GOVERNMENT OF INDIA
MINISTRY OF JAL SHAKTI
DEPARTMENT OF WATER RESOURCES, RIVER DEVELOPMENT & GANGA REJUVENATION
LOK SABHA
UNSTARRED QUESTION NO. 3380
ANSWERED ON 12.03.2026
IRRIGATION AND FLOOD MANAGEMENT PROJECTS IN BIHAR
†3380. SHRI RAJESH RANJAN:
Will the Minister of JAL SHAKTI be pleased to state:
(a) the details of major and medium irrigation and flood management projects approved in Bihar under the
Pradhan Mantri Krishi Sinchayee Yojana (PMKSY) and Accelerated Irrigation Benefit Programme (AIBP),
district-wise;
(b) the original timeline, current status and irrigation potential created for these projects along with details of
delayed projects and the reasons therefor;
(c) the details of funds approved, released and spent for these projects during the last five years, project-
wise;
(d) the details of the monitoring and review mechanism adopted by the Government to remove delays and to
ensure timely completion of irrigation projects in view of the recurring flood and drought conditions in the
State; and
(e) the details of the steps taken to expedite the completion of pending irrigation and flood management
projects and to strengthen climate-resilient irrigation infrastructure in Bihar?
ANSWER
THE MINISTER OF STATE FOR JAL SHAKTI
(SHRI RAJ BHUSHAN CHOUDHARY)
(a) to (c) Ninety-Nine (99) ongoing Major/Medium Irrigation projects (and 7 phases) with pari-passu
command area development in 88 projects were identified and included under PMKSY during 2016-17. Out
of them, two projects of Bihar, namely Durgawati Project benefiting Rohtas & Kaimur districts and Punpun
Barrage Project benefiting Patna, Arwal & Jehanabad district were included under Pradhan Mantri Krishi
Sinchayee Yojana-Accelerated Irrigation Benefits Programme (PMKSY-AIBP) with pari-passu command
area development in Durgawati Project under Pradhan Mantri Krishi Sinchayee Yojana-Command Area
Development and Water Management (PMKSY-CAD&WM).
Further, Nineteen (19) major and medium irrigation projects have been taken up for funding under
PMKSY-AIBP after approval of implementation of PMKSY for the period of 2021-26. Out of them two
projects, namely Kosi–Mechi Intra-State Link benefiting Araria, Purnea, Kishanganj & Katihar district and
North Koel Project benefiting Aurangabad, Gaya, Palamau & Garhwa district of Bihar.
The project-wise details are given at Annexure.
(d) & (e) In order to remove the delay and to ensure timely completion of these projects, the Ministry and the
State Government undertake project-wise periodic reviews meetings to monitor physical and financial
progress of the projects. Issues and bottlenecks under the projects are flagged over Project Monitoring
Group (PMG) portal and resolved in PMG review meetings. Further, Govt monitors these projects through a
dedicated dashboard, backed with a management information system maintained by DoWR, RD & GR. To
expedite completion, the projects are regularly visited and monitored by Central Water Commission under
DoWR, RD & GR, as well as by a dedicated Project Management Unit (PMU) under this Ministry.
***
1ANNEXURE
ANNEXURE REFERRED TO IN REPLY TO PART (a) to (c) OF UNSTARRED QUESTION NO. 3380 TO BE ANSWERED IN LOK SABHA ON
12.03.2026 REGARDING “IRRIGATION AND FLOOD MANAGEMENT PROJECTS IN BIHAR”.
Details of projects under PMSKY-AIBP and PMKSY-CADWM Schemes
(Rs. in Crore and Irrigation Potential & Command Area in Thousand Hectare)
Eligible Central Scheduled
Ultimate Irrigation
Central Assistance completion Present
Project Name Districts Estimated Irrigation Potential
S.No. Expenditure Assistance released under Status
Benefitted Cost Potential Created
under during PMKSY
PMKSY 2020–25
PMKSY-AIBP
December,
1 Durgawati Project Rohtas, Kaimur 1207.39 1183.46 90.07 14.12 39.61 35.50 Completed.
2019
Punpun Barrage Patna, Arwal, December, Headwork
2 685.28 409.17 106.02 0 13.68 3.68
Project Jehanabad 2019 completed.
Araria, Purnea, Physical
Kosi-Mechi Intra
3 Kishanganj & 6282.32 132.00 3652.56 0 210.516 0 March, 2029 Progress -
State Link Project
Katihar 4%
North Koel Project Aurangabad, Gaya, Physical
d4 (Bihar-Jharkhand Palamau & 2431.00 946.39 1836.41 49.82 95.521 0 June, 2026 Progress -
Interstate Project) Garhwa 38%
Total: 10605.99 2671.02 5685.06 63.94 359.327 39.18
Eligible Central
Scheduled
Central Assistance Command
S. Districts Estimated Expenditur Command completion Present
Project Name Assistance released Area
No. Benefitted Cost e Area under Status
under during Developed
PMKSY
PMKSY 2020–25
PMKSY-CAD&WM
Physical
Durgawati CADWM December,
1. Rohtas, Kaimur 142.20 75.64 50.66 0 30.51 19.13 progress -
Project 2019
63%
*****