GOVERNMENT OF INDIA
MINISTRY OF COAL
RAJYA SABHA
UNSTARRED QUESTION NO. 2698
ANSWERED ON 16.03.2026
SHORTAGE OF COAL AND ITS SUPPLY TO TAMIL NADU
2698 SHRI R. GIRIRAJAN:
Will the Minister of Coal be pleased to state:
(a) whether the Central Government has received any request from Government of Tamil Nadu
regarding the shortage of coal supply and its timely delivery from PSUs like Coal India Ltd,
Mahanadi Coalfields Ltd and if so, the details thereof and Government's action in this regard;
(b) the details of the quantity and value (in INR) of coal supplied to various industries both
public sector and private sectors in the State of Tamil Nadu; and
(c) the details of the quantity and value (in INR) of coal supplied to thermal power stations in
the State during the last five years, year-wise, power plant-wise?
ANSWER
MINISTER OF STATE FOR COAL AND MINES
(SHRI SATISH CHANDRA DUBEY)
(a): Supply of coal to the power plants including the power plants of Tamil Nadu is a continuous
process. Requests are received from various States, including Tamil Nadu, regarding coal
supplies. Coal supply is continuously monitored by the coal companies, power companies and
by an Inter-Ministerial Sub-Group comprising of representatives from Ministry of Power,
Ministry of Coal, Ministry of Railways, Central Electricity Authority (CEA), Coal India
Limited (CIL) and Singareni Collieries Company Limited (SCCL) which meets regularly to
take various operational decisions to enhance supply of coal to Thermal Power Plants. The
meetings of the Sub-Group Committee are attended by the representatives of the power plants.
Based on the requirement and the coal stock position, allocation of rakes is recommended by
the Sub-Group. The Sub-Group closely monitors rake allocation and movement to maintain
supply continuity. Logistical interventions by coal companies and the Sub-Group, undertaken
in collaboration with Railways, ensure allocation of sufficient railway rakes to the power plants,
as well as faster coal movement from coal mines to its power plants, thereby reducing transit
delays & ensuring steady plant operations.
Besides, an Inter-Ministerial Committee (IMC) has also been constituted comprising of
Chairman, Railway Board; Secretary, Ministry of Coal; Secretary, Ministry of Environment,
Forest and Climate Change and Secretary, Ministry of Power; to monitor augmentation of coal
supply and power generation capacity. Secretary, Ministry of New and Renewable Energy and
Chairperson, CEA are co-opted as Special Invitees as and when required by the IMC.
(b): The details of the coal quantity [in Million Tonnes (MT)] and value (in ₹ Crore) of coal
supplied by CIL and SCCL to the industries both Public sector and Private sector in the State
of Tamil Nadu for the year 2021-22, 2022-23, 2023-24, 2024-25 & 2025-26 (till February,
2026) is as under:
1Provisional
FY 2025-26
FY 2021-22 FY 2022-23 FY 2023-24 FY 2024-25 (Till February,
2026)
Coal
Bill Bill Bill Bill Bill
Company Bill Bill Bill Bill
Quantity Quantity Quantity Quantity Quantity /
Value / Value / Value / Value / Bill Value /
/ Coal / Coal / Coal / Coal Coal
Value Value Value Value Value (₹ Cr)
Supplied Supplied Supplied Supplied Supplied
(₹ Cr) (₹ Cr) (₹ Cr) (₹ Cr)
(in MT) (in MT) (in MT) (in MT) (in MT)
CIL
22.599 4169.89 26.688 4692.46 25.551 4458.25 25.527 4727.92 21.045 3651.88
SCCL 3.45 1089.75 1.98 858.07 2.798 1477.21 574.61
2.851 1832.45 0.806
(c): The year-wise, power plant-wise details of the coal quantity (in MT) supplied to the thermal
power plants in the State of Tamil Nadu and values in (in ₹ Crore) for the year 2021-22, 2022-
23, 2023-24, 2024-25 & 2025-26 (till February, 2026) is as under:
Coal Supplies by CIL
(Provisional)
FY 2025-26
FY 2021-22 FY 2022-23 FY 2023-24
FY 2024-25 (Till February,
2026)
Sl. Name of the Bill Bill Bill Bill Bill Bill Bill
Bill Bill Bill
No. Power Plant Quantity Quantity Quantity Quantity Value / Quantity Value /
Value / Value / Value /
/ Coal / Coal / Coal / Coal Value / Coal Value
Value Value Value
Supplied Supplied Supplied Supplied in (₹ Supplied in (₹
(₹ Cr) (₹ Cr) (₹ Cr)
(in MT) (in MT) (in MT) (in MT) Cr) (in MT) Cr)
1
TANGEDCO 14.936 2524.63 17.923 3075.05 19.072 3297.93 18.927 3304.45 14.386 2336.10
NLC Tamil
2
Nadu 1.448 361.91 2.017 354.50 1.954 342.02 0.038 5.74 0.00 0.27
(NTPL)
3 NTECL,
5.963 1220.65 6.533 1204.54 4.337 782.38 6.380 1382.28 5.605 1137.00
Vallur
Moxie Power
4
Generation 0.00 0.00 0.00 0.00 0.00 0.00 0.066 11.92 0.658 109.47
Limited
OPG Power
5
Generation 0.248 61.58 0.112 23.03 0.188 35.92 0.116 23.53 0.396 69.04
Pvt. Limited
Coastal
6 Energen
0.004 1.12 0.075 23.98 0.00 0.00 0.00 0.00 0.00 0.00
Private
Limited
7. SEPC Power
0.00 0.00 0.028 11.36 0.00 0.00 0.00 0.00 0.00 0.00
Pvt. Limited
2Coal Supplies by SCCL
FY 2025-26
FY 2021-22 FY 2022-23 FY 2023-24
FY 2024-25
(Till February,
2026)
Sl. Name of the Bill Bill Bill Bill Bill Bill Bill Bill Bill
Bill
No. Power Plant Quantity Value Quantity Value Quantity Value Quantity Value / Quantity
Value /
/ Coal / / Coal / / Coal / / Coal Value / Coal
Value in
Supplied Value Supplied Value Supplied Value Supplied in (₹ Supplied
(₹ Cr)
(in MT) (₹ Cr) (in MT) (₹ Cr) (in MT) (₹ Cr) (in MT) Cr) (in MT)
Mettur TPS I
1 2.57 766.24 1.40 568.37 1.84 954.06 1.83 1125.84 - -
& II
2 NTECL 0.56 162.22 0.34 140.23 0.75 387.08 0.34 253.48 - -
3 NCTPS - - - - - - 0.54 354.50 0.60 419.65
UDANGUDI
4 - - - - - - - - 0.07 44.30
TPS
3