GOVERNMENT OF INDIA
MINISTRY OF JAL SHAKTI
DEPARTMENT OF WATER RESOURCES, RIVER DEVELOPMENT & GANGA REJUVENATION
LOK SABHA
UNSTARRED QUESTION NO. 3358
ANSWERED ON 12.03.2026
WAINGANGA-NALGANGA RIVER LINKING PROJECT
3358. Dr. BACHHAV SHOBHA DINESH:
SHRI SANJAY UTTAMRAO DESHMUKH:
Will the Minister of JAL SHAKTI be pleased to state:
(a) the present status of the National River Linking Project (NRLP);
(b) whether the Government has approved the 463 kms Wainganga–Nalganga river linking project and
if so, the details thereof along with the districts covered under the said project;
(c) whether the Government is aware that large parts of Maharashtra suffer from malnutrition due to
lack of irrigation and if so, the details thereof;
(d) whether several regions have been excluded from NRLP despite serious irrigation issues and if so,
the reasons therefor; and
(e) the steps being taken by the Government to include such districts under the said project including
Washim district?
ANSWER
THE MINISTER OF STATE FOR JAL SHAKTI
(SHRI RAJ BHUSHAN CHOUDHARY)
(a) The Government of India has formulated the National Perspective Plan (NPP) for interlinking of
rivers, under which 30 Interlinking of Rivers (ILR) projects comprising 16 Peninsular and 14 Himalayan
links have been identified to address water scarcity and augment irrigation and other water-related
benefits across the country. The National Water Development Agency (NWDA), the nodal agency for
this programme, has completed Pre-Feasibility Reports (PFRs) for all 30 links, Feasibility Reports (FRs)
for 26 links, and Detailed Project Reports (DPRs) for 11 links. The status of these 30 link projects under
the NPP is enclosed at Annexure.
(b) NWDA has prepared the PFR and subsequently the DPR of the Wainganga–Nalganga river linking
project and submitted it to the Government of Maharashtra. As informed by the State Government, the
project has been accorded in-principal approval by the State Government. The project proposes
diversion of 1,804.78 MCM of water from the Gosikhurd Project on the Wainganga River to the
Nalganga basin through a 388.28 km link canal, to provide irrigation benefits over 4,04,281 hectares
in eight districts, i.e., Nagpur, Wardha, Amravati, Yavatmal, Akola, Buldhana, Washim, and Bhandara.
1(c) Matters relating to malnutrition fall primarily within the purview of the health and social welfare
sectors. However, the Government recognises that improved irrigation contributes to agricultural
stability, and projects such as the Wainganga–Nalganga link are expected to enhance water availability
in drought-prone regions of Maharashtra.
(d) & (e) The identification of ILR projects under the National Perspective Plan is based on
hydrological feasibility, water balance studies, technical parameters, and interstate considerations. The
State Government has informed that no regions have been excluded from the NPP. The Wainganga–
Nalganga River Linking Project already includes the Washim district among its beneficiary districts.
***
2ANNEXURE
ANNEXURE REFERRED TO IN REPLY TO PART (a) OF UNSTARRED QUESTION NO.
3358 TO BE ANSWERED IN LOK SABHA ON 12.03.2026 REGARDING “WAINGANGA-
NALGANGA RIVER LINKING PROJECT”.
Details and current status of ILR projects under the NPP
Peninsular Component
Sl. Name States benefited Status
No
1 Mahanadi (Manibhadra) - Godavari Andhra Pradesh (AP) and FR completed
(Dowlaiswaram) link Odisha
Alternate Mahanadi (Barmul)- AP and Odisha FR completed
Rushikulya–Godavari Dowlaiswaram) link
2 Godavari (Polavaram) - Krishna AP, Karnataka, FR Completed
(Vijayawada) link @ Maharashtra and
Telangana
3 a.) Godavari (Inchampalli) - Krishna Telangana FR completed
(Nagarjunasagar) link
b.) Alternate Godavari (Inchampalli) - DPR completed
Telangana
Krishna (Nagarjunasagar) link *
4 Godavari (Inchampalli/ SSMPP) - Krishna Telangana and AP DPR completed
(Pulichintala) link
5 a.) Krishna (Nagarjunasagar) - Pennar AP FR completed
(Somasila ) link
b.)Alternate Krishna (Nagarjunasagar) - DPR completed
AP
Pennar (Somasila ) link *
6 Krishna (Srisailam) – Pennar link AP DPR Completed
7 Krishna (Almatti) – Pennar link Karnataka &AP DPR completed
8 a.) Pennar (Somasila) - Cauvery (Grand AP, Tamil Nadu and FR completed
Anicut) link Puducherry
b.) Alternate Pennar (Somasila) - Cauvery AP, Tamil Nadu and
(Grand Anicut) link * Puducherry DPR completed
9 Cauvery (Kattalai) - Vaigai -Gundar link Tamil Nadu DPR completed
10 Parbati –Kalisindh - Chambal link Madhya Pradesh (MP) FR completed
and Rajasthan
b) Modified Parbati – Kalisindh-Chambal MP and Rajasthan MoA for
link implementation has
been signed by both
the States
11 Damanganga - Pinjal link Maharashtra (only water DPR completed and
supply to Mumbai) dropped from status of
“priority links”
12 Par-Tapi-Narmada link Gujarat and Maharashtra DPR completed and
dropped from status of
“priority links”
13 Ken-Betwa link Uttar Pradesh (UP) and DPR completed and
MP project is under
implementation
14 Pamba - Achankovil - Vaippar link Tamil Nadu and Kerala FR completed
15 Bedti - Varda link @@ Karnataka DPR completed
16 Netravati – Hemavati link*** Karnataka PFR completed
3* Due to pending consensus on Manibhadra and Inchampalli dams, Phase-I of Project to divert
unutilized waters of Godavari river, Study was carried out and DPR of Godavari (Inchampalli) –
Krishna (Nagarjunasagar) - Pennar (Somasila) – Cauvery (Grand Anicut) link projects (combined)
called as Godavari-Cauvery link was completed. The report has further been updated terminating the
link canal at Manimukhtanadi, a Tributary of Vellar river flowing adjacent to Cauvery basin.
@@ Bedti – Varda Link - DPR was prepared directly after preparation of its PFR, no FR was prepared.
@ Godavari (Polavaram) - Krishna (Vijayawada) Link- the project has been taken up by Govt. of
Andhra Pradesh and is under execution by Polavaram Project Authority.
*** Netravati – Hemavati link: Further studies not taken up after PFR preparation since after
implementation of Yettinahole project by Govt. of Karnataka, no surplus water is available in Netravati
basin for diversion through this link.
Himalayan Component
Sl. Name States / Countries Status
No benefited
1. Kosi-Mechi link** Bihar and Nepal PFR completed
2. Kosi-Ghaghra link Bihar, Uttar Pradesh (UP) FR completed
and Nepal
3. Gandak - Ganga link UP and Nepal FR completed
4. Ghaghra - Yamuna link UP and Nepal FR completed
5. Sarda - Yamuna link UP and Uttarakhand FR completed
6. Yamuna-Rajasthan link Haryana and Rajasthan FR completed
7. Rajasthan-Sabarmati link Rajasthan and Gujarat FR completed
8. Chunar - Sone Barrage link Bihar and UP FR completed
9. Sone Dam - Southern Tributaries of Bihar and Jharkhand Draft FR completed
Ganga link
10. Manas-Sankosh-Tista-Ganga (M-S-T-G) Assam, West Bengal and FR completed
link Bihar
11. Jogighopa-Tista-Farakka link Assam, WB and Bihar PFR completed
(Alternative to M-S-T-G) (The proposal has
been dropped)
12. Farakka-Sundarbans link WB FR completed
13. Ganga (Farakka) - Damodar- WB, Odisha and FR completed
Subarnarekha link Jharkhand
14. Subarnarekha-Mahanadi link WB and Odisha FR completed
**Kosi-Mechi Inter State link - PFR prepared and proposal was dropped due to international issues,
subsequently, on request of Govt. of Bihar, NWDA has taken up Kosi-Mechi Intra State link project.
*****
4