GOVERNMENT OF INDIA
MINISTRY OF RURAL DEVELOPMENT
DEPARTMENT OF RURAL DEVELOPMENT
LOK SABHA
UNSTARRED QUESTION NO. 244
ANSWERED ON 21/07/2026
PHASE-WISE CONSTRUCTION OF RURAL ROADS UNDER PMGSY
244. Shri Lumbaram Choudhary:
Shri Damodar Agrawal:
Smt. Kamlesh Jangde:
Shri Yogender Chandolia:
Shri Vijay Baghel:
Dr. Manna Lal Rawat:
Shri Jashubhai Bhilubhai Rathva:
Shri Kota Srinivasa Poojary:
Shri Ashish Dubey:
Shri P P Chaudhary:
Shri Jai Prakash:
Shri Vishweshwar Hegde Kageri:
Shri Bhojraj Nag:
Shri Mukeshkumar Chandrakaant Dalal:
Shri Dineshbhai Makwana:
Shri Jaswantsinh Sumanbhai Bhabhor:
Shri Amar Sharadrao Kale:
Dr. Hemang Joshi:
Shri Pradeep Kumar Singh:
Shri Bibhu Prasad Tarai:
Shri Nalin Soren:
Dr. Sanjay Jaiswal:
Shri Ravindra Shukla Alias Ravi Kishan:
Shri Naba Charan Majhi:
Dr. Rajesh Mishra:
Shri Bidyut Baran Mahato:
Smt. Malvika Devi:
Shri Rahul Singh Lodhi:
Dr. Hemant Vishnu Savara:
Shri Suresh Kumar Kashyap:
Dr. Nishikant Dubey:
Shri Vijay Kumar Dubey:
Shri Rodmal Nagar:
Shri Bhartruhari Mahtab:
Shri Kali Charan Singh:
Shri Khagen Murmu:
Page 1 of 13Shri Godam Nagesh:
Will the Minister of RURAL DEVELOPMENT be pleased to state:
(a) the total length in kilometres of rural roads constructed and the
number of habitations connected under the Pradhan Mantri
Gram Sadak Yojana (PMGSY-I, II, III and IV) till date during the
Financial Year 2025-26, State, district and phase-wise including
the States of Jharkhand, Gujarat and Rajasthan specially for
Chatra, Pali and Dahod Lok Sabha Constituencies;
(b) the details of roads sanctioned, completed, under construction
and proposed under PMGSY along with the funds sanctioned,
released and utilized during the last three years and the current
year, year, State and district-wise including Chatra Lok Sabha
Constituency;
(c) the details of the implementation plan for PMGSY during the
Financial Year 2026–27 particularly for upgradation and
maintenance of rural roads with special emphasis on roads in
tribal areas, State-wise including Chatra and Dahod Lok Sabha
Constituencies and Palghar district of Maharashtra;
(d) the targets fixed for construction and upgradation of rural roads
under the Scheme, State-wise particularly in Chhattisgarh,
Himachal Pradesh and Gujarat States including the current
status of past targets along with the goals set for the future in
Jabalpur, Shimla and Damoh Parliamentary Constituencies
during the Financial Year 2026-27;
(e) whether the Government has adopted any mechanism for
prioritising connectivity in Aspirational Districts, Western
Ghats, Tribal and Remote areas, if so, the details thereof
specially in tribal dominated districts of Dahod, Palghar,
Kalahandi and Nuapada of Gujarat, Maharashtra, Chhattisgarh
and Odisha; and
(f) the details of planned investment, including the contribution of
the Centre and the States including Gujarat, for implementation
of the Scheme?
ANSWER
MINISTER OF STATE IN THE MINISTRY OF RURAL DEVELOPMENT
(SHRI KAMLESH PASWAN)
(a): The details of total length of roads constructed and number of
habitations connected under all verticals of Pradhan Mantri Gram
Sadak Yojana till 16.07.2026 since inception, including for the States
of Jharkhand, Gujarat and Rajasthan, and specifically for Chatra, Pali
and Dahod Lok Sabha Constituencies, are given at Annexure-I.
Page 2 of 13Further, the phase-wise, state-wise and district-wise physical
details of road length sanctioned, completed, under-construction,
and habitations connected till date are available in the public domain
via the Online Management, Monitoring and Accounting System
(OMMAS) portal and may be seen at https://pmgsy.dord.gov.in/dbweb.
(b): The details of roads sanctioned, completed, under construction
and proposed under PMGSY along with the funds sanctioned,
released and utilized during the last three years and the current year
(as on 16.07.2026), year-wise and state-wise are given at Annexure-
II.
Further, the details of roads sanctioned, completed, under
construction and proposed under PMGSY along with funds utilized
during the last three years and the current year, year-wise, State-
wise and district-wise are available in the public domain via the
Online Management, Monitoring and Accounting System (OMMAS)
portal and may be seen at https://pmgsy.dord.gov.in/dbweb.
Further, year-wise details of roads sanctioned, completed,
under construction and proposed under PMGSY, along with funds
utilized during the last three years and the current year for Chatra
Lok Sabha Constituency, are given at Annexure-III.
(c) & (d): For the Financial Year 2026-27, physical targets for the
construction and upgradation of rural roads under PMGSY are
finalized in consultation with the respective State Governments
during the Annual Action Plan (AAP) meetings, based on the balance
of sanctioned works and the availability of budgetary resources.
District-wise targets are subsequently allocated by the States/UTs
within the state-wise targets allocated by the Ministry of Rural
Development. The FY 2026-27 physical targets for various PMGSY
verticals, including Pradhan Mantri Janjati Adivasi Nyaya Maha
Abhiyan (PM-JANMAN) for connectivity to Particularly Vulnerable
Tribal Groups (PVTGs) areas, are given at Annexure-IV.
PMGSY roads are constructed by the State Governments with a
design life of at least 10 years. As per PMGSY guidelines,
maintenance of roads constructed under the programme is the
responsibility of the State Governments. All PMGSY road works are
covered by an initial five year maintenance contracts to be entered
into along with the construction contract, with the same contractor,
as per the Standard Bidding Document. Maintenance funds to service
the contract are required to be budgeted by the State Governments
and placed at the disposal of the State Rural Roads Development
Agencies (SRRDAs) in a separate maintenance account. On expiry of
Page 3 of 13this 5 year post construction maintenance, PMGSY roads are required
to be placed under Zonal maintenance contracts consisting of 5 year
maintenance including renewal as per cycle, from time to time.
(e): The program guidelines of Pradhan Mantri Gram Sadak Yojana
(PMGSY) incorporate dedicated relaxation parameters to ensure
prioritized connectivity for special category areas, including
Aspirational Districts, Tribal (Schedule-V) areas, Desert Areas, and
Special Category areas. While eligibility criteria for other habitations
for getting connectivity under the scheme is a population of 500
persons (as per 2001 census under PMGSY-I and as per Census 2011
under PMGSY-IV), for Tribal (Schedule V) areas and Selected Tribal
and Backward Districts (as identified by the Ministry of Home Affairs
and Planning Commission) and for North-Eastern and Himalayan
States, unconnected habitations with a population of 250 and above
are eligible for providing all-weather road connectivity under the
scheme.
Furthermore, under the recently launched PMGSY-IV, these
relaxed population criteria (250+) continue to apply to Aspirational
Districts/Blocks, Tribal Schedule-V areas, and Desert Areas based on
Census 2011 data, with a further relaxation down to a population of
100 or more in districts affected by Left Wing Extremism.
Further, the Government has also integrated the road
connectivity components of the Dharti Aaba Janjatiya Gram Utkarsh
Abhiyan (DA-JGUA) and the Pradhan Mantri Anusuchit Jaati Abhyuday
Yojana (PM-AJAY) through convergence with PMGSY-IV. This
convergence framework applies to all States and Union Territories.
Under this framework priority is given to unconnected habitations
identified under DA-JGUA that have a population of 500 or more with
at least 50% Scheduled Tribe population, or those in Aspirational
Districts with a population of 250 or more including at least 50
Scheduled Tribe members. Similarly, under PM-AJAY, priority is
extended to unconnected habitations with a population of 500 or
more and at least 40% Scheduled Caste population as per Census
2011.
In addition to the above, road connectivity component
of Pradhan Mantri Janjati Adivasi Nyaya Maha Abhiyan (PM-
JANMAN) is also being implemented as a separate vertical under
PMGSY to provide connectivity to the habitations of Particularly
Vulnerable Tribal Groups(PVTG).
Under these systematic guidelines, eligible unconnected
habitations falling within the tribal-dominated districts of Dahod
Page 4 of 13(Gujarat), Palghar (Maharashtra), Kalahandi, and Nuapada (Odisha)
are extended connectivity benefits under the relaxed norms. Project
sanctions for these areas are processed based on the core network
planning and Detailed Project Reports (DPRs) formulated and
submitted by the respective State Governments in compliance with
the programme frameworks.
(f): The PMGSY was launched as 100% Centrally Sponsored
Scheme. However, subsequently, on the basis of the
recommendations of the Sub-Group of Chief Ministers on
Rationalization of Centrally Sponsored Schemes the fund sharing
pattern of PMGSY was changed in the ratio of 60:40 between the
Centre and States for all States/UT including Gujarat except for 8
North Eastern and 3 Himalayan States/UTs (with legislature) for
which it is 90:10 with effect from 2015-16. The Central share for the
UTs without legislature is 100%.
*****
Page 5 of 13Annexure-I
Annexure referred to in reply to part (a) of Lok Sabha unstarred
question No. 244 for answer on 21.07.2026
The State/UT-wise details of completed road length (in km) and
habitations connected under all the verticals of PMGSY as on
16.07.2026, including for the States of Jharkhand, Gujarat and
Rajasthan
Completed Road Connected
State/ UT
Length (in km) Habitations
Andaman & Nicobar 150 7
Andhra Pradesh 18,764 1,416
Arunachal Pradesh 14,909 622
Assam 32,212 13,721
Bihar 62,724 31,293
Chhattisgarh 44,828 10,691
Goa 155 1
Gujarat 15,458 3,047
Haryana 8,042 1
Himachal Pradesh 23,408 2,562
Jammu And Kashmir 19,875 2,132
Jharkhand 32,008 10,953
Karnataka 24,008 295
Keralam 4,836 401
Madhya Pradesh 90,955 17,493
Maharashtra 32,886 1,417
Manipur 10,914 622
Meghalaya 5,301 597
Mizoram 4,641 231
Nagaland 4,362 107
Odisha 71,763 16,991
Puducherry 87 -
Punjab 10,841 389
Rajasthan 76,177 15,970
Sikkim 4,923 350
Tamilnadu 26,349 1,985
Tripura 5,127 1,982
Uttar Pradesh 75,741 11,748
Uttarakhand 21,902 1,860
West Bengal 39,177 13,224
Telangana 13,146 704
Ladakh 1,352 64
Total 7,97,020 1,62,876
Page 6 of 13Details of completed road length (in km) and number of habitations
connected under all verticals of PMGSY as on 16.07.2026, Lok Sabha
Constituency-wise for Chatra, Pali and Dahod
Lok Sabha Completed Length (in Connected
Constituency Km) Habitations
Chatra 3,164 625
Pali 2,703 229
Dahod 1,776 739
Page 7 of 13Annexure-II
Annexure referred to in reply to part (b) of Lok Sabha unstarred question No. 244
for answer on 21.07.2026
Details of roads sanctioned, completed, under construction and proposed under
PMGSY along with the funds sanctioned, released and utilized during the financial
year 2023-24
Road Road Road Central Expedniture
Budget
Name of Length Length Length Share (inculding
Allocation
State/UT Sanctioned Completed Balance Released State Share)
(Rs in Cr)
(in km) (in km) (in km) (Rs in Cr) (Rs in Cr)
Andaman
And Nicobar 0 43 53 50.00 12.22 22.93
Andhra
Pradesh 1158 369 1759 400.00 140.64 368.03
Arunachal
Pradesh 1743 303 2549 590.00 339.90 320.09
Assam 0 610 447 590.00 391.29 571.22
Bihar 268 2252 3211 1030.00 963.37 1815.63
Chhattisgarh 1466 201 3304 610.00 401.77 388.09
Goa 0 0 0 0.00 0.00 0.00
Gujarat 2 619 279 370.00 298.41 330.33
Haryana 0 344 103 150.00 74.01 150.86
Himachal
Pradesh 2683 315 3529 750.00 617.56 371.54
Jammu And
Kashmir 535 956 1665 1450.00 1304.17 1256.96
Jharkhand 171 1431 3286 790.00 752.80 1323.90
Karnataka 0 457 284 290.00 72.25 404.03
Keralam 592 261 895 220.00 54.25 164.95
Ladakh 0 41 461 150.00 37.50 30.44
Madhya
Pradesh 295 910 1382 640.00 599.42 1105.16
Maharashtra 1573 1569 3514 1130.00 1110.80 1507.37
Manipur 491 59 1322 660.00 161.29 296.83
Meghalaya 0 399 559 440.00 122.59 238.19
Mizoram 488 149 518 370.00 141.37 381.62
Nagaland 489 132 551 230.00 161.29 94.01
Odisha 148 2587 1920 1125.00 1262.55 1589.76
Puducherry 0 24 2 50.00 0.27 11.89
Punjab 1164 956 1539 440.00 265.10 522.95
Rajasthan 476 1669 1321 550.00 404.79 633.09
Sikkim 303 94 449 150.00 94.37 130.13
Tamil Nadu 2869 985 3001 370.00 411.36 777.78
Telangana 27 493 1632 540.00 296.96 479.41
Tripura 542 112 884 290.00 185.03 112.64
Uttar
Pradesh 448 6799 3911 2365.00 2679.63 3791.65
Uttarakhand 1241 594 2273 740.00 551.05 800.68
West Bengal 0 362 544 380.00 99.28 309.11
Total 19170 26095 47147 17910.00 14007.29 20301.27
Note: Balance road length includes pending works from previous years.
Page 8 of 13Details of roads sanctioned, completed, under construction and proposed under
PMGSY along with the funds sanctioned, released and utilized during the financial
year 2024-25
Road Road Road Central Expedniture
Budget
Name of Length Length Length Share (inculding
Allocation
State/UT Sanctioned Completed Balance Released State Share)
(Rs in Cr)
(in km) (in km) (in km) (Rs in Cr) (Rs in Cr)
Andaman
200 14 237 16.88 0.05 3.97
And Nicobar
Andhra
358 387 1717 800.00 507.32 370.60
Pradesh
Arunachal
653 453 2738 700.00 609.00 726.10
Pradesh
Assam 564 277 717 350.00 79.24 264.55
Bihar 28 1646 1512 920.00 1195.44 2312.80
Chhattisgarh 986 457 3819 900.00 325.24 421.88
Goa 63 0 63 11.98 0.00 0.00
Gujarat 0 192 83 310.00 220.65 361.22
Haryana 0 94 4 100.00 27.38 34.60
Himachal
0 730 2785 650.00 634.82 904.14
Pradesh
Jammu And
0 775 852 1400.00 1028.25 1070.65
Kashmir
Jharkhand 0 1638 1634 1550.00 961.77 1374.96
Karnataka 64 170 166 220.00 100.58 142.81
Keralam 160 264 788 450.00 122.27 249.15
Ladakh 37 38 458 150.00 113.81 111.33
Madhya
1543 559 2324 840.00 703.29 966.83
Pradesh
Maharashtra 795 2049 2221 1020.00 854.93 1524.10
Manipur 281 68 1535 400.00 2.81 88.18
Meghalaya 752 289 1023 400.00 219.62 373.80
Mizoram 0 91 426 350.00 87.50 45.78
Nagaland 56 2 605 350.00 2.25 30.50
Odisha 63 881 1068 1000.00 712.39 736.53
Puducherry 108 0 110 100.00 25.00 0.00
Punjab 31 379 1189 400.00 319.87 328.82
Rajasthan 58 1213 157 500.00 450.46 932.86
Sikkim 0 56 389 280.00 70.00 148.98
Tamil Nadu 59 986 2070 750.00 638.66 741.43
Telangana 67 153 1533 460.00 132.57 399.90
Tripura 203 71 1012 400.00 172.75 98.25
Uttar
51 2808 1115 1920.00 1968.60 2703.84
Pradesh
Uttarakhand 0 966 1297 760.00 815.50 934.03
West Bengal 3251 405 3384 450.00 225.00 269.77
Total 10433 18110 39031 18908.86 13327.03 18672.36
Note: Balance road length includes pending works from previous years.
Page 9 of 13Details of roads sanctioned, completed, under construction and proposed under
PMGSY along with the funds sanctioned, released and utilized during the financial
year 2025-26
Road Road Road Central Expedniture
Budget
Name of Length Length Length Share (inculding
Allocation
State/UT Sanctioned Completed Balance Released State Share)
(Rs in Cr)
(in km) (in km) (in km) (Rs in Cr) (Rs in Cr)
Andaman
0 15 222 20.00 0.00 12.14
And Nicobar
Andhra
253 484 1461 860.00 118.74 432.40
Pradesh
Arunachal
0 738 1988 1000.00 490.98 775.52
Pradesh
Assam 1522 131 2111 800.00 229.91 211.38
Bihar 0 749 665 1040.00 386.88 1288.01
Chhattisgarh 2880 1812 4869 1520.00 557.23 357.12
Goa 0 0 63 0.00 0.00 0.00
Gujarat 0 36 26 100.00 126.82 281.14
Haryana 0 2 2 5.00 0.05 4.23
Himachal
1538 1265 3032 1100.00 936.32 1356.64
Pradesh
Jammu And
1781 326 2298 998.00 261.87 420.50
Kashmir
Jharkhand 1079 340 2369 950.00 150.54 631.64
Karnataka 0 42 98 75.00 36.13 48.94
Keralam 0 360 427 300.00 130.35 271.42
Ladakh 0 236 219 80.00 76.25 107.15
Madhya
0 865 1428 720.00 460.88 763.23
Pradesh
Maharashtra 0 1053 1118 1360.00 529.73 1402.23
Manipur 35 19 1552 20.00 49.24 40.99
Meghalaya 0 295 699 600.00 351.04 388.09
Mizoram 0 153 273 300.00 86.12 121.00
Nagaland 0 32 573 400.00 78.84 121.43
Odisha 0 640 401 660.00 285.61 447.72
Puducherry 0 8 102 2.00 0.98 6.56
Punjab 0 510 671 346.77 137.07 369.79
Rajasthan 3219 102 3272 830.00 221.46 314.94
Sikkim 384 161 609 175.00 115.14 175.99
Tamil Nadu 11 1926 152 1000.00 508.74 1465.19
Telangana 0 305 1194 575.00 209.80 527.56
Tripura 65 98 978 360.00 142.40 186.73
Uttar
0 580 514 1010.00 138.93 648.75
Pradesh
Uttarakhand 1228 820 1691 700.00 446.16 595.17
West Bengal 0 1543 1835 1000.00 534.31 1140.56
Total 13997 15648 36910 18906.77 7798.51 14914.16
Note: Balance road length includes pending works from previous years.
Page 10 of 13Details of roads sanctioned, completed, under construction and proposed under
PMGSY along with the funds sanctioned, released and utilized during the financial
year 2026-27 (as on 16.07.2026)
Road Road Road Central Expedniture
Budget
Name of Length Length Length Share (inculding
Allocation
State/UT Sanctioned Completed Balance Released State Share)
(Rs in Cr)
(in km) (in km) (in km) (Rs in Cr) (Rs in Cr)
Andaman
0 2 220 30.00 7.33 3.44
And Nicobar
Andhra
347 141 1664 480.00 46.87 78.12
Pradesh
Arunachal
0 176 1804 1150.00 39.63 44.03
Pradesh
Assam 0 60 2042 1050.00 66.15 73.50
Bihar 0 104 555 760.00 101.20 168.67
Chhattisgarh 0 151 4694 1870.00 135.14 225.23
Goa 0 0 63 50.00 0.00 0.00
Gujarat 202 9 219 303.00 17.45 29.09
Haryana 0 0 2 38.55 0.04 0.06
Himachal
0 356 2643 900.00 210.81 234.23
Pradesh
Jammu And
1600 24 3874 980.00 167.85 186.50
Kashmir
Jharkhand 0 150 2219 820.00 33.50 55.83
Karnataka 0 9 89 50.00 1.87 3.11
Keralam 0 38 388 300.00 30.87 51.46
Ladakh 0 13 195 70.00 17.11 20.56
Madhya
2502 226 3689 830.00 84.63 141.05
Pradesh
Maharashtra 96 247 959 690.00 73.34 122.24
Manipur 0 0 1552 1240.00 3.23 3.59
Meghalaya 0 101 595 780.00 99.26 110.29
Mizoram 0 0 273 450.00 87.78 97.53
Nagaland 538 7 1104 500.00 0.00 0.00
Odisha 1702 22 2077 156.93 33.40 55.66
Puducherry 0 17 86 20.00 8.29 13.81
Punjab 0 11 660 180.00 0.00 0.00
Rajasthan 0 317 2955 735.00 14.09 23.49
Sikkim 0 5 603 230.00 14.12 15.69
Tamil Nadu 0 39 112 105.00 31.02 51.70
Telangana 0 40 1154 675.00 19.78 32.97
Tripura 164 18 1124 382.00 21.93 24.37
Uttar
0 72 437 615.00 16.42 27.37
Pradesh
Uttarakhand 0 30 1651 420.00 18.28 20.31
West Bengal 777 462 2145 1150.00 93.24 155.40
Total 7928 2847 41848 18010.48 1494.62 2069.29
Note: Balance road length includes pending works from previous years.
Page 11 of 13Annexure-III
Annexure referred to in reply to part (b) of Lok Sabha unstarred
question No. 244 for answer on 21.07.2026
Details of road sanctioned, completed, under construction and
proposed under PMGSY along with the funds utilized during the last
three years and the current year (as on 16.07.2026), year-wise for
Chatra Lok Sabha Constituency
Road
Financial Road Length Road Length Expenditure
Year Sanctioned Length Completed Balance (₹ Cr.)
2023-24 11 168 346 139
2024-25 0 115 230 149
2025-26 102 42 289 74
2026-27 0 9 280 13
Total 113 334 - 375
Note: Balance road length includes pending works from previous
years.
Page 12 of 13Annexure-IV
Annexure referred to in reply to part (c) & (d) of Lok Sabha unstarred
question No. 244 for answer on 21.07.2026
Details of Physical Target for Financial Year 2026-27 under various
verticals of PMGSY, State/ UT wise
Sr. No. State Name Road Length (in km)
1 Andaman & Nicobar 96
2 Andhra Pradesh 976
3 Arunachal Pradesh 1966
4 Assam 1008
5 Bihar 647
6 Chhattisgarh 3786
7 Goa 62
8 Gujarat 126
9 Haryana 0
10 Himachal Pradesh 859
11 Jammu & Kashmir 1084
12 Jharkhand 1438
13 Karnataka 97
14 Keralam 434
15 Ladakh 209
16 Madhya Pradesh 1533
17 Maharashtra 951
18 Manipur 1238
19 Meghalaya 709
20 Mizoram 476
21 Nagaland 545
22 Odisha 226
23 Puducherry 0
24 Punjab 280
25 Rajasthan 2630
26 Sikkim 218
27 Tamil Nadu 151
28 Telangana 1193
29 Tripura 643
30 Uttar Pradesh 482
31 Uttarakhand 566
32 West Bengal 1845
Total 26474
*****