GOVERNMENT OF INDIA
DEPARTMENT OF ATOMIC ENERGY
LOK SABHA
STARRED QUESTION NO. 360
ANSWERED ON 12.08.2026
NUCLEAR POWER GENERATION UNDER ATOMIC ENERGY PROGRAMME
*360. DR. PRABHA MALLIKARJUN
Will the PRIME MINISTER be pleased to state:-
(a) whether the Government has taken steps to expand nuclear power generation under the
Atomic Energy programme to meet the growing energy demand of the country including
in States such as Karnataka;
(b) if so, the current installed nuclear power capacity and its share in the country’s total
energy mix;
(c) the details of nuclear power projects under construction and proposed including those in
the Southern Region;
(d) whether the targets under the nuclear power expansion programme have been achieved
and if so, the details thereof and if not, the reasons therefor;
(e) the details of safety measures and regulatory mechanisms put in place; and
(f) the details of roadmap for increasing nuclear power capacity to support country’s clean
energy transition?
ANSWER
THE MINISTER OF STATE FOR PERSONNEL, PUBLIC GRIEVANCES & PENSIONS
AND PRIME MINISTER’S OFFICE (DR. JITENDRA SINGH)
(a) to (f): A statement is laid on the Table of the House.
*****Government of India
Department of Atomic Energy
STATEMENT REFERRED TO IN REPLY TO PART (A) TO (F) IN RESPECT OF LOK
SABHA STARRED QUESTION NO. 360 FOR REPLY ON 12.08.2026 REGARDING
“NUCLEAR POWER GENERATION UNDER ATOMIC ENERGY PROGRAMME”
ASKED BY DR. PRABHA MALLIKARARJUN.
(a) Yes. The Government has taken steps to expand nuclear power generation in the country,
including in the State of Karnataka, where four units Kaiga–1 to 4 (4 X 220 MW) are in
operation, while two more units Kaiga–5&6 (2 X 700 MW) are under construction.
(b) The present installed nuclear power capacity in the country is 8,780 MW comprising of 24
nuclear power plants. The share of nuclear energy in the total electricity generation in the
country was 3.1% in the year 2025-26.
(c) The details are given in Annexure.
(d) The present nuclear power capacity of 8.78 GW is expected to reach about 22 GW by
2031-32 on progressive completion of projects which are presently at various stages of
construction/ commissioning and under pre-project activities.
(e) Highest priority is accorded to safety in all aspects of nuclear power viz. siting, design,
construction, commissioning, and operation. Nuclear power plants are designed adopting
safety principles of redundancy, diversity and fail-safe design features following an
overlapping defence-in-depth approach, in line with codes and guides of Atomic Energy
Regulatory Board (AERB). There is a robust regulatory mechanism of safety reviews at
multiple levels. The operations are performed adopting well laid out procedures by highly
qualified, trained and licensed personnel. The safety of nuclear power plants is
continuously monitored and reviewed internally and by the AERB.
(f) The roadmap for increasing nuclear power capacity comprises: (i) A near-term target of
about 22,380 MW by 2031-32, through the 13,600 MW presently under
construction/planning; (ii) A long-term target of 100 GW by 2047 under the Nuclear
Energy Mission for Viksit Bharat announced in the Union Budget 2025-26, to be pursued
through a combination of large-capacity reactors and indigenously developed Small
Modular Reactors (SMRs). The SHANTI Act, 2025 additionally enables licensed
participation of private Indian companies and joint ventures in the sector in support of this
roadmap.
*****Annexure
Nuclear Power Projects under Construction/ Commissioning
Location & State Project Capacity (MW)
Rawatbhata, Rajasthan RAPP-8 1 X 700
Gorakhpur, Haryana GHAVP-1&2 2 X 700
KKNPP-3&4 2 X 1000
Kudankulam, Tamilnadu
KKNPP-5&6 2 X 1000
Kaiga, Karnataka KAIGA-5&6 2 X 700
Kalpakkam, Tamilnadu PFBR 1 X 500
Projects Under Pre-project Activities
Gorakhpur, Haryana GHAVP-3&4 2 X 700
Chutka, Madhya Pradesh CMPAPP-1&2 2 X 700
MBRAPP-1&2 2 X 700
Mahi Banswara, Rajasthan
MBRAPP -3&4 2 X 700
Kalpakkam, Tamilnadu FBR -1 & 2 2 X 500
Proposed Nuclear Power Projects
Rawatbhata, Rajasthan RAPP-9&10 2 X 700
Kakrapar, Gujarat KAPP-5&6 2 X 700
Narora, Uttar Pradesh NAPP-3&4 2 X 700
In-Principle approved sites
Jaitapur, Maharashtra JNPP-1 to 6 6 X 1730
Kovvada, Andhra Pradesh Kovvada-1 to 6 6 X 1208
Haripur, West Bengal Haripur-1 to 6 6 X 1000
Mithi Virdi, Gujarat Mithi Virdi-1 to 6 6 X 1000
Bhimpur, Madhya Pradesh Bhimpur-1 to 4 4 X 700
*****