PARLIAMENT QUESTION: NUCLEAR POWER PROJECTS

Issued by Department of Atomic Energy

Read or download the official PDF of this gazette notification issued by the Department of Atomic Energy on 13th August 2026. Classified under Press Release.

Executive Summary & Key Takeaways

Executive Summary This report provides a status update on nuclear power projects currently under construction in India as of August 2026. It details the capacity, revised commissioning schedules, and financial allocations for various indigenous and foreign-cooperation reactors. The document outlines the reasons for project delays and the corrective measures being implemented to ensure the eventual addition of 8,000 MW to the national grid.

Key Points / Main Content

Project Status and Capacity

  • Indigenous Pressurised Heavy Water Reactors (IPHWR): RAPP-7 (Rawatbhata) commenced commercial operation on April 15, 2026. RAPP-8 is in advanced commissioning, expected by late 2026.
  • Long-term Projects: GHAVP-1 & 2 (Gorakhpur) are expected to take approximately six years from the "First Pour of Concrete." KAIGA-5 & 6 have revised commissioning dates of June 2031 and June 2032, respectively.
  • Fast Breeder Technology: The Prototype Fast Breeder Reactor (PFBR) at Kalpakkam has a revised commissioning target of March 2027.
  • Foreign Cooperation (LWR): Kudankulam (KKNPP) units 3 through 6 are scheduled for completion between June 2027 and March 2030.

Factors Influencing Delays

  • Technical and Environmental: Extensive design changes following the Fukushima incident and difficult soil conditions at the GHAVP site.
  • Supply Chain and Geopolitical: Delays in critical equipment supply from the Russian Federation and impacts from the Russia-Ukraine and USA/Israel-Iran conflicts.
  • Logistical: Disruptions caused by the Covid-19 pandemic, including contractor financial constraints and shortages of skilled manpower.

Corrective Measures and Implementation

  • Monitoring: Periodic reviews at multiple levels within NPCIL and DAE, alongside the constitution of a Board sub-committee for project monitoring.
  • Efficiency Drives: Adoption of "fleet mode" for reactor implementation and bulk ordering of long-delivery equipment to ensure timely supply.
  • Administrative Actions: Higher delegation of powers to NPCIL executives and frequent vendor/contractor meetings to resolve site-specific constraints.

Financial Overview

  • Detailed annexures track equity sanctioned, released, and utilized from 2021 to 2024.
  • Total equity utilized across major projects (excluding PFBR) reached Rs. 1,990 crore in the 2023-24 period.

Impact Analysis

National Grid and Energy Sector Impact The grid will see a cumulative capacity addition of 8,000 MW upon the progressive commissioning of these projects. Action Required Prepare for the integration of high-capacity nuclear power loads as projects like RAPP-8 and KKNPP-3 reach completion between 2026 and 2027.

NPCIL and Department of Atomic Energy (DAE) Impact These bodies are under increased pressure to manage revised timelines and escalating costs (some of which are currently "under revision"). Action Required Must conduct constant monitoring of project activities, identify constraints early, and execute mid-course corrections and re-sequencing of construction activities.

Contractors and Vendors Impact Contractors are facing financial crunches and manpower shortages that have slowed execution at sites like GHAVP. Action Required Attend frequent coordination meetings with NPCIL/DAE to resolve cash flow problems and address skilled labor requirements.

Parliament and Government Oversight Impact Informed of the specific geopolitical and technical reasons for project setbacks and the status of sanctioned funds. Action Required Continue monitoring the utilization of sanctioned equity and the progress of the "fleet mode" implementation to ensure return on investment.

Key Entities Referenced

Department of Atomic Energy (DAE): The primary government department responsible for the oversight, policy implementation, and funding of nuclear power projects in India. Nuclear Power Corporation of India Limited (NPCIL): The implementing agency responsible for project reviews, monitoring construction progress, and managing the execution of nuclear power plants. Indigenous Pressurised Heavy Water Reactors (IPHWR): A major category of nuclear reactor projects, such as RAPP and KAIGA, being developed indigenously to enhance India's nuclear power capacity. Light Water Reactors (LWR): Nuclear power projects implemented through foreign cooperation, specifically the Kudankulam Nuclear Power Project (KKNPP) series. Dr. Jitendra Singh: The Minister of State who provided the detailed parliamentary response regarding the status, funding, and challenges of ongoing nuclear projects.
Official Gazette PDF Record Download Official PDF (PARLIAMENT QUESTION: NUCLEAR POWER PROJECTS) →

Official Gazette Notification PDF Viewer

See Full Document Text & PDF Transcript
Department of Atomic Energy PARLIAMENT QUESTION: NUCLEAR POWER PROJECTS प्रव तथ: 13 AUG 2026 3:11PM by PIB Delhi The details of projects under construction are tabulated below. Sr. Project Location Capacity Commissioning Date Cost (Rs. Cro (MW) Original Status/ Revised Sanctioned R Indigenous Pressurised Heavy Water Reactors (IPHWR) 1 RAPP-7* Rawatbhata, 700 Jun- Commenced Rajasthan 2016 commercial operation on 15.04.2026 12,320 RAPP-8 700 Dec- In advanced stage 2016 of commissioning (expected to be operational in 2026) 2 GHAVP- Gorakhpur, 700 Sep- Completion of 1 Haryana 2020 construction and commissioning is 20,594 U expected to be r GHAVP- 700 Mar- completed in about 2 2021 6 years from First Pour of Concrete.3 KAIGA-5 Kaiga, 700 June- June-2031 21,000 Under 2026 revision Karnataka KAIGA-6 700 June- June-2032 2027 4 PFBR Kalpakkam, 500 Sep-2010 Mar- 2027 3492 Under Tamil Nadu revision Light Water Reactors (LWR) with Foreign Cooperation 5 KKNPP- Kudankulam, 1000 Mar-2023 Jun-2027 39,849 68,893 3 Tamil Nadu KKNPP- 1000 Nov- Jun-2028 4 2023 6 KKNPP- 1000 Dec-2026 Jun-2029 49,621 69,437 5 KKNPP- 1000 Sep-2027 Mar-2030 6 *Already commenced production in April 2026. However, cost available on Twin Unit basis (RAPP-7 & RAPP-8) The year-wise details of the funds sanctioned, released and utilized for each project under construction during the last five years are attached as Annexure. The major reasons for delay in construction/ commissioning of projects in the recent past have been due to extensive design changes following the Fukushima incident in Japan, delay in supply of critical equipment, Covid-19 pandemic & related issues, delay in supplies from Russian Federation (for KKNPP), delay in execution of works by contractors at site on account of financial crunch / cash flow problems post Covid, difficult site soil conditions (at GHAVP), shortage of skilled contractor manpower, and the impact due to ongoing Russia-Ukraine and USA/ Israel-Iran geopolitical conflict. To address the challenges, various measures are being implemented to ensure timely completion of the projects. The measures include, periodic project reviews at multiple levels in NPCIL & DAE, constant monitoring of progress of project activities, timely identification of constraints & making necessary mid-course corrections, frequent meetings with vendors/ contractors to resolve various issues and re-sequencing of construction activities to the extent possible, higher delegation of powers to various executives of NPCIL and constitution of Board sub-committee for monitoring of projects. In addition to this, bulk ordering of longdelivery equipment has been adopted and many equipment are under manufacturing/ progressive delivery for various reactors being implemented in fleet mode to ensure timely supply of long lead items for the projects. Upon progressive commissioning of the projects currently under construction, a cumulative capacity of 8000 MW would be added to the national grid. Annexure The year-wise details of Equity Sanctioned, Released and Utilized for each project under construction during the last five years are tabulated below: Amount in Rs. Crore 2021-22 2022-23 2023-2 Name of the Equity Equity Equity Equity Equity Equity Equity Equity Sanctio Released Utilized Sanctio Released Utilized Sanctio Releas Project ned ned ned GHAVP- 141 141 577 577 254 1&2 KKNPP- 363 363 1375 1375 1585 540 1952 1990 5&6 CMAPP- 7 7 0 0 12 1&2 MBRAPP- 15 15 0 0 23 1to 4 KAIGA- 8 8 0 0 102 5&6 GHAVP- 6 6 0 0 14 3&4 Total 540 540 540 1952 1952 1952 1990 1990 The year-wise details of Equity Sanctioned, Released and Utilized for PFBR during the last five years are tabulated below:2021-22 2022-23 2023-24 Name of the Equity Equity Equity Equity Equity Equity Equity Equity Sanctio Released Utilized Sanctio Released Utilized Sanctio Released Project ned ned ned PFBR 550 550 550 272 200 200 200 200 This information was given by the Minister of State (Ind. Charge) Science & Technology; Earth Sciences and Minister of State PMO; Personnel, Public Grievances and Pensions; Department of Atomic Energy and Space Dr. Jitendra Singh in a written reply in Rajya Sabha today. ***** NKR/AK (रलीज़ आईडी: 2298859) आगंतुक पटल : 1408 इस वज्ञ को इन भाषाओ ंम पढ़: Urdu , ही

Continue your research