See Full Document Text
GOVERNMENT OF INDIA
MINISTRY OF PORTS, SHIPPING AND WATERWAYS
RAJYA SABHA
UNSTARRED QUESTION NO. 3672
ANSWERED ON 24.03.2026
PORT-LED INDUSTRIALISATION AND LOGISTICS CONNECTIVITY
3672.SHRI IRANNA KADADI:
Will the Minister of PORTS, SHIPPING AND WATERWAYSbe pleased to state:
(a) the initiatives undertaken to enhance port-led industrialisation and logistics
connectivity from Belagavi to the New Mangalore Port and Goa ports;
(b) whether the systematic development of coastal economic zones (CEZs) has
effectively driven manufacturing growth in the hinterland;
(c) the details of investments successfully grounded in port modernisation and
mechanisation in Karnataka;
(d) the measurable reduction in cargo evacuation time achieved through improved last-
mile rail and road connectivity to these ports; and
(e) the steps taken to develop dedicated mega-ship repair and shipbuilding hubs along the
Karnataka coastline?
ANSWER
MINISTER OF PORTS, SHIPPING AND WATERWAYS
(SHRI SARBANANDA SONOWAL)
(a) New Mangalore Port(NMP) is connected to Belagavi through two rail routes - via
Goa and via Arsikere-Hassan. Ministry of Railways has been requested to undertakeHubli-
Ankola rail line project to shorten the route between NMP and Belagavi. As regards the road
connectivity,NMP is well connected to Belagavi by National Highway (NH)-66, NH-52 and
NH-48.
(b) 14 Coastal Economic Zones (CEZs) have been identified under the Sagarmala
Programme to promote port-led industrial development.Dakshin Kannada CEZ is one of the
CEZs being served by the NMP. This region has presence of petrochemical unitsthat have
witnessed growth due to large EXIM vessels berthing at NMP.
(c) In the state of Karnataka,a total of 9 projects have been completed for port
modernization at the NMPcovering capacity expansion, new infrastructure, mechanization,
technology upgradation and allotment of land for port led industries. The details of these
projectsareplaced at Annexure-I.In addition, Karnataka Maritime Board has also undertaken various initiatives for
modernisation, mechanization and development across the other than major ports in the state
of Karnataka.Thisincludes berths at Karwar port, Old Mangalore port (Bengre and City Side),
and Malpe port in PPP mode, development of Pavinakurve, Manki and Padubidri ports,
Integrated Logistics Management System (ILMS) and International Ship and Port Facility
Security (ISPS) code at Karwar port.
(d) Under Sagarmala programme,a total of 24 rail and road connectivity projects costing
Rs. 44,433 crorehave been undertakenin the state of Karnatakaout of which,4projects costing
Rs. 414 crore have been completed. These completed projects at NMP have significantly
reduced cargo evacuation time, especially in the case of cargo like coal and iron ore.
(e) The Union Cabinet, in its meeting held on 24.09.2025, approved Shipbuilding
Development Scheme (SbDS) for capacity and capability development for shipbuilding in
India. The scheme with a corpus of ₹19,989 crore is designed to accelerate India’s
shipbuilding capacity through targeted interventions for new infrastructure, modernization of
existing facilities, and risk mitigation. One of the key component of scheme is capital support
for greenfield clusters for which ₹9,930 crore is allocated to create multiple shipbuilding
clustersequipped with common maritime infrastructure such as breakwaters, channel and
basin development, land reclamation, internal connectivity, and regional capability
development centres.
Ministry of Port, Shipping and Waterways has informed all the coastal states
including Karnataka, requesting them to initiate necessary steps to establish greenfield
shipbuilding clusters in their respective states as per scheme guidelines. The state of
Karnataka is required to carry out requisite studies, formulate proposal for submission to
implementing agency of the scheme i.e. Directorate General of Shipping, to process for
further approval of the competent authority.Annexure-I
Total cost
Sl. No Name of Project
(in crore)
Construction of berth 18 in western dock Arm at New Mangalore
1 94.00
Port (NMP)
2 Implementation of RFID at NMP 6.17
3 Mechanisation of Berth 16 for handling bulk cargo at NMP 469.00
Development of 30 acres of stack yard and ancillary roads for
4 22.00
parking of Ro-Ro cargoes and cars - NMP
5 Implementation of Mobile X-Ray Container Scanner at NMP 40.00
Mechanization of Berth 14 and Backup area for handling Container
6 258.00
Terminal at NMP
Installation of Fire Fighting Equipment at Karwar Port in
7 18.21
Karnataka
8 Mechanised handling of coal at berth no.15 at NMP 230
Land allotment to private sector on lease for setting up port-led
9 1198
industries at NMP