GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 3091
TO BE ANSWERED ON 11.03.2026
SAFETY CONCERNS ON CHANDIGARH DELHI RAILWAY TRACK
3091. SHRI MANISH TEWARI:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government is aware of concerns regarding unsafe
conditions of track on the Chandigarh–Delhi route particularly
relating to excessive bouncing, swaying and instability of trains at
certain stretches and if so, the details thereof;
(b) whether such conditions have been reported in premium trains such
as the Delhi–Kalka Shatabdi Express and if so, the details thereof;
(c) whether complaints of these safety issues were brought to the
notice of the Railways during the last one year and if so, the action
taken thereon;
(d) whether any technical inspection, track maintenance audit/safety
review has been conducted on the said route and if so, the findings
thereof; and
(e) the corrective measures being undertaken by the Government to
ensure passenger safety, improve track quality and prevent any
potential accidents on said critical rail corridor?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e) Safety of train operation is accorded top priority on Indian
Railways (IR). There is a well-established system of inspection and
maintenance of railway tracks as prescribed in Indian Railways
Permanent Way Manual. The Chandigarh-Delhi route is also inspected
§and maintained in accordance with the prescribed provisions and is
safe for running of trains at permitted speed.
The tracks on IR are regularly inspected by designated officials as per
the laid down schedule. This includes daily patrolling, on-foot
inspection, trolley inspection and foot plate/rear window inspection by
the concerned officials. Further, to assess the health of track
geometry objectively, Track Recording Car (TRC) and Oscillation
Monitoring System (OMS) runs are conducted at scheduled
frequencies. The entire railway network of Indian Railways is covered
through TRC and OMS runs. Based on various inspections, necessary
action is taken in a time bound manner to ensure safety of track.
Strengthening, upgradation, modernisation and improvement of track
infrastructure is a continuous and ongoing process over Indian
Railways. The following measures are being taken by Indian Railways
to upgrade railway tracks:
i. Modern track structure consisting of 60kg, 90 Ultimate Tensile
Strength (UTS) rails, Wider and heavier Pre-stressed Concrete
Sleepers (PSC) with elastic fastening, fan-shaped layout turnout on
PSC sleepers and H-beam Sleepers on girder bridges are being
used while carrying out primary track renewals.
ii. The Thick Web Switches and Weldable CMS Crossings are being
used in turnout renewal works.
iii. Supply of 260m long rail panels have been increased to avoid
welding of joints, thereby improving safety and riding quality
iv. Thick Web Switch Expansion Joints are being used in place of
earlier Conventional/Improved SEJs.
v. Adoption of better welding technology for rails i.e. Flash Butt
Welding.
§vi. Adoption of mechanized system for track maintenance using high
output plain tampers and points & crossing tampers for improved
maintainability & reliability of track.
vii. Deployment of state-of-the-art modern machines including Rail
Grinding Machines to further improve asset reliability.
viii. Mechanisation of track laying activities through use of track
machines like PQRS, TRT, T-28 etc.
ix. Interlocking of Level Crossing (LC) Gates for enhancing safety at
LC gates.
x. Use of advanced Phased Array technology of testing of rail and
welds.
xi. Deployment of Integrated Track Monitoring Systems (ITMS) and
Oscillation Monitoring System (OMS) for comprehensive health
assessment to ascertain optimal maintenance requirements.
xii. Adoption of portable Track Measuring Trolley for continuous
recording of track parameters in yards.
xiii. Using web enabled Track Management System (TMS) for
integration and data analytics of the track inspection records
received through various sources to enable precise maintenance
inputs.
As a result of above measures, there has been significant increase in
speed potential of the tracks. The details of speed potential of railway
tracks during 2014 vis-a-vis 2026 are as under:
2014 2026 (up to
Sectional Speed
Feb’26)
(kmph)
% %
Track Km Track Km
5,036 6.3 23,713 22.4
130 & above
§110 - 130 26,409 33.3 62,036 58.7
< 110 47,897 60.4 19,923 18.9
Total 79,342 100 1,05,672 100
Safety:
Safety is accorded the highest priority on Indian Railways. As a
consequence of various safety measures taken over the years, there
has been a steep decline in the number of accidents. Number of
Consequential Train Accidents has reduced as shown below:-
Year Consequential Accidents
2014-15 135
2025-26 (upto 28.02.2026) 14 (90% lesser)
234
165
135
55
31
14
2005-06 2009-10 2014-15 2019-20 2024-25 2025-26
(Feb 2026)
Another important index showing improvement in safety in train
operations is Consequential Accident Index. This index measures
§
stnediccA
niarT
laitneuqesnoC
fo
.oNnumber of consequential accidents as a ratio of total running
Kilometers of all trains.
No. of consequential accidents
Accident Index =
No. of trains X million kilometers run
The details are as under:-
Year Accident Index
2014-15 0.11
2024-25 0.03 (73% lesser)
The various safety measures taken to enhance safety in train
operations are as under:-
1. On Indian Railways, the expenditure on Safety related activities has
increased over the years as under:-
Expenditure/ Budget on Safety related activities (₹ in Crore)
2013-14 2022-23 2023-24 2024-25 2025-26
39,200 87,336 1,01,662 1,14,022 1,17,693
2. Electrical/Electronic Interlocking Systems with centralized
operation of points and signals have been provided at 6,665 stations
up to 28.02.2026 to reduce accidents due to human failure.
3. Interlocking of Level Crossing (LC) Gates has been provided at
10,153 Level Crossing Gates up to 28.02.2026 for enhancing safety
at LC Gates.
4. Complete Track Circuiting of stations to enhance safety by
verification of track occupancy by electrical means has been
provided at 6,669 stations up to 28.02.2026.
§5. Detailed instructions on issues related with safety of Signaling, e.g.
mandatory correspondence check, alteration work protocol,
preparation of completion drawing, etc. have been issued.
6. System of disconnection and reconnection for S&T equipment as per
protocol has been re-emphasized.
7. All locomotives are equipped with Vigilance Control Devices (VCD)
to improve alertness of Loco Pilots.
8. Retro-reflective sigma boards are provided on the mast which is
located two OHE masts prior to the signals in electrified territories
to alert the crew about the signal ahead when visibility is low due to
foggy weather.
9. A GPS based Fog Safety Device (FSD) is provided to loco pilots in fog
affected areas which enables loco pilots to know the distance of the
approaching landmarks like signals, level crossing gates, etc.
10. Modern track structure consisting of 60kg, 90 Ultimate Tensile
Strength (UTS) rails, Prestressed Concrete Sleeper (PSC)
Normal/Wide base sleepers with elastic fastening, fan shaped layout
turnout on PSC sleepers, Steel Channel/H-beam Sleepers on girder
bridges is used while carrying out primary track renewals.
11. Mechanisation of track laying activity through use of track machines
like PQRS, TRT, T-28 etc. to reduce human errors.
12. Maximizing supply of 260m long rail panels for increasing progress
of rail renewal and avoiding welding of joints, thereby improving
safety.
13. Ultrasonic Flaw Detection (USFD) testing of rails to detect flaws and
timely removal of defective rails.
14. Laying of longer rails, minimizing the use of Alumino Thermic
Welding and adoption of better welding technology for rails i.e.,
Flash Butt Welding.
§15. Monitoring of track geometry by OMS (Oscillation Monitoring
System) and TRC (Track Recording Cars).
16. Patrolling of railway tracks to look out for weld/rail fractures.
17. The use of Thick Web Switches and Weldable CMS Crossing in
turnout renewal works.
18. Inspections at regular intervals are carried out to monitor and
educate staff for observance of safe practices.
19. Web based online monitoring system of track assets viz. Track
database and decision support system has been adopted to decide
rationalized maintenance requirement and optimize inputs.
20. Detailed instructions on issues related with safety of Track, e.g.
integrated block, corridor block, worksite safety, monsoon
precautions, etc. have been issued.
21. Preventive maintenance of railway assets (Coaches & Wagons) is
undertaken to ensure safe train operations.
22. Replacement of conventional ICF design coaches with LHB design
coaches is being done.
23. All unmanned level crossings (UMLCs) on Broad Gauge (BG) route
have been eliminated by January 2019.
24. Safety of Railway Bridges is ensured through regular inspection of
Bridges. The requirement of repair/rehabilitation of Bridges is taken
up based upon the conditions assessed during these inspections.
25. Indian Railways has displayed Statutory “Fire Notices” for
widespread passenger information in all coaches. Fire posters are
provided in every coach so as to educate and alert passengers
regarding various Do’s and Don’ts to prevent fire. These include
messages regarding not carrying any inflammable material,
explosives, prohibition of smoking inside the coaches, penalties etc.
§26. Production Units are providing Fire detection and suppression
system in newly manufactured Power Cars and Pantry Cars, Fire and
Smoke detection system in newly manufactured coaches.
Progressive fitment of the same in existing coaches is also
underway by Zonal Railways in a phased manner.
27. Regular counselling and training of staff is undertaken.
28. Concept of Rolling Block introduced in Indian Railways (Open Lines)
General Rules vide Gazette notification dated 30.11.2023, wherein
work of integrated maintenance/ repair/replacement of assets is
planned up to 52 weeks in advance on rolling basis and executed as
per plan.
The details of the Safety related works related to better maintenance
practices, Technological improvements, better infrastructure and
rolling stock etc. undertaken by Railways are tabulated below:-
2004-05 to 2014-15 to 2014-25 Vs.
S.N. Item
2013-14 2024-25 2004-14
Technological Improvements
1. Use of high-quality 57,450 Km 1.43 Lakh More than 2
rails (60 Kg) (Km) Km times
2. Longer Rail Panels 9,917 Km 77,522 Km Nearly 8 times
(260m) (Km)
3. Electronic 837 3,691 More than 4
Interlocking Stations Stations times
(Stations)
4. Fog Pass Safety As on As on 288 times
Devices (Nos.) 31.03.14: 31.03.25:
90 Nos. 25,939 Nos.
5. Thick Web Nil 28,301 Nos.
Switches (Nos.)
§Better Maintenance Practices
1. Primary Rail 32,260 Km 49,941 Km 1.5 times
Renewal(Track
Km)
2. USFD (Ultra Sonic 79.43 Lakh 2 Crore More than 2
Flaw detection) times
Testing of Welds
(Nos.)
3. Weld failures In 2013-14: In 2024-25: 90 %
(Nos.) 3699 Nos. 370 Nos. reduction
4. Rail fractures In 2013-14: In 2024-25: More than 88%
(Nos.) 2548 Nos. 289 Nos. reduction
Better Infrastructure and Rolling Stock
1. New Track KM 14,985 Km 34,428 Km More than 2
added (Track Km) times
2. Flyovers (RoBs)/ 4,148 Nos. 13,808 Nos. More than 3
Underpasses times
(RUBs) (Nos.)
3. Unmanned Level As on As on Removed
crossings 31.03.14: 31.03.24:
(Nos.) on BG 8,948 Nil (All
eliminated
by
31.01.19)
4. Manufacture of 2,337 Nos. 42,677 More than 18
LHB Coaches times
(Nos.)
Implementation of Kavach:
1. Kavach is an indigenously developed Automatic Train Protection
(ATP) system. Kavach is a highly technology intensive system,
which requires safety certification of highest order (SIL-4).
2. Kavach aids the Loco Pilot in running of trains within specified
speed limits by automatic application of brakes in case Loco Pilot
§fails to do so and also helps the trains to run safely during
inclement weather.
3. The first field trials on the passenger trains were started in
February 2016. Based on the experience gained and Independent
Safety Assessment of the system by Independent Safety Assessor
(ISA), three firms were approved in 2018-19, for supply of Kavach
Ver 3.2.
4. Kavach was adopted as National ATP system in July, 2020.
5. Implementation of Kavach System involves following Key Activities:
a. Installation of Station Kavach at each and every station, block
section.
b. Installation of RFID Tags throughout the track length.
c. Installation of telecom Towers throughout the section.
d. Laying of Optical Fibre Cable along the track.
e. Provision of Loco Kavach on each and every Locomotive running
on Indian Railways.
6. Based on deployment of Kavach version 3.2 on 1465 RKm on South
Central Railway and experience gained, further improvements were
made. Finally, Kavach specification version 4.0 was approved by
RDSO on 16.07.2024.
7. Kavach version 4.0 covers all the major features required for the
diverse railway network. This is a significant milestone in safety for
Indian Railways. Within a short period, IR has developed, tested and
started deploying Automatic Train Protection System.
8. Major improvement in Version 4.0 includes increased Location
Accuracy, Improved Information of Signal Aspects in bigger yards,
§Station to Station Kavach interface on OFC and Direct Interface to
existing Electronic Interlocking System. With these improvements,
Kavach Ver.4.0. is planned for large scale deployment over Indian
Railways.
9. After extensive and elaborate trials, Kavach Version 4.0 has been
successfully commissioned on 1452 Route Kilometres, covering the
high density Delhi- Mumbai and Delhi-Howrah routes as below:
SN Section Progress (Route
Km)
(1) Delhi-Mumbai route:
i Junction cabin – Palwal – Mathura – 667
Nagda section
ii Vadodara - Ahmedabad section 96
iii Vadodara - Virar section 336
(2) Delhi – Howrah route:
i Gaya Sarmatanr section 93
ii Chota Ambana - Bardhaman – Howrah 260
section
10. Further, track side Kavach implementation work has been taken
up on 24,427 RKM covering all GQ, GD, HDN and identified sections
of Indian Railways. These sections also pass through the State of
Tamil Nadu.
11. Progress of key items of Kavach on High density routes including
Delhi– Mumbai & Delhi– Howrah corridors as on 28.02.2026 is as
under:
S N Item Progress
i Laying of Optical Fibre Cable 8570 Km
§ii Installation of Telecom Towers 1100 nos
iii Station Data Centre 767 station
iv Installation of Track side 6776 RKm
equipment
v Provision of Kavach in Loco 4154 nos
12. In addition, work for installation of Kavach in 8979 Locomotives
and 1200 EMU/ MEMU has been taken up.
13. Specialized training programmes on Kavach are being conducted
at centralized training institutes of Indian Railways to impart
training to all concerned officials. By now more than 55,000
technicians, operators and engineers have been trained on Kavach
technology. This includes about 47,500 Loco Pilots & Assistant Loco
Pilots. Courses have been designed in collaboration with IRISET.
*****
§