**Executive Summary**
This document presents the Ministry of Power's response to Unstarred Question No. 17 in the Lok Sabha, answered on January 29, 2026, regarding installed power capacity. It outlines the composition of India's installed power capacity as of December 31, 2025, and details initiatives taken to promote renewable energy and nuclear power, targeting 500 GW of non-fossil energy capacity by 2030 and 100GW of nuclear power by 2047. The document also addresses measures to strengthen power infrastructure in the Chatra Parliamentary Constituency of Jharkhand.
**Key Points / Main Content**
* **Installed Power Capacity (as of 31.12.2025)**
* Total installed capacity: 513,730 MW
* Fossil fuel sources: 246,942 MW
* Non-fossil fuel sources: 266,788 MW
* Annexure-I provides a detailed breakdown by source (coal, lignite, gas, diesel, hydro, wind, solar, nuclear, etc.) and percentage.
* **Initiatives for Renewable Energy (RE) Capacity Addition:**
* 100% Inter State Transmission System (ISTS) charges waived for solar and wind power projects commissioned by June 30, 2025, with tapering off till June 2028. This includes co-located BESS, Hydro PSP, Green Hydrogen, and offshore wind projects commissioned by specified deadlines.
* Standard Bidding Guidelines issued for Grid Connected Solar, Wind, Wind-Solar Hybrid, and Firm & Dispatchable RE projects.
* Ministry of New & Renewable Energy (MNRE) issued Bidding Trajectory for RE power procurement bids of 50 GW/annum by Renewable Energy Implementing Agencies (REIAs) from FY 2023-24 to FY 2027-28.
* 100% Foreign Direct Investment (FDI) permitted under the automatic route.
* Support for laying new transmission lines and creating sub-stations under the Green Energy Corridor Scheme.
* Transmission plan prepared till 2032.
* Implementation of a scheme for setting up Solar Parks and Ultra Mega Solar Power projects.
* Launch of various schemes including PM-KUSUM, PM Surya Ghar Muft Bijli Yojana, National Green Hydrogen Mission, and Viability Gap Funding (VGF) Scheme for Offshore Wind Energy Projects.
* Approval of Viability Gap Funding (VGF) schemes for Battery Energy Storage Systems (BESS).
* Notification of Renewable Purchase Obligation (RPO) / Renewable Consumption Obligation (RCO) trajectory till 2029-30.
* Issuance of “Strategy for Establishments of Offshore Wind Energy Projects”.
* Implementation of Production Linked Incentive (PLI) scheme for High Efficiency Solar PV Modules.
* Promotion of Pumped Storage Projects (PSPs)
* **Nuclear Energy Expansion:**
* Target of 100 GW nuclear power capacity by 2047.
* Launch of a dedicated Nuclear Energy Mission with an allocation of ₹20,000 crore to develop Small Modular Reactors (SMRs) by 2033.
* Enactment of SHANTI Act, 2025 to harness nuclear energy with public and private sector involvement.
* Upgrading Bharat Small Reactors (BSRs).
* Enhancing fuel security through new uranium discoveries.
* Formation of joint venture ASHVINI by NPCIL and NTPC.
* **Other Initiatives:**
* National Green Hydrogen Mission targeting at least 5 MMT per annum of green hydrogen capacity by 2030.
* India achieved 50% installed electricity capacity from non-fossil fuel sources in June 2025.
* **Jharkhand Power Infrastructure**
* Two thermal power projects are under construction (details in Annexure-II).
* Steps are being taken to strengthen power infrastructure in the Chatra Parliamentary Constituency.
* **Strengthening of Transmission Infrastructure**
* 220/132/33 kV Grid Sub-Station, Itkhori has been constructed.
* Five Grid Sub-Stations are under implementation.
* **Strengthening of Distribution Infrastructure**
* Distribution works amounting to Rs 116.8 Cr have been sanctioned for Chatra Parliamentary constituency under RDSS.
* Household electrification works amounting to Rs 7.04 Cr have been sanctioned under RDSS for 1615 households in Chatra Parliamentary constituency.
* Distribution infrastructure works have also been taken up under the Mukhyamantri Ujjwal Jharkhand Yojana (MUJY) scheme.
**Impact Analysis**
**Ministry of Power**
* **Impact:** Responsible for implementing and overseeing the initiatives to achieve renewable energy and nuclear power targets.
* **Action Required:** Continue implementing the various schemes and policies, monitor progress, and address any challenges.
**Renewable Energy Implementing Agencies (REIAs)**
* **Impact:** Responsible for procuring and implementing RE projects based on the bidding trajectory issued by MNRE.
* **Action Required:** Participate in bidding processes and develop RE projects to meet the procurement targets.
**Power Generation Companies (GENCOs)**
* **Impact:** Involved in expanding generation capacity through renewable and nuclear power projects.
* **Action Required:** Align investment strategies with government policies, participate in tenders for new projects, and adopt new technologies.
**Consumers**
* **Impact:** Benefit from increased clean energy supply, improved power quality, and reduced emissions.
* **Action Required:** Adopt energy-efficient practices and participate in demand-side management programs.
**State Government of Jharkhand**
* **Impact:** Responsible for strengthening power infrastructure in the Chatra Parliamentary Constituency and implementing state-level schemes.
* **Action Required:** Coordinate with central government agencies, implement infrastructure projects, and ensure reliable power supply to consumers.
Key Entities Referenced
Ministry of Power: The primary government body responsible for the policy and matters related to power.
500 GW non-fossil energy capacity by 2030: India's commitment to achieve 500 GW of non-fossil energy capacity by 2030.
Net-Zero 2070 target: India's target to achieve Net-Zero emissions by 2070.
Jharkhand: The specific state mentioned in the question regarding power supply infrastructure in the Chatra Parliamentary Constituency.
Sustainable Harnessing and Advancement of Nuclear energy for Transforming India (SHANTI) Act, 2025: Legal framework to harness nuclear energy potential.
GOVERNMENT OF INDIA
MINISTRY OF POWER
LOK SABHA
UNSTARRED QUESTION NO.17
ANSWERED ON 29.01.2026
INSTALLED POWER CAPACITY
17. SHRI TATKARE SUNIL DATTATREY:
SHRI JAGDAMBIKA PAL:
SHRI KALI CHARAN SINGH:
Will the Minister of POWER
be pleased to state:
(a) the composition of the present installed power capacity of the country along
with the details of thermal, hydro, nuclear and renewable/non-fossil energy sources,
percentage-wise;
(b) the details of the policy, technical and investment factors contributing to
achieve over 500 GW installed capacity along with the impact of this achievement on
the Panchamrit Goals of COP -26 and the long-term energy transition roadmap;
(c) the steps taken/being taken by the Government to diversify India's energy
portfolio through clean and secure sources such as nuclear power;
(d) the steps taken by the Government to strengthen power generation,
transmission and distribution infrastructure, renewable energy projects and ensure
quality power supply to the consumers in Chatra Parliamentary Constituency of the
State of Jharkhand; and
(e) the manner in which expansion of clean, secure and reliable sources like nuclear
energy would strengthen India's long-term energy security and the manner in which it
would contribute to achieving the Net-Zero 2070 target?
A N S W E R
THE MINISTER OF STATE IN THE MINISTRY OF POWER
(SHRI SHRIPAD NAIK)
(a) : As on 31.12.2025, the country’s total installed generation capacity has reached
5,13,730 MW, comprising of 2,46,942 MW of fossil-fuel sources and 2,66,788 MW of non-
fossil fuel sources. The details of country's current composition of installed generation
capacity, indicating the share of renewable and non-fossil fuel sources, percentage-
wise, are given at Annexure-I:
(b), (c) & (e): 1. The Government of India has taken several steps and initiatives to
promote and accelerate renewable energy capacity in the country to realize the
commitment of 500 GW non-fossil energy capacity by 2030. These include, inter-alia,
the following:
(i) 100% Inter State Transmission System (ISTS) charges have been waived for
inter-state sale of solar and wind power for projects to be commissioned by
30th June 2025 (with waiver tapering off 25% annually till June 2028), for co-
located BESS projects commissioned by June 2028, for Hydro PSP projects
where construction work awarded by June 2028, for Green Hydrogen Projects
commissioned till December 2030 and for offshore wind projects
commissioned till December 2032.
…….2.- 2 -
(ii) Standard Bidding Guidelines for tariff based competitive bidding process for
procurement of Power from Grid Connected Solar, Wind, Wind-Solar Hybrid and
Firm & Dispatchable RE (FDRE) projects have been issued.
(iii) Ministry of New & Renewable Energy (MNRE) has issued Bidding Trajectory
for issuance of RE power procurement bids of 50 GW/annum by Renewable
Energy Implementing Agencies (REIAs) from FY 2023-24 to FY 2027-28.
(iv) Foreign Direct Investment (FDI) has been permitted up to 100 percent under
the automatic route.
(v) Laying of new transmission lines and creating new sub-station capacity has
been supported under the Green Energy Corridor Scheme for evacuation of
renewable power
(vi) To augment transmission infrastructure needed for steep RE trajectory,
transmission plan has been prepared till 2032.
(vii) Scheme for setting up of Solar Parks and Ultra Mega Solar Power projects is
being implemented to provide land and transmission to RE developers for
installation of RE projects at large scale
(viii) Schemes such as Pradhan Mantri Kisan Urja Suraksha evam Utthaan
Mahabhiyan (PM-KUSUM), PM Surya Ghar Muft Bijli Yojana, National
Programme on High Efficiency Solar PV Modules, New Solar Power Scheme
(for Tribal and PVTG Habitations/Villages) under Pradhan Mantri Janjati
Adivasi Nyaya Maha Abhiyan (PM JANMAN) and Dharti Aabha Janjatiya Gram
Utkarsh Abhiyan (DA JGUA), National Green Hydrogen Mission, Viability Gap
Funding (VGF) Scheme for Offshore Wind Energy Projects have been launched
(ix) Government of India, in September 2023, approved a Viability Gap Funding
(VGF) scheme for development of Battery Energy Storage Systems (BESS).
BESS capacity of 13.22 GWh is under implementation with a budgetary
allocation of Rs 3,760 Cr. under this scheme. Considering the increasing
demand of BESS, Ministry of Power, in June 2025, has approved another VGF
scheme for development of 30 GWh BESS capacity with a financial support of
Rs 5,400 Cr from Power System Development Fund (PSDF).
(x) To boost RE consumption, Renewable Purchase Obligation (RPO) followed by
Renewable Consumption Obligation (RCO) trajectory has been notified till
2029-30. The RCO which is applicable to all designated consumers under the
Energy Conservation Act 2001 will attract penalties on non-compliance. RCO
also includes specified quantum of consumption from Decentralized
Renewable Energy sources.
(xi) “Strategy for Establishments of Offshore Wind Energy Projects” has been
issued.
(xii) To achieve the objective of increased domestic production of Solar PV
Modules, the Govt. of India is implementing the Production Linked Incentive
(PLI) scheme for High Efficiency Solar PV Modules.
……..3.- 3 -
(xiii) Ministry of Power has initiated the steps to promote Pumped Storage
Projects (PSPs) to support renewable energy integration and grid stability.
At present, 10 Pumped Storage Projects totalling 11,870 MW are under
construction in the country.
2. Further, Nuclear power has huge potential to ensure long term energy security
and is vital for India’s clean energy transition towards Net Zero by 2070. It is a clean
and environment friendly source of base load power. The lifecycle emissions of
nuclear power are comparable to those of renewables like hydro and wind. The
Government of India has set an ambitious target of 100 GW nuclear power capacity
by 2047. Following steps have been taken to diversify India’s energy portfolio through
Nuclear Energy:
i. A dedicated Nuclear Energy Mission with an allocation of ₹20,000 crore has been
launched to develop at least five indigenously designed Small Modular Reactors
(SMRs) by 2033 and promote advanced nuclear technologies.
ii. Sustainable Harnessing and Advancement of Nuclear energy for Transforming
India (SHANTI) Act, 2025 has been enacted to pave a way to harness the
potential of India’s nuclear energy based on indigenous resources to the
maximum extent through active involvement of both the public and private
sectors.
iii. Bharat Small Reactors (BSRs) of 220 MW capacity based on India’s proven
Pressurized Heavy Water Reactor (PHWR) technology are being upgraded for
deployment in industrial hubs to support decarbonisation. BARC is also
developing Small Modular Reactors.
iv. India’s fuel security is being enhanced through new uranium discoveries,
including a significant discovery that would extend the life of the Jaduguda mine
by over 50 years. Progress in the closed fuel cycle, such as milestones achieved
in the Prototype Fast Breeder Reactor, will further support sustainable fuel
supply.
v. To accelerate capacity addition, NPCIL and NTPC have formed the joint venture
ASHVINI for developing nuclear power plants within the existing legal
framework.
3. The National Green Hydrogen Mission would also contribute significantly to
India’s efforts for decarbonization and also create opportunities for employment and
economic development. The Mission targets setting up at least 5 MMT per annum of
green hydrogen capacity by 2030.
4. India has achieved a landmark in its energy transition journey by reaching 50%
of its installed electricity capacity from non-fossil fuel sources in June, 2025 – more
than five years ahead of the target set under its Nationally Determined Contributions
(NDCs) to the Paris Agreement. This significant milestone underscores the country’s
steadfast commitment to climate action and sustainable development.
………4.- 4 -
The impact of this achievement on India’s long term energy transition roadmap is
crucial towards the goal of combating climate change, keeping in view energy
security, affordability and accessibility as critical inalienable priorities to ensure
growth and development alongside Energy transition of the economy towards net-zero
by 2070.
(d) : Two thermal power projects in the state of Jharkhand are at construction stage
as per details at Annexure-II. Further, as informed by the State Government of
Jharkhand, following steps have been/ are being taken to strengthen power
generation, transmission and distribution infrastructure in Chatra Parliamentary
Constituency:
Strengthening of Transmission infrastructure:
(i) 220/132/33 kV Grid Sub-Station, Itkhori has been constructed and energized on
01.10.2021. This Grid is dedicated towards power supply improvement to Chatra
Parliamentary Constituency.
(ii) Five more Grid Sub-Stations are under implementation for Chatra Parliamentary
Constituency namely Hunterganj, Simaria, Mahuhadhar, Chandwa & Dhara (Chatra).
Out of these five grid sub-station, construction of Simaria & Dhara (Chatra) Grid Sub-
Station has been completed and back charged and will be energized on full load after
completion of associated transmission line. Rest 03 Grid sub-stations are under
construction and will be energized after completion of the work.
Strengthening of Distribution infrastructure: Govt of India is supplementing the efforts
of the State to provide quality power supply to consumers through the Revamped
Distribution Sector Scheme (RDSS) . Under the scheme, distribution works amounting
to Rs 116.8 Cr have been sanctioned for Chatra Parliamentary constituency including
works pertaining to replacement of old/frayed cables, new HT/LT lines, upgradation
of HT/LT lines, new Distribution Transformers etc.
Further, the household electrification works amounting to Rs 7.04 Cr have been
sanctioned under RDSS for 1615 households in Chatra Parliamentary constituency
including households belonging to Particularly vulnerable Tribal groups (PVTG)
identified under PM-JANMAN (Pradhan Mantri Janjati Adivasi Nyaya Maha Abhiyan),
households belonging to scheduled Tribes identified under DAJGUA (Dharti Aaba
Janjatiya Gram Utkarsh Abhiyan) and households belonging to Scheduled Castes
identified under PM–AJAY (Pradhan Mantri Anusuchit Jaati Abhyuday Yojana).
Further as informed by the State, distribution infrastructure works have also
been taken up under the Mukhyamantri Ujjwal Jharkhand Yojana (MUJY) scheme.
Completed works under the scheme include electrification works related to 91 Nos of
habitations, 166 km of new 11 kV Line, 205 km of LT and installation of 115 No of
25kVA/63kVA/100 kVA Distribution transformers.
**********ANNEXURE-I
ANNEXURE REFERRED IN REPLY TO PART (a) OF UNSTARRED QUESTION NO.
17 ANSWERED IN THE LOK SABHA ON 29.01.2026
*************
The details of country's current composition of installed generation capacity, indicating
the share of renewable and non-fossil fuel sources, percentage-wise:
Installed Capacity (in MW) of the country as on 31.12.2025
Category Installed Capacity (MW) % Share in Total
Coal 2,19,610 42.75%
Lignite 6,620 1.29%
l
e
u
F Gas 20,122 3.92%
l
i
s
s
o Diesel 589 0.11%
F
Total Thermal/ Fossil 2,46,942 48.07%
RES (including Hydro) 2,58,008 50.22%
Hydro (including PSPs) 50,915 9.91%
Wind, Solar & Other RE 2,07,093 40.31%
Wind 54,511 10.61%
l
e
u
F Solar 1,35,810 26.44%
l
i
s
s
o BM Power/Cogen. 10,757 2.09%
F
-
n
o
N Waste to Energy 857 0.17%
Small Hydro 5,159 1.00%
Nuclear 8,780 1.71%
Total Non-Fossil Fuel 2,66,788 51.93%
Total Installed Capacity 5,13,730 100.0%
***********ANNEXURE-II
ANNEXURE REFERRED IN REPLY TO PART (d) OF UNSTARRED QUESTION NO.
17 ANSWERED IN THE LOK SABHA ON 29.01.2026
*************
Under-construction thermal power projects in the state of Jharkhand:
Name of the Capacity in
Sl. No Sector District Unit No.
Project MW
2 800
Patratu STPP
1 Ramgarh
(PVUNL)
3 800
CENTRAL
Koderma 1 800
2 TPS, St-II/ Koderma
DVC 2 800
**************