See Full Document Text
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 6188
TO BE ANSWERED ON 01.04.2026
SURVEY FOR NEW RAILWAY LINES IN MAHARASHTRA
†6188. SHRI BHUMARE SANDIPANRAO ASARAM:
DR. SHIVAJI BANDAPPA KALGE:
Will the Minister of RAILWAYS be pleased to state:
(a) whether any survey has been conducted for laying new railway lines,
gauge of old lines and electrification in various parts of the country
particularly in the State of Maharashtra;
(b) if so, the details of the length of railway lines to be laid, gauge
conversion and electrification in various States including Maharashtra,
location-wise; and
(c) the State-wise details for laying new railway lines, gauge conversion
and electrification particularly in Maharashtra during the current
financial year?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (c): Capacity enhancement of railway network has been taken up by
Indian Railways in a big way during last 11 years. The details of
commissioning/laying of new track across Indian Railways is given below:-
New track
Period Average commissioning of new tracks
Commissioned
2009-14 7,599 Km 4.2 Km/day
2014-25 34,428 Km 8.6 Km/day (more than 2 times)
§ Page 1 of 18Projects Sanctioned:
As on 01.04.2025, across Indian Railways, 431 Railway infrastructure
projects including port-connectivity (154 New Line, 33 Gauge Conversion
and 244 Doubling) of total length 35,966 Km, costing approx. 6.75 lakh
crore are sanctioned. The summary is as under:-
Length
Total Length Total Exp upto
No of Commissioned
Category NL/GC/DL Mar'25
Projects till Mar'25
(km) ( in Cr)
(Km)
New Lines 154 16,142 3,036 1,45,318
Gauge
33 4,180 2,997 22,753
Conversion
Doubling /
244 15,644 6,736 1,22,858
Multitracking
Total 431 35,966 12,769 2,90,929
Zone-wise/year-wise details of all Railway projects are made available in
public domain on Indian Railway’s website.
Some of the recently completed projects are as follows:
Length
S.
Name of project (in
No.
Kms)
1 Udhampur- Srinagar- Baramulla new line 272
2 Bhairabi - Sairang New Line 51
3 Deoband - Roorkee New Line 27
4 Churu - Ratangarh Doubling 43
5 Tori-Shivpur 3rd Line 44
6 Araria - Galgalia New Line 110
Page 2 of 18Length
S.
Name of project (in
No.
Kms)
7 Himmatnagar - Khedbrahma Guage Conversion 55
8 Bahraich- Nanpara -Nepalganj Guage Conversion 56
Domingarh- Gorakhpur -Kusumi 3rd Line & Gorakhpur -
9 21
Nakaha Doubling
10 Vijapur - Ambaliyasan Guage Conversion 43
11 Pune- Miraj -Londa Doubling 467
12 Manmad - Jalgaon 3rd Line 160
13 Phephna –Indara- Mau -Shahganj Doubling 150
14 Adraj -Moti -Vijapur Guage Conversion 40
15 Katni -Bina 3rd Line 279
16 Gandhidham- Adipur Quadrupling 21
17 Khatuwas - Narnaul Doubling 24
18 Penukonda- Dharmavaram Doubling 42
During last three years i.e. FY 2022-23, 2023-24, 2024-25 and the current
FY 2025-26, 306 projects (53 New Line, 17 Gauge Conversion and 236
Doubling) of total length 13,968 Km have been sanctioned across Indian
Railways.
Some of the major projects sanctioned are as follows:
Cost
SN Project Name (₹ in
Crore)
1 Chopan – Chunar doubling (102 Km) 1,553
2 Guntur – Bibinagar doubling (239 Km) 3,238
3 Mudkhed – Medchal & Mahbubnagar – Dhone doubling (418 5,655
Km)
Page 3 of 18Cost
SN Project Name (₹ in
Crore)
4 Samakhiali – Gandhidham Quadrupling (53 Km) 1,571
5 Merta City – Ras & Bypass at Merta Road new line (56 Km) 1,038
6 Lumding – Furkating doubling (140 Km) 2,334
7 Ajmer – Chanderiya doubling (178 Km) 1,813
8 Motumari – Vishnupuram with RoR doubling (100 Km) 1,746
9 Bikramshila – Katareah new line with new bridge on river 2,549
ganga (26 Km)
10 Gunupur – Therubali new line (74 Km) 1,326
11 Malkangiri – Pandurangapuram new line (174 Km) 4,109
12 Badampahar – Kendujhargarh new line (82 Km) 2,106
13 Junagarh – Nabarangpur new line (116 Km) 3,274
14 Buramara – Chakulia new line (60 Km) 1,639
15 Jalna – Jalgaon new line (174 Km) 7,105
16 Bangriposi – Gorumahisani new line (86 Km) 2,549
17 Chandil – Anara – Damodar 3rd line (121 Km) 2,170
18 Bargarh Road – Nawapara Road new line (138 Km) 2,926
19 Sardega – Bhalumuda new double line (37 Km) 1,360
20 Varanasi – Pt. Deen Dayal Upadhyaya Multitracking with
2,642
rail cum road bridge on river ganga (15 Km)
21 Jalgaon – Manmad 4th line (160 Km) 2,773
22 Bhusawal – Khandwa 3rd & 4th line (131 Km) 3,514
23 Sambalpur – Jarapada 3rd & 4th line (127 Km) 3,916
24 Jharsuguda – Sason 3rd & 4th line (35 Km) 1,181
25 Gondia – Ballarshah doubling (240 Km) 4,819
26 Kharsia – Naya Raipur – Parmalkasa 5th & 6th line (278 8,741
Km)
27 Wardha – Balharshah Quadrupling (135 Km) 2,381
Page 4 of 18Cost
SN Project Name (₹ in
Crore)
28 Ballari – Chikjajur doubling (185 Km) 3,342
29 Koderma – Barkakana doubling (133 Km) 3,063
30 Itarsi – Nagpur 4th line (297 Km) 5,451
31 Dangoaposi – Jaroli 3rd & 4th line (43 Km) 1,752
32 Secunderabad – Wadi 3rd & 4th line (173 Km) 5,012
33 Furkating – New Tinsukia doubling (194 Km) 3,634
34 Bakhtiyarpur – Rajgir – Tilaiya doubling (104 Km) 2,192
35 Gondia – Dongargarh 4th line (84 Km) 2,223
36 Wardha – Bhusawal 3rd & 4th line (314 Km) 9,197
37 Hosapete – Bellary quadrupling (65 Km) 2,372
38 Kasara – Manmad 3rd & 4th line (131 Km) 10,154
39 Punarakh – Kiul 3rd & 4th line (50 Km) 2,668
40 Gamharia – Chandil 3rd & 4th line (55 Km) 1,168
41 Sainthia- Pakhur 4th Line (81 Km) 1,569
42 Santragachi- Kharagpur 4th line (111 Km) 2,905
43 Nergundi – Barang & Khurda Road – Vizianagaram 3rd line 5,618
(385 Km)
44 Son Nagar – Andal 3rd and 4th Line (375 Km) 13,606
45 Gorakhpur Cantt – Valmiki Nagar doubling (96 Km) 1,270
46 Jaipur – Sawai Madhopur doubling (131 Km) 1,269
47 Luni – Samdari – Bhildi doubling (272 Km) 3,531
48 Narkatiaganj – Raxaul – Sitamarhi – Darbhanga & Sitamarhi
4,553
– Muzaffarpur doubling (256 Km)
49 Prayagraj (Iradatganj) – Manikpur 3rd line (84 Km) 1,640
50 Tirupati – Pakala – Katpadi doubling (104 Km) 1,332
51 Ratlam – Nagda 3rd and 4th line (41 Km) 1,018
Page 5 of 18Cost
SN Project Name (₹ in
Crore)
52 Aluabari Road – New Jalpaiguri 3rd & 4th line (57 Km) 1,786
53 Aurangabad (Chhatrapati Sambhajinagar) – Parbhani (177 2,179
Km)
54 Bhagalpur – Dumka – Rampurhat doubling (177 Km) 3,169
55 Itarsi – Bina 4th line (237 Km) 4,329
56 Vadodara – Ratlam 3rd & 4th line (259 Km) 8,885
57 Devbhumi Dwarka (Okha) – Kanalus doubling (141 Km) 1,457
58 Badlapur – Karjat 3rd and 4th line (32 Km) 1,324
59 Delhi – Ambala Cantt 3rd & 4th line (194 Km) 5,983
60 Gondia – Jabalpur doubling (231 Km) 5,236
61 Manmad – Indore new line (360 Km) 18,529
62 Errupelam – Amaravati – Nambur new line (57 Km) 2,245
63 Vadhavan Port and New Palghar station new double line (22 1,507
Km)
64 Deshalpar – Hajipir – Luna and Vayor – Lakhpat new line 2,526
(145 Km)
During last three years i.e. FY 2022-23, 2023-24, 2024-25 and the current
FY 2025-26, 982 Surveys (295 New line, 13 Gauge Conversion and 674
Doubling) of total length 67,010 Km have been sanctioned across Indian
Railways.
Maharashtra
Railway Budget:
Budget allocation during the last five years has increased significantly.
Budget allocation for infrastructure projects and safety works, falling
fully/partly in the State of Maharashtra is as under:
Page 6 of 18Period Outlay
2009-14 ₹1,171 crore/year
2025-26 ₹23,778 crore (More than 20 times)
Track construction:
The details of constructing new track falling fully/partly in the State of
Maharashtra during 2009-14 and 2014-25 is as under:
Period New track
Average commissioning of new tracks
Commissioned
2009-14 292 Km 58.4 Km/year
2014-25 2,292 Km 208.4 Km/year (More than 3 times)
Projects sanctioned:
As on 01.04.2025, 38 projects (11 New Lines, 02 Gauge Conversion and 25
Doubling), of a total length of 5,098 km, costing ₹89,780 crore, falling
fully/partly in Maharashtra, are sanctioned. The summary is as under:-
Category No. of Total Length Exp.
sanctioned Length Commissioned upto Mar'25
Projects (in Km) Upto Mar'25 (Km) (₹ in Cr.)
New Line 11 1,355 234 10,504
Gauge Conversion 02 609 334 4,286
Doubling/ 25 3,134 1,792 24,617
Multitracking
Total 38 5,098 2,360 39,407
Recently completed projects:
Details of some of the recently completed projects falling fully/partly in
Maharashtra are as under:
Page 7 of 18S.No. Project Cost
(₹ in crore)
1 Pune-Miraj-Londa Doubling (467 Km) 4,670
2 Jabalpur-Gondia Gauge Conversion (300 Km) 2,005
3 Chhindwara-Nagpur Gauge Conversion (150 Km) 1,512
4 Panvel-Pen Doubling (35 Km) 263
5 Pen-Roha Doubling (40 Km) 330
6 Udhna-Jalgaon Doubling (307 Km) 2,448
7 Mudkhed-Parbhani Doubling (81 Km) 673
8 Bhusawal-Jalgaon 3rd Line (24 Km) 325
9 Jalgaon-Bhusawal 4th Line (24 Km) 261
10 Daund-Gulbarga Doubling (225 Km) 3,182
Ongoing projects:
To further improve the Railway Infrastructure in the state of Maharashtra,
following works have been taken up:-
S.No. Name of the project Cost
(₹ In crore)
1 Ahilyanagar (Ahmednagar)-Beed-Parli Vaijnath 4,957
New Line (261 Km)
2 Baramati-Lonand New Line (64 Km) 1,844
3 Wardha-Nanded New Line (284 Km) 3,445
4 Indore-Manmad New Line (360 Km) 18,529
5 Wadsa-Gadchiroli New Line (52 Km) 1,886
6 Jalna-Jalgaon New Line (174 Km) 5,804
7 Daund-Manmad Doubling (236 Km) 3,037
8 Kalyan-Kasara 3rd Line (68 Km) 1,433
Page 8 of 18S.No. Name of the project Cost
(₹ In crore)
9 Wardha-Nagpur 3rd Line (76 Km) 698
10 Wardha-Ballarshah 3rd Line (132 Km) 1,385
11 Itarsi-Nagpur 3rd Line (280 Km) 2,450
12 Rajnandgaon-Nagpur 3rd Line (228 Km) 3,545
13 Wardha-Nagpur 4th Line (79 Km) 1,137
14 Jalgaon-Manmad 4th Line (160 Km) 2,574
15 Bhusawal-Khandwa 3rd & 4th Line (131 Km) 3,285
16 Solapur-Tuljapur-Osmanabad New Line (95 Km) 2,933
17 Panvel-Chowk Double Line (17 Km) 491
18 Wardha-Balharshah 4th Line (135 Km) 2,226
19 Itarsi-Nagpur 4th Line (297 Km) 5,010
20 Wardha-Bhusawal 3rd & 4th Line (314 Km) 9,197
21 Asangaon-Kasara 4th Line (35 Km) 794
22 Badlapur-Karjat 3rd & 4th Line (32 Km) 1,324
23 Gondia-Dongargarh 4th Line (84 Km) 2,223
24 Gondia-Balharshah Doubling (240 Km) 4,819
Surveys:
In last three years, 2022-23, 2023-24, 2024-25 and current financial year
2025-26, 98 surveys (29 New Line, 02 Gauge Conversion & 67 Doubling) of
total length 8,615 Km falling fully/partly in the State of Maharashtra have
been sanctioned in the state of Maharashtra.
Increasing train handling capacity in Mumbai area:
Presently, about 120 originating Mail/Express trains and about 3,200 sub
urban trains are handled daily in Mumbai area. To increase train handling
Page 9 of 18capacity at various stations in Mumbai area, following works have been
completed/taken up/planned at various stations:
SN Location Details
1 Bandra Terminus 3 Pit Lines have been completed
2 Mumbai Central Platform extension for 24 LHB coaches
3 Jogeshwari 2 additional platforms
4 Dadar 1 additional platform
5 Vasai road 6 platforms, 3 pit lines and 5 stabling lines
6 Panvel-Kalamboli 5 platforms , 4 pit lines and 2 sick lines
7 Kalyan 6 platforms and 4 pit lines
8 LTT 4 platforms and 2 pit lines
9 Parel 6 platforms, 5 pit lines, 6 stabling lines
10 Virar 25 stabling lines
11 Dahanu road 11 stabling lines
12 Mira road 25 stabling lines
In addition to above, Platform extension work at 34 stations to
accommodate 15 car EMUs have been taken up.
New projects for increasing capacity:
To improve the capacity of rail network in Mumbai suburban area, Mumbai
Urban Transport Project (MUTP)-II costing ₹8,087 crore, MUTP-III costing
₹10,947 crore and MUTP-IIIA costing ₹33,690 crore have been sanctioned.
These projects include following works in Mumbai Suburban Area:
SN Name of Project Cost
( in Crore)
CSMT-Kurla 5th & 6th Line (MUTP-II) (17.5 km) 891
1
Page 10 of 18SN Name of Project Cost
( in Crore)
2 Mumbai Central-Borivali 6th Line (MUTP-II) (30 km) 919
Extension of Harbour Line from Goregaon-Borivali (MUTP-
3 826
IIIA) (7 km)
4 Borivali-Virar 5th & 6th Line (MUTP-IIIA) (26 km) 2,184
5 Virar-Dahanu Road 3rd & 4th Line (MUTP-III) (64 km) 3,587
6 Panvel-Karjat Suburban Corridor (MUTP-III) (29.6 km) 2,782
Airoli-Kalwa (elevated) Suburban Corridor link
7 476
(MUTP-III) (3.3 km)
8 Kalyan-Asangaon 4thLine (MUTP-IIIA) (32 km) 1,759
9 Kalyan-Badlapur 3rd& 4th line (MUTP-IIIA) (14 km) 1,510
10 Kalyan-Kasara 3rd Line (67 km) 793
11 Naigaon-Juichandra double chord Line (6 km) 176
12 Nilaje-Kopar double chord Line (5 km) 338
13 Kalyan Yard remodeling work 866
New generation trains:
To enhance passenger carrying capacity, 238 rakes of 12 cars each with
doors have been sanctioned under MUTP-III & IIIA at a cost of ₹19,293
crore. The process for procurement of these rakes has been taken up.
Capacity Augmentation works for Pune Area:
Presently, about 33 originating Mail/Express trains are handled daily in
Pune area.
Page 11 of 18To increase train handling capacity at various stations in Pune area,
following works have been completed/taken up/planned at various
stations:
SN Location Details
1 Pune Junction 6 additional Platforms and Extension of 5
Platforms.
2 Hadapsar Extension of 3 Platforms to handle full
length trains.
3 Khadki Raising and Extension of PF-3/4 and
extension of running lines completed in
July’2025.
4 Alandi New Coaching Terminal with 9 additional
Platforms, 8 pit lines and 8 stabling lines
5 Phursungi 5 Stabling Lines at Phursungi
In addition to above, following capacity additional works have been
undertaken in Pune Area to increase the train handling capacity:
SN Name of Project
1 3rd Line between Hadapsar and Ghorpuri Yard
2 New Block station at Manjari Bhadrukin Pune-Daund Section and
Ramtekdi in Pune-Sasvad section
3 Bidirectional Signalling in Pune Sasvad Road Section
Page 12 of 18Bullet Train project:
Presently, the Mumbai-Ahmedabad High Speed Rail (MAHSR) Project (508
km) is under execution. The Project is passing through the States of
Gujarat, Maharashtra and Union Territory of Dadra & Nagar Haveli with 12
stations planned at Mumbai, Thane, Virar, Boisar, Vapi, Billimora, Surat,
Bharuch, Vadodara, Anand, Ahmedabad and Sabarmati.
Entire land (1,389.5 Ha.) for MAHSR project has been acquired. All
Statutory Clearances have been obtained. All 1,651 utilities have been
shifted. The delay in land acquisition in the State of Maharashtra has
impacted the project till 2021. The land acquisition picked up in 2022 in
Maharashtra.
The progress of various major items so far is as under:
Item Progress
Piers 430 kms.
Girder 341 kms.
Track Bed 174 kms.
OHE Masts 153 kms.
The progress of stations is given below:-
S.No. Station Status
Foundation works completed, Platform slab & roof
1 Sabarmati
structural works and finishing works are in progress
2 Ahmedabad Structural works completed and finishing works
3 Anand/Nadiad have been taken up.
4 Vadodara Foundation work completed, structural works and
Page 13 of 18finishing works have been taken up.
5 Bharuch
6 Surat Structural works completed and finishing works
7 Bilimora have been taken up.
8 Vapi
9 Boisar Foundation works have been taken up and in
10 Virar advanced stage. Structural works have been taken
11 Thane up.
This is an underground station. Foundation works
12 BKC (Mumbai)
almost completed and Base Slab has been taken up.
The progress on the River Bridges is as under:-
S. No. River Name Status
Sub-Structure work completed,
1 Sabarmati River (480m)
Superstructure work has been taken up.
2 Meshwa River (120m)
3 Vatrak River (280m)
Bridge construction completed.
Mohar (Shedhi) River
4
(160m)
11 out of 12 wells completed;5 spans
5 Mahi River (720m)
launched
6 Vishwamitri River (80m)
Bridge construction completed.
7 Dhadhar River (120m)
21 out of 25 wells completed; 4 spans
8 Narmada River (1366m)
launched
9 Kim River (120m) Bridge construction completed.
Foundation work has been taken up, 10
10 Tapi River (720m)
out of 12 wells completed
Page 14 of 1811 Mindhola River (240m)
12 Purna River (360m)
13 Ambika River (200m)
14 Venganiya River (200m)
15 Kaveri River (120m)
16 Kharera River (120m)
Bridge construction completed.
17 Auranga River (320m)
18 Par River (320m)
19 Kolak River (160m)
Daman Ganga River
20
(360m)
21 Darotha River (80m)
22 Jagani River (360m) Foundation works have been completed
12 Pile Cap and 11 Pier (out of 58)
23 Vaitarna River (2320m)
completed.
Ulhas River Branch Temporary Access Bridge (TAB)
24
(120m) completed to start the foundation work.
Geo-technical Investigation (GTI) has
Desai Khadi River Bridge
25 been completed and Design work has
(400m)
been taken up.
The work of the under-sea tunnel (approximately 21 km) has commenced,
out of which 4.8 km of tunnel between Ghansoli and Shilphata in
Maharashtra has been completed.
Further, to strengthen national transport infrastructure, provide a fillip to
regional connectivity, economic growth, tourism, investment and
employment generation, and encourage modal shift from road and air
transport to rail, the Government has announced the development of the
Page 15 of 18following seven new High-Speed Rail (HSR) corridors in the Union Budget
2026-27: -
(i) Mumbai–Pune
(ii) Pune–Hyderabad
(iii) Hyderabad–Bengaluru
(iv) Hyderabad–Chennai
(v) Chennai–Bengaluru
(vi) Delhi–Varanasi
(vii) Varanasi–Siliguri
Being highly capital intensive, the decision to sanction any HSR
Corridor/Project depends on many factors such as outcome of DPR, techno-
economic feasibility studies and availability of resources such as financing
options etc.
Dedicated freight corridor:
Western DFC also passes through Maharashtra. About 178 route Km of
western DFC is situated in Maharashtra which is about 12% of overall route
length of western DFC. 76 Km of this project from New Gholvad to New
Vaitarna in Maharashtra has already been commissioned. Balance works
have been taken up. Connectivity of WDFC to JNPT will boost the capacity to
handle cargo and container traffic from port to Delhi NCR.
Railway Electrification:
Electrification of railway network on Indian Railways has been taken up in
mission mode. So far, about 99.4% of Broad Gauge (BG) network has been
electrified. The electrification in remaining network has been taken up.
Page 16 of 18Electrification carried out during 2014-25 and before 2014 is as under:
Period Route Kilometer
Before 2014 (about 60 years) 21,801
2014-25 46,900
In Maharashtra, 100% of BG network has been electrified. Further, all new
line/multitracking projects are being sanctioned and constructed with
electrification.
Sanction of any railway project depend upon many parameters/factors
which include the following:
Anticipated traffic projections and remunerativeness of the
proposed route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives
Railway’s operational requirements
Socio-economic considerations
Overall availability of funds
Railway Infrastructure projects enable socio-economic development of the
region including:
Better connectivity of the region with other parts of the country
Faster movement of goods and services
Improving logistics efficiency and reduction in transportation cost.
Enhance line capacity
Page 17 of 18 Increase in direct and indirect employment opportunities for the
people of the region
Reduced operational bottlenecks
Development of tourism industry and increase in industrial activities
in the region.
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****
Page 18 of 18