O.I.H.
GOVERNMENT OF INDIA
MINISTRY OF RURAL DEVELOPMENT
DEPARTMENT OF RURAL DEVELOPMENT
LOK SABHA
UNSTARRED QUESTION NO. 1479
ANSWERED ON 28/07/2026
ROAD PROJECTS FOR BIHAR UNDER PMGSY
1479. Smt. Lovely Anand:
Will the Minister of RURAL DEVELOPMENT be pleased to state:
(a) whether the Government has launched the Pradhan Mantri Gram
Sadak Yojana (PMGSY) Phase-IV for the financial years 2024-29,
State-wise including Bihar;
(b) whether Bihar has been accorded priority under the schme in
view of its large rural population and road connetivity
requirment, if so, the details thereof;
(c) the details of the number of eligible rural habitations, number of
eligible projects, number of road proposals received from the
State Government and number of projects approved so far for
Bihar under PMGSY, district-wise;
(d) the details and the number of eligible rural habitations, eligible
projects, road proposals received from the State Government,
approved projects, approved road length, approved amount and
the current progress of the projects, district-wise including
Sheohar; and
(e) whether eligible project has not been approved by the
Government, if so, the details thereof and if not, the reasons
therefor along with the timeframe for their approval?
ANSWER
MINISTER OF STATE IN THE MINISTRY OF RURAL DEVELOPMENT
(SHRI KAMLESH PASWAN)
(a) & (b): The Union Cabinet approved Pradhan Mantri Gram Sadak
Yojana-IV (PMGSY-IV), for implementation during FY 2024–25 to FY
2028–29 with the target to provide all-weather road connectivity
(construction of 62,500 km of roads) to 25,000 eligible unconnected
habitations across the country with a total outlay of Rs.70,125 crore.
There is no state-wise target under PMGSY-IV. The eligibility criteria
Page 1 of 3of the habitations to be provided connectivity under PMGSY-IV based
on population norms of Census 2011 are as follows:
i. Habitations with a population of 500 and above in plains,
ii. Habitations with a population of 250 and above in Special
Category States (Arunachal Pradesh, Assam, Ladakh, Manipur,
Meghalaya, Mizoram, Nagaland, Sikkim, Tripura, Himachal
Pradesh, Jammu Kashmir and Uttarakhand), Special Category
Areas [Tribal Schedule-V Areas, Desert Areas, Aspirational
Blocks/ Districts and Hilly areas as notified by the respective
State Government (cross slope more than 25% gradient and the
elevation is more than 600 metres from the Mean Sea Level)]
and
iii. Habitations with a population of 100 and above in LWE affected
Districts including Legacy & Thrust Districts identified by MHA
from time to time.
(c) & (d): The identification of eligible habitations, preparation of
Detailed Project Reports (DPRs), and submission of proposals are
undertaken by the State Government through the State Rural Roads
Development Agency (SRRDA) using the Online Management,
Monitoring and Accounting System (OMMAS).
Across all phases of PMGSY (PMGSY-I, II, III, and RCPLWEA), a
total of 18,764 roads measuring 65,584 km and 2,085 bridges have
been sanctioned in the State of Bihar, out of which 62,724 km of road
length and 1821 bridges have been completed till date, connecting
31,293 habitations. The details of works sanctioned and completed
under all verticals of PMGSY in the State of Bihar including District-
wise details including that of Sheohar district are available in the
public domain via the Online Management, Monitoring and
Accounting System (OMMAS) portal and may be seen at
https://pmgsy.dord.gov.in/dbweb.
(e): Clearance of road proposals under PMGSY is an ongoing
process governed by programme guidelines. Projects are sanctioned
based on the following standard procedure:
i. Submission on OMMAS: The State Government prepares DPRs and
uploads vetted proposals on the OMMAS portal.
ii. Technical Scrutiny: DPRs are scrutinised by State Technical
Agencies (STAs), Principal Technical Agencies (PTAs) and National
Rural Infrastructure Development Agency (NRIDA).
iii. Empowered Committee Consideration: Eligible proposals are
placed before the Inter-Ministerial Empowered Committee (EC) of the
Ministry of Rural Development for consideration.
Proposals are deferred or not approved primarily due to:
Page 2 of 3 Incomplete Detailed Project Reports (DPRs) or pending
information sought from the State Government regarding them.
Issues related to land availability or alignment disputes.
Once the State Government resolves technical queries and
submits fully compliant proposals, they are considered for approval
by the Empowered Committee in a time-bound manner. As on date,
under PMGSY-IV, the State of Bihar has uploaded 20 nos of road
works for a length of 22.83 km covering 21 nos of habitations and 4
bridges on Programme MIS of PMGSY which are under scrutiny. No
other proposal is pending for sanction.
*****