GOVERNMENT OF INDIA
MINISTRY OF NEW AND RENEWABLE ENERGY
RAJYA SABHA
UNSTARRED QUESTION NO. 2862
ANSWERED ON 17.03.2026
WAIVER OF ISTS CHARGES FOR RENEWABLE ENERGY PROJECT
2862. SMT. GEETA ALIAS CHANDRAPRABHA
Will the Minister of NEW AND RENEWABLE ENERGY be pleased to state:
(a) the guidelines being followed for extending the waiver of inter state transmission
system (ISTS) charges to renewable energy projects;
(b) the arrangements made to ensure timely grid connectivity and evacuation for projects
availing the waiver; and
(c) whether any review mechanism has been put in place to assess the effect of the waiver
on project viability and grid utilisation?
ANSWER
THE MINISTER OF STATE FOR NEW & RENEWABLE ENERGY AND POWER
(SHRI SHRIPAD YESSO NAIK)
(a) The Inter-State Transmission System (ISTS) charges are governed by Central Electricity
Regulatory Commission (CERC) (Sharing of Inter State Transmission Charges and Losses)
Regulations, 2020 and its amendment thereafter. According to the 4th Amendment to the said
regulations dated 26.06.2025, The detail of ISTS charges waiver for specific categories of
renewable energy and energy storage projects is given in Annexure.
(b) The grid connectivity is regulated by the CERC (Connectivity and General Network
Access to the inter-State Transmission System) Regulations, 2022 as amended with defined
timelines and procedures.
As per the Regulation, the Nodal Agency for Connectivity or General Network Access (GNA)
to the ISTS is Central Transmission Utility (CTU).
Progress of renewable energy (RE) generation and associate ISTS is being monitored in
quarterly Joint Co-ordination Committee Meetings by CTU wherein efforts are being made to
avoid mismatches between RE developers and transmission service providers. Further,
transmission system is also being monitored at the level of Ministry of Power and Central
Electricity Authority (CEA).
CTU has now also been mandated to monitor the critical elements on monthly basis with
participation of transmission developers and generation project developers.
In case of non-availability of associated transmission system, CTU in consultation with CEA,
Grid-India and TSPs, evolves alternate/interim arrangement, wherever possible, so that timely
evacuation can be provided to RE projects.
Additionally, the Government has taken following measures to ensure timely grid connectivity
and evacuation for projects.• Green Energy Corridor Scheme is being implemented for evacuation of power from
RE projects from identified locations.
• The CEA prepared report on “Transmission System for Integration of over 500 GW
RE Capacity by 2030”.
• Advance transmission planning through the National Electricity Plan (Volume II:
Transmission), notified by Central Electricity Authority (CEA) in Oct, 2024.
(c) As per CERC regulations, the ISTS charges are shared by drawee DICs (Designated ISTS
Customers) and therefore, do not have direct impact on the cost of generation of renewable
energy project. Under Section 38 (2)(c) of the Electricity Act 2003, CTU has been mandated
to ensure development of an efficient, coordinated and economical system of ISTS.
*****ANNEXURE REFERRED TO IN PARTS (a) OF THE RAJYA SABHA UNSTARRED
QUESTION NO.2862 DUE FOR ANSWER ON 17.03.2026 REGARDING “WAIVER
OF ISTS CHARGES FOR RENEWABLE ENERGY PROJECT”.
Sl. Type of project ISTS Charges waiver Duration of
No. waiver from
commissioning
date
1 Renewable Energy Generating 100% for projects 25 years
Station (REGS) based on wind commissioned by 30th June
or solar source or RHGS based 2025; waiver reducing 25%
wind and solar source annually thereafter
2 Hydro Pumped Storage Plant 100% for projects where 25 years
award of construction work
by 30th June 2028
3 a. Battery ESS connected at a. 100% for projects 12 years
a substation where no commissioned by 30th
REGS is connected or June 2025; waiver
Battery ESS connected at reducing 25% annually
a substation where thereafter
REGS is connected but b. 100% for projects
Battery ESS is charged commissioned by 30th
from Grid or source June 2028
other than REGS
b. Battery ESS connected at
a substation where
REGS is connected and
is charged from such
REGS
3 Large hydro 100% for projects where date 18 years
projects(>25MW) of signing of PPA and award
of construction on or after
1.12.2022 and on or before
30.6.2025; waiver reducing
25% annually thereafter
4 Green Hydrogen /Green 100% for projects 25 years
Ammonia Plants that utilize commissioned by 31st Dec
renewable energy from Solar, 2030; waiver reducing 25%
Wind, Large Hydro or Energy annually thereafter
Storage Systems or any hybrid
combination of the
aforementioned technologies
5 Off shore wind power 100% for projects 25 years
commissioned by 31st Dec
2032; waiver reducing 25%
annually thereafter