Parliament Question: Nuclear Energy Mission

Issued by ATOMIC ENERGY · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task
Official Source Record View Original Source →
See Full Document Text
GOVERNMENT OF INDIA DEPARTMENT OF ATOMIC ENERGY LOK SABHA UNSTARRED QUESTION NO–3062 ANSWERED ON 11/03/2026 NUCLEAR ENERGY MISSION 3062. SHRI P P CHAUDHARY SHRI ALOK SHARMA DR. K SUDHAKAR SMT. MALA RAJYA LAXMI SHAH SMT. APARAJITA SARANGI DR. SANJAY JAISWAL SHRI BIBHU PRASAD TARAI Will the PRIME MINISTER be pleased to state:- (a) the details of progress under Nuclear Energy Mission including the budgetary allocation made for design, development and deployment of indigenous Small Modular Reactors (SMR); (b) the details of the Research and Development (R&D) milestones achieved and private sector partnerships established; and (c) whether the Department has assessed timeline for first SMR prototype and potential capacity addition towards 100GW nuclear target by 2047 and if so, the details thereof? ANSWER THE MINISTER OF STATE FOR PERSONNEL, PUBLIC GRIEVANCES & PENSIONS AND PRIME MINISTER’S OFFICE (DR. JITENDRA SINGH) (a) Under the Nuclear Energy Mission announced in the Union Budget 2025–26, a total budgetary provision of ₹20,000 crore has been made for the research, design, development, and deployment of Small Modular Reactors (SMRs). Bhabha Atomic Research Centre (BARC), a constituent unit of Department of Atomic Energy (DAE) has undertaken design and development works on SMRs namely, (i) 220 MWe Bharat Small Modular Reactor (BSMR-200), (ii) 55 MWe Small Modular Reactor (SMR-55), and (iii) Up to 5 MWth High temperature gas cooled reactor meant for hydrogen generation.The lead units of these SMRs will be established at DAE sites for technology demonstration. The estimated utilisation of the allocated funds by BARC toward setting up SMRs is mentioned below: Reactor Cost Outlay (Rs Cr.) Development and Construction of BSMR-200 5960 Development and Construction of SMR-55 (2 units) 7000 Design and construction of High Temperature Gas Cooled Reactor 320 (HTGCR) Design, engineering & development works for new reactors 800 Civil and General Infrastructure Development for reactors complex 452 The progress of these SMRs is as follows; (i) BSMR-200: AEC in-principle approval has been received for the project. Proposal for administrative & financial sanction is cleared by Atomic Energy Commission (AEC) for submission of the proposal to the Cabinet Committee. (ii) SMR-55: In-principle approval has been received for the project. (iii) HTGCR: In-principle approval has been received for the project. Detailed Project Report (DPR) has been prepared. Siting consent has been received and Terms of Reference (ToR) for obtaining environmental clearances has been received from Ministry of Environment, Forest and Climate Change (MoEF&CC). (b) The special material called “Advanced Purified Reactor Vessel Alloy (ApuRVA) and technology for forgings for reactor pressure vessels of BSMR-200 and SMR-55 has been developed indigenously in collaboration with Indian Industries. The control rod drive mechanism has also been developed in-house. Necessary technology for deployment of these reactors is available in the country. Majority of equipment are within manufacturing capability of Indian Industries with technological handholding by BARC. Therefore, Indian industries will be engaged in manufacturing of equipment. (c) Bharat Small Modular Reactor (BSMR) is being jointly designed and developed by BARC and Nuclear Power Corporation of India Limited (NPCIL), a Govt. of India enterprise under DAE. Estimated time for construction of BSMR is 60 to 72 months from receipt of administrative & financial approval. *****

Continue your research