**Summary:**
As of July 16, 2025, the Pradhan Mantri Gramin Sadak Yojana (PMGSY) in Kerala has sanctioned a total road length of 5,312.33 km across various interventions. Of this, 4,535.69 km has been completed, while 737.44 km is currently under execution.
A breakdown of the physical achievements under PMGSY since its inception is as follows:
* **PMGSY-I:** 3,308.37 km sanctioned, 3,241.0 km completed, 39.33 km balance.
* **PMGSY-II:** 582.88 km sanctioned, 562.24 km completed, 15.60 km balance.
* **PMGSY-III:** 1,421.06 km sanctioned, 732.45 km completed, 682.51 km balance.
The difference between the sanctioned and completed road lengths does not precisely match the balance due to factors such as road length reduction, alignment changes, and construction of partial lengths by other agencies. Detailed information on the phase-wise status of ongoing projects is available on the program website: www.omms.in (Progress Monitoring State Abstract Report).
The completion timeline for ongoing projects under PMGSY-III has been extended from March 2025 to March 2026, following requests from multiple states, including Kerala.
Key Entities Referenced
Pradhan Mantri Gramin Sadak Yojana (PMGSY): A rural road development program in India.
Kerala: A state in India, where the PMGSY program is being implemented.
Ministry of Rural Development: The Indian government ministry responsible for rural development programs, including PMGSY.
SHRI ANTO ANTONY: Member of Parliament who raised a question in Lok Sabha regarding PMGSY in Kerala.
SHRI KAMLESH PASWAN: Minister of State in the Ministry of Rural Development, who answered the question regarding PMGSY in Kerala.
PMGSY I: Phase I of the Pradhan Mantri Gramin Sadak Yojana program.
PMGSY II: Phase II of the Pradhan Mantri Gramin Sadak Yojana program.
PMGSY III: Phase III of the Pradhan Mantri Gramin Sadak Yojana program.
GOVERNMENT OF INDIA
MINISTRY OF RURAL DEVELOPMENT
DEPARTMENT OF RURAL DEVELOPMENT
LOK SABHA
UNSTARRED QUESTION NO. 348
ANSWERED ON 22/07/2025
PMGSY IN KERALA
348. SHRI ANTO ANTONY:
Will the Minister of RURAL DEVELOPMENT be pleased to state:
(a) the details of total sanctioned and completed road length
under each phase of Pradhan MantriGraminSadakYojana
(PMGSY) in Kerala till date;
(b) whether the Government received any reports regarding delay
in ongoing PMGSY works in Kerala;
(c) if so, the reasons therefor; and
(d) the details of current status of ongoing projects under PMGSY
in Kerala?
ANSWER
MINISTER OF STATE IN THE MINISTRY OF RURAL DEVELOPMENT
(SHRI KAMLESH PASWAN)
(a) to (d): A total of 5,312.33 km road length has been sanctioned
in Kerala under various ongoing interventions/verticals of
Pradhan MantriGraminSadakYojana (PMGSY), out of which 4,535.69
km road length has already been completed and 737.44 km road
length are at various stages of execution. The intervention/vertical
wise physical achievements under PMGSY since inception till
16.07.2025 are given below:
(Road length in Km)
Name of Sanctioned Completed Balance*
intervention/vertical
PMGSY-I 3,308.37 3,241.0 39.33
PMGSY-II 582.88 562.24 15.60
PMGSY III 1,421.06 732.45 682.51
Total: 5,312.33 4,535.69 737.44
* Balance road length is less than the difference of sanctioned and
completed length due to the reasons that some projects were
Page 1 of 2completed with less than the sanctioned length due to reduction in
road length, change in alignment, construction of part length by
other agencies, etc.
Phase-wise status of ongoing projects under PMGSY may be
accessed at Programme website www.omms.in > Progress
Monitoring > State Abstract Report.
The timeline for completion of ongoing projects under PMGSY III has
been revised from March, 2025 to March, 2026 based on requests
received from several States, including Kerala.
*****