Home India STATISTICS AND PROGRAMME IMPLEMENTATION Parliament Question: Pending Government Projects in Rohtak, ...
Date: 2026-07-29 Category: LOKSABHA_QNA State: Union Government Country: India

Parliament Question: Pending Government Projects in Rohtak, Haryana

Issued by STATISTICS AND PROGRAMME IMPLEMENTATION · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task
Official Source Record View Original Source →
See Full Document Text
GOVERNMENT OF INDIA MINISTRY OF STATISTICS AND PROGRAMME IMPLEMENTATION LOK SABHA UNSTARRED QUESTION NO. 1783 TO BE ANSWERED ON 29.07.2026 PENDING GOVERNMENT PROJECTS IN ROHTAK, HARYANA 1783. SHRI DEEPENDER SINGH HOODA: Will the Minister of STATISTICS AND PROGRAMME IMPLEMENTATION be pleased to state: (a) the number of Central Government projects pending in Rohtak Lok Sabha Constituency along with details of project report, funds allocated and utilised since their commencement, project and year- wise including current year; (b) whether delay in execution of any such projects has led to cost escalation and if so, the details thereof, project-wise; (c) the current status of each pending project in Rohtak Lok Sabha Constituency; and (d) the time period by which these pending projects are likely to be completed? ANSWER MINISTER OF STATE (INDEPENDENT CHARGE) OF THE MINISTRY OF STATISTICS AND PROGRAMME IMPLEMENTATION, MINISTER OF STATE (INDEPENDENT CHARGE) OF THE MINISTRY OF PLANNING AND MINISTER OF STATE IN THE MINISTRY OF CULTURE [RAO INDERJIT SINGH] (a) to (d): The Ministry of Statistics & Programme Implementation (MoSPI) is mandated to monitor the status of Ongoing Central Sector Infrastructure Projects costing Rs. 150 crore and above throughonline portal/ web monitoring system “Project Assessment Infrastructure Monitoring and Analytics for Nation-Building (PAIMANA)”. All line Ministries/ Departments/ Implementing Agencies regularly update the information of projects on PAIMANA portal via APIs (Application Programming Interfaces) and data entry mode. Accordingly, the State-wise details of all ongoing infrastructure projects are available in the Flash Report published by this Ministry on the website https://paimana-proj.mospi.gov.in/ReportPage. However, the data is monitored at the State level. Further, Monthly Flash Report encapsulates a range of key parameters such as Original/ Revised Date of Commissioning, Original Cost/ Latest Revised Cost, Cumulative Expenditure, Cumulative Physical Progress etc. based on information provided by Implementing Agencies/Ministry/Department. *****

Continue your research