GOVERNMENT OF INDIA
MINISTRY OF RURAL DEVELOPMENT
DEPARTMENT OF RURAL DEVELOPMENT
LOK SABHA
UNSTARRED QUESTION NO. 2733
ANSWERED ON 04/08/2026
SPARSH UNDER PMGSY
2733. Smt. Dhanorkar Pratibha Suresh:
Will the Minister of RURAL DEVELOPMENT be pleased to state:
(a) whether 46,200 houses (especially in Chandrapur, Ballarpur and
Mul talukas) out of 57,466 houses sanctioned under Pradhan
Mantri Awas Yojana (Gramin), (PMAY-G) Phase-II in Chandrapur
district are still under construction, if so, the reasons therefor;
(b) whether 28 thousand beneficiaries of the district are deprived
of the second installment due to lack of funds and are facing
crisis due to demolition of their kutcha houses, if so, the details
thereof;
(c) whether these pending installments will be treated as a special
case and released as soon as possible, if so, the details thereof;
(d) whether the new online system 'SPARSH' has been holding up
installments of the poor due to technical glitches like server
down, photo not being uploaded and if so, the plans to
streamline the process or provide an option for offline
verification; and
(e) whether the Government proposes to increase the central
subsidy for construction of houses keeping in view the rising
prices of building materials, if so, the details thereof?
ANSWER
MINISTER OF STATE IN THE MINISTRY OF RURAL DEVELOPMENT
(DR. CHANDRA SEKHAR PEMMASANI)
(a) to (c): Under the Pradhan Mantri Awaas Yojana-Gramin (PMAY-
G), the Ministry allocates targets to the State as a whole and the
District/Block/Gram Panchayat-wise targets are allocated/
distributed by State Governments/Union Territories as per the
provisions of the scheme. The State Government of Maharashtra has
fixed a target of 58,204 houses in the Chandrapur district during the
phase-II of the scheme i.e. FY 2024-25 onwards. As of 30.07.2026, a
Page 1 of 2total of 57,436 houses have been sanctioned in Chandrapur district,
56,266 beneficiaries have received first installment of assistance,
36,858 beneficiaries have received second installment of assistance
and 18,019 houses are already complete.
The State Government of Maharashtra has conveyed that after
the Geo-Tagging is completed by the field officials, the installment is
processed immediately and all Fund Transfer Orders (FTOs) are
processed by the field machinery within time. In addition, the State
Government has conveyed that the initial delay in construction of
rural houses was primarily due to shortage of rural masons and
technical issues in the newly introduced SNA SPARSH system.
(d): The technical issues in the implementation of the SNA SPARSH
system have since been addressed and the system is functioning
normally. The Ministry continuously monitors the performance of the
SNA SPARSH platform and undertakes necessary technical
improvements from time to time to ensure smooth processing of
instalments.
(e): Under the Pradhan Mantri Awaas Yojana–Gramin (PMAY-G),
financial assistance of ₹1.20 lakh per house is provided in plain areas
and ₹1.30 lakh per house in hilly States, including the Union
Territories of Jammu & Kashmir and Ladakh. The Government has
approved the continuation of PMAY-G till March, 2029 as per the
existing unit assistance for construction of 2 crore more houses.
*****