NUCLEAR POWER GENERATION CAPACITY
1705. SHRI SHAFI PARAMBIL
Will the PRIME MINISTER be pleased to state:-
(a) the present installed nuclear power generation capacity in the country, plant-wise along
with its percentage contribution to the total electricity generation;
(b) the details of nuclear power projects under construction and those approved during the
last five years indicating their present status and expected dates of commissioning;
(c) whether the Government has fixed any target for expanding nuclear power capacity by
2030 and 2047 and if so, the details thereof;
(d) the measures taken to promote indigenous nuclear technology, ensure fuel security and
enhance public safety at nuclear power plants; and
(e) the steps taken to encourage private sector participation in the nuclear power sector in
accordance with the existing legal framework?
ANSWER
THE MINISTER OF STATE FOR PERSONNEL, PUBLIC GRIEVANCES & PENSIONS
AND PRIME MINISTER’S OFFICE (DR. JITENDRA SINGH)
(a) The present installed nuclear power capacity in the country is 8,780 MW comprising of
24 nuclear power plants, contributing about 3.1% in 2025-26 in total electricity
generation. The details are tabulated in Annexure.
(b) The details of nuclear power projects under construction and their present status are
tabulated below.
Location Project Capacity Physical Expected Date Of
(MW) Progress/ Commissioning
Status
(as of June
2026)
Projects Under Construction / Commissioning
In advanced stage of
commissioning
Rajasthan RAPP-8 1 X 700 96.26 %
(expected to be
operational in 2026)
Kudankulam, KKNPP-3&4 2 X 1000 82.65 % June-2027/ June-2028
Tamilnadu
KKNPP- 5&6 2 X 1000 45.00 % June-2029/ March-2030Completion of
construction and
commissioning is
expected to be completed
Gorakhpur, in about 6 years from
GHAVP-1&2 2 X 700
Haryana First Pour of Concrete.
FPC will start after
completion of ground
improvement works of
Nuclear Island.
Kaiga,
KAIGA-5&6 2 X 700 June-2031/ June-2032
Karnataka
(c) & (d) Yes. The Government has drawn up a roadmap for reaching the 100 GW nuclear
power capacity by 2047, as announced in the Nuclear Energy Mission. As per the
roadmap, the present nuclear power capacity of 8.78 GW is expected to reach about 22
GW by 2031-32. Another 32 GW of nuclear power capacity is envisaged to be set up
under NPCIL beyond 2032 which will comprise of indigenous Pressurised Heavy Water
Reactors (PHWRs) and Light Water Reactors (LWRs). Additionally, the Government has
approved the pre-project activities of 2 x 500 MW FBR 1 & 2, to be built with the same
design as of PFBR of Kalpakkam. The balance of 45 GW comprising of reactors of
different technologies, is expected to be set up by other Public Sector Enterprises (Central
& State), Private sector and Joint Ventures in different business models.
Highest priority is accorded to safety in all aspects of nuclear power viz. siting, design,
construction, commissioning, and operation. Nuclear power plants are designed adopting
safety principles of redundancy, diversity and provided fail-safe design features following
an overlapping defence-in-depth approach, in line with codes and guides of Atomic
Energy Regulatory Board (AERB). There is a robust regulatory mechanism of safety
reviews at multiple levels. The safety of nuclear power plants is continuously monitored
and reviewed by the AERB. Required fuel security is ensured by Nuclear Fuel Complex, a
constituent unit of Department of Atomic Energy, Government of India.
(e) The Government has announced a Nuclear Energy Mission to reach a capacity of 100
GW nuclear power capacity by 2047 and formulated a roadmap for the same. The
Sustainable Harnessing and Advancement of Nuclear Energy for Transforming India
(SHANTI) Act 2025 enables wider participation in the nuclear power sector, both from
public and private sector.Annexure
TAPS-1 160
TAPS-2 160
Maharashtra Tarapur
TAPS-3 540
TAPS-4 540
RAPS-2 200
RAPS-3 220
RAPS-4 220
Rajasthan Rawatbhata
RAPS-5 220
RAPS-6 220
RAPS-7 700
MAPS-1 220
Kalpakkam
MAPS-2 220
Tamilnadu
KKNPP-1 1000
Kudankulam
KKNPP-2 1000
NAPS-1 220
Uttar Pradesh Narora
NAPS-2 220
KAPS-1 220
KAPS-2 220
Gujarat Kakrapar
KAPS-3 700
KAPS-4 700
KGS-1 220
KGS-2 220
Karnataka Kaiga
KGS-3 220
KGS-4 220
*****