GOVERNMENT OF INDIA
MINISTRY OF NEW AND RENEWABLE ENERGY
LOK SABHA
UNSTARRED QUESTION NO. 1698
ANSWERED ON 29.07.2026
REVIEW OF PROGRESS OF ROOFTOP SOLAR INSTALLATIONS
1698. DR. PRABHA MALLIKARJUN
Will the Minister of NEW AND RENEWABLE ENERGY be pleased to state:
(a) whether the Government has reviewed the progress of rooftop solar installations under the
Pradhan Mantri Surya Ghar Muft Bijli Yojana (PM-SGMBY);
(b) if so, the number of households benefitted, State-wise;
(c) the details of total subsidy released under the said yojana;
(d) whether implementation bottlenecks have been identified; and
(e) if so, the corrective measures taken by the Government to accelerate household solar adoption?
ANSWER
THE MINISTER OF STATE FOR NEW & RENEWABLE ENERGY AND POWER
(SHRI SHRIPAD YESSO NAIK)
(a) to (e) The progress of the PM Surya Ghar: Muft Bijli Yojana (PMSG: MBY) is being monitored
at different levels including through review meetings with various stakeholders across the country
from time to time.
The PM Surya Ghar: Muft Bijli Yojana (PMSG: MBY) is a demand-driven scheme wherein all
residential consumers in the country, having a grid-connected electricity connection with the local
DISCOM, can avail the benefits of the scheme, for installation of RTS systems by applying on the
National Portal (www.pmsuryaghar.gov.in) of the scheme.
Under the scheme, since its launch in February 2024, a total of 40,45,298 RTS systems have been
installed, benefitting 48,80,796 households, and an amount of Rs. 27,343.9 crore has been released
as Central Financial Assistance (CFA) to the beneficiaries across the country, as on 27.07.2026.
The State/UT-wise details are given in the Annexure.
To accelerate household RTS adoption and reduce implementation bottlenecks under the scheme,
the Ministry has taken the following measures:
• Online process from application to disbursal of subsidy directly into the bank account of the
residential consumer through the National Portal.
• Availability of collateral-free loan from nationalized banks at a concessional interest rate of
repo-rate plus 50 bps, i.e., 5.75% per annum for the present, with a tenure of 10 years.• Simplified the regulatory approval process by waiving technical feasibility requirement and
introducing auto load enhancement upto 10 kW.
• Net metering agreement has been made part of the application in the National Portal,
eliminating the requirement of signing a separate agreement.
• Simplified process for registration of vendors to ensure sufficient and qualified vendors are
available.
• Capacity building and training programmes being conducted for creating skilled manpower.
• Creating awareness about the scheme, through awareness and outreach program such as print
advertising in leading newspapers, TV commercials campaigns, Radio campaigns across FM
stations including regional channels, etc., in the country.
• Regular monitoring of the progress of the scheme at different levels including with
states/DISCOMs.
• Conducting regional review meetings from time to time.
• Established grievance redressal mechanism for timely resolution of grievances. A Call Centre
with telephone number 15555 is operational in 12 languages.
Further, MNRE and REC Ltd., as the National Programme Implementing Agency (NPIA), for
PMSG: MBY, work in close coordination with all the DISCOMs, for effective implementation
of the scheme.
*****Annexure referred to in reply of parts (a) to (e) of Lok Sabha Unstarred Question No. 1698
to be answered on 29.07.2026 regarding Review of Progress of Rooftop Solar Installations
State/UT-wise details of progress made under the PMSG: MBY across the country (As on
27.07.2026)
Installation Households Subsidy Released
State
S No. (Nos.) (Nos.) Amt (in cr.)
1 Gujarat 766278 1107607 5597.04
2 Maharashtra 692853 1078535 5017.02
3 Uttar Pradesh 703661 711324 4652.73
4 Kerala 305977 312823 2043.61
5 Rajasthan 272818 281881 1815.39
6 Andhra Pradesh 254701 259171 1358.36
7 Madhya Pradesh 156128 161512 1095.26
8 Assam 160077 160805 1148.37
9 Odisha 143890 144978 692.34
10 Haryana 114889 124817 730.11
11 Tamil Nadu 85742 101578 576.66
12 Uttarakhand 96203 96567 719.59
13 Chhattisgarh 82920 85414 498.17
14 Telangana 54668 70144 325.11
15 JAMMU And KASHMIR 38953 39106 298.93
16 Karnataka 22952 35450 163.44
17 Bihar 24328 24970 161.76
18
Punjab 17296 17305 110.07
19 NCT of Delhi 10575 15451 70.82
20 Himachal Pradesh 11835 11868 87.00
21 Meghalaya 61 9307 0.31
22 Puducherry 4751 4828 31.31
23 Goa 3358 4599 22.58
24 Tripura 4447 4459 32.52
25 Jharkhand 3279 3509 21.20
26 West Bengal 3132 3239 8.43
27 Ladakh 2028 2028 14.94
28 Manipur 1548 1548 11.38
29 Chandigarh 1375 1375 8.28
30 Mizoram 1347 1350 10.43
31 Lakshadweep 1186 1186 9.77
32 The Dadra & Nagar Haveli
and Daman & Diu 1138 1138 5.40
33 Nagaland 437 437 2.71
34 ANDAMAN And NICOBAR
ISLANDS 407 427 2.46
35 Sikkim 59 59 0.37
36 Arunachal Pradesh 1 1 0.01
Total 40,45,298 48,80,796 27,343.9