**Policy Summary: Third Launch Pad (TLP) Development at Satish Dhawan Space Centre** This document summarizes the current status of the Third Launch Pad (TLP) project at the Satish Dhawan Space Centre, Sriharikota, as of August 6, 2025. Financial sanction for the project was received in March 2025. The geotechnical investigation and topography survey of the site were completed by May 2025. Offers for road and electrical works are currently under evaluation. The establishment of the TLP facilities involves multiple work packages. Key milestones include: completion of civil works by May 2028, establishment of fluid systems and associated propellant storages by July 2028, establishment of launch pad facilities by September 2028, and commissioning of the facility by March 2029. The Department of Space intends to partner with Indian private players, MSMEs, and startups selected through a tendering process. This process will prioritize the "Make in India" and "Atmanirbhar Bharat" objectives. Specific details regarding these collaborations will be available after the bidding process is complete and contracts are awarded. This information was provided in response to Lok Sabha Unstarred Question No. 2863, answered on Wednesday, August 06, 2025, by the Minister of State in the Ministry of Personnel, Public Grievances, Pensions and in the Prime Minister's Office, Dr. Jitendra Singh.

Key Entities Referenced

Third Launch Pad: A spaceport launch facility under construction at Satish Dhawan Space Centre. Satish Dhawan Space Centre, Sriharikota: A spaceport in Andhra Pradesh, India, owned by the Indian Space Research Organisation (ISRO). Lavu Sri Krishna Devarayulu: Member of Parliament who raised the unstarred question in Lok Sabha. Prime Minister: The head of the government of India. Jitendra Singh: Minister of State in the Ministry of Personnel, Public Grievances Pensions and in the Prime Minister's Office. Make in India: An initiative by the Government of India to encourage domestic manufacturing. Atmanirbhar Bharat: An initiative by the Government of India to make India a self-reliant nation. MSMEs: Micro, Small and Medium Enterprises. These are being considered for partnerships in the Third Launch Pad project.
Official Source Record View Original Source →
See Full Document Text
GOVERNMENT OF INDIA DEPARTMENT OF SPACE LOK SABHA UNSTARRED QUESTION NO. 2863 TO BE ANSWERED ON WEDNESDAY, AUGUST 06, 2025 THIRD SATELLITE LAUNCH PAD 2863. SHRI LAVU SRI KRISHNA DEVARAYULU: Will the PRIME MINISTER be pleased to state: (a) the details regarding the current status of the construction and development of the Third Launch Pad (TLP) at Satish Dhawan Space Centre, Sriharikota, including timelines achieved and milestones pending; (b) whether the Government has partnered with or engaged private players, MSMEs or startups in the construction of the Third Launch Pad and related infrastructure; and (c) if so, the details of such collaborations along with the mechanisms adopted to ensure Make in India and Atmanirbhar Bharat objectives are met? ANSWER MINISTER OF STATE IN THE MINISTRY OF PERSONNEL, PUBLIC GRIEVANCES & PENSIONS AND IN THE PRIME MINISTER’S OFFICE (DR. JITENDRA SINGH): ****(a) The Financial Sanction for the Third Launch Pad Project was received in March 2025. Subsequently, the Geo technical investigation and topography survey of the site was completed by May 2025. Offers are under evaluation for road works and electrical works. Multiple work packages have been identified for the establishment of the TLP facilities. There are four major milestones, namely, completion of civil works (May 2028), establishment of fluid systems and associated propellant storages (July 2028), establishment of launch pad facilities (September 2028) and commissioning of the facility by March 2029. (b) & (c) The Department proposes to partner with Indian private players & MSMEs, who are selected through a tendering process ensuring Make-in-India and Atmanirbhar Bharat to the maximum extent possible. The details of such collaborations will be available after the completion of the bidding process and placement of contracts. ****