA RAJU 11.00 0.00 1.25 2.03 1.48 2.52 7.28
2 ANAKAPALLI 22.00 0.00 1.46 1.98 5.63 2.40 11.47
3 ANANTHAPURAMU 63.47 0.00 7.81 7.71 11.24 12.68 39.45
4 ANNAMAYYA 103.88 0.00 9.15 16.01 15.99 27.14 68.29
5 CHITTOOR 60.59 0.00 4.81 15.19 10.90 14.03 44.93
6 KURNOOL 53.41 0.00 6.11 7.90 8.70 11.61 34.31
7 NANDYAL 21.48 380.76 0.00 2.88 1.23 4.93 5.54 14.58
8 PARVATHIPURAM MANYAM 10.62 0.00 1.53 2.32 1.78 1.87 7.50
9 PRAKASAM 67.48 0.00 6.16 8.41 16.32 15.03 45.92
10 SRI SATHYA SAI 25.28 0.00 3.43 3.09 8.37 5.36 20.25
11 VISAKHAPATNAM 11.00 0.00 1.16 2.75 0.61 1.56 6.08
12 VIZIANAGARAM 17.96 0.00 1.28 1.95 4.80 2.49 10.53
13 YSR KADAPA 87.15 0.00 11.03 11.85 10.87 15.69 49.43
Grand Total 555.31 380.76 0.00 58.06 82.43 101.60 117.92 360.02
5ANNEXURE-III (c)
ANNEXURE REFERRED TO IN REPLY TO PART (a) to (d) OF UNSTARRED QUESTION NO.
227 TO BE ANSWERED IN LOK SABHA ON 29.01.2026 REGARDING “IMPLEMENTATION OF
PMKSY IN ANDHRA PRADESH”.
District-wise details of assets created under WDC-PMKSY in Andhra Pradesh
SI. Name of the Check Dam / Farm Pond / Nallah Percolation
Others Total
No. District Check Wall Dugout Pond Bund Tank
1 Annamayya 158 1042 907 77 211 2395
2 Prakasam 55 1220 317 81 40 1713
3 YSR Kadapa 114 1128 114 31 111 1498
4 Ananthapuramu 153 988 15 4 337 1497
5 Chittoor 97 10 960 173 68 1308
6 Kurnool 84 1110 1 9 96 1300
7 Sri Sathya Sai 49 682 8 3 98 840
8 Nandyal 36 500 9 5 174 724
9 Anakapalli 25 39 81 50 73 268
Parvathipuram
10 0 51 96 20 99 266
Manyam
11 Vizianagaram 63 32 9 12 63 179
Alluri Sitharama
12 3 41 29 43 40 156
Raju
13 Visakhapatnam 25 3 2 4 77 111
Total 862 6846 2548 512 1487 12255
6STATEMENT REFERRED TO IN PART (a) TO (d) OF THE REPLY TO LOK
SABHA UNSTARRED QUESTION NO 227 DUE FOR REPLY ON 29.01.2026
Annexure-III (d)
District-wise details of number of beneficiaries (farmers/farmer groups/SHGs) covered
under WDC-PMKSY in Andhra Pradesh
F.Y F.Y F.Y
F.Y 2024-25
2022-23 2023-24 2025-26
SI.
District Farmers / Farmers / Farmers / Farmers / Total
No.
Farmer Farmer Farmer SHGs Farmer
Groups Groups Groups Groups
Alluri Sitharama
1 0 663 74 264 122 1123
Raju
2 Anakapalli 47 962 137 1743 106 2995
3 Ananthapuramu 188 3384 521 1617 717 6427
4 Annamayya 249 4780 1075 4480 1629 12213
5 Chittoor 130 3247 393 3072 709 7551
6 Kurnool 181 2759 425 1665 748 5778
7 Nandyal 80 931 252 674 387 2324
Parvathipuram
8 15 793 130 283 68 1289
Manyam
9 Prakasam 126 2586 839 1791 709 6051
10 Sri Sathya Sai 79 1266 397 1157 324 3223
11 Visakhapatnam 49 894 110 852 47 1952
12 Vizianagaram 17 1169 90 1404 49 2729
13 Ysr Kadapa 283 5255 413 1407 763 8121
Total 1444 28689 4856 20409 6378 61776
*****