See Full Document Text
GOVERNMENT OF INDIA
MINISTRY OF STATISTICS AND PROGRAMME IMPLEMENTATION
LOK SABHA
UNSTARRED QUESTION No.617
TO BE ANSWERED ON 22.07.2026
INEQUALITY IN MPLADS WORKS
617. SHRI SUKHJINDER SINGH RANDHAWA:
Will the Minister of STATISTICS AND PROGRAMME
IMPLEMENTATION be pleased to state:
(a) whether the Government is aware of such cases in which Member
of Parliament Local Area Development (MPLAD) works of the MPs
belonging to the opposition party are delayed and their works are not
approved on time;
(b) whether the Government proposes to take punitive action against
such officers;
(c) if so, the reaction of the Government thereto;
(d) the number of such works in Gurdaspur district of Punjab which
could not be started or completed even after months of
recommendations or are being repeatedly recommended;
(e) whether the Government is likely to take cognizance in the matter
in which the BDPO Dera Baba Nanak herself said in the DISHA
committee in front of the entire administration that she would not get
the work done from the MPLAD fund even if you go to court and she
is under pressure of the local MLA; and
(f) if so, the details thereof?
ANSWER
MINISTER OF STATE (INDEPENDENT CHARGE) OF THE MINISTRY OF
STATISTICS AND PROGRAMME IMPLEMENTATION, MINISTER OF
STATE (INDEPENDENT CHARGE) OF THE MINISTRY OF PLANNING
AND MINISTER OF STATE IN THE MINISTRY OF CULTURE [RAO
INDERJIT SINGH]
(a) to (c) Under the MPLAD Scheme, Hon’ble Member of Parliament
send their recommendations of development works directly toDistrict Authorities through eSAKSHI portal and the same are
sanctioned and implemented by the District Authorities in
accordance with the administrative, financial and technical rules of
the concerned State/UT Governments and in accordance with the
Guidelines on MPLADS.
As per the MPLADS Guidelines, the Implementing District Authority
shall, before sanctioning any work, ensure that all requisite statutory
and regulatory clearances have been obtained from the competent
authorities, that the work conforms to the MPLADS Guidelines, and
that a written undertaking has been obtained from the concerned
User Agency confirming its willingness to bear the operation and
maintenance costs of the proposed asset from its own resources.
As per Para 4.3.4 of the MPLADS Guidelines 2023, in case of material
breach of MPLADS Guidelines by any individual/authority concerned,
he/she shall become liable for disciplinary/penal action. The
government of the State/UT concerned shall fix responsibility and
take necessary disciplinary action against the erring/delinquent
officials/implementing agencies/vendors etc. in all such cases of
material breach and wilful non-compliance of MPLADS Guidelines.
However, it has been observed that delays in the issuance of
administrative and technical sanctions for works recommended
under the MPLAD Scheme are generally attributable to factors such
as submission of incomplete proposals, local disputes, constraints
relating to land availability or site feasibility, requirements of
statutory clearances, and technical issues at the district level. As per
the MPLADS Guidelines, the responsibility for timely scrutiny,
sanction, and execution of works rests with the District Authorities.
Whenever instances of inordinate delay are brought to the notice of
the Ministry, the concerned State/UT Government and District
Authority are requested to examine the matter and take appropriate
administrative action against the responsible officials under the
applicable service rules. They are also advised to strengthen internal
monitoring and oversight mechanisms to ensure timely
implementation of works recommended by Hon’ble Members of
Parliament.
(d) to (e) As per Para 3.2.4 of the MPLADS Guidelines, 2023, the
sanction/rejection in respect of all recommendations made by the
Member of Parliament shall be issued by the Implementing District
Authority within 45 days from the date of receipt of the
recommendations to the Implementing District Authority.As per para 3.2.6 of the MPLADS Guidelines, 2023, the period of
operation of model code of conduct notified by the Election
Commission, as applicable to the jurisdiction of a particular
Implementing District Authority, shall not be included in the
reckoning of time limits as mentioned in para 3.2.4 of the MPLADS
Guidelines, 2023.
As per Para 3.2.12 of the MPLADS Guidelines, 2023, the sanction
letter issued by the Implementing District Authority shall stipulate a
time limit for completion of the work by the Implementing Agency,
which should generally not exceed one year. In exceptional cases,
for instance in difficult/ hilly terrain, etc., where the implementation
time is likely to exceed one-year, specific justification for the same
shall be incorporated in the sanction letter.
As per the information available on the eSAKSHI portal as on
20.07.2026, out of the 304 works recommended under MPLADS in
Gurdaspur Lok Sabha Constituency during 18th LS tenure, 4 works
remained unsanctioned after 45 days of recommendation. Further,
out of the 268 sanctioned works, 57 works have not been completed
even after one year of sanction.
As reported by the District Authority, the Deputy Commissioner,
Gurdaspur, issued a show-cause notice to the then Block
Development and Panchayat Officer (BDPO), Dera Baba Nanak, vide
Letter No. 327 dated 15.06.2026. The District Authority has further
reported that Letter No. 4412 dated 07.07.2026 was issued to the
Executive Engineer, Public Works Department, Gurdaspur, with
reference to the proceedings of the District Development
Coordination and Monitoring Committee (DISHA) meeting held on
17.02.2026. Further, the State Nodal Authority, Punjab has informed
that all the pending development works recommended by the Hon'ble
Member of Parliament under MPLADS are being reviewed in
accordance with the extant provisions of the Scheme for their timely
execution and completion.
*****