GOVERNMENT OF INDIA
MINISTRY OF STEEL
LOK SABHA
UNSTARRED QUESTION NO. 1470
FOR ANSWER ON 28.07.2026
INVESTMENT UNDER PLI SCHEME FOR SPECIALTY STEEL
1470. SHRI DINESHBHAI MAKWANA:
SHRI BIDYUT BARAN MAHATO:
SMT. SHOBHANABEN MAHENDRASINH BARAIYA:
SHRI RAMESH AWASTHI:
SHRI MANOJ TIWARI:
SHRI ANANTA NAYAK:
Will the Minister of STEEL be pleased to state:
(a) the cumulative investment realised against the projected outlays under the
Production Linked Incentive (PLI) Scheme for Specialty Steel as of June 2026;
(b) the details of incremental production capacity created and direct employment
generated by the manufacturing units approved under the Scheme;
(c) whether project implementation has commenced across the companies that signed
Memorandums of Understanding (MoUs) under PLI Scheme 1.2 for Specialty Steel
and if so, the details thereof; and
(d) whether any project has been approved, is under implementation, or is proposed
under the PLI Scheme for Specialty Steel in Keonjhar Lok Sabha Constituency,
Odisha and if so, the details of the investment, employment potential, implementation
status and expected timeline for commissioning?
ANSWER
THE MINISTER OF STATE IN THE (SHRI BHUPATHIRAJU SRINIVASA VARMA)
MINISTRY OF STEEL
(a)&(b): As of June, 2026, a cumulative investment of ₹26,320 crore, incremental
production of approximately 3.75 million tonnes, and direct employment for around
14,000 persons have been achieved under the Production Linked Incentive (PLI)
Scheme for Specialty Steel.
(c)&(d): Yes, Sir. The implementation of projects approved under PLI Scheme 1.2
has commenced and an investments of ₹1,400 crore has been made. Further, the
Scheme is applicable for all states in India. 167 projects of 100 companies from 15
States have been approved, which includes 19 projects in Odisha.
*****