**Executive Summary**
This document is a response to Lok Sabha Question No. 3148, concerning the metro rail network in Uttar Pradesh, answered on December 18, 2025. It outlines the current status, projected timelines, and financial support provided by the Union Government for metro and rapid transit projects in the state. Key deadlines and action items pertain to project completion and operational efficiency targets.
**Key Points / Main Content**
* **Operational Metro Network Details (Annexure-I):**
* Details of operational length and average daily ridership for metro and RRTS networks in Uttar Pradesh are provided.
* Specific figures are given for Lucknow, Kanpur, Agra, Noida, and Ghaziabad.
* **Ongoing Metro Projects:**
* Lucknow Metro Phase-1B (Charbagh to Vasantkunj) sanctioned in September 2025 at a cost of Rs. 5,801.05 Crore, with a projected 5-year completion period.
* Kanpur Metro (32.38 route Km at Rs. 11,076.48 Crore) and Agra Metro (29.4 route Km at Rs. 8,379.62 Crore) projects have been sanctioned.
* 15 km of metro network in Kanpur and 6 km in Agra are currently operational.
* UPMRCL reports no cost overruns in Lucknow, Kanpur, and Agra metro projects.
* **New Metro/RRTS Projects & Planning:**
* 'Urban planning' is a State subject, therefore, State Governments are responsible for planning and initiating urban transport infrastructure including metro and Regional Rapid Transit system Projects (RRTS).
* Meerut metro rail system (21.15 Km) is part of the Delhi-Meerut RRTS project.
* Metro projects, including Gorakhpur, are under extensive examination due to cost intensity, with approval dependent on feasibility and resource availability.
* RRTS projects are planned for implementation only in NCR. Lucknow- Kanpur is not a part of NCR.
* **Financial & Technical Support (Annexure-II):**
* Central Government support for Lucknow Phase-IA, Kanpur, Agra, and Delhi-Meerut RRTS projects is provided as per Annexure-II.
* Government has issued policies and guidelines for systematic and sustainable development of Metro and RRTS Projects in country including that of State of Uttar Pradesh.
**Impact Analysis**
**Impact**
* State Governments in Uttar Pradesh
* Responsible for planning and initiating urban transport infrastructure including metro and RRTS projects.
**Action Required**
* Assess feasibility of proposals and ensure long-term sustainability of projects.
**Impact**
* UP Metro Rail Corporation Limited (UPMRCL)
* Implementing agency for metro projects in Lucknow, Kanpur, and Agra.
**Action Required**
* Continue implementing metro projects within allocated budgets and timelines.
**Impact**
* Central Government
* Provides financial and technical support for metro and RRTS projects in Uttar Pradesh.
**Action Required**
* Assess project proposals and prioritize based on various factors, like population, peak hour traffic, development plans, etc.
**Impact**
* Citizens of Uttar Pradesh
* Improved transportation infrastructure via operational and planned metro/RRTS networks.
**Action Required**
* None.
Key Entities Referenced
Uttar Pradesh: The state where the metro rail network is being discussed.
Ministry of Housing and Urban Affairs: The central ministry responsible for metro rail projects
National Urban Transport Policy 2006: A national policy document related to urban transportation.
Metro Rail Policy 2017: A national policy document specifically for metro rail projects
Regional Rapid Transit System Projects (RRTS): A type of rapid transit system projects.
GOVERNMENT OF INDIA
MINISTRY OF HOUSING AND URBAN AFFAIRS
LOK SABHA
UNSTARRED QUESTION NO. 3148
TO BE ANSWERED ON DECEMBER 18, 2025
METRO RAIL NETWORK IN UTTAR PRADESH
NO. 3148. SHRI PUSHPENDRA SAROJ:
Will the Minister of HOUSING AND URBAN AFFAIRS be pleased to
state:
(a) the details of the current operational length of metro networks in
Uttar Pradesh, the present average daily ridership for each and the
targets set and achieved for network length and ridership, city-
wise including Lucknow, Kanpur, Agra, Noida and Ghaziabad;
(b) the status and projected timelines for completion of ongoing metro
phases including Lucknow Phase-2, Kanpur corridors and Agra
Phase-2, details of cost overruns or delays, if any and the extent to
which completion targets have been met;
(c) the status of new metro/rapid transit projects currently under
planning or Detailed Project Report (DPR) stage in Uttar Pradesh
including Lucknow-Kanpur RRTS, Meerut Metro and Gorakhpur
Metro along with their expected commencement timelines and
targets set and achieved; and
(d) the financial and technical support provided by the Union
Government for metro and rapid transit projects in Uttar Pradesh
along with the extent to which set targets for project completion
and operational efficiency have been achieved?
ANSWER
THE MINISTER OF STATE IN THE
MINISTRY OF HOUSING AND URBAN AFFAIRS
(SHRI TOKHAN SAHU)
(a) The details of current operational length of metro and RRTS
networks in Uttar Pradesh along with average daily ridership are given in
Annexure-I.
(b) The Lucknow metro Phase-1B from Charbagh to Vasantkunj of
11.165 route Km at a cost of Rs. 5,801.05 Crore have been sanctioned in
September, 2025 with projected completion period of 5 years from date
of sanction.
…2/--2-
The Kanpur Metro Rail Project of 32.38 route Km at a cost 11,076.48
Crore and Agra Metro Rail Project of 29.4 route Km at a cost of 8,379.62
Crore have already been sanctioned. Presently 15 km of metro network
in Kanpur and 6 km of metro network in Agra are operational. UP Metro
Rail Corporation Limited (UPMRCL), which is implementing agency for
metro projects in Lucknow, Kanpur and Agra has informed that there is
no cost overrun in these projects.
(c) ‘Urban planning’ is a State subject, therefore, the respective State
Governments are responsible for planning and initiating urban transport
infrastructure including metro and Regional Rapid Transit system
Projects (RRTS).
Central Government has issued National Urban Transport Policy 2006,
The Metro Rail Policy 2017, Transit Oriented Development Policy 2017,
Value Capture Financing Policy, Appraisal Guidelines for Metro Projects,
Standardization guidelines, Report on Benchmarking of Cost Estimation
of Metro Rail Projects etc. for systematic and sustainable development
of Metro and RRTS Projects in country including that of State of Uttar
Pradesh.
As per extant policy, RRTS project are planned for implementation only
in NCR. Lucknow- Kanpur is not a part of NCR.
Meerut metro rail system of 21.15 Km is integral part of already
sanctioned Delhi- Meerut RRTS project.
Metro projects including that of Gorakhpur are cost intensive requiring
extensive examination at different level in Central Government. Metro
project proposals of different cities are prioritized for approval based on
many factors like size of population, peak hour traffic, development
plans etc. Further, the approval of such proposal is always dependent
upon feasibility of proposal and availability of resources to ensure long
term sustainability of such projects.
(d) Financial support provided by Central Government for Lucknow
Phase-IA, Kanpur, Agra & Delhi-Meerut RRTS Project are as per table at
Annexure-II.
*****Annexure I
ANNEXURE REFERRED TO IN REPLY TO PART (a) OF THE LOK SABHA
QUESTION NO. 3148 FOR ANSWER ON 18.12.2025 REGARDING METRO
RAIL NETWORK IN UTTAR PRADESH ASKED BY SHRI PUSHPENDRA
SAROJ.
THE DETAILS OF CURRENT OPERATIONAL LENGTH OF METRO
NETWORKS IN UTTAR PRADESH, AVERAGE DAILY RIDERSHIP, CITY-
WISE:
S. No. Name of Metro Rail State City Total Operational Average Daily
Project Length Length (in Ridership
(in Kms) Kms)
1. Lucknow Metro Rail Uttar Pradesh Lucknow 22.878 22.878 78,000
Project
2. Kanpur Metro Rail Kanpur 32.38 15.00 Partial section is
Project operational
3. Agra Metro Rail Agra 29.4 6.00 Partial section is
Project operational
4. Noida Metro Rail Noida 29.707 29.707 68,869
Project
5. Delhi Metro Noida 17.761 17.761 5,80,000 (footfalls)
Corridors in Noida
6. Delhi Metro Ghaziabad 11.9 11.9 2,03,000 (footfalls)
Corridors in
Ghaziabad
7. Delhi Meerut (RRTS) Ghaziabad 68.65 47.00 Partial section is
in Ghaziabad and and Meerut operational
Meerut
Total 212.676 150.246ANNEXURE II
ANNEXURE REFERRED TO IN REPLY TO PART (d) OF THE LOK SABHA
QUESTION NO. 3148 FOR ANSWER ON 18.12.2025 REGARDING METRO
RAIL NETWORK IN UTTAR PRADESH ASKED BY SHRI PUSHPENDRA
SAROJ.
THE DETAILS OF FINANCIAL SUPPORT PROVIDED BY CENTRAL
GOVERNMENT TO UTTAR PRADESH FOR METRO & RRTS PROJECT:
Rs. In Crore
S. Name of Metro Rail/ RRTS Project Fund released by GoI
No. till date
1. Lucknow Metro Rail Project Phase-IA 4,802.00
2. Kanpur Metro Rail Project 6,174.61
3. Agra Metro Rail Project 3,741.51
4. Noida Metro Rail Project 970.62
5. Delhi Meerut RRTS Corridor (including Ghaziabad 20,718.65
and Meerut stretch)