GOVERNMENT OF INDIA
MINISTRY OF PORTS, SHIPPING AND WATERWAYS
LOK SABHA
UNSTARRED QUESTION NO. 940
ANSWERED ON 24.07.2026
SAGARMALA PROGRAMME AND PORT MODERNISATION
940. DR. VINOD KUMAR BIND:
SHRI ALOK SHARMA:
SHRI RAJESH NARANBHAI CHUDASAMA:
DR. BHOLA SINGH:
SHRI VIJAY KUMAR DUBEY:
SHRI PRATAP CHANDRA SARANGI:
SHRI VISHWESHWAR HEGDE KAGERI:
SHRI KRISHNA PRASAD TENNETI:
SHRI NABA CHARAN MAJHI:
SHRI ARUN GOVIL:
SHRI AVIMANYU SETHI:
DR. SANJAY JAISWAL:
SHRI RAVINDRA SHUKLA ALIAS RAVI KISHAN:
Will the Minister of PORTS, SHIPPING AND WATERWAYS be pleased to state:
प(cid:419)न, पोत प(cid:464)रवहन और जलमाग (cid:91) म(cid:287)ं ी
(a) the progress made under the Sagarmala Programme in terms of port modernisation,
new port development and coastal economic zone projects;
(b) the steps taken to enhance port capacity, efficiency, and reduce turnaround time at
major and non-major ports;
(c) whether the Government has undertaken any initiatives to improve last-mile
connectivity through road, rail and inland waterways and if so, the details thereof; and
(d) whether any projects relating to port-led development, fishing harbours, coastal
infrastructure, coastal community development or last-mile connectivity have been
sanctioned or implemented under the Sagarmala programme in Andhra Pradesh and if
so, the details thereof indicating the funds allocated and the present status of
implementation, district-wise including Bapatla district?
ANSWER
MINISTER OF PORTS, SHIPPING AND WATERWAYS
(SHRI SARBANANDA SONOWAL)
(a) Sagarmala scheme is a central sector scheme of Ministry of Ports, Shipping and
Waterways (MoPSW) with the target to promote port-led development in the country.
Under this scheme, MoPSW provides financial assistance for the projects under 5 pillarsnamely, port modernization, port connectivity, port-led industrialization, coastal
community development, and coastal shipping & inland water transport. The pillar wise
progress of the projects funded under Sagarmala scheme is available at Annexure-I.
(b) Government has taken several measures to enhance port capacity, improve
operational efficiency, and reduce vessel turnaround time at major ports. Infrastructure
development and capacity augmentation is a continuous process and includes
construction of new berths and terminals, mechanization, modernization and optimization
of existing berths and terminals, capital dredging to deepen drafts for accommodating
larger vessels, development of road and rail connectivity, and creation of supporting
infrastructure such as parking plazas. Further, port processes have been streamlined with
the implementation of One Nation One Port Process (ONOP) to improve operational
efficiency and reduce vessel turnaround time. As a result of these initiatives, the cargo
handling capacity of the Major and Other than Major Ports (OTMP) has increased to 2,818
Million Tonnes Per Annum (MTPA) as on March 2026 from ~1,400 MTPA in 2013-14.
(c) One of the objectives of Sagarmala programme is better port connectivity, efficient
cargo movement between ports and their respective hinterland to minimize overall
logistics cost. Sagarmala programme has a dedicated pillar of port connectivity which
focuses on the last mile and immediate hinterland connectivity of the ports via road, rail
and inland waterways. Further, Department for Promotion of Industry and Internal Trade
(DPIIT) has undertaken a comprehensive assessment of port connectivity and prepared
a Comprehensive Port Connectivity Plan (CPCP) in 2022 by reviewing connectivity of the
operational ports and identified the ports which needed improvement of road and/ or rail
connectivity with nearby economic hubs.
Subsequently, MoPSW in consultation with Ministry of Road, Transport and
Highways and Ministry of Railways has identified a total of 294 rail and road connectivity
projects, out of which, 84 projects (63 Rail and 21 Road) have been completed, 66
projects (27 Rail and 39 Road) are under implementation, and a total of 144 projects (42
Rail and 102 Road) are under planning stage. The connectivity projects within the port
limits are taken up by the Port Authorities and beyond the port limits are taken up by
Ministries like MoR, MoRTH or State Governments.
As regard to inland waterway connectivity projects, details of projects completed
by Inland Waterways Authority of India (IWAI) on National Waterways (NW) are as under:
i. 3 Multi Modal Terminals (MMTs) and 01 intermodal terminal on NW 1
ii. 1 MMT and 3 IWT terminals on NW 2
iii. 9 IWT terminals on NW 3;
iv. 02 Roll-on/Roll-off (Ro-Ro) terminals in Ernakulam
v. 01 Ro-Ro terminal on NW 4(d) The MoPSW has sanctioned financial assistance of ₹ 272 crore to 9 projects worth
₹ 1,286 crore under Sagarmala scheme in the state of Andhra Pradesh and the details of
these projects are available at Annexure-II. These projects are related to Ro-Pax and
passenger jetties, fishing harbours, port modernization and skill development.Annexure I
Details of Completed and under Implementation projects pillar wise under Sagarmala
Scheme:
Pillars Completed projectsUnder implementation projects
Number Cost (₹ Cr) Number Cost (₹ Cr)
Coastal Shipping and IWT 25 1178.5 17 1167.7
Coastal Community Development 19 1912.6 28 3008.4
Port Modernization 18 870.2 6 160.8
Port Connectivity 17 1413.2 3 201.3
Grand Total 79 5374.5 54 4538.2Annexure - II
List of Sagarmala-funded Projects in Andhra Pradesh:
Sl. Name of Proj Implementing Status District Project MoPS
N ect Agency cos W sha
o. t re
(₹ Cr) (₹ Cr)
1 Construction of Visakhapatna Completed Visakhapatna 43 30
coastal Berth m Port Authorit m
at Visakhapatn y (VPA)
am port
2 Construction of National HighwCompleted Visakhapatna 60 23.17
grade separat ays Authority o m
or from H-7 aref India (NHAI)
a to Port conne
ctivity Road by
passing Conve
nt Junction - Vi
sakhapatnam
Port
3 2 to 4 laning of NHAI Completed Visakhapatna 77.00 20.00
port road conn m
ectivity to NH –
5 -Phase II
4 Centre of ExcelIndian RegisterCompleted Visakhapatna 574.00 36.76
lence in Mariti of Shipping (I m
me and Shipbu RS)
ilding -CEMS -
AP-18 out of 2
4 Labs in Andh
ra Pradesh
5 Coastal District Ministry of Rur Completed Multiple district 0.14 0.14
s Skill Develop al Developmen s
ment Program t
- Phase I -And (DDU-GKY)
hra Pradesh
6 Development o Andhra Prades Completed Nellore 288 69.14
f Fishing Harboh Maritime Infr
ur in Juvvaladi astructure Dev
nne in SPSR N elopment Corp
ellore District, oration (APMID
Andhra Prades CL)
h7 Improvement o Andhra Prades Completed Kakinada 85.83 36.67
f Kakinada Anc h Maritime Boa
horage Ports inrd
frastructure in
East Godavari
district, Andhra
Pradesh
8 Modernisation VPA Under Implem Visakhapatna 178.51 50.00
of Visakhapatn entation m
am Fishing Har
bour
9 Coastal District Ministry of Rur Under Implem Multiple district 5.98 5.98
s Skill Develop al Developmen entation s
ment Program t
- Phase 2 -And (DDU-GKY)
hra Pradesh
*****