GOVERNMENT OF INDIA
MINISTRY OF HOUSING AND URBAN AFFAIRS
LOK SABHA
UNSTARRED QUESTION NO. 3312
TO BE ANSWERED ON MARCH 12, 2026
WATER SUPPLY AND SEWERAGE PROJECTS IN KHARGONE
NO. 3312. SHRI GAJENDRA SINGH PATEL:
Will the Minister of HOUSING AND URBAN AFFAIRS be pleased to
state:
(a) the number of cities in Khargone and Barwani districts of Khargone
Lok Sabha Constituency where water supply and sewerage projects
have been started under AMRUT 2.0 since January 2025;
(b) the manner in which progress is being measured with reference to
tap connections, non-revenue water reduction and improvement in
service quality;
(c) the steps taken to promote water reuse and sustainable urban water
management;
(d) whether any project has faced delays due to technical or financial
constraints and if so, the details thereof; and
(e) the measures being undertaken by Urban Local Bodies to ensure
long-term operation and maintenance?
ANSWER
THE MINISTER OF STATE IN THE
MINISTRY OF HOUSING AND URBAN AFFAIRS
(SHRI TOKHAN SAHU)
(a) to (c): Water and Sanitation is State subject. Government of India
supplements the efforts of the States through schematic interventions/
advisories. It provides financial and technical support to the States
through various schemes/ Missions such as Atal Mission for Rejuvenation
and Urban Transformation 2.0 (AMRUT 2.0). Under AMRUT/ AMRUT 2.0, the
States/ Union Territories are empowered to select, appraise, prioritise and
implement the projects.
As reported by the State, a total of 04 projects in water supply and
sewerage/septage management have been taken up by the State of
Madhya Pradesh in Khargone Lok Sabha Constituency, of which 3 projects
have been awarded since January, 2025. The details are as below:
…2/--2-
S.NO District ULB Project Title Approved Contract
Cost (in ₹ Award Date
crore)
1 KHARGAON KHARGONE Sewerage and 28.60 16-10-2025
Sewage
Treatment
Scheme for Nagar
Palika Khargone
2 BARWANI SENDHWA water Supply 22.56 25-06-2025
Scheme
3 KHARGAON MAHESHWAR Development of 3.19 16-03-2024
Overhead water
tank and
Distribution
network under
water supply
scheme Amrut 2.0
4 BARWANI BADWANI Water Supply 21.02 16-07-2025
Scheme Barwani
Under Amrut 2.0
The progress is measured in terms of household coverage of water
supply and sewerage connections. Through AMRUT/ AMRUT 2.0 and in
convergence with the States, 246 lakh water tap connections in the urban
areas have been provided so far. 182 lakh sewer connections (including
households covered through Faecal Sludge and Septage Management
(FSSM)) have been provided through AMRUT/ AMRUT 2.0 and in
convergence in AMRUT Cities. 93,457.51 km of water pipeline network has
been laid/ replaced and 26,995.61 km of sewer network has been laid/
replaced. Around 6,535 Million Litres per Day (MLD) of treated water are
reused by the States in industries, horticulture, agriculture, etc. In Madhya
Pradesh, 16.54 lakh water tap connections and 5.73 lakh sewer
connections (including households covered through FSSM) in the urban
areas have been provided so far.
Under AMRUT 2.0, cities have prepared City Water Balance Plans
(CWBPs), which include as-is assessment of water supply systems which
help cities/ ULBs for sustainable urban water management. Water body
rejuvenation is one of the major components of AMRUT 2.0. So far, 2,991
water body rejuvenation projects worth ₹6,083.32 crore have been
approved under this Mission, which include 430 water body rejuvenation
projects worth ₹511.75 crore in Madhya Pradesh. Further, to promote
groundwater recharge, demonstration of variety of recharge structures
and creating awareness among city officials and citizens on importance of
aquifer management, Shallow Aquifer Management (SAM) initiative under
AMRUT 2.0 was launched as a pilot project across 9 diverse Indian cities.
This has been further scaled up under SAM 2.0 to 75 additional cities
including 5 cities of Madhya Pradesh.
…3/--3-
For addressing non-revenue water issues, States have taken up Drink
from Tap (DfT) projects and Smart Monitoring Systems such as Supervisory
Control and Data Acquisition (SCADA), meters, pressure valves, etc. under
AMRUT 2.0 to strengthen maintenance systems, digital monitoring, energy
efficiency, etc. States are encouraged to implement at least one DfT
project in a District Metered Area (DMA) or ward within each AMRUT city.
408 project with 1,153 DMAs benefitting 16.72 lakh Households have been
approved under AMRUT 2.0. 258 water supply schemes under AMRUT have
SCADA system and 1,422 water supply projects under AMRUT 2.0 has
provision for SCADA system. Mission has provision of ₹3000 per
connection to enhance last mile connectivity.
AMRUT 2.0 has been envisaged to promote circular economy of
water through development of city water balance plan for each city
focusing on recycle/ reuse of treated sewage, rejuvenation of water bodies
and water conservation, etc. Under Sewerage component of the AMRUT
2.0 for 500 AMRUT cities, tertiary treatment with end-to-end reuse plan
(preferably in Public Private Partnership mode); provision/ augmentation
and rehabilitation of sewerage systems with end-to-end treatment and
reuse; tapping of used water for recycling; identifying the bulk users of
recycled used water and facilitating sale of used water to potential users
(e.g. industrial clusters such as textile/ leather/ paper/ power plants/
railways, etc.) are admissible components.
Further, MoHUA has launched “Jal Hi AMRIT” initiative under AMRUT
2.0 reforms, which aims to incentivize States and Union Territories (UTs)
to efficiently manage sewage treatment plants for recyclable treated
water meeting environmental standards on sustained basis. The focus of
this initiative is building capacity and incentivizing qualitative
improvements in the treated discharge effluent. To institutionalize
circularity, Water Resource Recovery Cells (WRRCs) have been
established in 25 States/ Union Territories under this initiative to plan,
monitor, and scale resource recovery interventions.
(d) & (e): As reported by the State of Madhya Pradesh, some projects may
experience delays due to technical issues, land availability, contractor
performance, or local administrative constraints. The State has informed
that regular monitoring is done through State Level Technical Committee
(SLTC) and review meetings, improved contract management, timely
release of funds and inclusion of Operation and Maintenance (O & M)
components in project design.
…4/--4-
The Mission guidelines advocates taking up projects with O&M
cost for at least five years, funded by way of levy of user charges or other
revenue streams. The Mission framework also emphasizes reforms such
as levy and collection of user charges, reduction of non-revenue water,
reuse and recycling of treated wastewater and improvement in financial
management practices to enhance the capacity of ULBs to sustainably
operate and maintain assets. Further under AMRUT 2.0 through various
reform initiatives such as Jal Hi Amrit and AMRUT Mitra, the Mission is
supporting the State/ ULBs in management of Water Treatment Plants and
Sewage Treatment Plants.
*****