Executive Summary:
The Ministry of Railways addresses questions regarding the status of railway projects in the Bhagalpur Lok Sabha constituency. It outlines the progress of station redevelopments under the Amrit Bharat Station Scheme, the status of Road Over Bridge/Road Under Bridge (ROB/RUB) projects, and other infrastructural projects in Bihar. The document highlights challenges affecting project timelines and emphasizes continuous monitoring through the Indian Railway Project Sanction and Management (IRPSM) portal.
Key Points / Main Content:
Amrit Bharat Station Scheme:
* 98 stations in Bihar, including Bhagalpur, Naugachia, Shivanarayanpur, Sabaur, Pirpainti, and Kahalgaon, are identified for development.
* Phase I work is completed at Pirpainti (station building elevation, portico, waiting hall, toilets, signage, and divyangjan facilities). Construction of a foot over bridge has been taken up.
* At Naugachia, the works for foundation of platform shelter, earthwork in circulating area have been completed and the works of new station building, construction of platform shelter and new foot over bridge have been taken up.
* At Shivanarayanpur, the works of station elevation, concourse area, waiting hall, coach/train indication boards, and signage have been completed and works of circulating area, Pay Use Toilet, construction of new foot over bridge have been taken up.
* At Sabaur, the works of OFC building, improvement of waiting halls have been completed and the works of station building elevation including portico, circulating area, concourse area, improvement to 2nd class waiting hall, provision of coach and train indication board, Visual display boards, signages, construction of new foot over bridge have been taken up.
* At Kahalgaon, the works of improvement to waiting hall, construction of new pay use toilet, divyangjan facilities and provision of signages have been completed and the works of improvement to station building elevation including portico, circulating area, concourse area, installation of Visual display boards and construction of new foot over bridge have been taken up.
* Master planning for Bhagalpur station development is underway.
Road Over Bridges/Road Under Bridges (ROBs/RUBs):
* Five ROBs/RUBs are sanctioned in Bhagalpur Constituency.
* Locations: LC No. 1A on Bhagalpur-Jamalpur section, LC No. 6 on Bhagalpur-Pirpainti section, LC No. 9 on Bhagalpur-Jamalpur section, LC No. 11spl on Katihar-Barauni section, and LC No. 5 on Sahibganj-Bhagalpur section.
* Work status varies from preparation of General Arrangement Drawing (GAD) and Detailed Estimate to work having been taken up.
Railway Projects in Bihar:
* 52 projects (31 New Lines, 01 Gauge Conversions and 20 Doubling) are sanctioned, with 1,014 km commissioned and Rs. 29,353 crore spent up to March 2025.
* Projects in the vicinity of Bhagalpur include the Vikramshila-Katareah, Sultanganj-Katuria, and Pirpainti-Jasidih New Lines.
Train Services:
* 104 train services, including 2 Vande Bharat services, serve Bhagalpur, including the Howrah-Bhagalpur Vande Bharat Express (introduced 15.09.2024).
New Bhagalpur Station:
* DPR prepared by Eastern Railway with a project cost of Rs. 310.45 crore.
General Information:
* Development/upgradation of stations is funded under Plan Head-53 Customer Amenities.
* East Central Railway and Eastern Railways have a total allocation of ₹942 crores for FY 2025-26 under Plan Head 53.
* Projects are monitored through the Indian Railway Project Sanction and Management (IRPSM) portal.
Impact Analysis:
Passengers:
* Impact: Improved station amenities, better connectivity, and enhanced travel experience.
* Action Required: Utilize the upgraded facilities and services.
Bhagalpur Constituency Residents:
* Impact: Enhanced rail infrastructure, improved connectivity, and potential socio-economic benefits.
* Action Required: Stay informed about project progress and potential disruptions.
Ministry of Railways:
* Impact: Responsible for overseeing project execution, managing funds, and addressing challenges.
* Action Required: Ensure timely project completion, monitor progress via IRPSM, and coordinate with stakeholders.
Zonal Railways (East Central Railway, Northeast Frontier Railway, Eastern Railway, North Eastern Railway):
* Impact: Responsible for project execution within their respective zones.
* Action Required: Execute projects according to sanctioned plans, address challenges, and coordinate with relevant authorities for clearances and approvals.
State Government of Bihar:
* Impact: Required to support projects through land acquisition, forestry clearances, and deposition of state share in cost-sharing projects.
* Action Required: Expedite land acquisition, provide necessary clearances, and ensure timely deposition of state share.
Key Entities Referenced
Bhagalpur Lok Sabha constituency: A parliamentary constituency where railway projects are being implemented or proposed.
Amrit Bharat Station Scheme: A scheme by the Ministry of Railways for the redevelopment of railway stations, with 1337 stations identified and 98 in Bihar including Bhagalpur and nearby stations.
Naugachia: A railway station in Bihar, being developed under the Amrit Bharat Station Scheme.
Shivanarayanpur: A railway station in Bihar, being developed under the Amrit Bharat Station Scheme.
Sabaur: A railway station in Bihar, being developed under the Amrit Bharat Station Scheme.
Pirpainti: A railway station in Bihar, being developed under the Amrit Bharat Station Scheme.
Kahalgaon: A railway station in Bihar, being developed under the Amrit Bharat Station Scheme.
Bihar: A state in India where multiple railway projects are underway, including station redevelopments and new lines.
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 538
TO BE ANSWERED ON 23.07.2025
STATUS OF RAILWAY PROJECTS IN BHAGALPUR
†538. SHRI AJAY KUMAR MANDAL:
Will the Minister of RAILWAYS be pleased to state:
(a) the details of the major railway projects (such as station
redevelopment, new line, track doubling, bridge, Vande Bharat train
facility) currently being implemented or proposed in Bhagalpur Lok
Sabha constituency at present;
(b) the details of financial approval, amount sanctioned, current status
(such as DPR prepared, land acquired, under construction or
completed) and likely timeline of each project;
(c) the details of the updated status of Navgachhiya, Shivnarayanpur,
Sabour, Pirpainti and Kahalgaon station under Amrit Bharat Yojana
along with the amount spent on it;
(d) whether a new terminal station is proposed to be constructed at
Bhagalpur and if so, the details along with the cost, location (e.g.
Jagdishpur) and present status of construction thereof; and
(e) whether any special committee, report or review system has been
framed at Railway Board/DRM level for monitoring supervision of the
projects and if so, the details thereof?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e): Ministry of Railways has launched Amrit Bharat Station
Scheme for redevelopment of stations. So far, 1337 stations have been
identified for development under Amrit Bharat Station Scheme.
...2/--2-
Presently Phase-I work of 105 stations have been completed and
commissioned and works have been taken up at 1110 stations.
Further, 98 stations located in state of Bihar including Bhagalpur,
Naugachia, Shivanarayanpur, Sabaur, Pirpainti and Kahalgaon railway
stations have been identified for development under Amrit Bharat
Station Scheme.
The progress at some of these stations is as given below:
At Pirpainti, phase-I work i.e. improvement to station building elevation,
portico, concourse area, circulating area, improvement of waiting hall,
construction of new pay & use toilet, signages and divyangjan facilities
have been completed. The work of construction of foot over bridge has
been taken up.
At Naugachia, the works for foundation of platform shelter, earthwork
in circulating area have been completed and the works of new station
building, construction of platform shelter and new foot over bridge have
been taken up.
At Shivanarayanpur, the works of station elevation, concourse area,
improvement to waiting hall, provision of coach and train indication
boards, Visual display boards, signages have been completed and
works of circulating area, Pay & Use Toilet, construction of new foot
over bridge have been taken up.
At Sabaur, the works of OFC building, improvement of waiting halls
have been completed and the works of station building elevation
including portico, circulating area, concourse area, improvement to 2nd
class waiting hall, provision of coach and train indication board, Visual
display boards, signages, construction of new foot over bridge have
been taken up.
…3/--3-
At Kahalgaon, the works of improvement to waiting hall, construction
of new pay & use toilet, divyangjan facilities and provision of signages
have been completed and the works of improvement to station building
elevation including portico, circulating area, concourse area,
installation of Visual display boards and construction of new foot over
bridge have been taken up.
Master planning for development of Bhagalpur railway station under
Amrit Bharat Station Scheme has been taken up. This is an iterative
process requiring optimization and the time frame for such optimization
cannot be indicated at this stage.
The Amrit Bharat Station scheme envisages development of stations on
a continuous basis with a long-term approach. It involves preparation of
master plans and their implementation in phases to improve the
amenities at the stations like improvement of station access,
circulating areas, waiting halls, toilets, lift/escalators as necessary,
platform surfacing and cover over platform, cleanliness, free Wi-Fi,
kiosks for local products through schemes like ‘One Station One
Product’, better passenger information systems, executive lounges,
nominated spaces for business meetings, landscaping, etc. keeping in
view the necessity at each station.
The scheme also envisages improvement of building, integrating the
station with both sides of the city, multimodal integration, amenities for
Divyangjans, sustainable and environment friendly solutions, provision
of ballastless tracks, etc. as per necessity, phasing and feasibility and
creation of city centre at the station in the long term.
Development/upgradation of stations on Indian Railways is a
continuous and ongoing process and works in this regard are
undertaken as per requirement, subject to inter-se priority and
availability of funds. The priority for development/upgradation of
stations is accorded to higher category of station over lower category
of station while sanctioning and executing the works.
..4/--4-
Development / upgradation of stations including under Amrit Bharat
Station Scheme is generally funded under Plan Head-53 ‘Customer
Amenities’. The details of allocation under Plan Head-53 are maintained
Zonal Railway-wise and not work-wise or station-wise or State-wise.
Bhagalpur Parliamentary Constituency falls under the jurisdiction of
East Central Railway and Eastern Railways for which a total allocation
of ₹942 crores (Budget Estimate) has been made for the financial year
2025-26 under Plan Head-53.
Further, development/redevelopment/upgradation of Railway Stations is
complex in nature involving safety of passengers & trains and requires
various statutory clearances such as fire clearance, heritage, tree
cutting, airport clearance etc. The progress also gets affected due to
brown field related challenges such as shifting of utilities, (involving
water/sewage lines, optical fiber cables, gas pipe lines, power/signal
cables etc.,) infringements, operation of trains without hindering
passenger movement, speed restrictions due to works carried out in
close proximity of high voltage power lines etc. and these factors
affect the completion time. Therefore, no time frame can be indicated
at this stage.
Railway infrastructural Projects in the State of Bihar are covered by
East Central Railway (ECR), Northeast Frontier Railway (NFR), Eastern
Railway (ER), North Eastern Railway (NER) Zone of Indian Railways.
Zonal Railway wise details of Railway projects are made available in
public domain on Indian Railway’s website.
Sanctioning and execution of works of Road Over Bridges/ Road Under
Bridges (ROBs/RUBs) in lieu of LCs is a continuous and ongoing process
on Indian Railways. Such works are prioritized and taken up on the
basis of its impact on safety and mobility in train operations and impact
on road users.
..5/--5-
No. of ROBs/RUBs constructed on Indian Railways during the period
2004-14 vis-a-vis 2014-26 (June’25) is as under:
Period ROBs/RUBs constructed
2004-14 4148
2014-26 (upto June’25) 13426 (including 558 Nos. in the
state of Bihar)
As on dt. 01.04.2025, 4402 Nos. ROBs/ RUBs are sanctioned at the cost
of Rs. 1,00,860 crore on Indian Railways including 218 Nos. Road Over
Bridge (ROB)/Road Under Bridge (RUB) at the cost of Rs. 6014 crore in
the State of Bihar, which are at various stages of planning and
execution. Out of these, 05 Nos. ROBs/RUBs are sanctioned in
Bhagalpur Constituency. Details are as under:-
Sanctioned RUBs/ROBs
S.N. Location ROB/ Cost Remarks
RUB/ (in
FOB Rs.
Cr.)
1 LC No. 1/A on ROB 90 The work of ROB has been
Bhagalpur- sanctioned. The works of
Jamalpur preparation of GAD and
section Detailed Estimate have been
2 LC No. 6 on ROB 82 taken up.
Bhagalpur-
Pirpainti
section
3 LC No. 9 on ROB 81
Bhagalpur-
Jamalpur
section
4 LC No. 11/spl ROB 42 The work of ROB has been
on Katihar- sanctioned. The work of
Barauni Railway portion has been
section completed and approach
portion has been taken up
5 LC No. 5 on LHS 6 The work of ROB has been
Sahibganj- sanctioned. GAD has been
Bhaglapur approved. The work has been
section taken up.
..6/--6-
Completion and commissioning of ROB/RUB works depend on various
factors like cooperation of State Governments in giving consent for
closure of LCs, fixing of approach alignment, approval of General
Arrangement Drawing (GAD), land acquisition, removal of
encroachments, shifting of infringing utilities, statutory clearances
from various authorities, law and order situation in the area of
project/work sites, duration of working season in a year for the
particular project/area due to climatic conditions etc. All these factors
affect the completion time of the projects / works.
As on 01.04.2025, 52 projects (31 New Lines, 01 Gauge Conversions
and 20 Doubling), of a total length of 4,663 km, costing Rs.86,107 crore,
falling fully/partly in Bihar, are sanctioned, out of which 1,014 km length
has been commissioned and an expenditure of Rs. 29,353 crore has
been incurred upto March’ 2025 including those falling fully/partly in
Bhagalpur. At present in the vicinity of Bhagalpur some railway projects
namely (i) Vikramshila-Katareah New Line (26 Km) with Bridge over
River Ganga, (ii) Sultanganj-Katuria New Line (77 Km) and (iii) Pirpainti-
Jasidih New Line (97 Km) have been taken up to further improve Rail
connectivity in the area.
At present 104 train service including, 02 Vande Bharat services are
catering to the needs of passengers of Bhagalpur. These services
include the service of 22309/22310 Howrah-Bhagalpur Vande Bharat
Express which has been introduced w.e.f. 15.09.2024. Besides,
introduction of train services, including Vande Bharat Express, is an
ongoing process on Indian Railways subject to traffic justification,
operational feasibility, resource availability etc.
..7/--7-
The DPR of ‘New Bhagalpur station with Coaching Facility’ has been
prepared by Eastern Railway with project cost as Rs. 310.45 crore.
Railway projects are surveyed/sanctioned/executed Zonal Railway wise
and not State-wise as the Railways’ projects may span across State
boundaries. Railway projects are sanctioned on the basis of
remunerativeness, traffic projections, last mile connectivity, missing
links and alternate routes, augmentation of congested/saturated
lines, demands raised by State Governments, Central Ministries,
Members of Parliament, other public representatives, Railway’s own
operational requirement, socio-economic considerations etc. depending
upon throw forward of ongoing projects and overall availability of funds.
Completion of any Railway project/s depends on various factors like
quick land acquisition by State Government, forestry clearance by
officials of forest department, deposition of State share by the State
Government in cost sharing projects, shifting of infringing utilities,
statutory clearances from various authorities, geological and
topographical conditions of area, law and order situation in the area of
project/s site, number of working months in a year for particular project
site due to climatic conditions, etc and all these factors affect the
completion time of the project/s. With above constraints, every effort is
being made to complete these projects at the earliest.
Monitoring of projects is done at various levels including through
dedicated portal of Indian Railways named Indian Railway Project
Sanction and Management (IRPSM). The issues faced by the executing
units are accordingly addressed.
*****