LOK SABHA
UNSTARRED QUESTION NO. 3915
TO BE ANSWERED ON 17.03.2026
INTEGRATED PROCESSING DEVELOPMENT SCHEME (IPDS)
3915. SHRI BIBHU PRASAD TARAI:
Will the Minister of TEXTILES वस्त्र मंत्री
be pleased to state :
(a) the details of new processing parks and existing textile processing projects approved and targets
achieved under the Integrated Processing Development Scheme (IPDS), State-wise;
(b) the current status of these projects in terms of physical and financial progress including funds
allocated, released and utilized, project and State-wise;
(c) the technologies implemented under IPDS in both new and existing clusters to ensure compliance
with environmental standards particularly in managing effluents and controlling pollution;
(d) whether it is a fact that the IPDS supports the existing textile processing clusters in the area of water
and waste water management and if so, the details thereof; and
(e) the details of the financial incentives, subsidies provided?
उत्तर
ANSWER
वस्त्र मंत्री (श्री गिरििाज ग िंह)
MINISTER OF TEXTILES
(SHRI GIRIRAJ SINGH)
(a) to (e): In order to facilitate the Indian Textile Industry to become globally competitive using
environmentally friendly processing standards and technology, and to address the issues of pollution in
the textile processing sector, the Ministry has been implementing Integrated Processing Development
Scheme since 12th FYP to support new Common Effluent Treatment Plants (CETP)/ upgradation of
CETPs in existing processing clusters as well as new processing parks. The scheme was under
implementation till 2021; after that the scheme has been continued to meet committed liabilities only.
The details of the projects approved under the scheme and their present status is as below:
(In crore)
S. Project GoI Grant
Name of the Project State District Status
No. Cost Released
Balotra Water Pollution Control
1 Treatment & Reverse Osmosis Private Rajasthan Barmer 131.89 62.45 Nearing Completion
Ltd
Jasol Water Pollution Control
2 Treatment & Reverse Osmosis Private Rajasthan Barmer 38.5 14.43 Nearing Completion
Limited
3 Sanganer Enviro Project Development Rajasthan Jaipur 159 37.5 Under Implementation
4 NextgenTextile Park Rajasthan Pali 129.42 6.3 Under Implementation
Pali Common Effluent Treatment Under
5 Rajasthan Pali 100 37.5
Plant Implementation
6 Gujarat Eco Textile Park Gujarat Palsana 146.39 54.84 Nearing Completion
TOTAL 705.2 213.02
The parks approved under the Scheme are implementing Zero Liquid Discharge (ZLD)
technology. Another technology being implementing is Multi Effect Evaporator (MEE) which further
helps in recovery of treated water.
****