GOVERNMENT OF INDIA
MINISTRY OF POWER
LOK SABHA
UNSTARRED QUESTION NO.3209
ANSWERED ON 06.08.2026
PROJECTS TO INCREASE POWER GENERATION, TRANSMISSION AND
DISTRIBUTION CAPACITY
†3209. SHRI RAJESH RANJAN:
Will the Minister of POWER
be pleased to state:
(a) whether the Government is implementing any new action plan to increase
power generation, transmission and distribution capacity in the country by the
year 2030, if so, the details thereof;
(b) the details of the projects sanctioned for the development of power
generation, transmission and distribution infrastructure in Bihar during the last
five years;
(c) whether the Government proposes to establish new high-capacity grid
substations and transmission lines in the Kosi-Seemanchal region of Bihar, if so,
the details thereof; and
(d) the time-frame fixed for implementation of such projects?
A N S W E R
THE MINISTER OF STATE IN THE MINISTRY OF POWER
(SHRI SHRIPAD NAIK)
(a): Government of India has taken the following actions to increase power
generation, transmission and distribution capacity in the country:
1. Generation and Storage Planning:
(i) As per National Electricity Plan (Generation), installed generation
capacity in 2031-32 is likely to be 874 GW. With a view to ensure
generation capacity remains ahead of projected demand, all the States,
in consultation with CEA, have prepared their “Resource Adequacy Plans
(RAPs)”, which are dynamic 10-year rolling plans and includes power
generation as well as power procurement planning.(ii) All the States were advised to initiate process for creating/ contracting
generation capacities; from all generation sources, as per their
Resource Adequacy Plans.
(iii) In order to augment the power generation capacity, the Government of
India has initiated following capacity addition programme:
a. Thermal Capacity Addition: The projected thermal (coal and lignite)
capacity requirement by the year 2035–36 is estimated at approximately
3,15,000 MW as against the 2,11,855 MW installed capacity as on
31.03.2023. To meet this requirement, Ministry of Power has envisaged to
set up an additional minimum 1,05,000 MW coal and lignite based thermal
capacity.
Accordingly, Thermal capacities of around 21,080 MW have been
commissioned since April 2023 till 30.06.2026. In addition, 47,545 MW of
thermal capacity (including 4,845 MW of stressed thermal power projects)
is currently under construction. The contracts of 16,000 MW have been
awarded and are due for construction.
b. Central Electricity Authority (CEA) has projected hydro power
capacity addition of about 16,448 MW during the period 2026–27 to 2031–
32. Of this, 400 MW has been commissioned as on 30.06.2026 and 12,973
MW are presently under construction.
c. Nuclear Capacity Addition: 8,000 MW of Nuclear Capacity is under
construction and targeted to be completed by 2031-32. 5,600 MW of Nuclear
Capacity is under various stages of planning and approval.
d. Renewables Capacity Addition: 1,47,720 MW Renewable Capacity
including 119,580 MW of Solar (including Hybrid-Solar) and 27,720 MW of
Wind (including Hybrid-wind) is under construction while 47,830 MW of
Renewable Capacity including 44,440 MW of Solar is at various stages of
planning and targeted to be completed by 2029-30.
e. Addition of Energy Storage Systems: As on 30.06.2026, 15,870
MW/95,220 MWh Pumped Storage Projects (PSPs) are under construction.
Further, a total of 6,580 MW/39,480 MWh capacity of Pumped Storage
Projects (PSPs) are concurred and yet to be taken up for construction. As
on 30.06.2026, 15,754 MW / 42,530 MWh Battery Energy Storage System
(BESS) capacity are under construction, 11,747 MW / 38,425 MWh has been
awarded and 19,192 MW / 67,574 MWh BESS capacity are under tendering
stage.
2. Promotion of Renewable Energy (RE) Generation:
(i) 100% Inter State Transmission System (ISTS) charges have been waived
for inter-state sale of solar and wind power for projects to be
commissioned by 30th June 2025 (with waiver tapering off 25% annually
till June 2028), for co-located BESS projects commissioned by June2028, for Hydro PSP projects where construction work awarded by June
2028, for Green Hydrogen Projects commissioned till December 2030
and for offshore wind projects commissioned till December 2032.
(ii) Standard Bidding Guidelines for tariff based competitive bidding process
for procurement of Power from Grid Connected Solar, Wind, Wind-Solar
Hybrid and Firm & Dispatchable RE (FDRE) projects have been issued.
(iii) Renewable Energy Implementing Agencies (REIAs) are regularly inviting
bids for procurement of RE power.
(iv) Foreign Direct Investment (FDI) has been permitted up to 100 percent
under the automatic route.
(v) To augment transmission infrastructure needed for steep RE trajectory,
transmission plan has been prepared till 2032.
(vi) Laying of new intrastate transmission lines and creating new sub-station
capacity has been supported under the Green Energy Corridor Scheme
for evacuation of renewable power.
(vii) Scheme for setting up of Solar Parks and Ultra Mega Solar Power projects
is being implemented to provide land and transmission to RE developers
for installation of RE projects at large scale.
(viii) Schemes such as Pradhan Mantri Kisan Urja Suraksha evam Utthaan
Mahabhiyan (PM-KUSUM), PM Surya Ghar Muft Bijli Yojana, National
Programme on High Efficiency Solar PV Modules, New Solar Power
Scheme (for Tribal and PVTG Habitations/Villages) under Pradhan Mantri
Janjati Adivasi Nyaya Maha Abhiyan (PM JANMAN) and Dharti Aabha
Janjatiya Gram Utkarsh Abhiyan (DA JGUA), National Green Hydrogen
Mission, Viability Gap Funding (VGF) Scheme for Offshore Wind Energy
Projects have been launched.
(ix) To encourage RE consumption, Renewable Purchase Obligation (RPO)
followed by Renewable Consumption Obligation (RCO) trajectory has
been notified till 2029-30. The RCO which is applicable to all designated
consumers under the Energy Conservation Act, 2001 will attract
penalties on non-compliance.
(x) “Strategy for Establishment of Offshore Wind Energy Projects” has been
issued.
(xi) Green Term Ahead Market (GTAM) has been launched to facilitate sale of
Renewable Energy Power through exchanges.
(xii) Production Linked Incentive (PLI) scheme has been launched to achieve
the objective of localization of supply chain for solar PV Modules.3. Transmission:
Inter and Intra-State Transmission System has been planned and
implementation of the same is taken up in matching time frame of generation
capacity addition. As per the National Electricity Plan (Transmission), about
1,91,474 ckm of transmission lines and 1,274 GVA of transformation capacity is
planned to be added (at 220 kV and above voltage level) during the ten-year period
from 2022-23 to 2031-32.
In addition to the above, the Ministry of Power has issued guidelines dated
14.06.2024, 21.03.2025 and 15.12.2025 regarding the payment of compensation
for Right of Way (RoW) for transmission lines, wherein the land rate has been
linked to the prevailing market rate. These guidelines address the key challenges
of RoW arising from landowners demanding higher compensation than the rates
determined by the State Government
4. Distribution :
Government of India has supplemented the efforts of the States earlier
through schemes like Deen Dayal Upadhyaya Gram Jyoti Yojana (DDUGJY),
Integrated Power Development Scheme (IPDS), Pradhan Mantri Sahaj Bijli Har
Ghar Yojana (SAUBHAGYA) and currently under Revamped Distribution Sector
Scheme (RDSS), to help them achieve the objective of providing quality and
reliable supply of power.
Government of India launched RDSS in July 2021 with the objective of
improving the quality and reliability of power supply to consumers through a
financially sustainable and operationally efficient distribution Sector. The
scheme has an outlay of Rs. 3,03,758 Cr. and estimated Gross Budgetary Support
(GBS) from Central Government of Rs. 97,631 Cr. Under the scheme, financial
assistance is being provided to the Distribution Utilities (excluding Private Sector
Utilities) for loss reduction infrastructure works and smart metering works.
Projects worth Rs. 1.53 lakh crore for loss reduction infrastructure and Rs. 1.31
lakh crore for smart metering works have been sanctioned under the scheme
which would help improve the reliability and quality of power supply in the
country.
In addition to above, to support the power distribution utilities to improve
their Aggregate Technical and Commercial (AT&C) losses some of the key
initiatives taken, in addition to RDSS, are as under:
(i) Additional Borrowing consent of 0.5% of Gross Sate Domestic Product
(GSDP) to State Governments, which is conditional on them undertaking
specific reforms in the power sector.(ii) Additional Prudential Norms for sanctioning of loans to State owned
power utilities contingent on the performance of power distribution
utilities against prescribed conditions.
(iii) Rules for implementation of Fuel and Power Purchase Cost Adjustment
(FPPCA) and cost reflective tariff so as to ensure that all prudent cost
for supply of electricity is passed through.
(iv) Rules and Standard Operating Procedure issued for proper subsidy
accounting and their timely payment.
(b): The details of the projects sanctioned for the development of power
generation, transmission and distribution infrastructure in Bihar during the last
five years are given below:
I. Generation:
The detail of thermal power project sanctioned in the state of Bihar in the
last five years is given at Annexure-I. No Hydroelectric projects / Pumped Storage
Projects in the state of Bihar were concurred by Central Electricity Authority
(CEA) during the last 5 years. In addition, no nuclear project has been planned in
the last five years.
II. Transmission:
To cater to the future, Inter State Transmission System (ISTS) requirements
in the State of Bihar, about 1,016 ckm transmission lines along with
reconductoring of about 468 ckm, about 8,200 MVA transformation capacity
augmentation, and 500 MW HVDC back-to-back refurbishment/upgradation at
Pusauli are under construction / under planning. The details of major schemes
under ISTS which have been approved in last five years along with its
implementation status viz. completed, under construction, under bidding & under
planning are as under:
1. ISTS Substations (S/s) Completed:
i. Creation of 220 kV level at existing 400/132 kV Banka (New) (POWERGRID),
ii. Creation of 220 kV level at existing 400/132 kV Lakhisarai (New)
(POWERGRID).
2. Under construction:
i. Reconductoring of Kahalgaon – Farakka 400 kV Double circuit (D/c) line
with High Tension Low Sag (HTLS) conductor:
ii. Upgradation of Pusauli 1x500 MW HVDC (High Voltage Direct Current)
Back-to-Back to 2x500 MW with SiC VSC (Silicon Carbide Voltage Source
Converter) based HVDC Back-to-Back:
iii. Diameter completion at Sasaram (POWERGRID) S/s3. Under bidding:
Establishment of Nawada (ISTS) 765/400/220 kV S/s including associated
lines viz. LILO of Gaya – Balia 765 kV Single circuit (S/c) line at Nawada
(ISTS) S/s & Nawada (ISTS) – Durgapur (New) – Jeerat (ISTS) 765 kV D/c
line.
Further, it is to mention that ISTS augmentation is being carried out on
continuous basis in Bihar commensurate with generation addition, demand
growth, and as per drawl requirement of state from ISTS network.
III. Distribution:
Under RDSS Scheme, works of Rs. 10,559 Crores for distribution
infrastructure works and Rs. 2,021 Crores for smart metering works have been
sanctioned for the State of Bihar. Sanctioned distribution infrastructure works
include upgradation / augmentation of sub-stations and distribution transformers,
upgrading of conductors, laying of ABC / covered conductors, segregation of
mixed-load feeders, etc. All the distribution schemes are scheduled to be
completed within sanctioned period i.e. by 31stMarch, 2028.
(c) & (d) : As per the Resource Adequacy Plan (Transmission) for Bihar, the
details of upcoming grid substations and transmission lines in the Kosi-
Seemanchal region of Bihar along with tentative time frame is given at
Annexure-II.
***************ANNEXURE-I
ANNEXURE REFERRED IN REPLY TO PART (b) OF UNSTARRED QUESTION NO.
3209 ANSWERED IN THE LOK SABHA ON 06.08.2026
*************
The detail of thermal power project taken up for implementation in the state of Bihar in the
last five years:
Sl. Implementing Unit Capacity
Project Name LOA Date
No. Agency No. (MW)
U-4 800
Nabinagar Super
1 Thermal Power Project, NTPC March 2025 U-5 800
Stage-II
U-6 800
U-1 800
Pirpainti Ultra-
2 Supercritical Thermal Adani Power June 2025 U-2 800
Power Plant
U-3 800
*************ANNEXURE-II
ANNEXURE REFERRED IN REPLY TO PARTS (c) & (d) OF UNSTARRED QUESTION
NO. 3209 ANSWERED IN THE LOK SABHA ON 06.08.2026
*************
Details of upcoming grid substations and transmission lines in the Kosi-Seemanchal
region of Bihar:
Likely
Sl. No. Grid Sub-station/Transmission Lines Completion
Time Frame
2028-29
1 132/33 kV, 2x80 MVA at Bhawanipur
LILO of Dhamdaha – Banmankhi 132 kV S/c line at
2028-29
2 Bhawanipur (ACSR Panther) (25 km loop in and 25 km Loop
out).
3 220/132 kV, 2x200+2x80 MVA S/s at Kasba 2030-31
4 Katihar(ISTS) – Kasba 220 kV D/c Line (twin Moose) (50 ckm) 2030-31
LILO of Kishanganj - Madhepura 220 kV D/C line at Kasba (50
5 2030-31
ckm Loop in 50 ckm Loop out)
6 220/132/33 kV, 2x200+2x80 MVA S/s at Raniganj 2031-32
LILO of Kishanganj – Madhepura 220 kV D/c Line at Raniganj
7 2031-32
(50 ckm Loop in and 50 ckm Loop out)
8 132/33 kV, 2x80 MVA S/s at Sanauli 2033-34
9 Kasba - Sanuli 132 kV D/c Line (80 ckm) 2033-34
10 132/33 kV, 2x80 MVA S/s at Bahadurganj 2032-33
11 Thakurganj – Bahadurganj 132 kV D/c Line (80 ckm) 2032-33
****************