Official Gazette Notification Text
Official Transcriptरजिस्ट्री स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99 सी.जी.-डी.एल.-अ.-17112026-277975 xxxGIDHxxx CG-DL-E-17112026-277975 xxxGIDExxx असाधारण EXTRAORDINARY भाग I—खण्ड 1 PART I—Section 1 प्राजधकार स ेप्रकाजित PUBLISHED BY AUTHORITY स.ं 339] नई दिल्ली, मगं लवार, नवम्ब र 10, 2026/कार्तकि 19, 1948 No. 339] NEW DELHI, TUESDAY, NOVEMBER 10, 2026/KARTIKA 19, 1948 परे ोजलयम और प्राकृजतक गसै मत्रं...
रजिस्ट्री स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99 सी.जी.-डी.एल.-अ.-17112026-277975 xxxGIDHxxx CG-DL-E-17112026-277975 xxxGIDExxx असाधारण EXTRAORDINARY भाग I—खण्ड 1 PART I—Section 1 प्राजधकार स ेप्रकाजित PUBLISHED BY AUTHORITY स.ं 339] नई दिल्ली, मगं लवार, नवम्ब र 10, 2026/कार्तकि 19, 1948 No. 339] NEW DELHI, TUESDAY, NOVEMBER 10, 2026/KARTIKA 19, 1948 परे ोजलयम और प्राकृजतक गसै मत्रं ालय अजधसचू ना नई दिल्ली, 10 नवम् बर, 2026 भारत सरकार द्वारा जनिी सयं क्तु उद्यमों को छोटे, मध्यम आकार के और खोि े गए क्षत्रे ों को आवटं टत करन े वाल े उत्पािन भागीिारी सजं विाओं (पीएससी) के जवस्ट्तार के जलए नीजत। फा. स.ं अन्व-े 11019 (18)/33/2026-ओएनिी-IV.— भारत सरकार (जिस े इसके बाि सरकार के रूप म ें संिर्भित दकया गया ह)ै ने पहले जवस्ट्तार िने े के जलए एक पारििी और पटरभाजित ढांचा रखने के जलए छोटे और मध्यम आकार के खोिे गए क्षेत्रों को जवस्ट्तार िेने के जलए 28.03.2016 की तारीख की नीजत को मंिूरी िी थी। तेलक्षेत्र (जवजनयमन और जवकास) संिोधन अजधजनयम, 2025 और परे ोजलयम और प्राकृजतक गैस जनयम, 2025 की अजधसूचना के पटरणामस्ट्वरूप, नीजत को अब संिोजधत दकया गया ह।ै यह सिं ोजधत नीजत हाइड्रोकाबिन के इष्टतम िोहन के जलए इन क्षेत्रों में अपन े जनवेि की योिना बनाने में संजविाकारों (प्रचालकों/पीआई धारकों) की मिि करेगी। नीजत की मुख्य जविेिताए ं इस प्रकार ह:ैं
1. प्रस्ट्ततु ीकरण, सजं विा जवस्ट्तार के जलए अनरु ोध पर जवचार और अनमु ोिन
1.1 संजविाकार को संजविा की अवजध के आधे समय (या संजविा की जवस्ट्ताटरत अवजध) की समाजि के बाि दकसी भी समय, लेदकन संजविा की समाजि जतजथ स े कम स े कम 2 वि ि पहले, एमओपीएनिी को संजविा के जवस्ट्तार के जलए 8594 GI/2026 (1)2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART I—SEC.1] प्रचालन सजमजत(ओसी) द्वारा जवजधवत अनुमोदित आवेिन िमा करना चाजहए, जिसकी एक प्रजत डीिीएच को िी िानी चाजहए।
1.2 डीिीएच संजविाकार द्वारा आविे न िमा करने के 6 महीन े के भीतर पीएमओपीएनिी को जसफाटरि करेगा।
1.3 डीिीएच से प्रस्ट्ताव प्राि होन ेके 3 महीने के भीतर सरकार जवस्ट्तार के अनरु ोध पर जनणिय लगे ी।
2. जवस्ट्तार के जलए जवत्तीय मानिंड
2.1 सरकारी जहस्ट्सा: मूल पीएससी अवजध के बाि संजविा की जवस्ट्ताटरत अवजध के िौरान लाभ पेरोजलयम (पीपी) का सरकारी जहस्ट्सा जनम्नानुसार होगा: पीएसी का जवस्ट्ताटरत समय (पीएससी की मलू िीओआई पीपी की िर अवजध के बाि) जवस्ट्तार के वि ि 1 स ेविि 10 तक सामान्य पीएससी प्रावधानों का उपयोग करके गणना दकए गए जहस्ट्से से 10% अजधक जवस्ट्तार के वि ि 11 स ेविि 20 तक सामान्य पीएससी प्रावधानों का उपयोग करके गणना दकए गए जहस्ट्से से 5% अजधक जवस्ट्तार के वि ि 21 स ेविि 30 तक सामान्य पीएससी प्रावधानों का उपयोग करके गणना दकए गए जहस्ट्से से 2.50% अजधक विि 30 के बाि सामान्य पीएससी प्रावधानों का उपयोग करके गणना दकए गए जहस्ट्से के अनुसार
2.2 संजविा की जवस्ट्ताटरत अवजध के िौरान, प्रोदफट पेरोजलयम की सरकारी जहस्ट्सेिारी, जनवेि गुणक (आईएम)/कर पश्चात टरटनि की िर (पीटीआरआर) के आधार पर, विि-िर-विि जभन्न हो सकती ह।ै (स्ट्पष्टता के जलए, यदि संजविा की जवस्ट्ताटरत अवजध के वि ि 1 से वि ि 10 के िौरान दकसी भी विि म ें सामान्य पीएससी प्रावधानों का उपयोग करके गणना की गई लाभ पेरोजलयम की सरकारी जहस्ट्सेिारी 20% ह,ै तो उस अवजध के िौरान लाभ पेरोजलयम की िेय सरकारी जहस्ट्सेिारी 30% (20% + 10%) होगी)।
2.3 रॉयल्टी और उपकर: संजविा की जवस्ट्ताटरत अवजध के िौरान, रॉयल्टी और उपकर नामांकन व्यवस्ट्था की प्रचजलत िरों पर िेय होंग े और छोटे और मध्यम आकार के क्षेत्रों िोनों के जलए पीएससी में जनधािटरत टरयायती िरों पर नहीं। सभी संजविाकारों द्वारा उनके भाग लेन े वाल े ब्याि के अनुपात म ेंरॉयल्टी और उपकर िये होगा।
3. मल्ू याकं न के जलए पवू ापि क्षे ाएं
3.1 आवेिन की तारीख को वैध खनन पट्टा/पेरोजलयम पट्टा वाल े जनम्नजलजखत क्षेत्रों के जलए जवस्ट्तार के प्रस्ट्ताव पर जवचार दकया िाएगा: (क) जिन क्षेत्रों में परीक्षण/वाजणजययक उत्पािन िरूु हो गया ह।ै (ख) जवकास योिना द्वारा कवर दकए गए क्षेत्र, पट्टे क्षेत्र में दकसी भी खोि के जलए, जिसे एमसी द्वारा अनुमोिन के जलए प्रस्ट्तुत दकया गया है, एमसी द्वारा ऐस ेएफडीपी के अनुमोिन के अधीन हो। (ग) वे क्षेत्र िहा ं संजविाकार द्वारा डीिीएच को फमि अन्वेिण कायक्रि म प्रस्ट्तुत दकया गया ह,ै बैंक गारंटी द्वारा समर्थित ह ैऔर आवेिन की तारीख को मौिूिा जवकास क्षेत्र के अंतगति िाजमल नहीं ह।ै[भाग I—खण् ड 1] भारत का रािपत्र : असाधारण 3
3.2 संजविा जवस्ट्तार के जलए आवेिन जनम्नजलजखत ितों को पूरा करना चाजहए: क) संजविाकार को तीसरे पक्ष के टरिवि लेखापरीक्षा प्रजतवेिन के माध्यम से िेि वसूली योग्य आरजक्षत की उपलब्धता प्रिर्िित करने में सक्षम होना चाजहए, जिसे जवस्ट्तार के जलए आवेिन के साथ प्रस्ट्ततु दकया िाना ह।ै इस उद्देश्य के जलए 'टरिवि' की पटरभािा पेरोजलयम संसाधन प्रबधं न प्रणाली (पीआरएमएस) दििाजनििे ों के अनुसार होगी। ख) यदि जवस्ट्तार के जलए अनरु ोध दकए गए दकसी जवकास क्षेत्र के िेि 2पी/पी50 (2पी/50 टरिवि का अथि ह ैजसद्ध और संभाजवत भंडार, जिनके उत्पािन की 50% संभावना ह)ै वसूली योग्य भंडार [तले + गैस के तले -समकक्ष (ओ+ओईिी)] 5 एमएमबीबीएल से अजधक ह,ैं तो िीिीएच द्वारा अनुरजक्षत और समय-समय पर संिोजधत सूची में िाजमल दकसी अंतरराष्ट्रीय ख्याजत प्राि सलाहकार से 'तीसरे पक्ष द्वारा टरिवि लेखापरीक्षा कराना चाजहए। ग) संजविाकार िेि भंडार के िोहन के जलए आवेिन िमा करत े समय प्रस्ट्ताजवत जवस्ट्तार अवजध के जलए संिोजधत क्षेत्र जवकास योिना (आरएफडीपी) प्रस्ट्तुत करेगा। इसमें जनम्नजलजखत बातें िाजमल होंगी, लेदकन यह इन्हीं तक सीजमत नहीं होंगे:
(i) ऑयल इजनजियली इन प्लेस (ओआईआईपी) और गैस इजनजियली इन प्लेस (िीआईआईपी)
(ii) िेि 2पी/पी50 जनकासीयोग्य टरिवि
(iii) टरज़वोयर जसमुलेिन अध्ययनों पर आधाटरत भजवष्य का उत्पािन प्रोफाइल
(iv) प्रस्ट्ताजवत कायि कायिक्रम और प्रस्ट्ताजवत जवस्ट्तार अवजध के जलए अनुमाजनत व्यय घ) संिोजधत एफडीपी में एक 'आधार उत्पािन प्रोफाइल' (अथाति 'कुछ न करन'े की जस्ट्थजत, जिसमें पहल े से स्ट्वीकृत इनपुट म ें कोई बिलाव नहीं दकया िाता) और बेस केस के आधार पर एक 'अनिु ंजसत उत्पािन प्रोफाइल' िाजमल होगा। इसमें संबंजधत कायि कायिक्रम और कायिक्रम की मात्रा भी िाजमल होगी, जिसमें िहााँ भी लागू हो, आईओआर/ईओआर घटक भी िाजमल दकए िान े चाजहए। ङ) इस तरह के आरएफडीपी पर प्रबंधन सजमजत (एमसी) द्वारा जवचार दकया िाएगा और िहां उजचत समझा िाएगा, एमसी इस नीजत के तहत सरकार द्वारा दिए िा रह े पीएससी के जवस्ट्तार की ित ि के अधीन, ऐसी जवकास योिना (वतिमान पीएससी से परे की अवजध सजहत) के जलए सिति अनुमोिन प्रिान करेगी। एमसी द्वारा इस तरह की सिति मंिूरी से संजविाकार को पीएससी अवजध में जवस्ट्तार का कोई अजधकार नहीं जमलगे ा। च) आवेिन िमा करत े समय प्रचालक को तकनीकी जविेिज्ञता का प्रमाण प्रस्ट्तुत करना चाजहए। छ) आवेिन िमा करत े समय, संजविाकार को िुरुआत से लेकर अब तक खोि े गए कूपों और उत्पािन (योिनाबद्ध बनाम वास्ट्तजवक) की कुल उपलजब्धयों का जववरण िेना चाजहए। ज) सरकार के सभी वैधाजनक िेय राजि और भुगतान का भुगतान दकया िाना चाजहए और संजविाकार दकसी भी कारण से सरकार का जडफॉल्टर नहीं होना चाजहए। जवस्ट्तार अनुरोधों पर जवचार करत े समय सरकार लंजबत मध्यस्ट्थता को भी ध्यान म ेंरखगे ी।
4. अनरु ोध के मल्ू याकं न के जलए मानिंड
4.1 संजविाकार के जपछल े प्रिििन को जवस्ट्तार के अनरु ोध पर अनकु ूल रूप स े जवचार करन े के जलए संतोििनक होना चाजहए।
4.2 जपछला प्रििनि जनम्नजलजखत मानिंडों के आधार पर आंका िाएगा: (क) संजविाकार ने जपछले 10 विों में आवेिन की तारीख तक एमसी द्वारा अनुमोदित क्षेत्र जवकास योिना के कम से कम 70% जवकास कूपों जड्रल दकया होना चाजहए या4 THE GAZETTE OF INDIA : EXTRAORDINARY [PART I—SEC.1] संजविाकार को आवेिन की तारीख तक, जपछले 10 विों के जलए पहले से स्ट्वीकृत एफडीपी या अनुमोदित कायि कायिक्रम के संिभि में, प्रजतबद्ध उत्पािन का 70% हाजसल करना होगा। (ख) संजविाकार को पीएससी के अनुसार साइट रीस्ट्टोरेिन फंड (एसआरएफ) और साइट रीस्ट्टोरेिन प्लान (एसआरपी) के प्रावधानों का अनुपालन करना चाजहए। िहा ं भी पीएससी एसआरएफ और एसआरपी के जलए प्रावधान नहीं करता ह,ै संजविाकार को जवस्ट्ताटरत संजविा के एक भाग के रूप म ें एसआरएफ और एसआरपी का प्रस्ट्ताव करना चाजहए।
5. सरकार को नए बोजलयों को आमजं त्रत करन े का जवकल्प: उपयुिक्त खंड 3 और 4 में उजल्लजखत उपरोक्त ितों म ें से दकसी का भी अनपु ालन करने म ें जवफलता की जस्ट्थजत में, सरकार के पास क्षेत्र के और जवकास के जलए सबसे प्रजतस्ट्पधी बोली के जलए नए बोजलयों को आमंजत्रत करने और उसे प्रिान करने का जवकल्प होगा।
6. मध्यस्ट्थता का स्ट्थान: संजविाकार को पेरोजलयम और प्राकृजतक गैस जनयम, 2025 के जनयम 51 के अनुसार मध्यस्ट्थता का स्ट्थान चुनन ेकी अनुमजत िी िाएगी।
7. जवस्ट्तार की अवजध:
7.1 इन पीएससी के जलए जवस्ट्तार, तले और गैस क्षेत्रों िोनों के जलए, क्षेत्र के आर्थिक िीवन के अंत तक, तीस विों स े अजधक नहीं की एक या अजधक दकस्ट्तों में माना िाएगा।
7.2 "क्षेत्र के आर्थिक िीवन का अंत" अजभव्यजक्त का अथि समय का वह बबंि ुहोगा जिसके बाि जनरंतर उत्पािन को वस्ट्तुजनष्ठ रूप से व्यावसाजयक रूप से अव्यवहायि प्रिर्िित दकया िाता ह।ै
8. बकैं गारंटी की प्रस्ट्तजु त:
8.1 संजविाकार, संजविाकार द्वारा संजविा क्षेत्र में दकए िान े वाले कायि कायिक्रम के संबंध में, एमसी द्वारा अनुमोदित कुल अनुमाजनत वार्ििक व्यय के 10% के बराबर बैंक गारंटी (बीिी) प्रिान करेगा।
8.2 यदि संजविाकार अनुमोदित कायि कायिक्रम को पूरा करने में जवफल रहता है, तो एमसी द्वारा गजतजवजध को पूरा करने के जलए एक विि तक की अनग्रु ह अवजध िी िा सकती है, िो अनुग्रह अवजध की अवजध के जलए बैंक गारंटी की वैधता का जवस्ट्तार करन ेऔर अगल ेविि के कायि कायिक्रम को बाजधत नहीं करने के जलए संजविाकार के अधीन है।
8.3 इसके अलावा, संजविाकार को आगामी वि ि के वार्ििक कायि कायिक्रम और उस वि ि के बिट के जवरुद्ध एक और नई बैंक गारंटी िमा करनी होगी।
9. अन्य ित ें
9.1 पूविवती नीजत दिनांक 28.03.2016 के तहत दिए गए पीएससी जवस्ट्तार उनकी जनधािटरत समाजि जतजथ तक वैध रहगें े।
9.2 मूल पीएससी अवजध के बाि पहली बार जवस्ट्तार के जलए या वतिमान म ें अनुमोदित जवस्ट्तार अवजध स े आग े के जवस्ट्तार के जलए कोई भी आवेिन, जविेि रूप से, इस नीजत िस्ट्तावेि के प्रावधानों द्वारा िाजसत होगा।
9.3 जवस्ट्तार प्रिान करते समय, सरकार को दकसी जविेि पीएससी के जलए जवजिष्ट, कोई भी अजतटरक्त ितें जनधािटरत करन े का अजधकार होगा।
9.4 सरकार जबना कोई कारण बताए पीएससी को आग े बढ़ाने का अजधकार सुरजक्षत रखेगी।
9.5 इस नीजत म ेंजनधािटरत ित ि पीएससी के मौिूिा प्रावधानों को रद्द कर िगे ी।
9.6 यदि कोई संजविाकार इस नीजत स े सहमत नहीं ह,ै तो क्षत्रे को यथाजस्ट्थजत के आधार पर पुन: बोली लगाने के जलए जवचार दकया िाएगा।[भाग I—खण् ड 1] भारत का रािपत्र : असाधारण 5
9.7 सरकार को राष्ट्रीय तले कंपजनयों (एनओसीि) यानी ओएनिीसी या ओआईएल को क्षत्रे सौंपने का अजधकार भी होगा। 10 क्षत्रे ों की सचू ीीः 22 क्षत्रे ों की सचू ी अनलु ग्नक-क म ेंिी गई ह।ै जवनोि िेिन, संयुक्त सजचव अनलु ग्नक-क (22 छोटे और मध्यम आकार के क्षत्रे ) क्रमाकं मध्यम आकार के क्षत्रे के रूप म ेंप्रिान दकए गए 1 खारसांग 2 रव्वा एसएल छोटे आकार के फील्ड के रूप म ेंम ेंप्रिान दकए गए 1 ढोलका 2 वेवल 3 अिोल 4 कैम्बे 5 भंडूत 6 हिीरा 7 पीवाई-1 8 बाओला 9 मोढेरा 10 बकरोल 11 लोहार 12 कर्ििसन6 THE GAZETTE OF INDIA : EXTRAORDINARY [PART I—SEC.1] 13 अल्लोरा 14 अमगरु ी 15 ढोलासन 16 काँवारा 17 उत्तर बालोल 18 उत्तर कठना 19 उनावा 20 पीवाई-3 MINISTRY OF PETROLEUM AND NATURAL GAS
NOTIFICATION New Delhi, the 10th November, 2026 Policy for the Grant of Extension to Production Sharing Contracts (PSC) signed by the Government of India awarding small, medium sized and discovered fields to private Joint Ventures.
F. No. Expl-11019(18)/33/2026-ONG-IV.— The Government of India (hereinafter referred as Government) had earlier approved a policy dated 28.03.2016 for granting extension to small and medium size discovered fields in order to have a transparent and defined framework for granting extensions. Consequent upon the Notification of Oilfields (Regulation and Development) Amendment Act, 2025 and Petroleum and Natural Gas Rules, 2025, the Policy is now revised. This revised Policy will help Contractors (operators / PI holders) in planning their investments in these fields for optimal exploitation of hydrocarbons. The salient features of the policy are as follows:-
1. SUBMISSION, CONSIDERATION AND APPROVAL OF REQUEST FOR CONTRACT EXTENSION
1.1 The Contractor should submit the application duly approved by the Operating Committee (OC) for extension of Contract to MoPNG at any time after the expiry of half of the term (or the extended term of the Contract), but at least 2 years prior to the expiry date of Contract, with a copy to DGH.
1.2 DGH will make a recommendation to MoPNG within 6 months of submission of application by the Contractor.
1.3 The Government will take a decision on the request for extension within 3 months of receipt of the proposal from DGH.
2. FISCAL PARAMETERS FOR EXTENSION
2.1 Government Share: The Government share of Profit Petroleum (PP) during the extended period of contract,
beyond the original PSC period shall be as under:
Extended period of PSC Rate of GoI PP (beyond original term of PSC) Year 1 to year 10 of extension 10% higher than the share as calculated using the normal PSC provisions Year 11 to year 20 of extension 5% higher than the share as calculated using the normal PSC provisions[भाग I—खण् ड 1] भारत का रािपत्र : असाधारण 7 Year 21 to year 30 of extension 2.50% higher than the share as calculated using the normal PSC provisions Beyond year 30 As per the share as calculated using the normal PSC provisions
2.2 Government share of Profit Petroleum, during the extended period of contract, may vary from year to year, based on Investment Multiple (IM) /Post Tax Rate of Return (PTRR). (For the sake of clarity, if the Government share of Profit Petroleum as calculated using the normal PSC provisions in any year during year 1 to year 10 of the extended period of contract is say 20%, the payable Government share of Profit Petroleum during that period shall be 30% (20%+10%)).
2.3 Royalty and Cess: During the extended period of contract, the royalty and cess shall be payable at prevailing rates of nomination regime and not at concessional rates as stipulated in the PSC for both small and medium sized fields. Royalty and cess will be payable by all the Contractors in proportion to their participating Interest.
3. PREREQUISITES FOR EVALUATION
3.1 The proposal for extension shall be considered for the following areas, having valid mining lease/ petroleum lease, on the date of application:
(a) Areas where test/ commercial production has commenced.
(b) Areas covered by a development plan, for any discoveries in the lease area, which has been submitted to Management Committee (MC) for approval, subject to approval of such FDP by MC.
(c) Areas where firm exploration programme has been submitted by the Contractor to DGH, backed by a Bank Guarantee and not covered under existing development area on the date of application.
3.2 The application for contract extension should fulfil the following conditions:
(a) Contractor should be able to demonstrate the availability of balance recoverable Reserves through a Third-Party Reserves Audit report, to be submitted along with the application for extension. The definition of "Reserves' for the purpose would be as per Petroleum Resource Management System
(PRMS) guidelines.
(b) If the remaining 2P/P50 (2P/P50 reserves implies proven + probable reserves having a 50% certainty of being produced) recoverable reserves [Oil+ Oil Equivalent of Gas (O+OEG)] of any development area requested for extension, are more than 5 MMBBL, the Third Party Reserves Audit needs to be done by a consultant of international repute as per the empanelled list maintained by DGH and as amended by from time to time.
(c) Contractor would submit a Revised Field Development Plan (RFDP), for the proposed extension period, at the time of submission of extension application, for exploitation of the remaining reserves.
This will include, but not be limited to, the following:
(i) In place-Oil Initially in Place (OIIP) and Gas Initially in Place (GIIP)
(ii) Balance 2P/P50 Recoverable Reserves
(iii) Future Production Profile based on Reservoir Simulation Studies
(iv) Proposed Work Programme and the estimated expenditure for the proposed extension period.
(d) Revised FDP would include a Base Production Profile (do nothing case, with no change in the earlier approved input, if any) and a Revised Production Profile (over the Base case), including the corresponding Work Programme and Programme Quantity, which should include Improved Recovery / Enhanced Recovery components, wherever applicable.
(e) Such RFDP will be considered by the Management Committee (MC). Where thought fit, the MC will grant conditional approval for such development plan (including the period beyond the current PSC), subject to the condition of extension of PSC being granted by the Government under this policy.
Such conditional approval by MC will not confer any right on the Contractor for extension in PSC period.
(f) While submitting the application, the operator should submit proof of technical expertise.
(g) The Contractor, while submitting the application for extension, should submit cumulative achievement of drilled wells and production (planned vs actual) since inception.8 THE GAZETTE OF INDIA : EXTRAORDINARY [PART I—SEC.1]
(h) All the statutory dues and payments due to Government should have been cleared and the Contractor should not be a defaulter to the Government on any account. Government would also take into account pending arbitration while considering extension requests.
4. CRITERIA FOR EVALUATION OF REQUEST
4.1 The past performance of the Contractor should be satisfactory for the request of extension to be favourably considered.
4.2 The past performance would be judged on the basis of following criteria:
(a) Contractor should have drilled, at least 70% of the development wells of the field development plan, as approved by the MC as on date of application for last 10 years, OR Contractor must have achieved 70% of the committed production as on date of application, with reference to the earlier approved FDP or approved Work Programme for the last 10 years.
(b) Contractor should have complied with the provisions of creation of Site Restoration Fund (SRF) and Site Restoration Plan (SRP) as per the PSC. Wherever PSC does not provide for SRF and SRP, the Contractor should propose a SRF and a SRP, as a part of extended contract.
5. OPTION TO GOVERNMENT TO INVITE FRESH BIDS: In the event of failure to comply with any of the above conditions, mentioned in clauses 3 and 4 above, Government shall have the option to invite fresh bids for further development of the area and to award the field to the most competitive bid.
6. SEAT OF ARBITRATION: The Contractor shall be allowed to choose the seat of arbitration as per Rule 51 of the Petroleum and Natural Gas Rules, 2025.
7. DURATION OF EXTENSION:
7.1 The extension for these PSCs would be considered both for oil and gas fields, till the end of the economic life of the field, in one or more instalments of not more than thirty years each.
7.2 The expression “end of economic life of the field” shall mean the point in time beyond which continued production is objectively demonstrated to be commercially unviable.
8. SUBMISSION OF BANK GUARANTEE:
8.1 Contractor shall provide, Bank Guarantee (BG) equal to 10% of the total estimated annual expenditure, in respect of the Work Programme approved by the MC for being undertaken by the Contractor in the contract area.
8.2 In case the contractor fails to complete the approved work program, grace period of up to one year can be granted by the MC, to complete the activity, subject to the contractor extending the validity of the Bank Guarantee for the duration of grace period and not hampering the next year's work program.
8.3 In addition, the Contractor will have to submit another fresh Bank Guarantee for the forthcoming year against the annual work programme and budget of that year.
9. OTHER CONDITIONS
9.1 Any extension of a Production Sharing Contract (PSC) granted pursuant to the erstwhile policy framework dated 28 March 2016 shall subsist and remain valid until its respective scheduled expiration date, subject to the same terms and conditions prescribed under the extension.
9.2 Any application for the first time extension beyond original PSC period or for further extension beyond the currently approved extension period, will be governed, exclusively, by the provisions of this policy document.
9.3 At the time of granting extension, the Government shall have the right to stipulate any further conditions, specific to any particular PSC.
9.4 Government shall reserve the right, not to extend a PSC, without assigning any reason thereof.
9.5 The condition stipulated in this policy will override the existing provisions of the PSC.
9.6 In case any contractor is not agreeable to this policy, then the field will be considered for rebidding, on as-is where-is basis.
9.7 Government would also have the right to assign the field to National Oil Companies (NOCs) i.e. ONGC or OIL.[भाग I—खण् ड 1] भारत का रािपत्र : असाधारण 9
10. LIST OF FIELDS: The list of 22 fields is placed at Annexure-A.
VINOD SESHAN, Jt. Secy.
ANNEXURE-A (22 small and medium size fields) SL AWARDED AS MEDIUM SIZED FIELDS 1 Kharsang 2 Ravva SL AWARDED AS SMALL SIZED FIELDS 1 Dholka 2 Wavel 3 Asjol 4 Cambay 5 Bhandut 6 Hazira 7 PY-1 8 Baola 9 Modhera 10 Bakrol 11 Lohar 12 Karjisan 13 Allora 14 Amguri 15 Dholasan 16 Kanwara 17 North Balol 18 North Kathana 19 Unawa 20 PY-3 Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064 and Published by the Controller of Publications, Delhi-110054.