Executive Summary:
The Ministry of Railways addresses railway development works, particularly in Kollam, under Lok Sabha Unstarred Question No. 634. The response details the Amrit Bharat Station Scheme, progress at Kollam and other stations, and the status of the Kundara Pallimukku Road Over Bridge (ROB). While station development is ongoing, no specific completion dates are provided due to various factors.
Key Points / Main Content:
Amrit Bharat Station Scheme:
* Launched for station redevelopment, with 1337 stations identified.
* Phase I work completed at 105 stations, with work underway at 1110 stations.
* 35 stations in Kerala, including Kollam, are included in the scheme, with work underway at 33 stations.
* Focuses on continuous station development with master plans implemented in phases.
* Aims to improve amenities such as access, waiting halls, toilets, and passenger information systems.
Progress at Specific Stations:
* Kollam: Work completed on service building, substation, multi-level car parking, parcel building structural work, and south terminal segment I Block A & B. Ongoing work on other segments, foot over bridge, air concourse, and platform shelter.
* Punalur: Lifts, new platform shelter, passenger information system, and train/coach indication boards are completed. Improvements underway for circulating/parking areas, station elevation, pedestrian pathway, and waiting hall.
* Ernakulam Town: Structural work of West Terminal building Segment 1 and residential tower is completed, and block and plastering work has begun. Foundation work completed for the foot over bridge gangway.
Funding and Implementation:
* Station development is an ongoing process, prioritized based on station category and fund availability.
* Funded under Plan Head 53 Customer Amenities.
* Southern Railways allocated Rs 1122 crores under Plan Head 53 for the financial year 2025-26.
* Development is complex, requiring statutory clearances and facing challenges like utility shifting and operational constraints.
Kundara Pallimukku ROB:
* Sanctioned in 2012-13 at a cost of Rs.37.24 crore on a cost-sharing basis.
* Executed on a dual entity basis: Railway portion by railway and approaches portion by State Govt.
* Land acquisition is pending by the State Government (RBDCK).
* General Arrangement Drawing (GAD) has been approved.
Road Over Bridges/Road Under Bridges (ROBs/RUBs) General Information:
* Construction/Sanctioning is an ongoing process.
* 4402 ROBs/RUBs are sanctioned at the cost of Rs. 100860 crore on Indian Railways including 140 Nos. Road Over Bridges Road Under Bridges at the cost of Rs. 4837 crore in the State of Kerala.
* Completion depends on State Government cooperation, land acquisition, utility shifting, and clearances.
* Currently, 13 ROBs/FOBs with ramps are sanctioned in the Kollam Parliamentary constituency.
Impact Analysis:
Ministry of Railways:
* Impact: Responsible for the execution and oversight of the Amrit Bharat Station Scheme and ROB construction.
* Action Required: Continue to implement the Amrit Bharat Station Scheme, allocate funds, and coordinate with state governments for ROB projects.
State Government of Kerala (specifically Roads and Bridges Development Corporation of Kerala Limited - RBDCK):
* Impact: Responsible for land acquisition and construction of approach portions for ROB projects.
* Action Required: Expedite land acquisition for the Kundara Pallimukku ROB and other ROB projects to ensure timely completion.
Railway Passengers/Citizens of Kollam:
* Impact: Will benefit from improved station amenities and infrastructure, as well as enhanced connectivity through ROBs.
* Action Required: None specified, but can monitor progress and provide feedback to relevant authorities.
Key Entities Referenced
Kollam Railway Station: A railway station in Kollam, Kerala, which is undergoing development work.
Amrit Bharat Station Scheme: A Ministry of Railways scheme for the redevelopment and upgradation of railway stations in India.
Kundara Pallimukku ROB: A Road Over Bridge (ROB) being constructed at Kundara Pallimukku in Kollam district, Kerala.
Ashwini Vaishnaw: The Minister of Railways, Information Broadcasting and Electronics Information Technology.
Kerala: A state in India where multiple railway development projects are underway.
Punalur station: A railway station in Kerala where various development works are being carried out.
Ernakulam Town: A railway station in Kerala where development works are being carried out.
Southern Railways: A zonal railway of Indian Railways, under whose jurisdiction Kollam railway station falls.
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 634
TO BE ANSWERED ON 23.07.2025
RAILWAY DEVELOPMENT WORK IN KOLLAM
634. SHRI N K PREMACHANDRAN:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government proposes to complete the Railway
Development works in a time bound manner, if so the action taken
thereon;
(b) the present status of Railway Development work in Kollam Railway
Station and proposed date of its completion;
(c) the details of the action taken for preservation of Chinese Palace in
Kollam Railway Station;
(d) the details of the action taken for the construction of Kundara –
Pallimukku ROB and the proposed date of its completion;
(e) whether the Government proposes to include the construction of
the said ROB in the special scheme of Railways for funding 100% cost
by the Railways;
(f) if so, the action taken thereon; and
(g) the details of action taken by the Government for timely completion
of ROBs in Kollam Lok sabha Constituency?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (g): Ministry of Railways has launched Amrit Bharat Station
Scheme for redevelopment of stations. So far, 1337 stations have been
identified for development under Amrit Bharat Station Scheme.Presently Phase-I work of 105 stations have been completed and
commissioned and works have been taken up at 1110 stations.
Further, 35 stations located in state of Kerala including Kollam railway
stations have been identified for development under Amrit Bharat
Station Scheme.
Out of these 35 stations, the development works have been taken up
on 33 stations. The works have been taken up at a good pace. The
progress at some of these stations is as given below:
At Kollam station, the work of service building, substation, Multi level
car parking and structural work of parcel building, south terminal
segment I (Block A & B) have been completed. The work for
structural work of south terminal segment I (block C), south terminal
segment II, foot over bridge, air concourse and platform shelter works
have been taken up.
At Punalur station, works of provision of lifts, new platform shelter,
passenger information system, train indication boards, coach
indication boards have been completed and the works of
improvements in circulating area and parking area, station elevation
including portico, separate pedestrian pathway and construction of
new waiting hall have been taken up.
At Ernakulam Town, the Structural work of West Terminal building –
Segment 1 and residential tower is completed and block work and
plastering works have been taken up. The foundation work for the foot
over bridge gangway has been completed. The 6th floor slab work,
block work and plastering work of Multi level car parking have been
taken up.The Amrit Bharat Station scheme envisages development of stations
on a continuous basis with a long-term approach. It involves
preparation of master plans and their implementation in phases to
improve the amenities at the stations like improvement of station
access, circulating areas, waiting halls, toilets, lift/escalators as
necessary, platform surfacing and cover over platform, cleanliness,
free Wi-Fi, kiosks for local products through schemes like ‘One Station
One Product’, better passenger information systems, executive
lounges, nominated spaces for business meetings, landscaping, etc.
keeping in view the necessity at each station.
The scheme also envisages improvement of building, integrating the
station with both sides of the city, multimodal integration, amenities
for Divyangjans, sustainable and environment friendly solutions,
provision of ballastless tracks, etc. as per necessity, phasing and
feasibility and creation of city centre at the station in the long term.
Development/upgradation of stations on Indian Railways is a
continuous and ongoing process and works in this regard are
undertaken as per requirement, subject to inter-se priority and
availability of funds. The priority for development/upgradation of
stations is accorded to higher category of station over lower category
of station while sanctioning and executing the works.
Development / upgradation of stations including under Amrit Bharat
Station Scheme is generally funded under Plan Head-53 ‘Customer
Amenities’. The details of allocation under Plan Head-53 are
maintained Zonal Railway-wise and not work-wise or station-wise or
State-wise. Kollam railway station falls under the jurisdiction of
Southern Railways for which a total allocation of Rs 1122 crores
(Budget Estimate) has been made for the financial year 2025-26 under
Plan Head-53.Further, development/redevelopment/upgradation of Railway Stations
is complex in nature involving safety of passengers & trains and
requires various statutory clearances such as fire clearance, heritage,
tree cutting, airport clearance etc. The progress also gets affected
due to brown field related challenges such as shifting of utilities,
(involving water/sewage lines, optical fiber cables, gas pipe lines,
power/signal cables etc.,) infringements, operation of trains without
hindering passenger movement, speed restrictions due to works
carried out in close proximity of high voltage power lines etc. and
these factors affect the completion time. Therefore, no time frame can
be indicated at this stage.
The work for construction of Road Over Bridge (ROB) at Kundara -
Pallimukku in lieu of LC No.526 at Km.748/1-2 in between Ezhukone-
Kundara stations in Kollam- Sengottai section of Madurai division was
sanctioned at the cost Rs.37.24 crore in the year 2012-13 on cost
sharing basis.
This work is being executed on dual entity basis i.e. Railway portion
by railway and approaches portion by State Govt. i.e. Roads and
Bridges Development Corporation of Kerala Limited (RBDCK). Land
Acquisition is yet to be done by State Govt. The General Arrangement
Drawing (GAD) has been approved.
Sanctioning and execution of works of Road Over Bridges/ Road Under
Bridges (ROBs/RUBs) in lieu of LCs is a continuous and ongoing
process on Indian Railways. Such works are prioritized and taken up
on the basis of its impact on safety and mobility in train operations
and impact on road users.No. of ROBs/RUBs constructed on Indian Railways during the period
2004-14 vis-a-vis 2014-26 (upto June’25) is as under:
Period ROBs/RUBs constructed
2004-14 4148
2014-26 (upto June’25) 13426 (including 118 Nos. in the state of
Kerala)
As on dt. 01.04.2025, 4402 Nos. ROBs/ RUBs are sanctioned at the
cost of Rs. 100860 crore on Indian Railways including 140 Nos. Road
Over Bridges / Road Under Bridges at the cost of Rs. 4837 crore in the
State of Kerala, which are at various stages of planning and execution.
Out of which, 49 Nos. ROBs works in the state of Kerala are held up
due to delay in land acquisition
Presently, 13 nos. ROBs/FOB with ramp are sanctioned in Kollam
Parliamentary constituency which are at various stages of planning
and execution.
Completion and commissioning of ROB/RUB works depend on various
factors like cooperation of State Governments in giving consent for
closure of LCs, fixing of approach alignment, approval of General
Arrangement Drawing (GAD), land acquisition, removal of
encroachments, shifting of infringing utilities, statutory clearances
from various authorities, law and order situation in the area of
project/work sites, duration of working season in a year for the
particular project/area due to climatic conditions etc. All these
factors affect the completion time of the projects / works.
*****