See Full Document Text
GOVERNMENT OF INDIA
MINISTRY OF STEEL
RAJYA SABHA
UNSTARRED QUESTION NO. 1752
FOR ANSWER ON 13.02.2026
PLI SCHEME FOR SPECIALITY STEEL
1752. SMT. SAGARIKA GHOSE:
Will the Minister of STEEL be pleased to state:
(a) quantity of speciality steel created under different categories since the inception of
the Production Linked Incentive (PLI) scheme;
(b) total investments received and utilized during the financial year 2024-25;
(c) total number of review meetings initiated in the on-going Research and Development
(R&D) projects since October 2024; and
(d) reasons for the foreclosure of the project on energy efficient production of medium
carbon ferromanganese in electric arc furnace?
ANSWER
THE MINISTER OF STATE IN THE (SHRI BHUPATHIRAJU SRINIVASA VARMA)
MINISTRY OF STEEL
(a)to(d): About 2.4 million tonnes of specialty steel has been produced domestically,
and an investment of about ₹ 23,600 crore has been made under the Production Linked
Incentive (PLI) Scheme up to December, 2025.
Research and Development (R&D) projects are reviewed. Project Review
Committee (PRC) takes a decision on projects based on factors including progress,
achievability of results, conflict of views between the project stakeholders, if any etc.
*****