Executive Summary:
This document pertains to Lok Sabha Unstarred Question No. 1583 regarding the Pradhan Mantri Awaas Yojana Gramin (PMAYG) in Maharashtra, answered on July 29, 2025. It addresses the number of houses sanctioned and constructed, beneficiaries on the waiting list, and potential increases in construction targets. It also covers funding, technical resources, and administrative support provided by the Union Government to State Governments. The extended timeline for completion of the Awaas 2024 survey for Maharashtra is July 31, 2025.
Key Points / Main Content:
PMAYG Implementation:
• PMAYG aims to provide assistance for the construction of Pucca houses with basic amenities in rural areas, targeting "Housing for All."
• The initial target was 2.95 crore houses from FY 2016-17 to 2023-24. An additional 2 crore houses are targeted from FY 2024-25 to 2028-29.
• Maharashtra has been allocated a target of 43,70,829 houses, with 40,82,626 sanctioned and 13,80,724 completed as of July 24, 2025.
• District-wise targets are fixed by the State Government.
Awaas Survey 2024:
• A survey is being conducted to update the Awaas List for identifying eligible rural households using modified exclusion criteria.
• The survey is conducted through the Awaas 2024 Mobile App, launched on September 17, 2024.
• The extended deadline for Maharashtra to complete the survey is July 31, 2025.
Funding and Support:
• Funding patterns vary: 90:10 (Centre:State) for North Eastern and Himalayan States, 60:40 for other states, and 100% by the Centre for Union Territories without legislature.
• Administrative funds are provisioned at 2% of program funds, with 0.30% retained centrally and 1.70% released to States/UTs.
• Additional administrative funds are available for the North Eastern Region and Hill States from the central share.
• Up to 5% of targets under PMAYG are reserved for Special Projects based on proposals from States/UTs.
Technical Support:
• End-to-end monitoring via AwaasSoft MIS.
• Awaas App for geo-referenced, time-stamped photographs of houses during construction.
• Dedicated Programme Management Units (PMU) at State/District/Block level.
• PAHAL, a compendium of House Design Typologies, is available on the PMAYG website.
• Regular review meetings and Regional Workshops are conducted by the Ministry.
Annexure Data (as of 24.07.2025):
• Provides district-wise details of targets, houses sanctioned, houses completed, and completion gap against sanction under PMAYG in Maharashtra.
Impact Analysis:
State Government of Maharashtra:
Impact: Responsible for fixing district-wise targets, sanctioning houses, and ensuring construction. Needs to complete the Awaas 2024 survey by July 31, 2025.
Action Required: Complete Awaas 2024 survey by the deadline; utilize available technical support and administrative funds effectively.
Beneficiaries (Rural Households):
Impact: Eligible households receive assistance for constructing houses. The Awaas 2024 survey identifies additional eligible beneficiaries.
Action Required: Participate in the Awaas 2024 survey if not already included in existing databases.
Ministry of Rural Development:
Impact: Oversees PMAYG implementation, allocates targets and funds, provides technical support, and monitors progress.
Action Required: Continue to provide funding, technical resources, and conduct review meetings to support State Governments in achieving targets.
District/Block Level Administrations:
Impact: Responsible for implementing and monitoring PMAYG at the local level.
Action Required: Utilize the Awaas App for inspection, establish dedicated PMUs, and ensure effective implementation of the scheme.
Key Entities Referenced
Pradhan Mantri Awaas Yojana Gramin (PMAYG): A rural housing scheme implemented by the Ministry of Rural Development, Government of India, aiming to provide pucca houses with basic amenities to eligible rural households.
Ministry of Rural Development: The central government ministry responsible for implementing the Pradhan Mantri Awaas Yojana Gramin (PMAYG) and other rural development programs.
Maharashtra: A state in India where the PMAYG scheme is being implemented, and for which district-wise data on housing sanctions and construction is provided.
Yavatmal district, Maharashtra: A district in Maharashtra, India, specifically mentioned in the context of houses sanctioned and constructed under PMAYG.
Washim district, Maharashtra: A district in Maharashtra, India, specifically mentioned in the context of houses sanctioned and constructed under PMAYG.
SECC 2011: Socio Economic and Caste Census 2011, used as a beneficiary database for the PMAYG scheme.
AwaasSoft MIS: An online Management Information System (MIS) used for end-to-end monitoring and tracking of transactional processes under the PMAYG scheme.
Awaas 2024 Mobile App: An Android-based mobile application used for conducting household surveys to identify eligible beneficiaries for the PMAYG scheme.
O.I.H.
GOVERNMENT OF INDIA
MINISTRY OF RURAL DEVELOPMENT
DEPARTMENT OF RURAL DEVELOPMENT
LOK SABHA
UNSTARRED QUESTION NO. 1583
ANSWERED ON 29/07/2025
PMAY-G IN MAHARASHTRA
1583. Shri Sanjay UttamraoDeshmukh:
Will the Minister of RURAL DEVELOPMENT be pleased to state:
(a) whether it is a fact that the number of houses sanctioned and
constructed under Pradhan MantriAwasYojanaGramin (PMAY-
G) in Maharashtra varies from district to district, district-wise;
(b) if so, the number of houses sanctioned and constructed so far
in Yavatmal-Washim districts;
(c) the number of beneficiaries lying in the waiting list at present
and the number of those houses not have sanctioned so far in
Maharashtra, district-wise;
(d) whether the Government proposes to increase the number of
houses set to be constructed in Maharashtra under the said
scheme;
(e) if so, the time by which it is likely to be increased and the
steps taken so far in this regard;
(f) whether the Union Government is formulating any special plan
to provide funds, technical resources or administrative support
to the State Governments to achieve the set target;
(g) if so, the details thereof; and
(h) if not, the reasons therefor?
ANSWER
MINISTER OF STATE IN THE MINISTRY OF RURAL DEVELOPMENT
(DR. CHANDRA SEKHAR PEMMASANI)
(a) to (e): The Ministry of Rural Development is implementing the
Pradhan Mantri Awaas Yojana - Gramin (PMAY-G) w.e.f. 1st April,
2016 to provide assistance to eligible rural households for the
construction of Pucca houses with basic amenities to achieve the
objective of "Housing for All" in rural areas. Under the PMAY-G, the
initial target was construction of 2.95 crore houses during FY 2016-
17 to 2023-24. The Government of India has approved the proposal
Page 1 of 4for implementation of the scheme for 5 more years during FY 2024-
25 to 2028-29 to provide assistance to 2 crore additional houses.
The existing beneficiary database of Maharashtra as per
SECC 2011 PWL and Awaas+ 2018 survey has already been
saturated through allocation of targets by the Ministry. The Ministry
has allocated a target of 43,70,829 houses to the state of
Maharashtra, against which the state has given sanctions to
40,82,626 beneficiaries and 13,80,724 houses have been completed
as on 24.07.2025. The Ministry allocates the targets to the State/UT
as a whole and District-wise/Block-wise/Gram Panchayat wise
targets are fixed by the State. The district wise detail of targets
fixed by the state, houses sanctioned and houses completed,
including Washim and Yavatmal districts, as of 24.07.2025, is at the
Annexure.
The Government of India has also approved the conduct of an
exercise for updating the Awaas+ List for identifying eligible rural
households using modified exclusion criteria under the scheme. In
line with the approval of the Government of India, a survey is being
conducted for the identification of additional eligible rural
households under the scheme. The household survey which started
on 27th December 2024, is being conducted as per the modified
exclusion criteria through Awaas+ 2024 Mobile App, which was
launched on 17.09.2024. The initial timeline of Awaas+ 2024
household survey was 31st March, 2025 which was extended till
30th April 2025 and 15th May 2025 for all States/UTs. Thereafter,
the States/UTs who requested for extension in timeline have been
granted additional time for completion of survey exercise. For the
State of Maharashtra, the extended timeline for completion of
survey is 31st July 2025.
(f) to (h): Under PMAY-G, the funding pattern for the North
Eastern States and Himalayan States of Uttarakhand,
Himachal Pradesh and Union Territory of Jammu and Kashmir (UT)
is 90:10 between Centre and State whereas for the rest of the
states, this ratio is 60:40 between Centre and State. For Union
Territories without legislature, 100% funding is borne by the Centre.
ln addition, PMAY-G provisions for administrative funds at 2%
of the programme funds with bifurcation of 0.30% retained at
central level and release of 1.70% to the States/UTs for meeting the
administrative expenses as per the Framework for Implementation
(FFl) of the PMAY-G.
Page 2 of 4Within this overall limit of 2% administrative funds, PMAY-G
also provisions additional administrative funds to the North Eastern
Region (NER) and Hill States from the central share of funds.
Further, up to 5% of the targets under PMAY-G, are reserved
for Special Projects. The Ministry allocates targets for Special
Projects on the basis of proposals received from States/UTs as per
the FFI of PMAY-G.
Further, the Ministry provides technical support to the State
Governments/UT Administrations in the following manner:
(i) End to end monitoring and tracking of transactional processes
through AwaasSoft MIS.
(ii) Android based mobile application- ‘Awaas+ App’ for inspection of
houses.The application empowers officials and citizens to capture
and upload geo-referenced time stamped photographs of the house
at various stages of construction thereby reducing time lags in
verification.
(iii) Provision for constitution of dedicated Programme Management
Unit (PMU) at State/District/Block level for implementation and
monitoring of PMAY-G.
(iv) Keeping in view the diverse landscape of different States/UTs,
PAHAL - A compendium of House Design Typologies has been
developed and is available on the website of PMAY-G.
(v) Regular review meetings and Regional Workshops are conducted
by the Ministry with the States/UTs regarding various facets of
PMAY-G including sharing of best practices.
*****
Page 3 of 4Annexure
ANNEXURE REFERRED FOR REPLY TO PART (a) to (e) OF
LOK SABHA UNSTARRED QUESTION NO. 1583 TO BE ANSWERED ON 29.07.2025
regarding PMAY-G in Maharashtra
District wise targets fixed by the State, houses sanctioned, houses completed
and completion gap against sanction under Pradhan Mantri Awaas Yojana (PMAY-
G) in the state of Maharashtra (as of 24.07.2025)
Targets Completion
S. House House
District Name fixed by the Gap against
No Sanctioned Completed
State sanction
1 Ahmednagar 187536 186562 58907 127655
2 Akola 87375 85972 49675 36297
3 Amravati 162004 150921 85836 65085
4 Beed 206737 194814 39252 155562
5 Bhandara 120016 118904 61647 57257
6 Buldhana 151928 141504 35762 105742
7 Chandrapur 104398 98531 42988 55543
8 Chatrapati Sambhaji Nagar 166720 159856 36523 123333
9 Dharashiv 83694 78328 12955 65373
10 Dhule 181326 174926 62279 112647
11 Gadchiroli 79919 78541 37321 41220
12 Gondia 162419 161552 105915 55637
13 Hingoli 100095 90001 18117 71884
14 Jalgaon 215695 207803 72808 134995
15 Jalna 158793 143043 23944 119099
16 Kolhapur 71758 70654 16246 54408
17 Latur 95154 89929 18149 71780
18 Nagpur 57562 56538 35205 21333
19 Nanded 310449 275413 63819 211594
20 Nandurbar 258852 251924 115580 136344
21 Nashik 255256 247147 94303 152844
22 Palghar 95771 95755 41694 54061
23 Parbhani 146260 133540 19867 113673
24 Pune 59494 56890 17875 39015
25 Raigad 25985 25858 9948 15910
26 Ratnagiri 29290 29063 10047 19016
27 Sangli 67474 63673 19791 43882
28 Satara 58746 57436 15309 42127
29 Sindhudurg 16885 16826 5629 11197
30 Solapur 157138 146363 41326 105037
31 Thane 28752 28659 10278 18381
32 Wardha 40507 38933 19048 19885
33 Washim 88398 88100 19896 68204
34 Yavatmal 250464 238667 62785 175882
Total 42,82,850 40,82,626 13,80,724 27,01,902
*****