See Full Document Text
GOVERNMENT OF INDIA
MINISTRY OF POWER
LOK SABHA
UNSTARRED QUESTION NO.6228
ANSWERED ON 02.04.2026
IRREGULAR POWER SUPPLY IN KOLAR DISTRICT OF KARNATAKA
6228. SHRI M MALLESH BABU:
Will the Minister of POWER
be pleased to state:
(a) whether the Government has received reports regarding erratic power supply and
low voltage issues in the Kolar district causing frequent burnout of irrigation pump sets
and significant crop losses and if so, the details thereof;
(b) the current status of the feeder segregation work in Kolar under the Revamped
Distribution Sector Scheme (RDSS) and the number of agricultural feeders that have been
successfully separated from non-agricultural loads till date;
(c) whether the Government has finalised a roadmap for transition of these separated
agricultural feeders to solar power under the PM-KUSUM scheme, if so, the details
thereof;
(d) the technical and financial support available to farmers for upgrading their pumping
infrastructure such as efficient pumps or motors to better handle voltage fluctuations;
and
(e) whether the Government plans to implement real-time, IT-enabled monitoring of
agricultural feeders in water-stressed regions like Kolar to ensure accountability from the
local DISCOMs regarding the duration and quality of power supply, if so, the details
thereof?
A N S W E R
THE MINISTER OF STATE IN THE MINISTRY OF POWER
(SHRI SHRIPAD NAIK)
(a): Electricity being a concurrent subject, supply and distribution of electricity to
consumers is within the purview of the respective State Government/ distribution utility.
Further, as per Rule (10) of the Electricity (Rights of Consumers) Rules, 2020, the
distribution licensee shall supply 24x7 power to all consumers. However, the Commission
may specify lower hours of supply for some categories of consumers like agriculture. The
Rules are applicable for all States and for all areas.
As communicated by the State, the distribution utility has not received any report
regarding erratic power supply or low-voltage issues leading to frequent burnout of
irrigation pump sets or significant crop losses in Kolar district. Further, 7 hours of 3-
phase power is being supplied to all the agricultural feeders in Kolar district.
(b): As reported by the State, 291 feeders have been segregated under State scheme
and through CAPEX works in Kolar district. The State of Karnataka has not participated
under Revamped Distribution Sector Scheme (RDSS) for feeder segregation works.
…………2.- 2 -
(c) & (d): Pradhan Mantri Kisan Urja Suraksha evam Utthan Mahabhiyan (PM-KUSUM)
scheme aims to de-dieselize the farm sector and enhance the income of farmers. Under
the scheme, Central Government subsidy is given for the installation of standalone solar
pumps and for the solarization of existing grid-connected agricultural pumps. The
scheme is demand-driven, and capacities are allocated based on the demand raised by
the State and milestone achieved.
The sanction and achievement of the State of Karnataka under the scheme is as
below:
Component-A (MW) Component-B (Nos.) Component-C (Nos.)
Sanction Achievements Sanction Achievement Sanction Achievement
pumps pumps
0 0 41,365 5,533 7,63,588 86,827
Further, as reported by the State, the required capacity of pumps or motors in
Karnataka must be procured and installed by the IP set users themselves and such
consumers have to mandatorily install energy efficient star rated pump sets.
(e) : As reported by the State, a total of 5,216 feeders of BESCOM (Bangalore
Electricity Supply Company Ltd.) have been integrated with the National Feeder
Monitoring System (NFMS), out of which 2,103 are agricultural feeders. The Distribution
Control Centre of BESCOM continuously monitors all such 11 kV feeders and ensures
that the duration and quality of power supply to agricultural consumers is maintained as
per Government of Karnataka/KERC norms.
**************